This assignment presents a case study of the Food Test Lab Project, focusing on its objectives, schedule, and cost-related aspects. The project aimed to establish a food testing laboratory and faced challenges such as schedule changes and cost overruns. The analysis delves into the causes of these issues, including the Fipronil testing, resource shortages, and the need for more accurate project planning and resource allocation. The project also highlights the importance of change management and the incorporation of potential changes during implementation. The document concludes with suggestions for improving future projects, emphasizing the need for more resources, accurate allocation, and a planned approach to change implementation. The study provides a valuable insight into the project management of the Food Test Lab, which can assist students with their studies.
Document Page
Project Management
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Objectives and Priorities
Objectives
The main objective of this
project was to launch the Food
Test lab on 1st July 2019
Apart from that, the objective of
the project was to successfully
complete the Fibronil Testing
Both the project objectives were
successfully met.
Priorities
The Schedule was the main
priority of the project along with
the performance.
The project was completed in
estimated time
This indicates that the project
priorities were met.
Document Page
Changes in project Schedule
There have been certain
changes in the Schedule of the
project
The main contributing event for
the schedule change includes
the Fipronil Testing
One activity needed 4 more
days to complete that resulted
in schedule conflict and changes
in project schedule.
Document Page
Cost Overrun
The Project faced certain cost
overrun.
This is mainly because of the
change in project schedule
Resource shortage is another
contribution event of Cost
Overrun in FTL project
The Figure on the left indicates
the cost Overrun
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Lesson Learnt
Capturing the lesson learnt is considering to be an on going effort of
project implementation
The major lesson learnt associated with the FTL project are as follows-
Accurate Project Planning is required for ensuring that project followed
appropriate specifications
Appropriate budget estimation is quite essential to ensure project
success
Change management should be implemented in a planned manner
Document Page
Suggestion
The suggestions that can be provided on basis of FTL project are as
follows-
The Project should have considered more available resources
Resource allocation should have been more accurate for this project
It is suggested that change implementation of the project follows a
planned approach
It is suggested that project should have a scope for incorporation of any
vital change during project implementation.