Project Management Report: Future Frigates (War Ships) Analysis
VerifiedAdded on 2022/09/26
|20
|2207
|16
Project
AI Summary
This project management report provides a comprehensive analysis of the Future Frigates (War Ships) project. The report is divided into three parts: Part A provides an overview of the project, including the budget, social and economic rationale, key information, scope, estimated costs, time requirements, construction phases, and environmental considerations. Part B focuses on risk analysis, including qualitative and quantitative assessments, and presents a risk matrix. Part C outlines a risk mitigation plan, evaluating identified risks, prioritizing them, and detailing mitigation strategies. The analysis considers factors such as schedule slippage, design flaws, inexperienced workers, and resource management, offering insights into potential challenges and effective solutions. The report also includes a detailed bibliography of the sources consulted.

Running head: PROJECT MANAGEMENT
Future Frigates (War Ships)
Name of the Student
Name of the University
Author’s Note
Future Frigates (War Ships)
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Table of Contents
Part A: Project Overview.................................................................................................................2
A.1 Overall budget for the project...............................................................................................2
A2: Social and economic rationale..............................................................................................2
A3: Key information about the project........................................................................................2
A4: Scope and size.......................................................................................................................3
A5. Budget and estimated cost....................................................................................................4
A6. Time required........................................................................................................................5
A7. Construction elements or phases...........................................................................................6
A8. Environmental costs or benefits............................................................................................7
Part B: Risk analysis........................................................................................................................8
B1. Risk analysis.........................................................................................................................8
B2. Risk matrix..........................................................................................................................11
Part C: Risk mitigation plan..........................................................................................................13
Mitigation strategy.....................................................................................................................15
Bibliography..................................................................................................................................17
PROJECT MANAGEMENT
Table of Contents
Part A: Project Overview.................................................................................................................2
A.1 Overall budget for the project...............................................................................................2
A2: Social and economic rationale..............................................................................................2
A3: Key information about the project........................................................................................2
A4: Scope and size.......................................................................................................................3
A5. Budget and estimated cost....................................................................................................4
A6. Time required........................................................................................................................5
A7. Construction elements or phases...........................................................................................6
A8. Environmental costs or benefits............................................................................................7
Part B: Risk analysis........................................................................................................................8
B1. Risk analysis.........................................................................................................................8
B2. Risk matrix..........................................................................................................................11
Part C: Risk mitigation plan..........................................................................................................13
Mitigation strategy.....................................................................................................................15
Bibliography..................................................................................................................................17

2
PROJECT MANAGEMENT
Part A: Project Overview
A.1 Overall budget for the project
It is found that in order to undertake the project of “Future Frigate”, the government has
approved budget of over $6 billion so that the design activity will incorporate the various needs
of the Australians and for conducting prototyping of ship blocks.
A2: Social and economic rationale
Benefits and drawbacks
The Future Frigate will be helpful in providing Australian defence force with highest
levels of submarines capability and it will further help in setting in place proper naval
shipbuilding. It is considered to be advantageous for the Australian Defence force as they can
detect, track as well as destroy the submarines of enemy (Slocombe 2017). In context to
economic field, it is found that due to construction of Future Frigates, a greater number of jobs
will be generated which will become a significant source of strength for the economy of
Australia (Defence.gov.au 2020). Moreover, the companies that will provide input for the
construction will also generate huge amount of revenue which will further improve the
Australia’s revenue.
On the other hand, it is found that the Government of Australia provides above $6 billion
for proper design and construction of Future Frigates and expenditure of such a huge amount on
a project at once can create some economic challenges for the country and this is considered as a
drawback (Schmidt 2017).
PROJECT MANAGEMENT
Part A: Project Overview
A.1 Overall budget for the project
It is found that in order to undertake the project of “Future Frigate”, the government has
approved budget of over $6 billion so that the design activity will incorporate the various needs
of the Australians and for conducting prototyping of ship blocks.
A2: Social and economic rationale
Benefits and drawbacks
The Future Frigate will be helpful in providing Australian defence force with highest
levels of submarines capability and it will further help in setting in place proper naval
shipbuilding. It is considered to be advantageous for the Australian Defence force as they can
detect, track as well as destroy the submarines of enemy (Slocombe 2017). In context to
economic field, it is found that due to construction of Future Frigates, a greater number of jobs
will be generated which will become a significant source of strength for the economy of
Australia (Defence.gov.au 2020). Moreover, the companies that will provide input for the
construction will also generate huge amount of revenue which will further improve the
Australia’s revenue.
On the other hand, it is found that the Government of Australia provides above $6 billion
for proper design and construction of Future Frigates and expenditure of such a huge amount on
a project at once can create some economic challenges for the country and this is considered as a
drawback (Schmidt 2017).
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
A3: Key information about the project
They various key information that is mainly related with the Future Frigate project are
reflected in the below table:
Criteria Explanation
Budget $6 billion
Time period 2015-2020
Dimension of Future frigates Length -149.9 metres Maximum beam - 20.8
metres
Displacement Full Load 8,800 tonnes
Weapons MU90 torpedos, Mk45 Mod4 5” gun, SM2 &
ESSM missiles and more
Top speed 27+ knots
Accommodation 180 crew including embarked flight with
accommodation as well as services up to 208.
A4: Scope and size
The project scope includes:
Government first pass approval
RFT released
Combat Management System selected
Government Second Pass Approval
Construction
Prototyping of ship blocks in the new shipyard
Combination of Aegis CMS, CEAFAR and the Standard
PROJECT MANAGEMENT
A3: Key information about the project
They various key information that is mainly related with the Future Frigate project are
reflected in the below table:
Criteria Explanation
Budget $6 billion
Time period 2015-2020
Dimension of Future frigates Length -149.9 metres Maximum beam - 20.8
metres
Displacement Full Load 8,800 tonnes
Weapons MU90 torpedos, Mk45 Mod4 5” gun, SM2 &
ESSM missiles and more
Top speed 27+ knots
Accommodation 180 crew including embarked flight with
accommodation as well as services up to 208.
A4: Scope and size
The project scope includes:
Government first pass approval
RFT released
Combat Management System selected
Government Second Pass Approval
Construction
Prototyping of ship blocks in the new shipyard
Combination of Aegis CMS, CEAFAR and the Standard
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
Missile II and Evolved Sea Sparrow
Operations and sustainment
A5. Budget and estimated cost
The estimated cost for designing as well as constructing Future frigates will be around $
6 billion which is showcased with the help of the below figure:
Figure 1: Budget
PROJECT MANAGEMENT
Missile II and Evolved Sea Sparrow
Operations and sustainment
A5. Budget and estimated cost
The estimated cost for designing as well as constructing Future frigates will be around $
6 billion which is showcased with the help of the below figure:
Figure 1: Budget

5
PROJECT MANAGEMENT
(Source: Created by Author)
A6. Time required
The future Frigates commencement starts on 2015 and it is found that the entire work
including design, prototyping, construction as well as project review will be completed by 2020.
The entire schedule is reflected below in the form of Gantt chart.
PROJECT MANAGEMENT
(Source: Created by Author)
A6. Time required
The future Frigates commencement starts on 2015 and it is found that the entire work
including design, prototyping, construction as well as project review will be completed by 2020.
The entire schedule is reflected below in the form of Gantt chart.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
Figure 2: Time needed
(Source: Created by Author)
A7. Construction elements or phases
The various construction elements or activities that are mainly associated with Future
Frigates construction is mainly reflected in the table below:
Activities Duration Start Finish
Government first pass
approval
240 days Fri 01-04-16 Thu 02-03-17
RFT released 140 days Fri 03-03-17 Thu 14-09-17
Combat Management System
selected
200 days Fri 15-09-17 Thu 21-06-18
Government Second Pass
Approval
400 days Fri 22-06-18 Thu 02-01-20
Prototyping of ship blocks
in the new shipyard
150 days Fri 03-01-20 Thu 30-07-20
Combination of Aegis
CMS, CEAFAR and the
Standard
50 days Fri 31-07-20 Thu 08-10-20
Missile II and Evolved Sea
Sparrow
60 days Fri 09-10-20 Thu 31-12-20
Operations and sustainment 40 days Fri 01-01-21 Thu 25-02-21
PROJECT MANAGEMENT
Figure 2: Time needed
(Source: Created by Author)
A7. Construction elements or phases
The various construction elements or activities that are mainly associated with Future
Frigates construction is mainly reflected in the table below:
Activities Duration Start Finish
Government first pass
approval
240 days Fri 01-04-16 Thu 02-03-17
RFT released 140 days Fri 03-03-17 Thu 14-09-17
Combat Management System
selected
200 days Fri 15-09-17 Thu 21-06-18
Government Second Pass
Approval
400 days Fri 22-06-18 Thu 02-01-20
Prototyping of ship blocks
in the new shipyard
150 days Fri 03-01-20 Thu 30-07-20
Combination of Aegis
CMS, CEAFAR and the
Standard
50 days Fri 31-07-20 Thu 08-10-20
Missile II and Evolved Sea
Sparrow
60 days Fri 09-10-20 Thu 31-12-20
Operations and sustainment 40 days Fri 01-01-21 Thu 25-02-21
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
A8. Environmental costs or benefits
Funding mechanism
The entire project of Future Frigates construction was funded by the government. In
addition to this, it is analyzed that due to future Frigates, a number of job opportunities open
which assists in raising money and improving the economic condition of Australia. In addition to
this, the inputs that are delivered to Future Frigates also makes money and it is considered as a
source of money making from the project (Defence.gov.au 2020).
Key stakeholders
The key stakeholders that are associated with the Future Frigates project are listed below:
Project manager
Project planner
Financial manager
HR manager
Contractor
Construction manager
Worker
Civil engineers
PROJECT MANAGEMENT
A8. Environmental costs or benefits
Funding mechanism
The entire project of Future Frigates construction was funded by the government. In
addition to this, it is analyzed that due to future Frigates, a number of job opportunities open
which assists in raising money and improving the economic condition of Australia. In addition to
this, the inputs that are delivered to Future Frigates also makes money and it is considered as a
source of money making from the project (Defence.gov.au 2020).
Key stakeholders
The key stakeholders that are associated with the Future Frigates project are listed below:
Project manager
Project planner
Financial manager
HR manager
Contractor
Construction manager
Worker
Civil engineers

8
PROJECT MANAGEMENT
Part B: Risk analysis
B1. Risk analysis
Qualitative risk analysis
In the below table, qualitative risk analysis method is used as per PMBOK, in order to
determine the risks that are associated with the Future Frigates project.
Risk Id Risk Description Impact (1-5) Probability (1-5)
R1 Schedule
slippage
During the design,
prototyping as well
as construction of
Future Frigates, if
the project
managers are
unable to track the
schedule the
chances of schedule
slippage is quite
high that further
causes delay in the
progress of the
project (Kerzner
2017).
5 4
R2 Improper design If the design of the 5 5
PROJECT MANAGEMENT
Part B: Risk analysis
B1. Risk analysis
Qualitative risk analysis
In the below table, qualitative risk analysis method is used as per PMBOK, in order to
determine the risks that are associated with the Future Frigates project.
Risk Id Risk Description Impact (1-5) Probability (1-5)
R1 Schedule
slippage
During the design,
prototyping as well
as construction of
Future Frigates, if
the project
managers are
unable to track the
schedule the
chances of schedule
slippage is quite
high that further
causes delay in the
progress of the
project (Kerzner
2017).
5 4
R2 Improper design If the design of the 5 5
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
of the project Future Frigate is not
appropriate then it
would be quite
difficult for the
BAE systems for
undertaking
construction with
the Global combat
Ship-Australia
design (Marchewka
2016).
R3 Inexperienced
workers
The workers who
are working for
Future Frigates
construction, if not
experienced then
they will unable to
handle such types
of construction
properly and the
chances of delay
within the project
rises (Almeida,
4 3
PROJECT MANAGEMENT
of the project Future Frigate is not
appropriate then it
would be quite
difficult for the
BAE systems for
undertaking
construction with
the Global combat
Ship-Australia
design (Marchewka
2016).
R3 Inexperienced
workers
The workers who
are working for
Future Frigates
construction, if not
experienced then
they will unable to
handle such types
of construction
properly and the
chances of delay
within the project
rises (Almeida,
4 3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
Hankins and
Williams 2017).
Quantitative risk analysis
It is found that quantitative risk analysis method is used as per PMBOK, in order to
determine the risks that are associated with the Future Frigates project.
Id Risk/
opportunity
Description Probability Cost impact Expected
monetary
value
1 Improper use
of resources
If the resources that is
mainly associated
with the future Frigate
project is not
effectively used
during project
progress then more
resources will be
required that will
further enhance the
total cost of the
project (Martens and
Carvalho 2017).
5% $2,000,000 $100,000
2 Scope creep Due to scope creep, a
number of new
10% $3,000,000 300,000
PROJECT MANAGEMENT
Hankins and
Williams 2017).
Quantitative risk analysis
It is found that quantitative risk analysis method is used as per PMBOK, in order to
determine the risks that are associated with the Future Frigates project.
Id Risk/
opportunity
Description Probability Cost impact Expected
monetary
value
1 Improper use
of resources
If the resources that is
mainly associated
with the future Frigate
project is not
effectively used
during project
progress then more
resources will be
required that will
further enhance the
total cost of the
project (Martens and
Carvalho 2017).
5% $2,000,000 $100,000
2 Scope creep Due to scope creep, a
number of new
10% $3,000,000 300,000

11
PROJECT MANAGEMENT
facilities will be
added within the
future Frigates that is
considered to be
advantageous
(Slocombe 2017).
B2. Risk matrix
Risk matrix for qualitative analysis
Consequences
Negligible
1
Minor
2
Moderate
3
Major
4
Catastrophic
5
Likelihood
Almost
certain
5
Improper
design of the
project
Likely
4
Schedule
slippage
Possible
3
Inexperienced
workers
Unlikely
2
Rare
PROJECT MANAGEMENT
facilities will be
added within the
future Frigates that is
considered to be
advantageous
(Slocombe 2017).
B2. Risk matrix
Risk matrix for qualitative analysis
Consequences
Negligible
1
Minor
2
Moderate
3
Major
4
Catastrophic
5
Likelihood
Almost
certain
5
Improper
design of the
project
Likely
4
Schedule
slippage
Possible
3
Inexperienced
workers
Unlikely
2
Rare
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 20

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.