This report is a project charter for the I-Crop project, focusing on the development of a mobile application and website for Globex Corp. It outlines the project's purpose, objectives, and background, including the Measurable Organizational Value (MOV) across social, operational, customer, and financial dimensions. The scope defines in-scope and out-of-scope items, assumptions, and constraints. The Work Breakdown Structure (WBS) details milestones, activities, and resource assignments with associated costs. The report also includes a risk management plan, verification and validation activities, and a project evaluation and closure checklist. The report concludes with an annotated bibliography, citing relevant articles on project management and complexity.
Document Page
Running head: ICT PROJECT MANAGEMENT
ICT Project Management
“I-Crop Project”
Name of the Student:
Student ID:
Name of the University:
Author’s note:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1ICT PROJECT MANAGEMENT
Introduction
The following assignment is a project charter document developed for integrating the analysis of
the mobile application and website development for I-Crop project. The purpose of the charter is
to form an initial requirement document for the stakeholders so that they can understand the
project more easily.
Purpose
The purpose of the report is to develop a project charter that can be used as an initial document
containing all required documents for getting an overview of the mobile application and website
development for I-Crop project.
The objectives of the report are,
To develop an initial document comprising of information about the project schedule and
budgetary information
To enhance the management of the successful development by passing on the information
to its stakeholders
Project Description
Project Details
The website and mobile application would be effectively helpful in managing the project
objectives. The orders and services would be increased and managed easily with the help of the
improved communication plan development.
Document Page
2ICT PROJECT MANAGEMENT
Project Background
The Globex has decided to implement a new mobile application and website development and
named it ‘I-Crop Project’. It would help them in managing the customers and getting active
feedbacks from their customer.
Part one: MOV – Measurable Organizational Value
Social: The social media platform would be responsible for the development of the successful
management of the activities and aligning the formation of the increased management
operations. The utilization of the improved functional development would be helpful for aligning
the completion of the activities.
Operational: The operational development would be implied for easing the management of the
successful development of activities. It is largely responsible for the continuation of the activities
and forming management of the functional development.
Customer: The customer focus on the website development for I-Crop project would be
effectively aligned with the independent management of the activities. The customer
involvement would be effectively deployed for listing the evaluation of the functions for taking
care of actions.
Financial: The financial operations of the I-Crop project would be held responsible for the
completion of the activities and aligning development model.
Values
Document Page
3ICT PROJECT MANAGEMENT
Better- the implementation of the I-Crop project would be effectively deployed for integrating
the utilization and formation of the successful continuation of the projects.
Faster- the faster completion of the projects would be implied for forming the cohesive
management of the activities.
Cheaper- the overall cost required for the completion of the activities of Globex can be reduced
by the help of the automatic activities due to the I-Crop project.
Do more- the applications of I-Crop project would be implied for taking care of the prominent
development of the operations like communication and information transfer.
Rank Impact Metrics Timeframe (in months)
1 Financial Profit Margin 3
2 Customer Feedbacks and Orders 4
3 Operational Processing Time 2
4 Strategy Effective Implication 1
5 Social Feedbacks on social media web 5
Part Two: Project Scope
In scope- The in scope items of the project of website and mobile application for I-Crop include
the development of the project plan, initiation documents, design, website development, mobile
application development, UX development, testing activities, and final documentation.
Out of scope- the out of scope items of the project include the transportation requirements,
change management, and communication plan.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4ICT PROJECT MANAGEMENT
Assumptions- It has been assumed for the project of website and mobile application for I-Crop
that,
Project would be completed in the estimated time and budget
Uses of the provident development factors can be implied for successful alignment
development
Resources required for the completion of the project would be done cohesively
Constraints- the factors of time, budget, and resource usage are the primary constraints for the
project of website and mobile application for I-Crop
Scope Management plan
Resources: Analyst, Application Designer, Application Developer, Documenter, Engineer,
Planner, Programmer, Project Manager, Website Designer, and Website Developer
Technology: Design Development, Mobile Application Development, Mobile Application UI
Development, Testing technology, and Website Development
Facilities: UI simulation environment and Testing facility is required for the completion of the
project of website and mobile application for I-Crop
Part Three: Work Breakdown structure
Milestones
WBS Milestone Name Duration Start Finish
1.5 Signing off 0 days Fri 10/12/18 Fri 10/12/18
Document Page
5ICT PROJECT MANAGEMENT
2.5 Approving Complete Plan 0 days Mon 10/29/18 Mon 10/29/18
3.1.5 Approving Website 0 days Tue 11/13/18 Tue 11/13/18
3.2.5 Approving Mobile Application 0 days Wed 11/28/18 Wed 11/28/18
5.5 Closure 0 days Thu 1/31/19 Thu 1/31/19
Activities / Tasks
WBS Task Name
0 I-Crop Project
1 Initial Phase
1.1 Analyzing requirements
1.2 Making Project Charter Documents
1.3 Making Project Initiation Documents
1.4 Submitting documents
1.5 Signing off
2 Planning Phase
2.1 Selecting Plan Methodology
2.2 Making Plan Outline
2.3 Reviewing Plan Outline
2.4 Making Complete Plan
2.5 Approving Complete Plan
Document Page
6ICT PROJECT MANAGEMENT
3 Designing Phase
3.1 Website Designing
3.1.1 Selecting Design Platform
3.1.2 Making Website Outline
3.1.3 Reviewing Website Outline
3.1.4 Making Complete Website
3.1.5 Approving Website
3.2 Mobile Application Designing
3.2.1 Selecting Design Platform
3.2.2 Making Mobile Application Outline
3.2.3 Reviewing Mobile Application Outline
3.2.4 Making Complete Mobile Application
3.2.5 Approving Mobile Application
4 Development Phase
4.1 Website Development
4.1.1 Buying Website Domain
4.1.2 Developing Website Interface
4.1.3 Aligning Functions of Website
4.1.4 Making Programs for Website
4.1.5 Checking Mobile Compatibility
4.1.6 Completion of Website Development
4.2 Mobile Application Development
4.2.1 Developing Application Interface
4.2.2 Making Programs for Mobile Application
4.2.3 Integrating Mobile Applications
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7ICT PROJECT MANAGEMENT
4.2.4 Completion of Mobile Application Development
5 Closure Phase
5.1 Making Closure Reports
5.2 Making Evaluation Checklist
5.3 Submitting Report Documents
5.4 Signing off
5.5 Closure
Resource Assignments
ID Resource Name Work
1 Analyst 16 hrs
2 Documenter 104 hrs
3 Planner 72 hrs
4 Project Manager 56 hrs
5 Website Designer 72 hrs
6 Application Designer 72 hrs
7 Engineer 72 hrs
8 Website Developer 96 hrs
9 Programmer 72 hrs
10 Application Developer 80 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
T W T M S S F T W T M S
Sep 23, '18 Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
16h
40h 24h 16h 24h
40h 32h
8h 8h 40h
32h 40h
24h 48h
16h 32h 24h
56h 40h
16h 8h 48h
24h 56h
1.67 0.33 0.67 0.33
1 2 1
1
Estimates for Each Activity / Task
WBS Task Name Resource Names Cost
0 I-Crop Project $80,005.00
1 Initial Phase $4,670.00
1.1 Analyzing requirements Analyst $160.00
1.2 Making Project Charter Documents Documenter, $1,735.00
Document Page
8ICT PROJECT MANAGEMENT
Documents[1]
1.3 Making Project Initiation Documents Documenter,
Documents[1] $1,735.00
1.4 Submitting documents Documenter $1,040.00
1.5 Signing off $0.00
2 Planning Phase $7,200.00
2.1 Selecting Plan Methodology Planner $1,120.00
2.2 Making Plan Outline Planner $1,680.00
2.3 Reviewing Plan Outline Project Manager $2,160.00
2.4 Making Complete Plan Planner $2,240.00
2.5 Approving Complete Plan $0.00
3 Designing Phase $25,760.00
3.1 Website Designing $12,880.00
3.1.1 Selecting Design Platform Website Designer,
Design Tools[1] $3,400.00
3.1.2 Making Website Outline Website Designer $2,400.00
3.1.3 Reviewing Website Outline Engineer $2,080.00
3.1.4 Making Complete Website Website Designer,
Design Tools[1] $5,000.00
3.1.5 Approving Website $0.00
3.2 Mobile Application Designing $12,880.00
3.2.1 Selecting Design Platform Application Designer,
Design Tools[1] $3,400.00
3.2.2 Making Mobile Application Outline Application Designer $2,400.00
Document Page
9ICT PROJECT MANAGEMENT
3.2.3 Reviewing Mobile Application Outline Engineer $2,080.00
3.2.4 Making Complete Mobile Application Application Designer,
Design Tools[1] $5,000.00
3.2.5 Approving Mobile Application $0.00
4 Development Phase $34,200.00
4.1 Website Development $16,520.00
4.1.1 Buying Website Domain Engineer,
Domain Cost[1] $3,080.00
4.1.2 Developing Website Interface Website Developer $3,520.00
4.1.3 Aligning Functions of Website Website Developer $2,640.00
4.1.4 Making Programs for Website Programmer $2,880.00
4.1.5 Checking Mobile Compatibility Website Developer $1,760.00
4.1.6 Completion of Website Development Website Developer $2,640.00
4.2 Mobile Application Development $17,680.00
4.2.1 Developing Application Interface Application Developer $2,640.00
4.2.2 Making Programs for Mobile Application Programmer $5,760.00
4.2.3 Integrating Mobile Applications Engineer $3,120.00
4.2.4 Completion of Mobile Application
Development Application Developer $6,160.00
5 Closure Phase $8,175.00
5.1 Making Closure Reports Documenter,
Documents[1] $1,735.00
5.2 Making Evaluation Checklist Project Manager $3,240.00
5.3 Submitting Report Documents Documenter $1,040.00
5.4 Signing off Project Manager $2,160.00
5.5 Closure $0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10ICT PROJECT MANAGEMENT
Project Budget
Resource Name Work Standard Rate Cost
Analyst 16 hrs $10.00/hr $160.00
Documenter 104 hrs $65.00/hr $6,760.00
Planner 72 hrs $70.00/hr $5,040.00
Project Manager 56 hrs $135.00/hr $7,560.00
Website Designer 72 hrs $100.00/hr $7,200.00
Application Designer 72 hrs $100.00/hr $7,200.00
Engineer 72 hrs $130.00/hr $9,360.00
Website Developer 96 hrs $110.00/hr $10,560.00
Programmer 72 hrs $120.00/hr $8,640.00
Application Developer 80 hrs $110.00/hr $8,800.00
Documents 3 $175.00 $525.00
Design Tools 4 $1,800.00 $7,200.00
Domain Cost 1 $1,000.00 $1,000.00
Total Budget $80,005.00
Document Page
11ICT PROJECT MANAGEMENT
Part Four: Risk Management Plan
Assumption made:
Project would be completed in the estimated budget
Uses of the resources have been done considering the alignment of functions.
Resources required for the completion of the project would be done cohesively
Risk Identification
Delay in completion: It is resulted due to the major or minor problems in execution of the
operations of project resulting in untimely completion of the project
Shortage of resources: It is resulted due to the lack of adequate resources in the project or due
to misuses of the resources by the project team
Design flaws: It is resulted due to the flaws in the design of the website and mobile application
that needed to be corrected by the designer
Functional errors: It is the issues in the website and mobile application due to the functions not
working properly or programming errors