Business Development Report: Northstone Ltd. Flyover Project Analysis

Verified

Added on  2023/01/11

|14
|817
|74
Report
AI Summary
This report provides a comprehensive overview of a flyover construction project undertaken by Northstone Ltd. in the UK. It delves into the essential aspects of project management, including business drivers such as resource procurement and project planning, and the project objectives, which aim to reduce travel time. The report outlines expected benefits, estimated costs, and assumptions made during the project. It includes detailed communication plans, work breakdown structures, and a network diagram. Furthermore, it presents a risk register to identify and mitigate potential challenges. References to relevant project management literature are also provided. This report serves as a practical example of project management principles applied to a real-world construction scenario, demonstrating the importance of planning, risk assessment, and communication for successful project execution.
Document Page
Project
management
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Content
Introduction
Business Drivers
Project Objectives
Expected Benefits
Estimated Cost
Assumptions and Constraints
Communication plans
Work based divisions
Network diagram
Risk register
Conclusion
Refernces
Document Page
Introduction
Project management facilitate in taking necessary steps for
managing the project which includes initiation, planning of the
resources required their implementation and monitoring etc. In this
presentation the project of constructing a flyover is taken into
consideration by a UK based constructing company Northstone Ltd.
For managing the project they need to provide the overview o the
project and the business plan etc.
Document Page
Business Drivers
The business drivers are key activities and inputs and for
undertaking this project various activities includes procurement
of resources, planning of the structure of the bridge, setting the
time limit for completing the project on time. Various resources
to be used in the construction include the building material,
funds that to be procured, labour for constructing the project.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Project Objectives
The objective of undertaking this project is to reduce the time of
travelling as the flyover will connect two roads as there is
railway crossing which takes time to travel from one side to
other. With this flyover the waiting time will be reduced. .
Document Page
Expected Benefits
The estimated benefits of undertaking this project is around 40%
of the amount to be taken from the government as the company
has contract with the labour contractor who will provide them the
labour on agreed rated. Similarly they can gather material from
the agreed suppliers which will reduce the chances of impact of
increased prices.
Document Page
Estimated Cost
Estimated cost of undertaking the project is given below:
Particulars Amount (£)
Estimated cost of material 58000
Estimated cost of labour 65000
Estimated indirect cost such as travelling,
electricity, development of the software etc.
25000
Estimated cost of purchasing safety
equipments and taking license
5000
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Assumptions and Constraints
For undertaking the project various assumptions are to be
taken by the project managers. The assumptions that are
related with the project include that in the near future their
will not be any change in the prices of the material and the
labour rates will also be constant.
Document Page
Communication Plans
The communication is very much necessary
for undertaking any project. The company has
to specify the flow of communication for
which the people can communicate among
themselves. Communication would help in
bringing the transparency among the activities
if employees which would benefit the both the
organization and the employees (Kerzner,
2017).
Document Page
Work Breakdown Structure
Work break down structure is a structure in which
the activities which needs to be included into the
project gets breakdown into small activities and
that to into the sequence in which they needs to get
executed. The break down of activities has helped
the project in making it simpler and much clear.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Activity list and network diagram
Activity list is the list which is prepared by the
project in charge stating the activities which
would be including into the completion of the
project. Activities includes the minor to major task
or work which help in contributing into the
completion of the project. Whereas network dialog
refers to the diagram in which the activities are
presented into diagram along with the sequence in
which they need to get performed.
Document Page
Risk register
Risk register is the table which tells the project
holder about the risk which is being associated
with the project. There are many risks which
can get included some of them includes,
financial risks, resources risks, man power
risks and the so on (Burke, 2013).
Document Page
Conclusion
From the presentation presented above, the
proper planning which needs to be taken under
account before starting up a project has been
presented. These may include risk register,
communication plans, network diagrams,
work divisions and the so on.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
REFERENCES
Nicholas, J.M. and Steyn, H., 2017. Project management for
engineering, business and technology. Taylor & Francis.
Gino, F., 2018. The business case for curiosity.
Liu, J., Zhang, N., Kang, C., Kirschen, D. and Xia, Q., 2017.
Cloud energy storage for residential and small commercial
consumers: A business case study. Applied energy, 188,
pp.226-236.
Burke, R., 2013. Project management: planning and control
techniques. New Jersey, USA, 26.
Kerzner, H., 2017. Project management: a systems approach
to planning, scheduling, and controlling. John Wiley &
Sons.
chevron_up_icon
1 out of 14
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]