This project report details the implementation of a CRM system for Fluent Retail, covering various aspects of project management. The report begins with an introduction and background of the organization, followed by clearly defined project objectives, scope (both in and out of scope), and work identification. It then outlines the project's time and cost estimations, including a detailed WBS, project schedule table, Gantt chart, and project planning view. Resource optimization and risk review are also considered. The report further discusses the approach for project management, selection of project tools, and concludes with a summary of findings and a bibliography. The project follows a traditional agile methodology, with phases for initialization, planning, developing, and closing. The project's estimated duration is 83 days with a budget of approximately $50,000.00. The report provides a comprehensive overview of the entire project lifecycle, making it a valuable resource for students studying project management and CRM implementation.
Document Page
Running head: PROJECT FINAL REPORT
Project Final Report
“Implementation of CRM for Fluent Retail”
Name of the Student:
Student ID:
Name of the University:
Author’s note:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT FINAL REPORT
Table of Contents
1. Introduction..................................................................................................................................2
2. Organization Background............................................................................................................2
3. Project Objectives........................................................................................................................3
4. Project Scope...............................................................................................................................4
5. Work Identification......................................................................................................................4
6. Time and Cost Estimation...........................................................................................................5
7. Sequencing and Scheduling the task............................................................................................7
7.1 Project Schedule Table..........................................................................................................8
7.2 Project Gantt chart...............................................................................................................10
7.3 Project WBS........................................................................................................................11
7.4 Project Planning View.........................................................................................................11
8. Optimize the resources..............................................................................................................12
9. Review of Risks.........................................................................................................................15
10. Approach for Management of Project.....................................................................................17
11. Selection of Project Tools........................................................................................................18
12. Conclusion...............................................................................................................................19
13. Bibliography............................................................................................................................21
Document Page
2PROJECT FINAL REPORT
1. Introduction
The project management has been very helpful for taking care of the factors for the
alignment of the successful and effective management of the work. The project management
tools and principles has been aligned specifically with the implication of the works and the
management of the operations for the organization. The analysis of the works has been
successfully aligned with the consideration of the works integrating the management of the
successful and effective work development. The significant analysis of the work factors would
be effectively implied for the utilization of the smart project completion. The following
assignment would involve the taking care of the documentation requirement by the stakeholders.
The management has been implied with the use of the Ms-Project schedule and WBS
documentation for the project of “Implementation of CRM for Fluent Retail”. The report would
provide an initial documentation aligning with the development of the final documentation for
the Fluent Retail organization.
2. Organization Background
The project of “Implementation of CRM for Fluent Retail” has been considered for the
alignment of the successful documentation and the alignment of the specific and improved
management process. The final documentation would be developed considering the alignment of
the activities and ensuring the implication model. The Fluent Retail is one of the most prominent
works for the implication and development of the market size and aligning the development of
the factors for taking care of the works and ensuring the management of the smart project
development. The organization powers Omni channel merchants for the smart customer
experience. The management and implication of the works would be largely induced with the
Document Page
3PROJECT FINAL REPORT
formation of the successive management of the services for the users. The organization would be
effectively implied with the continuation of the user experience and delight management. The
rapid plugs and play development would involve the meeting of the changing demands of the
customers. The realization of the benefits of the cloud is another major motive of the Fluent
retails organization.
3. Project Objectives
The objectives of the project include the identification of the work required for the
alignment of the works and forming the alignment of the work. The project objectives would be
considered for the management of the works and the utilization of the effective work
identification for the project. The completion of the works would be effectively implied for
taking care of the implication management. The management of the works would be aligned with
the project objectives for integrating the work. The identified project objectives for the project
are,
To develop the project for developing and installing a CRM system at Fluent
Retails for taking care of the works and deploying the management of the
information for the customers
To use project management factors for developing an information document for
the customers and aligning the management of the specific work analysis
To imply the categorization of the works integrating the smart analysis of the
works for taking care of the activities
To complete the project in the estimated budget and schedule for ensuring that the
investors get the returns in investment
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT FINAL REPORT
To formulate the implication of the work integrating the management of the
successful work integration and development
4. Project Scope
The project would be effectively implied with the development of the successful and
effective management process. The project scope would be listed for the formation of the smart
management. The combination of the integrated work management can be implied with the
project of Implementation of CRM for Fluent Retail. The project scope would be dependent on
the deliverable for the implication management. The alignment of the work would be resulted in
integrating the work for the formation. The project scope can be divided into in scope and out of
scope. The in scope items for the project would include the effective deliverable plan, design of
the application, implementation plan, and development plan. The integration would be implied
for entrapping the effective project management plan and listing the probable development of
facilities. The implication would be successfully developed for ensuring that the project scope
are implied with the successive integration management.
5. Work Identification
The project would include the alignment of the works and managing the successive
integration management. The identification of the works would be implied for forming the
management of the improved functional development. The integration would be implied
cohesively and the formation of the works listing the integration of the works. The works
included in this project are designing, interface development, database development, and final
system development. The complete project has been divided into 4 main summary tasks namely
Document Page
5PROJECT FINAL REPORT
initiating, planning, developing, and closing. The explanation of the four phases has been given
below,
Initialization: The first phase of the project activities that includes the management of
the information and collecting them based on the successive work implication. The activities
included in this phase are requirement analysis, charter documentation, project initiation
documents, and submission of documents. The sign off is the milestone of this phase.
Planning: The planning is the second phase of the project plan that involves the
development of the specific project plan integrating the alignment of the successive and smart
project development. The project plan development would be integrated with the activities of
project kick off meeting, activity listing, scheduling of activities, and risk management planning.
The plan approval is the milestone of the project phase.
Developing: the developing phase is induced with the consideration of the works for the
creation of the smart project completion development. The development of the smart work
development can be implied with the designing of the system and development of the system.
The system design is done for forming the outlay of the smart project integration management.
The design sub-phase would include the activities of selection of design platform, outline is
made, design simulation, completion of design, and design approval. The development sub-phase
is implied with the management of the works pertaining the management of the successful
development management. The development sub-phase would involve the activities of UI
development, programming the functions, integrating the database, prototyping the application,
and system development.
Document Page
6PROJECT FINAL REPORT
Closing: the closing phase would include the activities of testing and monitoring, final
documentation, submission of documents, sign off, and closed. The closing phase is
characterized by the formation of the closure documentation and the ending of the project
proposal.
6. Time and Cost Estimation
The project schedule has been developed using the effective alignment of the works and
the simplification of the improved analysis and development. The Ms-Project schedule would be
used for the development of the project schedule and the alignment of the work identification.
The project time and cost estimation is given below,
WBS Task Name Duratio
n Cost
1.1 Requirement Analysis 2 days $640.00
1.2 Charter Documentation 3 days $1,200.00
1.3 Project Initiation Documents 3 days $1,200.00
1.4 Submission of documents 2 days $720.00
1.5 Sign off 0 days $0.00
2.1 Project Kick off Meeting 1 day $640.00
2.2 Activity Listing 2 days $800.00
2.3 Scheduling of activities 3 days $1,200.00
2.4 Risk Management Planning 5 days $2,200.00
2.5 Plan Approval 0 days $0.00
3.1.1 Selection of design platform 2 days $1,040.00
3.1.2 Outline is made 3 days $1,910.00
3.1.3 Design Simulation 4 days $4,240.00
3.1.4 Completion of Design 7 days $3,990.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT FINAL REPORT
3.1.5 Design Approval 0 days $0.00
3.2.1 UI development 5 days $4,300.00
3.2.2 Programming the functions 9 days $7,400.00
3.2.3 Integrating the database 7 days $5,720.00
3.2.4 Prototyping the Application 6 days $3,120.00
3.2.5 System Development 8 days $4,480.00
4.1 Testing and Monitoring 5 days $2,640.00
4.2 Final Documentation 3 days $1,200.00
4.3 Submission of documents 2 days $720.00
4.4 Sign off 1 day $640.00
4.5 Closed 0 days $0.00
Total 83 days $50,000.00
Hence, it is evident from the table that the project would consume a total of 83 days and a
budget of approximately $50,000.00. The budget estimation has been done considering the
bottom up estimation. Each of the cost factor would be aligned and summed for forming the
analysis of the improvement factor. The management would be implied for the listing of the
factors and integrating the works for taking care of the smart listing management. The work
integrating would be done for aligning the successful completion of the works and the listing of
the specific system development.
7. Sequencing and Scheduling the task
The project had been developed considering the traditional agile methodology. The
project activities would be developed steadily for the alignment of the improved functional and
Document Page
8PROJECT FINAL REPORT
effective activities. The project schedule would be developed considering the management of the
activities for taking care the completion of the work. The project activities are sequenced first to
last relation and the precedence of start to last facilities would be implied with the consideration
for work and system alignment. The significance of implementing the works would be
established with the alignment of the improved work experience.
7.1 Project Schedule Table
WBS Task Name Duratio
n Start Finish Predecessors
0 “Implementation of CRM for Fluent
Retail” 83 days Mon
11/19/18 Wed 3/13/19
1 Initialization 10 days Mon
11/19/18 Fri 11/30/18
1.1 Requirement Analysis 2 days Mon
11/19/18 Tue 11/20/18
1.2 Charter Documentation 3 days Wed
11/21/18 Fri 11/23/18 2
1.3 Project Initiation Documents 3 days Mon
11/26/18
Wed
11/28/18 3
1.4 Submission of documents 2 days Thu 11/29/18 Fri 11/30/18 4
1.5 Sign off 0 days Fri 11/30/18 Fri 11/30/18 5
2 Planning 11 days Mon 12/3/18 Mon
12/17/18
2.1 Project Kick off Meeting 1 day Mon 12/3/18 Mon 12/3/18 6
2.2 Activity Listing 2 days Tue 12/4/18 Wed 12/5/18 8
2.3 Scheduling of activities 3 days Thu 12/6/18 Mon
12/10/18 9
2.4 Risk Management Planning 5 days Tue 12/11/18 Mon 10
Document Page
9PROJECT FINAL REPORT
12/17/18
2.5 Plan Approval 0 days Mon
12/17/18
Mon
12/17/18 11
3 Developing 51 days Tue
12/18/18 Tue 2/26/19
3.1 Design 16 days Tue
12/18/18 Tue 1/8/19
3.1.1 Selection of design platform 2 days Tue 12/18/18 Wed
12/19/18 12
3.1.2 Outline is made 3 days Thu 12/20/18 Mon
12/24/18 15
3.1.3 Design Simulation 4 days Tue 12/25/18 Fri 12/28/18 16
3.1.4 Completion of Design 7 days Mon
12/31/18 Tue 1/8/19 17
3.1.5 Design Approval 0 days Tue 1/8/19 Tue 1/8/19 18
3.2 Development 35 days Wed 1/9/19 Tue 2/26/19
3.2.1 UI development 5 days Wed 1/9/19 Tue 1/15/19 19
3.2.2 Programming the functions 9 days Wed 1/16/19 Mon 1/28/19 21
3.2.3 Integrating the database 7 days Tue 1/29/19 Wed 2/6/19 22
3.2.4 Prototyping the Application 6 days Thu 2/7/19 Thu 2/14/19 23
3.2.5 System Development 8 days Fri 2/15/19 Tue 2/26/19 24
4 Closing 11 days Wed 2/27/19 Wed 3/13/19
4.1 Testing and Monitoring 5 days Wed 2/27/19 Tue 3/5/19 25
4.2 Final Documentation 3 days Wed 3/6/19 Fri 3/8/19 27
4.3 Submission of documents 2 days Mon 3/11/19 Tue 3/12/19 28
4.4 Sign off 1 day Wed 3/13/19 Wed 3/13/19 29
4.5 Closed 0 days Wed 3/13/19 Wed 3/13/19 30
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT FINAL REPORT
7.2 Project Gantt chart
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Implementation of CRM
for Fluent Retail
83 days Mon
11/19/18
Wed 3/13/19
1 1 Initialization 10 days Mon 11/19/18 Fri 11/30/18
2 1.1 Requirement Analysis 2 days Mon 11/19/18 Tue 11/20/18
3 1.2 Charter Documentation3 days Wed 11/21/18 Fri 11/23/18
4 1.3 Project Initiation Documents3 days Mon 11/26/18 Wed 11/28/18
5 1.4 Submission of documents2 days Thu 11/29/18 Fri 11/30/18
6 1.5 Sign off 0 days Fri 11/30/18 Fri 11/30/18
7 2 Planning 11 days Mon 12/3/18 Mon 12/17/18
8 2.1 Project Kick off Meeting1 day Mon 12/3/18 Mon 12/3/18
9 2.2 Activity Listing 2 days Tue 12/4/18 Wed 12/5/18
10 2.3 Scheduling of activities3 days Thu 12/6/18 Mon 12/10/18
11 2.4 Risk Management Planning5 days Tue 12/11/18 Mon 12/17/18
12 2.5 Plan Approval 0 days Mon 12/17/18 Mon 12/17/18
13 3 Developing 51 days Tue 12/18/18 Tue 2/26/19
14 3.1 Design 16 days Tue 12/18/18 Tue 1/8/19
15 3.1.1 Selection of design platform2 days Tue 12/18/18 Wed 12/19/18
16 3.1.2 Outline is made 3 days Thu 12/20/18 Mon 12/24/18
17 3.1.3 Design Simulation 4 days Tue 12/25/18 Fri 12/28/18
18 3.1.4 Completion of Design7 days Mon 12/31/18 Tue 1/8/19
19 3.1.5 Design Approval 0 days Tue 1/8/19 Tue 1/8/19
20 3.2 Development 35 days Wed 1/9/19 Tue 2/26/19
21 3.2.1 UI development 5 days Wed 1/9/19 Tue 1/15/19
22 3.2.2 Programming the functions9 days Wed 1/16/19 Mon 1/28/19
23 3.2.3 Integrating the database7 days Tue 1/29/19 Wed 2/6/19
24 3.2.4 Prototyping the Application6 days Thu 2/7/19 Thu 2/14/19
25 3.2.5 System Development8 days Fri 2/15/19 Tue 2/26/19
26 4 Closing 11 days Wed 2/27/19 Wed 3/13/19
27 4.1 Testing and Monitoring5 days Wed 2/27/19 Tue 3/5/19
28 4.2 Final Documentation 3 days Wed 3/6/19 Fri 3/8/19
29 4.3 Submission of documents2 days Mon 3/11/19 Tue 3/12/19
30 4.4 Sign off 1 day Wed 3/13/19 Wed 3/13/19
31 4.5 Closed 0 days Wed 3/13/19 Wed 3/13/19
Analyst
Documenter,Documents[1]
Documenter,Documents[1]
Documenter
11/30
Project Manager
Planner
Planner
Risk Analyst
12/17
Designer
Designer,Design Tools[1]
Tester,Designer,Testing Tools[1]
Designer,Design Tools[1]
1/8
Developer,UI tools[1]
Programmer,Program Language Software[1]
Developer,Database[1]
Tester,Testing Tools[1]
Developer
Tester,Testing Tools[1]
Documenter,Documents[1]
Documenter
Project Manager
3/13
W T F S S M T W T F S S M T W T F S S M T W T
Nov 4, '18 Nov 25, '18 Dec 16, '18 Jan 6, '19 Jan 27, '19 Feb 17, '19 Mar 10, '19 Mar 31, '19 Apr 21, '19
Document Page
11PROJECT FINAL REPORT
7.3 Project WBS
Implementation of CRM
for Fluent Retail
Initialization
Requirement
Analysis
Charter
Documentation
Project Initiation
Documents
Submission of
documents
Sign off
Planning
Project Kick off
Meeting
Activity Listing
Scheduling of
activities
Risk Management
Planning
Plan Approval
Developing
Design
Selection of design
platform
Outline is made
Design Simulation
Completion of
Design
Design Approval
Development
UI development
Programming the
functions
Integrating the
database
Prototyping the
Application
System
Development
Closing
Testing and
Monitoring
Final Documentation
Submission of
documents
Sign off
Closed
7.4 Project Planning View
0
1 1.1 1.2
1.3 1.4 1.5
2 2.1 2.2
2.3 2.4 2.5
3
3.1 3.1.1
3.1.2
3.1.3 3.1.4 3.1.5
3.2 3.2.1
3.2.2
3.2.3 3.2.4 3.2.5
4 4.1 4.2
4.3 4.4 4.5
Implementation of CRM
for Fluent Retail
$50,000.00 696 hours
Initialization
$3,760.00 80 hours
Requirement Analysis
$640.00 16 hours
Charter Documentation
$1,200.00 24 hours
Project Initiation
Documents
$1,200.00 24 hours
Submission of documents
$720.00 16 hours
Sign off
$0.00 0 hours
Planning
$4,840.00 88 hours
Project Kick off Meeting
$640.00 8 hours
Activity Listing
$800.00 16 hours
Scheduling of activities
$1,200.00 24 hours
Risk Management
Planning
$2,200.00 40 hours
Plan Approval
$0.00 0 hours
Developing
$36,200.00 440 hours
Design
$11,180.00 160 hours
Selection of design
platform
$1,040.00 16 hours
Outline is made
$1,910.00 24 hours
Design Simulation
$4,240.00 64 hours
Completion of Design
$3,990.00 56 hours
Design Approval
$0.00 0 hours
Development
$25,020.00 280 hours
UI development
$4,300.00 40 hours
Programming the
functions
$7,400.00 72 hours
Integrating the database
$5,720.00 56 hours
Prototyping the
Application
$3,120.00 48 hours
System Development
$4,480.00 64 hours
Closing
$5,200.00 88 hours
Testing and Monitoring
$2,640.00 40 hours
Final Documentation
$1,200.00 24 hours
Submission of documents
$720.00 16 hours
Sign off
$640.00 8 hours
Closed
$0.00 0 hours