Project Management Assignment: Fisher Street Car Park Project Analysis
VerifiedAdded on 2021/04/17
|22
|3769
|73
Project
AI Summary
This project management assignment analyzes the construction of the Fisher Street Car Park by ADCO Construction Company for the Fairfield City Council. The project involves a 3-story car park with environmentally sustainable features. The assignment includes an updated business case, revised project charter, and a detailed project management plan. The plan covers scope, duration, budget, and resource allocation, including a work breakdown structure and Gantt chart. The project's scope includes construction, drainage, landscaping, and sustainable initiatives. The budget is approximately AUD 4,432,400.00, with a planned duration of three years. The assignment also addresses project integration, scope, schedule, and cost management, including assumptions, constraints, and change control. The project experienced scope creep, extending the schedule by one month, and details the various phases from planning to closure.

Running head: PROJECT MANAGEMENT
Project: Fisher Street Car Park Construction
Name of the Student
Name of the University
Author’s Note
Project: Fisher Street Car Park Construction
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Table of Contents
Question 2........................................................................................................................................3
Question 2 (a)..............................................................................................................................3
1. Defining organization and the project.................................................................................3
2. Updated business case and revised project charter..............................................................3
3. Project management plan...................................................................................................11
Bibliography..................................................................................................................................27
PROJECT MANAGEMENT
Table of Contents
Question 2........................................................................................................................................3
Question 2 (a)..............................................................................................................................3
1. Defining organization and the project.................................................................................3
2. Updated business case and revised project charter..............................................................3
3. Project management plan...................................................................................................11
Bibliography..................................................................................................................................27

2
PROJECT MANAGEMENT
Question 2
Question 2 (a)
1. Defining organization and the project
The paper mainly focusses on the construction of Fisher Street Car Park for Fairfield
City Council by the ADCO Construction Company. It is identified that the company “ADCO
Construction” which is one of the leading construction company in Australia engages in
constructing the Fisher Street Car Park in order to provide proper car parking facility
(Adcoconstruct.com.au 2018). The project mainly includes car parking for 180 vehicles over 3-
storey building that is split into five different levels. The company also includes some of the
environmentally sustainable initiatives including 30 kW photovoltaic system that is mainly
installed on the top level of the car parking area. In addition to this, the design that is made for
the façade treatment is very much spectacular with various significant black butt timber
stenciling in order to provide proper themed mural.
2. Updated business case and revised project charter
2.1 Business case
The paper mainly focusses on the construction of Fisher Street Car Park, which is mainly
located in the area of Cabramatta by the ADCO construction company in order to provide proper
parking facility. The project was mainly funded by the Commonwealth Nation building program
so that the people of Cabramatta does not have to face any issues or challenges related with
parking. In addition to this, the ADCO construction company utilizes some of the environmental
sustainable features including 180-grid connection array that is mainly accounted for over 35%
of the annual energy needs of the parking area (Adcoconstruct.com.au 2018). The entire project
PROJECT MANAGEMENT
Question 2
Question 2 (a)
1. Defining organization and the project
The paper mainly focusses on the construction of Fisher Street Car Park for Fairfield
City Council by the ADCO Construction Company. It is identified that the company “ADCO
Construction” which is one of the leading construction company in Australia engages in
constructing the Fisher Street Car Park in order to provide proper car parking facility
(Adcoconstruct.com.au 2018). The project mainly includes car parking for 180 vehicles over 3-
storey building that is split into five different levels. The company also includes some of the
environmentally sustainable initiatives including 30 kW photovoltaic system that is mainly
installed on the top level of the car parking area. In addition to this, the design that is made for
the façade treatment is very much spectacular with various significant black butt timber
stenciling in order to provide proper themed mural.
2. Updated business case and revised project charter
2.1 Business case
The paper mainly focusses on the construction of Fisher Street Car Park, which is mainly
located in the area of Cabramatta by the ADCO construction company in order to provide proper
parking facility. The project was mainly funded by the Commonwealth Nation building program
so that the people of Cabramatta does not have to face any issues or challenges related with
parking. In addition to this, the ADCO construction company utilizes some of the environmental
sustainable features including 180-grid connection array that is mainly accounted for over 35%
of the annual energy needs of the parking area (Adcoconstruct.com.au 2018). The entire project
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
will be executed successfully within 3 years of its commencement and it is found that an extra 1-
month time is provided in order to allow the scope creep. Furthermore, the project needs budget
of around AUD 4,432,400.00 in order to complete the construction of Fisher Street Car Park.
2.2 Scope
The scope of the project is elaborated below.
In-scope: The in-scope of the project are as follows:
Construction of a 3 Storey car park
Creating drainage as well as landscaping area
Developing environmental sustainable initiatives
Installation of photovoltaic system
Butt timber stenciling
Designing facade treatment
80-panel grid connected solar array
Out-Scope: The out-scope of the project are as follows:
Detailed description about the materials that are supplied for the project is not
provided
Information about external stakeholders of the project are not provided in detail
2.3 Duration
It is assumed that the company “ADCO construction” generally required 3 years in order
to complete the project successfully. It is found that 1-month extra is provided to the project
manager in order to allow scope creep thus it is estimated that the entire project will be
successfully completed by 7/26/22
PROJECT MANAGEMENT
will be executed successfully within 3 years of its commencement and it is found that an extra 1-
month time is provided in order to allow the scope creep. Furthermore, the project needs budget
of around AUD 4,432,400.00 in order to complete the construction of Fisher Street Car Park.
2.2 Scope
The scope of the project is elaborated below.
In-scope: The in-scope of the project are as follows:
Construction of a 3 Storey car park
Creating drainage as well as landscaping area
Developing environmental sustainable initiatives
Installation of photovoltaic system
Butt timber stenciling
Designing facade treatment
80-panel grid connected solar array
Out-Scope: The out-scope of the project are as follows:
Detailed description about the materials that are supplied for the project is not
provided
Information about external stakeholders of the project are not provided in detail
2.3 Duration
It is assumed that the company “ADCO construction” generally required 3 years in order
to complete the project successfully. It is found that 1-month extra is provided to the project
manager in order to allow scope creep thus it is estimated that the entire project will be
successfully completed by 7/26/22
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
WBS Task Name Duration Start Finish
0
Construction of Fisher Street Car Park
by ADCO
1122 days Mon 4/9/18 Tue 7/26/22
1 Planning phase 25 days Mon 4/9/18 Fri 5/11/18
1.1 Development of project plan 5 days Mon 4/9/18 Fri 4/13/18
1.2 Creation of resource plan 3 days Mon 4/16/18 Wed 4/18/18
1.3 Development of financial plan 3 days Thu 4/19/18 Mon 4/23/18
1.4
Development of quality management
plan
3 days Tue 4/24/18 Thu 4/26/18
1.5
Development of risk management
plan
4 days Fri 4/27/18 Wed 5/2/18
1.6
Development of communication
management plan
3 days Thu 5/3/18 Mon 5/7/18
1.7 Development of procurement 4 days Tue 5/8/18 Fri 5/11/18
1.8
Milestone 1: Completion of project
planning phase
0 days Fri 5/11/18 Fri 5/11/18
2 Initiation phase of the project 15 days Mon 5/14/18 Fri 6/1/18
2.1 Development of business case 4 days Mon 5/14/18 Thu 5/17/18
2.2 Undertaking feasibility analysis for 3 days Fri 5/18/18 Tue 5/22/18
PROJECT MANAGEMENT
WBS Task Name Duration Start Finish
0
Construction of Fisher Street Car Park
by ADCO
1122 days Mon 4/9/18 Tue 7/26/22
1 Planning phase 25 days Mon 4/9/18 Fri 5/11/18
1.1 Development of project plan 5 days Mon 4/9/18 Fri 4/13/18
1.2 Creation of resource plan 3 days Mon 4/16/18 Wed 4/18/18
1.3 Development of financial plan 3 days Thu 4/19/18 Mon 4/23/18
1.4
Development of quality management
plan
3 days Tue 4/24/18 Thu 4/26/18
1.5
Development of risk management
plan
4 days Fri 4/27/18 Wed 5/2/18
1.6
Development of communication
management plan
3 days Thu 5/3/18 Mon 5/7/18
1.7 Development of procurement 4 days Tue 5/8/18 Fri 5/11/18
1.8
Milestone 1: Completion of project
planning phase
0 days Fri 5/11/18 Fri 5/11/18
2 Initiation phase of the project 15 days Mon 5/14/18 Fri 6/1/18
2.1 Development of business case 4 days Mon 5/14/18 Thu 5/17/18
2.2 Undertaking feasibility analysis for 3 days Fri 5/18/18 Tue 5/22/18

5
PROJECT MANAGEMENT
the project
2.3 Establishment of project charter 3 days Wed 5/23/18 Fri 5/25/18
2.4
Appointment of project team
members
4 days Mon 5/28/18 Thu 5/31/18
2.5 Approval of the project 1 day Fri 6/1/18 Fri 6/1/18
2.6
Milestone 2: Completion of initiation
phase of the project
0 days Fri 6/1/18 Fri 6/1/18
3 Execution phase of the project 1052 days Mon 6/4/18 Tue 6/14/22
3.1 Soil preparation foundation 90 days Mon 6/4/18 Fri 10/5/18
3.2 Raw material procurement 120 days Mon 10/8/18 Fri 3/22/19
3.3 Construction of a 3 Storey car park 190 days Mon 3/25/19 Fri 12/13/19
3.4
Creating drainage as well as
landscaping area
220 days Mon 12/16/19 Fri 10/16/20
3.5
Developing environmental
sustainable initiatives
100 days Mon 10/19/20 Fri 3/5/21
3.6 Installation of photo voltaic system 120 days Mon 3/8/21 Fri 8/20/21
3.7 Butt timber stenciling 50 days Mon 8/23/21 Fri 10/29/21
3.8 Designing facade treatment 80 days Mon 11/1/21 Fri 2/18/22
PROJECT MANAGEMENT
the project
2.3 Establishment of project charter 3 days Wed 5/23/18 Fri 5/25/18
2.4
Appointment of project team
members
4 days Mon 5/28/18 Thu 5/31/18
2.5 Approval of the project 1 day Fri 6/1/18 Fri 6/1/18
2.6
Milestone 2: Completion of initiation
phase of the project
0 days Fri 6/1/18 Fri 6/1/18
3 Execution phase of the project 1052 days Mon 6/4/18 Tue 6/14/22
3.1 Soil preparation foundation 90 days Mon 6/4/18 Fri 10/5/18
3.2 Raw material procurement 120 days Mon 10/8/18 Fri 3/22/19
3.3 Construction of a 3 Storey car park 190 days Mon 3/25/19 Fri 12/13/19
3.4
Creating drainage as well as
landscaping area
220 days Mon 12/16/19 Fri 10/16/20
3.5
Developing environmental
sustainable initiatives
100 days Mon 10/19/20 Fri 3/5/21
3.6 Installation of photo voltaic system 120 days Mon 3/8/21 Fri 8/20/21
3.7 Butt timber stenciling 50 days Mon 8/23/21 Fri 10/29/21
3.8 Designing facade treatment 80 days Mon 11/1/21 Fri 2/18/22
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
3.9 80 panel grid connected solar array 82 days Mon 2/21/22 Tue 6/14/22
3.10
Milestone 3: Completion of
execution phase
0 days Tue 6/14/22 Tue 6/14/22
4 Closure phase 30 days Wed 6/15/22 Tue 7/26/22
4.1 Reviewing project 8 days Wed 6/15/22 Fri 6/24/22
4.2 Checking the Fisher car park area 9 days Mon 6/27/22 Thu 7/7/22
4.3 Stakeholder sign off 8 days Fri 7/8/22 Tue 7/19/22
4.4 Documentation 5 days Wed 7/20/22 Tue 7/26/22
4.5
Milestone 4: Completion of closure
phase
0 days Tue 7/26/22 Tue 7/26/22
2.4 Budget estimate
The ADCO construction company generally required budget of around AUD
4,432,400.00 in order to complete the construction of Fisher Street Car Park successfully. The
table that is provided below highlights the cost that is required for executing each of the project
activities are listed in the table below:
Task Name Duration Resource Names Cost
PROJECT MANAGEMENT
3.9 80 panel grid connected solar array 82 days Mon 2/21/22 Tue 6/14/22
3.10
Milestone 3: Completion of
execution phase
0 days Tue 6/14/22 Tue 6/14/22
4 Closure phase 30 days Wed 6/15/22 Tue 7/26/22
4.1 Reviewing project 8 days Wed 6/15/22 Fri 6/24/22
4.2 Checking the Fisher car park area 9 days Mon 6/27/22 Thu 7/7/22
4.3 Stakeholder sign off 8 days Fri 7/8/22 Tue 7/19/22
4.4 Documentation 5 days Wed 7/20/22 Tue 7/26/22
4.5
Milestone 4: Completion of closure
phase
0 days Tue 7/26/22 Tue 7/26/22
2.4 Budget estimate
The ADCO construction company generally required budget of around AUD
4,432,400.00 in order to complete the construction of Fisher Street Car Park successfully. The
table that is provided below highlights the cost that is required for executing each of the project
activities are listed in the table below:
Task Name Duration Resource Names Cost
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
Construction of Fisher Street
Car Park by ADCO
1122 days
AUD
4,432,400.00
Planning phase 25 days AUD 11,560.00
Development of project plan 5 days Project manager AUD 2,000.00
Creation of resource plan 3 days Project planner AUD 1,080.00
Development of financial plan 3 days Project manager AUD 1,200.00
Development of quality
management plan
3 days Project planner AUD 1,080.00
Development of risk
management plan
4 days
Project manager, Sub-
contractor
AUD 2,720.00
Development of
communication management plan
3 days Project manager, Architect AUD 2,040.00
Development of procurement 4 days Project planner AUD 1,440.00
Milestone 1: Completion of
project planning phase
0 days AUD 0.00
Initiation phase of the project 15 days AUD 6,520.00
Development of business case 4 days Architect, Contractor AUD 2,400.00
Undertaking feasibility
analysis for the project
3 days Project planner AUD 1,080.00
Establishment of project
charter
3 days Project manager AUD 1,200.00
Appointment of project team 4 days Project planner AUD 1,440.00
PROJECT MANAGEMENT
Construction of Fisher Street
Car Park by ADCO
1122 days
AUD
4,432,400.00
Planning phase 25 days AUD 11,560.00
Development of project plan 5 days Project manager AUD 2,000.00
Creation of resource plan 3 days Project planner AUD 1,080.00
Development of financial plan 3 days Project manager AUD 1,200.00
Development of quality
management plan
3 days Project planner AUD 1,080.00
Development of risk
management plan
4 days
Project manager, Sub-
contractor
AUD 2,720.00
Development of
communication management plan
3 days Project manager, Architect AUD 2,040.00
Development of procurement 4 days Project planner AUD 1,440.00
Milestone 1: Completion of
project planning phase
0 days AUD 0.00
Initiation phase of the project 15 days AUD 6,520.00
Development of business case 4 days Architect, Contractor AUD 2,400.00
Undertaking feasibility
analysis for the project
3 days Project planner AUD 1,080.00
Establishment of project
charter
3 days Project manager AUD 1,200.00
Appointment of project team 4 days Project planner AUD 1,440.00

8
PROJECT MANAGEMENT
members
Approval of the project 1 day Project manager AUD 400.00
Milestone 2: Completion of
initiation phase of the project
0 days AUD 0.00
Execution phase of the project 1052 days
AUD
4,404,000.00
Soil preparation foundation 90 days Contractor, Supervisor AUD 57,600.00
Raw material procurement 120 days
Contractor, Sub-contractor,
Supervisor
AUD 110,400.00
Construction of a 3 storey car
park
190 days
Builder, Contractor, Sub-
contractor, Additional
expenditure[1],Construction
materials[1]
AUD
2,667,200.00
Creating drainage as well as
landscaping area
220 days
Architect, Builder,
Contractor, Additional
expenditure[1]
AUD 693,600.00
Developing environmental
sustainable initiatives
100 days
Architect, Builder,
Contractor, Additional
expenditure[1]
AUD 588,000.00
Installation of photo voltaic
system
120 days
Builder, Contractor, Sub-
contractor, Supervisor
AUD 144,000.00
Butt timber stenciling 50 days Architect, Contractor, AUD 46,000.00
PROJECT MANAGEMENT
members
Approval of the project 1 day Project manager AUD 400.00
Milestone 2: Completion of
initiation phase of the project
0 days AUD 0.00
Execution phase of the project 1052 days
AUD
4,404,000.00
Soil preparation foundation 90 days Contractor, Supervisor AUD 57,600.00
Raw material procurement 120 days
Contractor, Sub-contractor,
Supervisor
AUD 110,400.00
Construction of a 3 storey car
park
190 days
Builder, Contractor, Sub-
contractor, Additional
expenditure[1],Construction
materials[1]
AUD
2,667,200.00
Creating drainage as well as
landscaping area
220 days
Architect, Builder,
Contractor, Additional
expenditure[1]
AUD 693,600.00
Developing environmental
sustainable initiatives
100 days
Architect, Builder,
Contractor, Additional
expenditure[1]
AUD 588,000.00
Installation of photo voltaic
system
120 days
Builder, Contractor, Sub-
contractor, Supervisor
AUD 144,000.00
Butt timber stenciling 50 days Architect, Contractor, AUD 46,000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
Supervisor
Designing facade treatment 80 days Contractor, Sub-contractor AUD 48,000.00
80 panel grid connected solar
array
82 days Architect, Contractor AUD 49,200.00
Milestone 3: Completion of
execution phase
0 days AUD 0.00
Closure phase 30 days AUD 10,320.00
Reviewing project 8 days Supervisor AUD 2,560.00
Checking the Fisher car park
area
9 days Supervisor AUD 2,880.00
Stakeholder sign off 8 days Project planner AUD 2,880.00
Documentation 5 days Project manager AUD 2,000.00
Milestone 4: Completion of
closure phase
0 days AUD 0.00
2.5 Assumptions and Constraints
Assumptions: The assumptions of the project are as follows:
The project will be completed within 3 years after commencement
The budget that is needed for constructing the Fisher Street Car Park is around AUD
4,432,400.00
The scope of the project will be followed in order to complete the project within the due
date.
PROJECT MANAGEMENT
Supervisor
Designing facade treatment 80 days Contractor, Sub-contractor AUD 48,000.00
80 panel grid connected solar
array
82 days Architect, Contractor AUD 49,200.00
Milestone 3: Completion of
execution phase
0 days AUD 0.00
Closure phase 30 days AUD 10,320.00
Reviewing project 8 days Supervisor AUD 2,560.00
Checking the Fisher car park
area
9 days Supervisor AUD 2,880.00
Stakeholder sign off 8 days Project planner AUD 2,880.00
Documentation 5 days Project manager AUD 2,000.00
Milestone 4: Completion of
closure phase
0 days AUD 0.00
2.5 Assumptions and Constraints
Assumptions: The assumptions of the project are as follows:
The project will be completed within 3 years after commencement
The budget that is needed for constructing the Fisher Street Car Park is around AUD
4,432,400.00
The scope of the project will be followed in order to complete the project within the due
date.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
Constraints: The constraints of the project are provided below:
Budget: It is quite important to complete the entire project within AUD 4,432,400.00. If
the project is not completed within the assumed budget then the project manager will face
number of budget related issues during project progress.
Time: It is quite necessary to complete the entire project within 3 years. If the project is
not completed within 3 years then the budget of the project will increase which will create
number of issues and challenges for the project.
Scope: It is necessary to follow the scope of the project in order to complete the complete
the construction of Fisher street car park within the assumed time and budget.
3. Project management plan
3.1 Project integration management
Development of project
plan
Execution of project plan Integrated change control
It was planned that the
entire project will be
completed with 3 years
after commencement
The entire project plan was
not executed within 3 years
due to scope creep.
The project manager extends
the schedule of the project by
1 month in order to allow
scope creep.
It was assumed that budget
of around 4,146,400.00 is
needed in order to complete
the project.
As per the planning, the
entire project management
plan will be completed within
4,146,400.00
No changes needed
It was planned that the The project do not follow the The scope creep extends the
PROJECT MANAGEMENT
Constraints: The constraints of the project are provided below:
Budget: It is quite important to complete the entire project within AUD 4,432,400.00. If
the project is not completed within the assumed budget then the project manager will face
number of budget related issues during project progress.
Time: It is quite necessary to complete the entire project within 3 years. If the project is
not completed within 3 years then the budget of the project will increase which will create
number of issues and challenges for the project.
Scope: It is necessary to follow the scope of the project in order to complete the complete
the construction of Fisher street car park within the assumed time and budget.
3. Project management plan
3.1 Project integration management
Development of project
plan
Execution of project plan Integrated change control
It was planned that the
entire project will be
completed with 3 years
after commencement
The entire project plan was
not executed within 3 years
due to scope creep.
The project manager extends
the schedule of the project by
1 month in order to allow
scope creep.
It was assumed that budget
of around 4,146,400.00 is
needed in order to complete
the project.
As per the planning, the
entire project management
plan will be completed within
4,146,400.00
No changes needed
It was planned that the The project do not follow the The scope creep extends the

11
PROJECT MANAGEMENT
project will follow the scope
of the project in order to
complete the project on
time
scope and as a result, scope
creep occurs within the
project.
time of the project by 1
month.
3.2 Project scope management
Detailed scope
The scope of the project is elaborated below:
In-scope: The in-scope of the project includes:
Construction of a 3 Storey car park
Developing drainage as well as landscaping area
Developing proper initiatives related with environmental sustainability
Designing facade treatment
Installation of photovoltaic system
Butt timber stenciling
80-panel grid connected solar array
Out-Scope: The out-scope of the project are as follows:
Proper details about project external stakeholders are not provided
Detailed description about the materials that are supplied by the project suppliers are
not provide
List of resources
PROJECT MANAGEMENT
project will follow the scope
of the project in order to
complete the project on
time
scope and as a result, scope
creep occurs within the
project.
time of the project by 1
month.
3.2 Project scope management
Detailed scope
The scope of the project is elaborated below:
In-scope: The in-scope of the project includes:
Construction of a 3 Storey car park
Developing drainage as well as landscaping area
Developing proper initiatives related with environmental sustainability
Designing facade treatment
Installation of photovoltaic system
Butt timber stenciling
80-panel grid connected solar array
Out-Scope: The out-scope of the project are as follows:
Proper details about project external stakeholders are not provided
Detailed description about the materials that are supplied by the project suppliers are
not provide
List of resources
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 22

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.