Gothaer Insurance Group GCOM Project 19: Request for Proposal (RFP)
VerifiedAdded on  2022/09/15
|27
|4194
|31
Project
AI Summary
This document is a Request for Proposal (RFP) for the GCOM Project 19, undertaken for Gothaer Insurance Group. The project aims to develop a digital policy system utilizing an agile SCRUM methodology to allow customers to create customized insurance contracts. The RFP outlines the project description, scope of services, and detailed timeline with associated constraints. It includes a comprehensive budget breakdown, resource and technology requirements, and evaluation criteria. The document also addresses potential risks and provides references. The project is divided into pre-planning, detailed planning, agile setup, agile sprints, and deployment/closure phases. The sprints involve the development of various contract types, including individual, group, and family contracts, as well as the policy and distribution systems. The project's success hinges on adhering to the specified timeline and budget, with a focus on delivering a robust and adaptable insurance policy system.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

GCOM Project
19
Request for Proposal (RFP)
19
Request for Proposal (RFP)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Request for Proposal (RFP)
Table of Contents
Introduction...........................................................................................................................................2
Background.......................................................................................................................................2
Purpose..............................................................................................................................................2
Project Description................................................................................................................................2
Scope of Services..................................................................................................................................3
Project Methodology.............................................................................................................................3
Timeline – Constraints..........................................................................................................................4
Budget Constraints..............................................................................................................................11
Resource Requirements.......................................................................................................................15
Technology Requirements...................................................................................................................23
Evaluation Criteria...............................................................................................................................24
Possible Risks......................................................................................................................................24
References...........................................................................................................................................25
1
Table of Contents
Introduction...........................................................................................................................................2
Background.......................................................................................................................................2
Purpose..............................................................................................................................................2
Project Description................................................................................................................................2
Scope of Services..................................................................................................................................3
Project Methodology.............................................................................................................................3
Timeline – Constraints..........................................................................................................................4
Budget Constraints..............................................................................................................................11
Resource Requirements.......................................................................................................................15
Technology Requirements...................................................................................................................23
Evaluation Criteria...............................................................................................................................24
Possible Risks......................................................................................................................................24
References...........................................................................................................................................25
1

Request for Proposal (RFP)
Introduction
Background
The project is being carried out for Gothaer Insurance Group and it includes the development
of a policy system that does not require an agent to process the insurance policies and
contracts for the customers. It will be a digital system that will allow the customers to create
customized contracts as per the requirements and the applicable rules (Gotz et al., 2018).
The organization has decided to adopt agile methodology as the preferred approach and the
SCRUM development process will be used for the project development. The organization
does not have the resources and skills for the agile processes and it will be cost-effective to
outsource the process rather than carrying out the in-house development.
Purpose
The document is the Request for Proposal (RFP) document that comprises of the resource and
technology requirements for the project as per the applicable time & cost constraints.
Project Description
The project includes the modelling of the insurance system for the GoSMART program that
will comprise of the tariffs and underwriting rules. The component that will be primarily
modelled is GCOM and it will include the policy system and distributed system for the
process. The user will be able to develop the customized contracts in accordance with the
rules and standards (Rajasekaran, 2015). The approval and review cycle will be integrated
and the exception handling processes will be created as well.
The basic structure of the product machine has been shown in the image below.
2
Introduction
Background
The project is being carried out for Gothaer Insurance Group and it includes the development
of a policy system that does not require an agent to process the insurance policies and
contracts for the customers. It will be a digital system that will allow the customers to create
customized contracts as per the requirements and the applicable rules (Gotz et al., 2018).
The organization has decided to adopt agile methodology as the preferred approach and the
SCRUM development process will be used for the project development. The organization
does not have the resources and skills for the agile processes and it will be cost-effective to
outsource the process rather than carrying out the in-house development.
Purpose
The document is the Request for Proposal (RFP) document that comprises of the resource and
technology requirements for the project as per the applicable time & cost constraints.
Project Description
The project includes the modelling of the insurance system for the GoSMART program that
will comprise of the tariffs and underwriting rules. The component that will be primarily
modelled is GCOM and it will include the policy system and distributed system for the
process. The user will be able to develop the customized contracts in accordance with the
rules and standards (Rajasekaran, 2015). The approval and review cycle will be integrated
and the exception handling processes will be created as well.
The basic structure of the product machine has been shown in the image below.
2

Request for Proposal (RFP)
GCOM Process (Gotz et al., 2018)
Scope of Services
The project team will carry out the processes and services as per the agile SCRUM
methodology. The team will not be essentially carrying out the user interface design and set-
up. The basic design will be developed to carry out the coding and algorithm writing
accordingly (Kalyani & Mehta, 2019).
The scope will include the requirement assessment as per the project information, setting up
of the environment, and execution of the sprints. These sprints will include the programming
activities for the development of the backend that will comprise of the tariffs and contract
rules and guidelines. The exception handling, approval, and review scenarios will be
accordingly developed (Ashbacher, 2010).
Project Methodology
The methodology that has been decided to be used for the project is agile SCRUM
methodology. The basic flow of the methodology has been shown in the figure below.
Agile SCRUM process
The methodology has been preferred over the Waterfall model as there will be numerous
changes that may appear during the integration of GCOM in the GoSMART program.
Waterfall follows a traditional approach wherein the incorporation of the changes may not be
3
GCOM Process (Gotz et al., 2018)
Scope of Services
The project team will carry out the processes and services as per the agile SCRUM
methodology. The team will not be essentially carrying out the user interface design and set-
up. The basic design will be developed to carry out the coding and algorithm writing
accordingly (Kalyani & Mehta, 2019).
The scope will include the requirement assessment as per the project information, setting up
of the environment, and execution of the sprints. These sprints will include the programming
activities for the development of the backend that will comprise of the tariffs and contract
rules and guidelines. The exception handling, approval, and review scenarios will be
accordingly developed (Ashbacher, 2010).
Project Methodology
The methodology that has been decided to be used for the project is agile SCRUM
methodology. The basic flow of the methodology has been shown in the figure below.
Agile SCRUM process
The methodology has been preferred over the Waterfall model as there will be numerous
changes that may appear during the integration of GCOM in the GoSMART program.
Waterfall follows a traditional approach wherein the incorporation of the changes may not be
3
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Request for Proposal (RFP)
readily possible (Carvalho & Mello, 2011). The SCRUM methodology will allow the
development and project processes to be conducted in sprints. This will make sure that any of
the modifications and improvements are correctly implemented.
Timeline – Constraints
The resources carrying out the project will be required to adhere with the following schedule.
The pre-planning and detailed planning will be done by the internal team. The Business
Advisor, Data Scientist, and Joe Freya (Scrum Master) will be the internal resources that will
remain involved in the subsequent phases as well (Tkachenko & Sivokoz, 2017).
WBS Task Name Duration Start Finish Successors Predecessors
1 GCOM Project 342 days
Tue
04-12-
18
Wed
25-03-
20
1.1 Pre-Planning Processes 39 days
Tue
04-12-
18
Fri 25-
01-19
1.1.1 GoSMART Program -
Business Case Analysis 11 days
Tue
04-12-
18
Tue 18-
12-18 4,5,24
1.1.2
Determination of the role
of GCOM in GoSMART
project
7 days
Wed
19-12-
18
Thu 27-
12-18 8 3
1.1.3 Current status analysis 9 days
Wed
19-12-
18
Mon 31-
12-18 6 3
1.1.4
Evaluation of
methodologies -
Agile/Waterfall
11 days
Tue
01-01-
19
Tue 15-
01-19 7,8 5
1.1.5 Milestone 1: Project
methodology 0 days
Tue
15-01-
19
Tue 15-
01-19 6
1.1.6 Staffing Requirements 8 days Wed Fri 25- 9 4,6
4
readily possible (Carvalho & Mello, 2011). The SCRUM methodology will allow the
development and project processes to be conducted in sprints. This will make sure that any of
the modifications and improvements are correctly implemented.
Timeline – Constraints
The resources carrying out the project will be required to adhere with the following schedule.
The pre-planning and detailed planning will be done by the internal team. The Business
Advisor, Data Scientist, and Joe Freya (Scrum Master) will be the internal resources that will
remain involved in the subsequent phases as well (Tkachenko & Sivokoz, 2017).
WBS Task Name Duration Start Finish Successors Predecessors
1 GCOM Project 342 days
Tue
04-12-
18
Wed
25-03-
20
1.1 Pre-Planning Processes 39 days
Tue
04-12-
18
Fri 25-
01-19
1.1.1 GoSMART Program -
Business Case Analysis 11 days
Tue
04-12-
18
Tue 18-
12-18 4,5,24
1.1.2
Determination of the role
of GCOM in GoSMART
project
7 days
Wed
19-12-
18
Thu 27-
12-18 8 3
1.1.3 Current status analysis 9 days
Wed
19-12-
18
Mon 31-
12-18 6 3
1.1.4
Evaluation of
methodologies -
Agile/Waterfall
11 days
Tue
01-01-
19
Tue 15-
01-19 7,8 5
1.1.5 Milestone 1: Project
methodology 0 days
Tue
15-01-
19
Tue 15-
01-19 6
1.1.6 Staffing Requirements 8 days Wed Fri 25- 9 4,6
4

Request for Proposal (RFP)
16-01-
19 01-19
1.1.7 Milestone 2: Staffing
Needs 0 days Fri 25-
01-19
Fri 25-
01-19 11 8
1.2 Detailed Planning Process 43 days
Mon
28-01-
19
Wed
27-03-
19
1.2.1 Analysis of project stages
- 1 and 2 12 days
Mon
28-01-
19
Tue 12-
02-19 12,14,15,16 9
1.2.2 Scope Statement 9 days
Wed
13-02-
19
Mon 25-
02-19 14,15,16 11
1.2.3 Project Estimates 9 days
Tue
26-02-
19
Fri 08-
03-19 17
1.2.3.1 Project schedule 9 days
Tue
26-02-
19
Fri 08-
03-19 17 11,12
1.2.3.2 Project budget 9 days
Tue
26-02-
19
Fri 08-
03-19 17 11,12
1.2.3.3 Project scope 9 days
Tue
26-02-
19
Fri 08-
03-19 11,12
1.2.4 Milestone 3: Project
Estimates 0 days Fri 08-
03-19
Fri 08-
03-19 18,19,20 13,14,15
1.2.5 Planning of Project
Areas 13 days
Mon
11-03-
19
Wed
27-03-
19
17
1.2.5.1 Risk Management &
Handling
6 days Mon
11-03-
Mon 18-
03-19
21 17
5
16-01-
19 01-19
1.1.7 Milestone 2: Staffing
Needs 0 days Fri 25-
01-19
Fri 25-
01-19 11 8
1.2 Detailed Planning Process 43 days
Mon
28-01-
19
Wed
27-03-
19
1.2.1 Analysis of project stages
- 1 and 2 12 days
Mon
28-01-
19
Tue 12-
02-19 12,14,15,16 9
1.2.2 Scope Statement 9 days
Wed
13-02-
19
Mon 25-
02-19 14,15,16 11
1.2.3 Project Estimates 9 days
Tue
26-02-
19
Fri 08-
03-19 17
1.2.3.1 Project schedule 9 days
Tue
26-02-
19
Fri 08-
03-19 17 11,12
1.2.3.2 Project budget 9 days
Tue
26-02-
19
Fri 08-
03-19 17 11,12
1.2.3.3 Project scope 9 days
Tue
26-02-
19
Fri 08-
03-19 11,12
1.2.4 Milestone 3: Project
Estimates 0 days Fri 08-
03-19
Fri 08-
03-19 18,19,20 13,14,15
1.2.5 Planning of Project
Areas 13 days
Mon
11-03-
19
Wed
27-03-
19
17
1.2.5.1 Risk Management &
Handling
6 days Mon
11-03-
Mon 18-
03-19
21 17
5

Request for Proposal (RFP)
19
1.2.5.2 Stakeholders and
Communications 7 days
Mon
11-03-
19
Tue 19-
03-19 21 17
1.2.5.3 Quality & Integration 6 days
Wed
20-03-
19
Wed 27-
03-19 22 19,20
1.2.6 Milestone 4: Project Plan 0 days
Wed
27-03-
19
Wed 27-
03-19 24 21
1.3 Agile Set-up 39 days
Thu
28-03-
19
Tue 21-
05-19
1.3.1
Determination of the
project requirements - Product
Backlog
13 days
Thu
28-03-
19
Mon 15-
04-19 25,26 22,3
1.3.2
Procurement of tools and
configurations - Workstation
Set-up
17 days
Tue
16-04-
19
Wed 08-
05-19 26 24
1.3.3 Development of meeting
and communication schedule 9 days
Thu
09-05-
19
Tue 21-
05-19 27 24,25
1.3.4 Milestone 5: Agile Set-up 0 days
Tue
21-05-
19
Tue 21-
05-19 30 26
1.4 Agile Sprints 167 days
Wed
22-05-
19
Thu 09-
01-20
1.4.1 Sprint 1 16 days
Wed
22-05-
19
Wed
12-06-
19
1.4.1.1 Product Machine - Basic
Design
5 days Wed
22-05-
Tue 28- 31 27
6
19
1.2.5.2 Stakeholders and
Communications 7 days
Mon
11-03-
19
Tue 19-
03-19 21 17
1.2.5.3 Quality & Integration 6 days
Wed
20-03-
19
Wed 27-
03-19 22 19,20
1.2.6 Milestone 4: Project Plan 0 days
Wed
27-03-
19
Wed 27-
03-19 24 21
1.3 Agile Set-up 39 days
Thu
28-03-
19
Tue 21-
05-19
1.3.1
Determination of the
project requirements - Product
Backlog
13 days
Thu
28-03-
19
Mon 15-
04-19 25,26 22,3
1.3.2
Procurement of tools and
configurations - Workstation
Set-up
17 days
Tue
16-04-
19
Wed 08-
05-19 26 24
1.3.3 Development of meeting
and communication schedule 9 days
Thu
09-05-
19
Tue 21-
05-19 27 24,25
1.3.4 Milestone 5: Agile Set-up 0 days
Tue
21-05-
19
Tue 21-
05-19 30 26
1.4 Agile Sprints 167 days
Wed
22-05-
19
Thu 09-
01-20
1.4.1 Sprint 1 16 days
Wed
22-05-
19
Wed
12-06-
19
1.4.1.1 Product Machine - Basic
Design
5 days Wed
22-05-
Tue 28- 31 27
6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Request for Proposal (RFP)
19 05-19
1.4.1.2 Development of Rules 7 days
Wed
29-05-
19
Thu 06-
06-19 32 30
1.4.1.3 Test & Review 4 days Fri 07-
06-19
Wed 12-
06-19 33,35 31
1.4.1.4 Milestone 6: Basic
Design 0 days
Wed
12-06-
19
Wed 12-
06-19 36 32
1.4.2 Sprint 2 19 days
Thu
13-06-
19
Tue 09-
07-19
1.4.2.1 Refinements in Design 4 days
Thu
13-06-
19
Tue 18-
06-19 32
1.4.2.2 Insurance Contracts -
Individual 16 days
Thu
13-06-
19
Thu 04-
07-19 37 33
1.4.2.3 Test & Review 3 days Fri 05-
07-19
Tue 09-
07-19 38 36
1.4.2.4 Milestone 7: Individual
Contracts 0 days
Tue
09-07-
19
Tue 09-
07-19 40 37
1.4.3 Sprint 3 23 days
Wed
10-07-
19
Fri 09-
08-19
1.4.3.1 Refinements in
Individual Contracts 4 days
Wed
10-07-
19
Mon 15-
07-19 41 38
1.4.3.2 Insurance Contracts -
Groups & Family 16 days
Tue
16-07-
19
Tue 06-
08-19 42 40
1.4.3.3 Test & Review 3 days Wed Fri 09- 43 41
7
19 05-19
1.4.1.2 Development of Rules 7 days
Wed
29-05-
19
Thu 06-
06-19 32 30
1.4.1.3 Test & Review 4 days Fri 07-
06-19
Wed 12-
06-19 33,35 31
1.4.1.4 Milestone 6: Basic
Design 0 days
Wed
12-06-
19
Wed 12-
06-19 36 32
1.4.2 Sprint 2 19 days
Thu
13-06-
19
Tue 09-
07-19
1.4.2.1 Refinements in Design 4 days
Thu
13-06-
19
Tue 18-
06-19 32
1.4.2.2 Insurance Contracts -
Individual 16 days
Thu
13-06-
19
Thu 04-
07-19 37 33
1.4.2.3 Test & Review 3 days Fri 05-
07-19
Tue 09-
07-19 38 36
1.4.2.4 Milestone 7: Individual
Contracts 0 days
Tue
09-07-
19
Tue 09-
07-19 40 37
1.4.3 Sprint 3 23 days
Wed
10-07-
19
Fri 09-
08-19
1.4.3.1 Refinements in
Individual Contracts 4 days
Wed
10-07-
19
Mon 15-
07-19 41 38
1.4.3.2 Insurance Contracts -
Groups & Family 16 days
Tue
16-07-
19
Tue 06-
08-19 42 40
1.4.3.3 Test & Review 3 days Wed Fri 09- 43 41
7

Request for Proposal (RFP)
07-08-
19 08-19
1.4.3.4 Milestone 8:
Group/Family Contracts 0 days Fri 09-
08-19
Fri 09-
08-19 45 42
1.4.4 Sprint 4 21 days
Mon
12-08-
19
Mon
09-09-
19
1.4.4.1 Modifications &
Changes 4 days
Mon
12-08-
19
Thu 15-
08-19 46 43
1.4.4.2 Policy System - Filters
& Algorithms 14 days Fri 16-
08-19
Wed 04-
09-19 47 45
1.4.4.3 Test & Review 3 days
Thu
05-09-
19
Mon 09-
09-19 48,50 46
1.4.4.4 Milestone 9: Policy
System 0 days
Mon
09-09-
19
Mon 09-
09-19 47
1.4.5 Sprint 5 21 days
Tue
10-09-
19
Tue 08-
10-19
1.4.5.1 Modifications &
Changes 4 days
Tue
10-09-
19
Fri 13-
09-19 51 47
1.4.5.2 Distribution System -
Filters & Algorithms 14 days
Mon
16-09-
19
Thu 03-
10-19 52 50
1.4.5.3 Test & Review 3 days Fri 04-
10-19
Tue 08-
10-19 53 51
1.4.5.4 Milestone 10:
Distribution System 0 days
Tue
08-10-
19
Tue 08-
10-19 55 52
8
07-08-
19 08-19
1.4.3.4 Milestone 8:
Group/Family Contracts 0 days Fri 09-
08-19
Fri 09-
08-19 45 42
1.4.4 Sprint 4 21 days
Mon
12-08-
19
Mon
09-09-
19
1.4.4.1 Modifications &
Changes 4 days
Mon
12-08-
19
Thu 15-
08-19 46 43
1.4.4.2 Policy System - Filters
& Algorithms 14 days Fri 16-
08-19
Wed 04-
09-19 47 45
1.4.4.3 Test & Review 3 days
Thu
05-09-
19
Mon 09-
09-19 48,50 46
1.4.4.4 Milestone 9: Policy
System 0 days
Mon
09-09-
19
Mon 09-
09-19 47
1.4.5 Sprint 5 21 days
Tue
10-09-
19
Tue 08-
10-19
1.4.5.1 Modifications &
Changes 4 days
Tue
10-09-
19
Fri 13-
09-19 51 47
1.4.5.2 Distribution System -
Filters & Algorithms 14 days
Mon
16-09-
19
Thu 03-
10-19 52 50
1.4.5.3 Test & Review 3 days Fri 04-
10-19
Tue 08-
10-19 53 51
1.4.5.4 Milestone 10:
Distribution System 0 days
Tue
08-10-
19
Tue 08-
10-19 55 52
8

Request for Proposal (RFP)
1.4.6 Sprint 6 26 days
Wed
09-10-
19
Wed
13-11-
19
1.4.6.1 Modifications &
Changes 5 days
Wed
09-10-
19
Tue 15-
10-19 56 53
1.4.6.2 Customized Contracts 8 days
Wed
16-10-
19
Fri 25-
10-19 57 55
1.4.6.3 Contract Review &
Approval Cycle 10 days
Mon
28-10-
19
Fri 08-
11-19 58 56
1.4.6.4 Test & Review 3 days
Mon
11-11-
19
Wed 13-
11-19 59 57
1.4.6.5 Milestone 11: Review &
Approval Cycle 0 days
Wed
13-11-
19
Wed 13-
11-19 61 58
1.4.7 Sprint 7 22 days
Thu
14-11-
19
Fri 13-
12-19
1.4.7.1 Modifications &
Changes 3 days
Thu
14-11-
19
Mon 18-
11-19 62 59
1.4.7.2 Exception Handling
Rules - Contract Building 8 days
Tue
19-11-
19
Thu 28-
11-19 63 61
1.4.7.3 Exception Handling
Rules - Tariffs 8 days Fri 29-
11-19
Tue 10-
12-19 64 62
1.4.7.4 Test & Review 3 days
Wed
11-12-
19
Fri 13-
12-19 65 63
1.4.7.5 Milestone 12: Rules 0 days Fri 13- Fri 13- 67 64
9
1.4.6 Sprint 6 26 days
Wed
09-10-
19
Wed
13-11-
19
1.4.6.1 Modifications &
Changes 5 days
Wed
09-10-
19
Tue 15-
10-19 56 53
1.4.6.2 Customized Contracts 8 days
Wed
16-10-
19
Fri 25-
10-19 57 55
1.4.6.3 Contract Review &
Approval Cycle 10 days
Mon
28-10-
19
Fri 08-
11-19 58 56
1.4.6.4 Test & Review 3 days
Mon
11-11-
19
Wed 13-
11-19 59 57
1.4.6.5 Milestone 11: Review &
Approval Cycle 0 days
Wed
13-11-
19
Wed 13-
11-19 61 58
1.4.7 Sprint 7 22 days
Thu
14-11-
19
Fri 13-
12-19
1.4.7.1 Modifications &
Changes 3 days
Thu
14-11-
19
Mon 18-
11-19 62 59
1.4.7.2 Exception Handling
Rules - Contract Building 8 days
Tue
19-11-
19
Thu 28-
11-19 63 61
1.4.7.3 Exception Handling
Rules - Tariffs 8 days Fri 29-
11-19
Tue 10-
12-19 64 62
1.4.7.4 Test & Review 3 days
Wed
11-12-
19
Fri 13-
12-19 65 63
1.4.7.5 Milestone 12: Rules 0 days Fri 13- Fri 13- 67 64
9
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Request for Proposal (RFP)
12-19 12-19
1.4.8 Sprint 8 19 days
Mon
16-12-
19
Thu 09-
01-20
1.4.8.1 Integration of the rules
and back-end processes 11 days
Mon
16-12-
19
Mon 30-
12-19 68 65
1.4.8.2 Final verifications &
Validations 8 days
Tue
31-12-
19
Thu 09-
01-20 69 67
1.4.8.3 Milestone 13: Integrated
product machine 0 days
Thu
09-01-
20
Thu 09-
01-20 71 68
1.5 Deployment & Closure 54 days Fri 10-
01-20
Wed
25-03-
20
1.5.1 Deployment with Alpha &
Beta Systems 21 days Fri 10-
01-20
Fri 07-
02-20 72 69
1.5.2 Reflection & Performance
measurement 12 days
Mon
10-02-
20
Tue 25-
02-20 73 71
1.5.3 Closure documentation 21 days
Wed
26-02-
20
Wed 25-
03-20 74 72
1.5.4 Milestone 14: Project
Closure 0 days
Wed
25-03-
20
Wed 25-
03-20 73
Budget Constraints
It will be required that the strict budget constraints are followed throughout the project. The
estimation of these costs has been done keeping the probable changes in the GCOM
integration and the associated risks in to consideration (Sharma & Bali, 2018).
10
12-19 12-19
1.4.8 Sprint 8 19 days
Mon
16-12-
19
Thu 09-
01-20
1.4.8.1 Integration of the rules
and back-end processes 11 days
Mon
16-12-
19
Mon 30-
12-19 68 65
1.4.8.2 Final verifications &
Validations 8 days
Tue
31-12-
19
Thu 09-
01-20 69 67
1.4.8.3 Milestone 13: Integrated
product machine 0 days
Thu
09-01-
20
Thu 09-
01-20 71 68
1.5 Deployment & Closure 54 days Fri 10-
01-20
Wed
25-03-
20
1.5.1 Deployment with Alpha &
Beta Systems 21 days Fri 10-
01-20
Fri 07-
02-20 72 69
1.5.2 Reflection & Performance
measurement 12 days
Mon
10-02-
20
Tue 25-
02-20 73 71
1.5.3 Closure documentation 21 days
Wed
26-02-
20
Wed 25-
03-20 74 72
1.5.4 Milestone 14: Project
Closure 0 days
Wed
25-03-
20
Wed 25-
03-20 73
Budget Constraints
It will be required that the strict budget constraints are followed throughout the project. The
estimation of these costs has been done keeping the probable changes in the GCOM
integration and the associated risks in to consideration (Sharma & Bali, 2018).
10

Request for Proposal (RFP)
WBS Task Name Duration Start Finish Cost
11
WBS Task Name Duration Start Finish Cost
11

Request for Proposal (RFP)
1 GCOM Project 342 days Tue 04-12-18 Wed 25-03-20 $499,936.00
1.1 Pre-Planning
Processes 39 days Tue 04-12-18 Fri 25-01-19 $48,312.00
1.1.1 GoSMART Program
- Business Case Analysis 11 days Tue 04-12-18 Tue 18-12-18 $15,576.00
1.1.2
Determination of the
role of GCOM in
GoSMART project
7 days Wed 19-12-18 Thu 27-12-18 $5,152.00
1.1.3 Current status
analysis 9 days Wed 19-12-18 Mon 31-12-18 $6,120.00
1.1.4
Evaluation of
methodologies -
Agile/Waterfall
11 days Tue 01-01-19 Tue 15-01-19 $15,576.00
1.1.5 Milestone 1: Project
methodology 0 days Tue 15-01-19 Tue 15-01-19 $0.00
1.1.6 Staffing
Requirements 8 days Wed 16-01-19 Fri 25-01-19 $5,888.00
1.1.7 Milestone 2: Staffing
Needs 0 days Fri 25-01-19 Fri 25-01-19 $0.00
1.2 Detailed Planning
Process 43 days Mon 28-01-19 Wed 27-03-19 $40,616.00
1.2.1 Analysis of project
stages - 1 and 2 12 days Mon 28-01-19 Tue 12-02-19 $8,160.00
1.2.2 Scope Statement 9 days Wed 13-02-19 Mon 25-02-19 $6,120.00
1.2.3 Project Estimates 9 days Tue 26-02-19 Fri 08-03-19 $12,744.00
1.2.3.
1 Project schedule 9 days Tue 26-02-19 Fri 08-03-19 $6,624.00
1.2.3.
2 Project budget 9 days Tue 26-02-19 Fri 08-03-19 $6,120.00
1.2.4 Milestone 3: Project
Estimates 0 days Fri 08-03-19 Fri 08-03-19 $0.00
1.2.5 Planning of Project 13 days Mon 11-03-19 Wed 27-03-19 $13,592.00
12
1 GCOM Project 342 days Tue 04-12-18 Wed 25-03-20 $499,936.00
1.1 Pre-Planning
Processes 39 days Tue 04-12-18 Fri 25-01-19 $48,312.00
1.1.1 GoSMART Program
- Business Case Analysis 11 days Tue 04-12-18 Tue 18-12-18 $15,576.00
1.1.2
Determination of the
role of GCOM in
GoSMART project
7 days Wed 19-12-18 Thu 27-12-18 $5,152.00
1.1.3 Current status
analysis 9 days Wed 19-12-18 Mon 31-12-18 $6,120.00
1.1.4
Evaluation of
methodologies -
Agile/Waterfall
11 days Tue 01-01-19 Tue 15-01-19 $15,576.00
1.1.5 Milestone 1: Project
methodology 0 days Tue 15-01-19 Tue 15-01-19 $0.00
1.1.6 Staffing
Requirements 8 days Wed 16-01-19 Fri 25-01-19 $5,888.00
1.1.7 Milestone 2: Staffing
Needs 0 days Fri 25-01-19 Fri 25-01-19 $0.00
1.2 Detailed Planning
Process 43 days Mon 28-01-19 Wed 27-03-19 $40,616.00
1.2.1 Analysis of project
stages - 1 and 2 12 days Mon 28-01-19 Tue 12-02-19 $8,160.00
1.2.2 Scope Statement 9 days Wed 13-02-19 Mon 25-02-19 $6,120.00
1.2.3 Project Estimates 9 days Tue 26-02-19 Fri 08-03-19 $12,744.00
1.2.3.
1 Project schedule 9 days Tue 26-02-19 Fri 08-03-19 $6,624.00
1.2.3.
2 Project budget 9 days Tue 26-02-19 Fri 08-03-19 $6,120.00
1.2.4 Milestone 3: Project
Estimates 0 days Fri 08-03-19 Fri 08-03-19 $0.00
1.2.5 Planning of Project 13 days Mon 11-03-19 Wed 27-03-19 $13,592.00
12
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Request for Proposal (RFP)
Areas
1.2.5.
1
Risk Management
& Handling 6 days Mon 11-03-19 Mon 18-03-19 $4,416.00
1.2.5.
2
Stakeholders and
Communications 7 days Mon 11-03-19 Tue 19-03-19 $4,760.00
1.2.5.
3
Quality &
Integration 6 days Wed 20-03-19 Wed 27-03-19 $4,416.00
1.2.6 Milestone 4: Project
Plan 0 days Wed 27-03-19 Wed 27-03-19 $0.00
1.3 Agile Set-up 39 days Thu 28-03-19 Tue 21-05-19 $57,960.00
1.3.1
Determination of the
project requirements -
Product Backlog
13 days Thu 28-03-19 Mon 15-04-19 $33,384.00
1.3.2
Procurement of tools
and configurations -
Workstation Set-up
17 days Tue 16-04-19 Wed 08-05-19 $17,952.00
1.3.3
Development of
meeting and
communication schedule
9 days Thu 09-05-19 Tue 21-05-19 $6,624.00
1.3.4 Milestone 5: Agile
Set-up 0 days Tue 21-05-19 Tue 21-05-19 $0.00
1.4 Agile Sprints 167 days Wed 22-05-19 Thu 09-01-20 $256,784.00
1.4.1 Sprint 1 16 days Wed 22-05-19 Wed 12-06-19 $22,128.00
1.4.1.
1
Product Machine -
Basic Design 5 days Wed 22-05-19 Tue 28-05-19 $2,640.00
1.4.1.
2
Development of
Rules 7 days Wed 29-05-19 Thu 06-06-19 $10,528.00
1.4.1.
3 Test & Review 4 days Fri 07-06-19 Wed 12-06-19 $8,960.00
1.4.1.
4
Milestone 6: Basic
Design 0 days Wed 12-06-19 Wed 12-06-19 $0.00
1.4.2 Sprint 2 19 days Thu 13-06-19 Tue 09-07-19 $27,000.00
13
Areas
1.2.5.
1
Risk Management
& Handling 6 days Mon 11-03-19 Mon 18-03-19 $4,416.00
1.2.5.
2
Stakeholders and
Communications 7 days Mon 11-03-19 Tue 19-03-19 $4,760.00
1.2.5.
3
Quality &
Integration 6 days Wed 20-03-19 Wed 27-03-19 $4,416.00
1.2.6 Milestone 4: Project
Plan 0 days Wed 27-03-19 Wed 27-03-19 $0.00
1.3 Agile Set-up 39 days Thu 28-03-19 Tue 21-05-19 $57,960.00
1.3.1
Determination of the
project requirements -
Product Backlog
13 days Thu 28-03-19 Mon 15-04-19 $33,384.00
1.3.2
Procurement of tools
and configurations -
Workstation Set-up
17 days Tue 16-04-19 Wed 08-05-19 $17,952.00
1.3.3
Development of
meeting and
communication schedule
9 days Thu 09-05-19 Tue 21-05-19 $6,624.00
1.3.4 Milestone 5: Agile
Set-up 0 days Tue 21-05-19 Tue 21-05-19 $0.00
1.4 Agile Sprints 167 days Wed 22-05-19 Thu 09-01-20 $256,784.00
1.4.1 Sprint 1 16 days Wed 22-05-19 Wed 12-06-19 $22,128.00
1.4.1.
1
Product Machine -
Basic Design 5 days Wed 22-05-19 Tue 28-05-19 $2,640.00
1.4.1.
2
Development of
Rules 7 days Wed 29-05-19 Thu 06-06-19 $10,528.00
1.4.1.
3 Test & Review 4 days Fri 07-06-19 Wed 12-06-19 $8,960.00
1.4.1.
4
Milestone 6: Basic
Design 0 days Wed 12-06-19 Wed 12-06-19 $0.00
1.4.2 Sprint 2 19 days Thu 13-06-19 Tue 09-07-19 $27,000.00
13

Request for Proposal (RFP)
1.4.2.
1
Refinements in
Design 4 days Thu 13-06-19 Tue 18-06-19 $2,112.00
1.4.2.
2
Insurance
Contracts - Individual 16 days Thu 13-06-19 Thu 04-07-19 $23,424.00
1.4.2.
3 Test & Review 3 days Fri 05-07-19 Tue 09-07-19 $1,464.00
1.4.2.
4
Milestone 7:
Individual Contracts 0 days Tue 09-07-19 Tue 09-07-19 $0.00
1.4.3 Sprint 3 23 days Wed 10-07-19 Fri 09-08-19 $27,640.00
1.4.3.
1
Refinements in
Individual Contracts 4 days Wed 10-07-19 Mon 15-07-19 $2,112.00
1.4.3.
2
Insurance
Contracts - Groups &
Family
16 days Tue 16-07-19 Tue 06-08-19 $24,064.00
1.4.3.
3 Test & Review 3 days Wed 07-08-19 Fri 09-08-19 $1,464.00
1.4.3.
4
Milestone 8:
Group/Family Contracts 0 days Fri 09-08-19 Fri 09-08-19 $0.00
1.4.4 Sprint 4 21 days Mon 12-08-19 Mon 09-09-19 $24,000.00
1.4.4.
1
Modifications &
Changes 4 days Mon 12-08-19 Thu 15-08-19 $4,064.00
1.4.4.
2
Policy System -
Filters & Algorithms 14 days Fri 16-08-19 Wed 04-09-19 $14,224.00
1.4.4.
3 Test & Review 3 days Thu 05-09-19 Mon 09-09-19 $5,712.00
1.4.4.
4
Milestone 9: Policy
System 0 days Mon 09-09-19 Mon 09-09-19 $0.00
1.4.5 Sprint 5 21 days Tue 10-09-19 Tue 08-10-19 $19,192.00
1.4.5.
1
Modifications &
Changes 4 days Tue 10-09-19 Fri 13-09-19 $4,064.00
1.4.5.
2
Distribution
System - Filters &
14 days Mon 16-09-19 Thu 03-10-19 $13,664.00
14
1.4.2.
1
Refinements in
Design 4 days Thu 13-06-19 Tue 18-06-19 $2,112.00
1.4.2.
2
Insurance
Contracts - Individual 16 days Thu 13-06-19 Thu 04-07-19 $23,424.00
1.4.2.
3 Test & Review 3 days Fri 05-07-19 Tue 09-07-19 $1,464.00
1.4.2.
4
Milestone 7:
Individual Contracts 0 days Tue 09-07-19 Tue 09-07-19 $0.00
1.4.3 Sprint 3 23 days Wed 10-07-19 Fri 09-08-19 $27,640.00
1.4.3.
1
Refinements in
Individual Contracts 4 days Wed 10-07-19 Mon 15-07-19 $2,112.00
1.4.3.
2
Insurance
Contracts - Groups &
Family
16 days Tue 16-07-19 Tue 06-08-19 $24,064.00
1.4.3.
3 Test & Review 3 days Wed 07-08-19 Fri 09-08-19 $1,464.00
1.4.3.
4
Milestone 8:
Group/Family Contracts 0 days Fri 09-08-19 Fri 09-08-19 $0.00
1.4.4 Sprint 4 21 days Mon 12-08-19 Mon 09-09-19 $24,000.00
1.4.4.
1
Modifications &
Changes 4 days Mon 12-08-19 Thu 15-08-19 $4,064.00
1.4.4.
2
Policy System -
Filters & Algorithms 14 days Fri 16-08-19 Wed 04-09-19 $14,224.00
1.4.4.
3 Test & Review 3 days Thu 05-09-19 Mon 09-09-19 $5,712.00
1.4.4.
4
Milestone 9: Policy
System 0 days Mon 09-09-19 Mon 09-09-19 $0.00
1.4.5 Sprint 5 21 days Tue 10-09-19 Tue 08-10-19 $19,192.00
1.4.5.
1
Modifications &
Changes 4 days Tue 10-09-19 Fri 13-09-19 $4,064.00
1.4.5.
2
Distribution
System - Filters &
14 days Mon 16-09-19 Thu 03-10-19 $13,664.00
14

Request for Proposal (RFP)
Algorithms
1.4.5.
3 Test & Review 3 days Fri 04-10-19 Tue 08-10-19 $1,464.00
1.4.5.
4
Milestone 10:
Distribution System 0 days Tue 08-10-19 Tue 08-10-19 $0.00
1.4.6 Sprint 6 26 days Wed 09-10-19 Wed 13-11-19 $49,464.00
1.4.6.
1
Modifications &
Changes 5 days Wed 09-10-19 Tue 15-10-19 $2,640.00
1.4.6.
2
Customized
Contracts 8 days Wed 16-10-19 Fri 25-10-19 $20,160.00
1.4.6.
3
Contract Review &
Approval Cycle 10 days Mon 28-10-19 Fri 08-11-19 $25,200.00
1.4.6.
4 Test & Review 3 days Mon 11-11-19 Wed 13-11-19 $1,464.00
1.4.6.
5
Milestone 11:
Review & Approval
Cycle
0 days Wed 13-11-19 Wed 13-11-19 $0.00
1.4.7 Sprint 7 22 days Thu 14-11-19 Fri 13-12-19 $35,040.00
1.4.7.
1
Modifications &
Changes 3 days Thu 14-11-19 Mon 18-11-19 $3,168.00
1.4.7.
2
Exception
Handling Rules -
Contract Building
8 days Tue 19-11-19 Thu 28-11-19 $15,936.00
1.4.7.
3
Exception
Handling Rules - Tariffs 8 days Fri 29-11-19 Tue 10-12-19 $15,936.00
1.4.7.
4 Test & Review 3 days Wed 11-12-19 Fri 13-12-19 $0.00
1.4.7.
5
Milestone 12:
Rules 0 days Fri 13-12-19 Fri 13-12-19 $0.00
1.4.8 Sprint 8 19 days Mon 16-12-19 Thu 09-01-20 $52,320.00
1.4.8.
1
Integration of the
rules and back-end
11 days Mon 16-12-19 Mon 30-12-19 $11,616.00
15
Algorithms
1.4.5.
3 Test & Review 3 days Fri 04-10-19 Tue 08-10-19 $1,464.00
1.4.5.
4
Milestone 10:
Distribution System 0 days Tue 08-10-19 Tue 08-10-19 $0.00
1.4.6 Sprint 6 26 days Wed 09-10-19 Wed 13-11-19 $49,464.00
1.4.6.
1
Modifications &
Changes 5 days Wed 09-10-19 Tue 15-10-19 $2,640.00
1.4.6.
2
Customized
Contracts 8 days Wed 16-10-19 Fri 25-10-19 $20,160.00
1.4.6.
3
Contract Review &
Approval Cycle 10 days Mon 28-10-19 Fri 08-11-19 $25,200.00
1.4.6.
4 Test & Review 3 days Mon 11-11-19 Wed 13-11-19 $1,464.00
1.4.6.
5
Milestone 11:
Review & Approval
Cycle
0 days Wed 13-11-19 Wed 13-11-19 $0.00
1.4.7 Sprint 7 22 days Thu 14-11-19 Fri 13-12-19 $35,040.00
1.4.7.
1
Modifications &
Changes 3 days Thu 14-11-19 Mon 18-11-19 $3,168.00
1.4.7.
2
Exception
Handling Rules -
Contract Building
8 days Tue 19-11-19 Thu 28-11-19 $15,936.00
1.4.7.
3
Exception
Handling Rules - Tariffs 8 days Fri 29-11-19 Tue 10-12-19 $15,936.00
1.4.7.
4 Test & Review 3 days Wed 11-12-19 Fri 13-12-19 $0.00
1.4.7.
5
Milestone 12:
Rules 0 days Fri 13-12-19 Fri 13-12-19 $0.00
1.4.8 Sprint 8 19 days Mon 16-12-19 Thu 09-01-20 $52,320.00
1.4.8.
1
Integration of the
rules and back-end
11 days Mon 16-12-19 Mon 30-12-19 $11,616.00
15
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Request for Proposal (RFP)
processes
1.4.8.
2
Final verifications
& Validations 8 days Tue 31-12-19 Thu 09-01-20 $40,704.00
1.4.8.
3
Milestone 13:
Integrated product
machine
0 days Thu 09-01-20 Thu 09-01-20 $0.00
1.5 Deployment &
Closure 54 days Fri 10-01-20 Wed 25-03-20 $96,264.00
1.5.1 Deployment with
Alpha & Beta Systems 21 days Fri 10-01-20 Fri 07-02-20 $32,424.00
1.5.2
Reflection &
Performance
measurement
12 days Mon 10-02-20 Tue 25-02-20 $16,800.00
1.5.3 Closure
documentation 21 days Wed 26-02-20 Wed 25-03-20 $47,040.00
1.5.4 Milestone 14: Project
Closure 0 days Wed 25-03-20 Wed 25-03-20 $0.00
Resource Requirements
The resources that will be needed to conduct the project are included in the table below.
These resources will be required as per the schedule mapped. The resources will be expected
to allocate 40 hours in a week of 5 working days throughout the project timeline. The
Business Advisor, Data Scientist, and Joe Freya (Scrum Master) will be the internal resources
that will remain involved in the project phases and will provide the required support.
WBS Task Name Duration Start Finish Successors Predecessors Resource
Names
1.3 Agile Set-up 39 days
Thu
28-
03-19
Tue
21-05-
19
1.3.1 Determination of
the project
requirements -
13 days Thu
28-
03-19
Mon
15-04-
19
24,25 21,3 Business
Advisor ,Dat
a
16
processes
1.4.8.
2
Final verifications
& Validations 8 days Tue 31-12-19 Thu 09-01-20 $40,704.00
1.4.8.
3
Milestone 13:
Integrated product
machine
0 days Thu 09-01-20 Thu 09-01-20 $0.00
1.5 Deployment &
Closure 54 days Fri 10-01-20 Wed 25-03-20 $96,264.00
1.5.1 Deployment with
Alpha & Beta Systems 21 days Fri 10-01-20 Fri 07-02-20 $32,424.00
1.5.2
Reflection &
Performance
measurement
12 days Mon 10-02-20 Tue 25-02-20 $16,800.00
1.5.3 Closure
documentation 21 days Wed 26-02-20 Wed 25-03-20 $47,040.00
1.5.4 Milestone 14: Project
Closure 0 days Wed 25-03-20 Wed 25-03-20 $0.00
Resource Requirements
The resources that will be needed to conduct the project are included in the table below.
These resources will be required as per the schedule mapped. The resources will be expected
to allocate 40 hours in a week of 5 working days throughout the project timeline. The
Business Advisor, Data Scientist, and Joe Freya (Scrum Master) will be the internal resources
that will remain involved in the project phases and will provide the required support.
WBS Task Name Duration Start Finish Successors Predecessors Resource
Names
1.3 Agile Set-up 39 days
Thu
28-
03-19
Tue
21-05-
19
1.3.1 Determination of
the project
requirements -
13 days Thu
28-
03-19
Mon
15-04-
19
24,25 21,3 Business
Advisor ,Dat
a
16

Request for Proposal (RFP)
Product Backlog
Scientist ,Fin
ance
Analyst ,Joe
Freya
1.3.2
Procurement of
tools and
configurations -
Workstation Set-up
17 days
Tue
16-
04-19
Wed
08-05-
19
25 23
Senior
Application
Developer
1,Senior
Application
Developer 2
1.3.3
Development of
meeting and
communication
schedule
9 days
Thu
09-
05-19
Tue
21-05-
19
26 23,24 Joe Freya
1.3.4 Milestone 5: Agile
Set-up 0 days
Tue
21-
05-19
Tue
21-05-
19
29 25
1.4 Agile Sprints 167 days
Wed
22-
05-19
Thu
09-01-
20
1.4.1 Sprint 1 16 days
Wed
22-
05-19
Wed
12-06-
19
1.4.1.1 Product Machine
- Basic Design 5 days
Wed
22-
05-19
Tue
28-05-
19
30 26
Senior
Application
Developer 1
1.4.1.2 Development of
Rules 7 days
Wed
29-
05-19
Thu
06-06-
19
31 29
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 2
1.4.1.3 Test & Review 4 days Fri Wed 32,34 30 Application
17
Product Backlog
Scientist ,Fin
ance
Analyst ,Joe
Freya
1.3.2
Procurement of
tools and
configurations -
Workstation Set-up
17 days
Tue
16-
04-19
Wed
08-05-
19
25 23
Senior
Application
Developer
1,Senior
Application
Developer 2
1.3.3
Development of
meeting and
communication
schedule
9 days
Thu
09-
05-19
Tue
21-05-
19
26 23,24 Joe Freya
1.3.4 Milestone 5: Agile
Set-up 0 days
Tue
21-
05-19
Tue
21-05-
19
29 25
1.4 Agile Sprints 167 days
Wed
22-
05-19
Thu
09-01-
20
1.4.1 Sprint 1 16 days
Wed
22-
05-19
Wed
12-06-
19
1.4.1.1 Product Machine
- Basic Design 5 days
Wed
22-
05-19
Tue
28-05-
19
30 26
Senior
Application
Developer 1
1.4.1.2 Development of
Rules 7 days
Wed
29-
05-19
Thu
06-06-
19
31 29
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 2
1.4.1.3 Test & Review 4 days Fri Wed 32,34 30 Application
17

Request for Proposal (RFP)
07-
06-19
12-06-
19
Programmer,
Joe Freya,
Quality
Assurance
Officer,
Senior
Application
Developer 1
1.4.1.4 Milestone 6:
Basic Design 0 days
Wed
12-
06-19
Wed
12-06-
19
35 31
1.4.2 Sprint 2 19 days
Thu
13-
06-19
Tue
09-07-
19
1.4.2.1 Refinements in
Design 4 days
Thu
13-
06-19
Tue
18-06-
19
31
Senior
Application
Developer 1
1.4.2.2 Insurance
Contracts - Individual 16 days
Thu
13-
06-19
Thu
04-07-
19
36 32
Application
Programmer,
Finance
Analyst ,Insu
rance Expert
1.4.2.3 Test & Review 3 days
Fri
05-
07-19
Tue
09-07-
19
37 35
Quality
Assurance
Officer
1.4.2.4 Milestone 7:
Individual Contracts 0 days
Tue
09-
07-19
Tue
09-07-
19
39 36
1.4.3 Sprint 3 23 days
Wed
10-
07-19
Fri 09-
08-19
1.4.3.1 Refinements in
Individual Contracts
4 days Wed
10-
Mon
15-07-
40 37 Senior
Application
18
07-
06-19
12-06-
19
Programmer,
Joe Freya,
Quality
Assurance
Officer,
Senior
Application
Developer 1
1.4.1.4 Milestone 6:
Basic Design 0 days
Wed
12-
06-19
Wed
12-06-
19
35 31
1.4.2 Sprint 2 19 days
Thu
13-
06-19
Tue
09-07-
19
1.4.2.1 Refinements in
Design 4 days
Thu
13-
06-19
Tue
18-06-
19
31
Senior
Application
Developer 1
1.4.2.2 Insurance
Contracts - Individual 16 days
Thu
13-
06-19
Thu
04-07-
19
36 32
Application
Programmer,
Finance
Analyst ,Insu
rance Expert
1.4.2.3 Test & Review 3 days
Fri
05-
07-19
Tue
09-07-
19
37 35
Quality
Assurance
Officer
1.4.2.4 Milestone 7:
Individual Contracts 0 days
Tue
09-
07-19
Tue
09-07-
19
39 36
1.4.3 Sprint 3 23 days
Wed
10-
07-19
Fri 09-
08-19
1.4.3.1 Refinements in
Individual Contracts
4 days Wed
10-
Mon
15-07-
40 37 Senior
Application
18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Request for Proposal (RFP)
07-19 19 Developer 1
1.4.3.2
Insurance
Contracts - Groups &
Family
16 days
Tue
16-
07-19
Tue
06-08-
19
41 39
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 2
1.4.3.3 Test & Review 3 days
Wed
07-
08-19
Fri 09-
08-19 42 40
Quality
Assurance
Officer
1.4.3.4
Milestone 8:
Group/Family
Contracts
0 days
Fri
09-
08-19
Fri 09-
08-19 44 41
1.4.4 Sprint 4 21 days
Mon
12-
08-19
Mon
09-09-
19
1.4.4.1 Modifications &
Changes 4 days
Mon
12-
08-19
Thu
15-08-
19
45 42
Application
Programmer,
Senior
Application
Developer 1
1.4.4.2 Policy System -
Filters & Algorithms 14 days
Fri
16-
08-19
Wed
04-09-
19
46 44
Finance
Analyst ,Seni
or
Application
Developer 1
1.4.4.3 Test & Review 3 days
Thu
05-
09-19
Mon
09-09-
19
47,49 45
Quality
Assurance
Officer,
Business
Advisor ,Joe
Freya
1.4.4.4 Milestone 9: 0 days Mon Mon 46
19
07-19 19 Developer 1
1.4.3.2
Insurance
Contracts - Groups &
Family
16 days
Tue
16-
07-19
Tue
06-08-
19
41 39
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 2
1.4.3.3 Test & Review 3 days
Wed
07-
08-19
Fri 09-
08-19 42 40
Quality
Assurance
Officer
1.4.3.4
Milestone 8:
Group/Family
Contracts
0 days
Fri
09-
08-19
Fri 09-
08-19 44 41
1.4.4 Sprint 4 21 days
Mon
12-
08-19
Mon
09-09-
19
1.4.4.1 Modifications &
Changes 4 days
Mon
12-
08-19
Thu
15-08-
19
45 42
Application
Programmer,
Senior
Application
Developer 1
1.4.4.2 Policy System -
Filters & Algorithms 14 days
Fri
16-
08-19
Wed
04-09-
19
46 44
Finance
Analyst ,Seni
or
Application
Developer 1
1.4.4.3 Test & Review 3 days
Thu
05-
09-19
Mon
09-09-
19
47,49 45
Quality
Assurance
Officer,
Business
Advisor ,Joe
Freya
1.4.4.4 Milestone 9: 0 days Mon Mon 46
19

Request for Proposal (RFP)
Policy System 09-
09-19
09-09-
19
1.4.5 Sprint 5 21 days
Tue
10-
09-19
Tue
08-10-
19
1.4.5.1 Modifications &
Changes 4 days
Tue
10-
09-19
Fri 13-
09-19 50 46
Insurance
Expert ,Senio
r Application
Developer 2
1.4.5.2
Distribution
System - Filters &
Algorithms
14 days
Mon
16-
09-19
Thu
03-10-
19
51 49
Application
Programmer,
Finance
Analyst
1.4.5.3 Test & Review 3 days
Fri
04-
10-19
Tue
08-10-
19
52 50
Quality
Assurance
Officer
1.4.5.4 Milestone 10:
Distribution System 0 days
Tue
08-
10-19
Tue
08-10-
19
54 51
1.4.6 Sprint 6 26 days
Wed
09-
10-19
Wed
13-11-
19
1.4.6.1 Modifications &
Changes 5 days
Wed
09-
10-19
Tue
15-10-
19
55 52
Senior
Application
Developer 2
1.4.6.2 Customized
Contracts
8 days Wed
16-
10-19
Fri 25-
10-19
56 54 Finance
Analyst ,Insu
rance
Expert ,Appli
cation
Programmer,
Senior
Application
20
Policy System 09-
09-19
09-09-
19
1.4.5 Sprint 5 21 days
Tue
10-
09-19
Tue
08-10-
19
1.4.5.1 Modifications &
Changes 4 days
Tue
10-
09-19
Fri 13-
09-19 50 46
Insurance
Expert ,Senio
r Application
Developer 2
1.4.5.2
Distribution
System - Filters &
Algorithms
14 days
Mon
16-
09-19
Thu
03-10-
19
51 49
Application
Programmer,
Finance
Analyst
1.4.5.3 Test & Review 3 days
Fri
04-
10-19
Tue
08-10-
19
52 50
Quality
Assurance
Officer
1.4.5.4 Milestone 10:
Distribution System 0 days
Tue
08-
10-19
Tue
08-10-
19
54 51
1.4.6 Sprint 6 26 days
Wed
09-
10-19
Wed
13-11-
19
1.4.6.1 Modifications &
Changes 5 days
Wed
09-
10-19
Tue
15-10-
19
55 52
Senior
Application
Developer 2
1.4.6.2 Customized
Contracts
8 days Wed
16-
10-19
Fri 25-
10-19
56 54 Finance
Analyst ,Insu
rance
Expert ,Appli
cation
Programmer,
Senior
Application
20

Request for Proposal (RFP)
Developer
1,Senior
Application
Developer 2
1.4.6.3 Contract Review
& Approval Cycle 10 days
Mon
28-
10-19
Fri 08-
11-19 57 55
Finance
Analyst ,Insu
rance
Expert ,Appli
cation
Programmer,
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.6.4 Test & Review 3 days
Mon
11-
11-19
Wed
13-11-
19
58 56
Quality
Assurance
Officer
1.4.6.5
Milestone 11:
Review & Approval
Cycle
0 days
Wed
13-
11-19
Wed
13-11-
19
60 57
1.4.7 Sprint 7 22 days
Thu
14-
11-19
Fri 13-
12-19
1.4.7.1 Modifications &
Changes 3 days
Thu
14-
11-19
Mon
18-11-
19
61 58
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.7.2 Exception
Handling Rules -
8 days Tue
19-
Thu
28-11-
62 60 Application
Programmer,
21
Developer
1,Senior
Application
Developer 2
1.4.6.3 Contract Review
& Approval Cycle 10 days
Mon
28-
10-19
Fri 08-
11-19 57 55
Finance
Analyst ,Insu
rance
Expert ,Appli
cation
Programmer,
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.6.4 Test & Review 3 days
Mon
11-
11-19
Wed
13-11-
19
58 56
Quality
Assurance
Officer
1.4.6.5
Milestone 11:
Review & Approval
Cycle
0 days
Wed
13-
11-19
Wed
13-11-
19
60 57
1.4.7 Sprint 7 22 days
Thu
14-
11-19
Fri 13-
12-19
1.4.7.1 Modifications &
Changes 3 days
Thu
14-
11-19
Mon
18-11-
19
61 58
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.7.2 Exception
Handling Rules -
8 days Tue
19-
Thu
28-11-
62 60 Application
Programmer,
21
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Request for Proposal (RFP)
Contract Building 11-19 19
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 1
1.4.7.3
Exception
Handling Rules -
Tariffs
8 days
Fri
29-
11-19
Tue
10-12-
19
63 61
Application
Programmer,
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 2
1.4.7.4 Test & Review 3 days
Wed
11-
12-19
Fri 13-
12-19 64 62
1.4.7.5 Milestone 12:
Rules 0 days
Fri
13-
12-19
Fri 13-
12-19 66 63
1.4.8 Sprint 8 19 days
Mon
16-
12-19
Thu
09-01-
20
1.4.8.1
Integration of the
rules and back-end
processes
11 days
Mon
16-
12-19
Mon
30-12-
19
67 64
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.8.2 Final verifications
& Validations
8 days Tue
31-
12-19
Thu
09-01-
20
68 66 Application
Programmer,
Business
Advisor ,Dat
22
Contract Building 11-19 19
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 1
1.4.7.3
Exception
Handling Rules -
Tariffs
8 days
Fri
29-
11-19
Tue
10-12-
19
63 61
Application
Programmer,
Finance
Analyst ,Insu
rance
Expert ,Senio
r Application
Developer 2
1.4.7.4 Test & Review 3 days
Wed
11-
12-19
Fri 13-
12-19 64 62
1.4.7.5 Milestone 12:
Rules 0 days
Fri
13-
12-19
Fri 13-
12-19 66 63
1.4.8 Sprint 8 19 days
Mon
16-
12-19
Thu
09-01-
20
1.4.8.1
Integration of the
rules and back-end
processes
11 days
Mon
16-
12-19
Mon
30-12-
19
67 64
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.8.2 Final verifications
& Validations
8 days Tue
31-
12-19
Thu
09-01-
20
68 66 Application
Programmer,
Business
Advisor ,Dat
22

Request for Proposal (RFP)
a
Scientist ,Fin
ance
Analyst ,Insu
rance
Expert ,Joe
Freya,
Quality
Assurance
Officer,
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.8.3
Milestone 13:
Integrated product
machine
0 days
Thu
09-
01-20
Thu
09-01-
20
70 67
1.5 Deployment &
Closure 54 days
Fri
10-
01-20
Wed
25-03-
20
1.5.1
Deployment with
Alpha & Beta
Systems
21 days
Fri
10-
01-20
Fri 07-
02-20 71 68
Application
Programmer,
Senior
Application
Developer
1,Senior
Application
Developer 2
1.5.2
Reflection &
Performance
measurement
12 days
Mon
10-
02-20
Tue
25-02-
20
72 70
Data
Scientist ,Joe
Freya
23
a
Scientist ,Fin
ance
Analyst ,Insu
rance
Expert ,Joe
Freya,
Quality
Assurance
Officer,
Senior
Application
Developer
1,Senior
Application
Developer 2
1.4.8.3
Milestone 13:
Integrated product
machine
0 days
Thu
09-
01-20
Thu
09-01-
20
70 67
1.5 Deployment &
Closure 54 days
Fri
10-
01-20
Wed
25-03-
20
1.5.1
Deployment with
Alpha & Beta
Systems
21 days
Fri
10-
01-20
Fri 07-
02-20 71 68
Application
Programmer,
Senior
Application
Developer
1,Senior
Application
Developer 2
1.5.2
Reflection &
Performance
measurement
12 days
Mon
10-
02-20
Tue
25-02-
20
72 70
Data
Scientist ,Joe
Freya
23

Request for Proposal (RFP)
1.5.3 Closure
documentation 21 days
Wed
26-
02-20
Wed
25-03-
20
73 71
Application
Programmer,
Joe Freya,
Quality
Assurance
Officer,
Senior
Application
Developer 1
1.5.4 Milestone 14:
Project Closure 0 days
Wed
25-
03-20
Wed
25-03-
20
72
Technology Requirements
The implementation of the GCOM process and the entire GoSMART procedure will be done
over the cloud and the cloud services and databases will be required for the purpose of data
storage, handling, and retrieval.
The security tools, such as anti-malware tools, anti-denial, and network security tools along
with the cloud backup storage services will be required to safeguard the data at all times.
Evaluation Criteria
The Test & Review process will be included in every sprint. The evaluation will be done by
mapping the functionalities and rules implemented as per the specifications and organization
standards.
The ethical, legal, and security compliance shall be maintained 100% all throughout and the
industry standards around insurance and financial schemes shall be adhered with.
Possible Risks
GoSMART process is a large-scale process and GCOM is one of the components of the
same. The integration of GCOM with the existing components and applications will be
required to be done. There are certain risks that can emerge in the process.
24
1.5.3 Closure
documentation 21 days
Wed
26-
02-20
Wed
25-03-
20
73 71
Application
Programmer,
Joe Freya,
Quality
Assurance
Officer,
Senior
Application
Developer 1
1.5.4 Milestone 14:
Project Closure 0 days
Wed
25-
03-20
Wed
25-03-
20
72
Technology Requirements
The implementation of the GCOM process and the entire GoSMART procedure will be done
over the cloud and the cloud services and databases will be required for the purpose of data
storage, handling, and retrieval.
The security tools, such as anti-malware tools, anti-denial, and network security tools along
with the cloud backup storage services will be required to safeguard the data at all times.
Evaluation Criteria
The Test & Review process will be included in every sprint. The evaluation will be done by
mapping the functionalities and rules implemented as per the specifications and organization
standards.
The ethical, legal, and security compliance shall be maintained 100% all throughout and the
industry standards around insurance and financial schemes shall be adhered with.
Possible Risks
GoSMART process is a large-scale process and GCOM is one of the components of the
same. The integration of GCOM with the existing components and applications will be
required to be done. There are certain risks that can emerge in the process.
24
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Request for Proposal (RFP)
Technical risks, such as failure of a tool or a product may be witnessed which may lead to the
issues in maintenance of overall continuity. It is possible that the overrun of schedule or
budget may be observed which may lead to the disturbances in the associated concepts and
functions (Buganova & Simickova, 2019).
There are also risks associated with scope creep that may emerge. The changes in the
integration requirements or the policy schemes may lead to delay in the schedule or overrun
of the budget.
25
Technical risks, such as failure of a tool or a product may be witnessed which may lead to the
issues in maintenance of overall continuity. It is possible that the overrun of schedule or
budget may be observed which may lead to the disturbances in the associated concepts and
functions (Buganova & Simickova, 2019).
There are also risks associated with scope creep that may emerge. The changes in the
integration requirements or the policy schemes may lead to delay in the schedule or overrun
of the budget.
25

Request for Proposal (RFP)
References
Ashbacher, C. (2010). Succeeding With Agile: Software Development Using Scrum, by Mike
Cohn. The Journal Of Object Technology, 9(4). doi: 10.5381/jot.2010.9.4.r1
Buganova, K., & Simickova, J. (2019). Risk management in traditional and agile project
management. Transportation Research Procedia, 40, 986-993. doi:
10.1016/j.trpro.2019.07.138
Carvalho, B., & Mello, C. (2011). Scrum agile product development method - literature
review, analysis and classification. Product Management & Development, 9(1), 39-
49. doi: 10.4322/pmd.2011.005
Gotz, O., Wai, Y., Klein, S., Gras, M., Werner, M., Robmehl, M., & Basten, D. (2018). The
(Go)SMART Way to Agility: Managing a Scrum Subproject in a Waterfall
Environment. Journal Of Information Technology Teaching Cases, 8(2), 149-160.
doi: 10.1057/s41266-018-0035-9
Kalyani, D., & Mehta, D. (2019). Study of Agile Scrum and Alikeness of Scrum Tools.
International Journal Of Computer Applications, 178(43), 21-28. doi:
10.5120/ijca2019919318
Rajasekaran, V. (2015). Issues in Scrum Agile Development Principles and Practices in
software development. Indian Journal Of Science And Technology, 8(35). doi:
10.17485/ijst/2015/v8i35/79037
Sharma, A., & Bali, M. (2018). Comparative Study on Software Development Methods:
Agile vs Scrum. International Journal Of Emerging Research In Management And
Technology, 6(6), 165. doi: 10.23956/ijermt.v6i6.263
Tkachenko, I., & Sivokoz, K. (2017). Using Flexible Technologies Agile and Scrum for
Managing Project Stakeholders. Upravlenets, 68(4), 85-95. doi: 10.29141/2218-5003-
2017-6-4-10
26
References
Ashbacher, C. (2010). Succeeding With Agile: Software Development Using Scrum, by Mike
Cohn. The Journal Of Object Technology, 9(4). doi: 10.5381/jot.2010.9.4.r1
Buganova, K., & Simickova, J. (2019). Risk management in traditional and agile project
management. Transportation Research Procedia, 40, 986-993. doi:
10.1016/j.trpro.2019.07.138
Carvalho, B., & Mello, C. (2011). Scrum agile product development method - literature
review, analysis and classification. Product Management & Development, 9(1), 39-
49. doi: 10.4322/pmd.2011.005
Gotz, O., Wai, Y., Klein, S., Gras, M., Werner, M., Robmehl, M., & Basten, D. (2018). The
(Go)SMART Way to Agility: Managing a Scrum Subproject in a Waterfall
Environment. Journal Of Information Technology Teaching Cases, 8(2), 149-160.
doi: 10.1057/s41266-018-0035-9
Kalyani, D., & Mehta, D. (2019). Study of Agile Scrum and Alikeness of Scrum Tools.
International Journal Of Computer Applications, 178(43), 21-28. doi:
10.5120/ijca2019919318
Rajasekaran, V. (2015). Issues in Scrum Agile Development Principles and Practices in
software development. Indian Journal Of Science And Technology, 8(35). doi:
10.17485/ijst/2015/v8i35/79037
Sharma, A., & Bali, M. (2018). Comparative Study on Software Development Methods:
Agile vs Scrum. International Journal Of Emerging Research In Management And
Technology, 6(6), 165. doi: 10.23956/ijermt.v6i6.263
Tkachenko, I., & Sivokoz, K. (2017). Using Flexible Technologies Agile and Scrum for
Managing Project Stakeholders. Upravlenets, 68(4), 85-95. doi: 10.29141/2218-5003-
2017-6-4-10
26
1 out of 27
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.