Data Analysis Project: Gantt Chart and Project Plan

Verified

Added on  2025/04/07

|3
|253
|62
AI Summary
Desklib provides past papers and solved assignments for students. This project uses Gantt charts for data analysis.
Document Page
MS Project
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Task Mode Task Name Duration Start Finish Predecessors
Auto
Scheduled Gantt chart 206 days Mon 05-11-
18
Wed 29-05-
19
Auto
Scheduled Plan Review 26 days Mon 05-11-
18
Fri 30-11-
18
Auto
Scheduled Specify Research Questions 6 days Mon 05-11-
18
Sat 10-11-
18
Auto
Scheduled Develop Plan Protocol 11 days Sun 11-11-
18
Wed 21-11-
18 3
Auto
Scheduled Validate Review Protocol 9 days Thu 22-11-
18 Fri 30-11-18 4
Auto
Scheduled Conduct Review 31 days Sat 01-12-
18
Mon 31-12-
18
Auto
Scheduled Identify Relevant Research 8 days Sat 01-12-
18
Sat 08-12-
18
Auto
Scheduled Select Primary Studies 7 days Sun 09-12-
18
Sat 15-12-
18 7
Auto
Scheduled Access Study Quality 5 days Sun 16-12-
18
Thu 20-12-
18 8
Auto
Scheduled Extract Required Data 6 days Fri 21-12-
18
Wed 26-12-
18 9
Auto
Scheduled Synthesis Data 5 days Thu 27-12-
18
Mon 31-12-
18 10
Auto
Scheduled Document Review 33 days Tue 01-01-
19
Sat 02-02-
19
Auto
Scheduled Write Review Report 20 days Tue 01-01-
19
Sun 20-01-
19 11
Auto
Scheduled Validate Rport 13 days Mon 21-01-
19
Sat 02-02-
19 13
Auto
Scheduled Final review 84 days Thu 07-03-
19
Wed 29-05-
19
Auto
Scheduled Strategies Project 8 days Thu 07-03-
19
Thu 14-03-
19 14
Auto
Scheduled
Literature Review research
for a suitable solution 20 days Fri 15-03-
19
Wed 03-04-
19 16
Auto
Scheduled
Checking the feasibility of
research and solution 7 days Thu 04-04-
19
Wed 10-04-
19 17
Auto
Scheduled Financial and resource check 7 days Thu 11-04-
19
Wed 17-04-
19 18
Auto
Scheduled
A rough report for reality
check 12 days Thu 18-04-
19
Mon 29-04-
19 19
Auto
Scheduled
A Symmetric literature
review 20 days Tue 30-04-
19
Sun 19-05-
19 20
Auto
Scheduled Final Report 10 days Mon 20-05-
19
Wed 29-05-
19 21
Document Page
Figure 1: Gantt chart