This project management report details the development of a mobile-based farming application for Globex Corporation. The report begins with an introduction and project description, followed by an analysis of the Measurable Organizational Value (MOV), defining the project's impact, stakeholders, timeframe, and overall value. The scope of the project is then defined, including requirements, in-scope and out-of-scope elements, and resource allocation. A Work Breakdown Structure (WBS) is presented, outlining project milestones, activities, resources, and time estimations. The report also addresses risk planning and analysis, identifying potential risks and proposing management strategies. A quality management plan is included, detailing the team's philosophy and methods for ensuring quality. Finally, the report concludes with project closure and evaluation, including an annotated bibliography and a checklist for project completion.
Document Page
Running head: ICT PROJECT MANAGEMENT
ICT Project Management
Name of Student-
Name of University-
Author’s Note-
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1ICT PROJECT MANAGEMENT
Table of Contents
Introduction......................................................................................................................................3
Project Description..........................................................................................................................3
Part One: MOV (Measurable Organizational Value)......................................................................3
1. Impact Area of Given case Study:...........................................................................................3
2. Target and Expectation of Stakeholders:.................................................................................4
3. Timeframe Included:...............................................................................................................5
4. Summarization of MOV:.........................................................................................................5
Part Two: Defining Scope...............................................................................................................6
1. Defining Scope and Producing Scope Management Plan:......................................................6
1.1 Requirements of projects...................................................................................................6
1.2 In scope and project out Scope..........................................................................................6
2. Management of Scope:............................................................................................................6
3. Resources of Project:...............................................................................................................7
Part Three: Work Breakdown Structure..........................................................................................7
1. Milestones in project schedule:...............................................................................................7
2. Activities performed for each deliverables:.............................................................................8
3. Resources Used........................................................................................................................9
4. Estimating time for all activities..............................................................................................9
5. Project Budget.......................................................................................................................10
Document Page
2ICT PROJECT MANAGEMENT
Part Four: Risk Planning and Risk Analysis..................................................................................14
1. Assumptions made:................................................................................................................14
2. Risk Identification Framework:.............................................................................................14
3. Risk Management Strategy:...................................................................................................15
Part Five: Quality Management Plan.............................................................................................16
1. Philosophy of team:...............................................................................................................16
2. Ensuring Quality:...................................................................................................................17
2.1 Verification Activities:....................................................................................................17
2.2 Validation Activities:.......................................................................................................17
Part 6: Closure and Evaluation:.....................................................................................................17
1. Annotated Bibliography:.......................................................................................................17
2. Checklist:...............................................................................................................................17
3. Project Evaluation:.................................................................................................................18
Bibliography:.................................................................................................................................19
Appendix:......................................................................................................................................21
Document Page
3ICT PROJECT MANAGEMENT
Introduction
The report below describes the case study of Globex Corporation who is in charge to
make the mobile based farming application. This report states measurable organization value for
the application that is to be built while developing the system. This project also states the project
scope that will be used for developing the application software. There is also a WBS that states
the work breakdown structure of developing the project and risk framework is also identified that
might occur while project development. This report also contains a project evaluation and project
closure phase related with the project.
Project Description
The Globex Corporation is a company that is famous for its excellence and provides help
to the farmers to increase their production and their working efficiency. The application that is
being developed in this project will include technologies that will provide commercial solutions
to all farmers using the application. This project mainly aims to provide an application so that
they can make easy decisions and can handle the problem related to growing of crops.
Part One: MOV (Measurable Organizational Value)
1. Impact Area of Given case Study:
Operational: The application of Globex built will have accuracy related to the
functionality of the application and also includes high operational value.
Strategy: The strategy of the mobile based application is to manage all the farmers who
are associated with the system. The application will also help to monitor the farmers.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4ICT PROJECT MANAGEMENT
Customer: The customers associated with the system are the farmers and the owner of
Globex will not be affected from the system.
Social: Mobile based application of Globex Corporation will help the organization to
efficiently manage all the operations related to farming.
Financial: The system of the MBFSA will help the organization to earn profit.
2. Target and Expectation of Stakeholders:
Stakeholders Expectations Target
(Need for
Improvement)
Virtucon The company that manages the project
along with Globex
High
Globex Corporation Globex need a mobile based information
system for helping the farmers
High
Development Team Develop the farmer mobile application High
Farmers and
Volunteers
Includes Communication Medium
Document Page
5ICT PROJECT MANAGEMENT
3. Timeframe Included:
Figure 1: Timeframe of the project
4. Summarization of MOV:
Serial
No
MOV Description
1 Project Description Defines the project aim and objective
2 Impact Area Identifying all impacts related to finance,
budget, risks and quality of the project.
3 Value of project Performance value should be provided.
4 Stakeholders expectation Helps to increase efficiency in the project
5 Timeframe 223 Days
Document Page
6ICT PROJECT MANAGEMENT
Part Two: Defining Scope
1. Defining Scope and Producing Scope Management Plan:
1.1 Requirements of projects
The requirement of the project includes that the project should be cost efficient, and
should maintain the time frame of the project. The project should have high performance value
and should be functional.
1.2 In scope and project out Scope
In scope of project is
ï‚· Developing the system within in the budget scheduled.
ï‚· Should be able the manage the team members of the project
ï‚· Should be able to farmers associated.
Project out scope
ï‚· Training should be provided to the employees of Globex for handling the system.
ï‚· Install the application system
2. Management of Scope:
All the activities should be followed so that the project can be competed in the give time
frame.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7ICT PROJECT MANAGEMENT
3. Resources of Project:
Figure 1: Screenshot of resource Sheet
Part Three: Work Breakdown Structure
1. Milestones in project schedule:
Project WBS:
Development of Mobile
application
System Design
Requirement
Specification
Analysis of
requirement
Designing interface
prototype
Defining features of
prototype
Accessing roles
prototype
Finalysing the
prototype
Project Inititaion
Developing the
project charter
Project sign in
Project planning
Defining scope
Scope management
plan
Establish team for
project development
Developing WBS
Defining project
schedule
Establishing budget
Performing Analysis
of Risks
Quality management
Checklists
System Development
Developing the
coding
Debudding the
coding
System testing
Carrying out unit
testing
Component testing
Implementing
integration testing
User Testing
Acceptance Testing
Checklists
System installation
Deploying the
system
Employee training
Provide training
materials
Maintenance
Checklists
Project Closure
Checking all
contrainsts
Documentation
Project sign off
Handing over the
project
Document Page
8ICT PROJECT MANAGEMENT
Figure 2: Work Breakdown Structure
Project Milestones:
Task Name Duration Start Finish
Finalizing the prototype 0 days Tue 23/04/19 Tue 23/04/19
Project sign in 0 days Tue 30/04/19 Tue 30/04/19
Checklists 0 days Wed 10/07/19 Wed 10/07/19
Checklists 0 days Tue 15/10/19 Tue 15/10/19
Checklists 0 days Fri 15/11/19 Fri 15/11/19
Project sign off 0 days Wed 11/12/19 Wed 11/12/19
Handing over the project 0 days Wed 11/12/19 Wed 11/12/19
2. Activities performed for each deliverables:
Deliverables Activities
System Design
Requirement Specification
Analysis of requirement
Designing interface prototype
Defining features of prototype
Accessing roles prototype
Finalizing the prototype
Project Initiation
Developing the project charter
Project sign in
Project planning
Defining scope
Scope management plan
Establish team for project development
Developing WBS
Defining project schedule
Establishing budget
Performing Analysis of Risks
Quality management
Checklists
System Development Developing the coding
Debugging the coding
System testing Carrying out unit testing
Component testing
Implementing integration testing
User Testing
Document Page
9ICT PROJECT MANAGEMENT
Acceptance Testing
Checklists
System installation
Deploying the system
Employee training
Provide training materials
Maintenance
Checklists
Project Closure
Checking all constraints
Documentation
Project sign off
Handing over the project
3. Resources Used
Resource Name Type Material
Label Initials Group Max.
Units Std. Rate
Project Manager Work P 100% $110.00/hr
Quality manager Work Q 100% $90.00/hr
Financial manager Work F 100% $90.00/hr
Programmer Work P 100% $50.00/hr
Prototype designer Work P 100% $50.00/hr
Risk Manager Work R 100% $12.00/hr
Employees of Globex
Corporation Work E 100% $10.00/hr
Hardware Requirement Material H $1,500.00
Software Requirement Material S $2,000.00
Software Engineer Work S 100% $60.00/hr
System analyst Work S 100% $60.00/hr
Team members Work T 100% $10.00/hr
4. Estimating time for all activities
Task Name Duration Start Finish
Development of Mobile Application 223 days Mon 4/02/19 Wed 11/12/19
System Design 57 days Mon 4/02/19 Tue 23/04/19
Requirement Specification 10 days Mon 4/02/19 Fri 15/02/19
Analysis of requirement 10 days Mon 18/02/19 Fri 1/03/19
Designing interface prototype 10 days Mon 4/03/19 Fri 15/03/19
Defining features of prototype 15 days Mon 18/03/19 Fri 5/04/19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10ICT PROJECT MANAGEMENT
Accessing roles prototype 12 days Mon 8/04/19 Tue 23/04/19
Finalizing the prototype 0 days Tue 23/04/19 Tue 23/04/19
Project Initiation 56 days Wed 24/04/19 Wed 10/07/19
Developing the project charter 5 days Wed 24/04/19 Tue 30/04/19
Project sign in 0 days Tue 30/04/19 Tue 30/04/19
Project planning 8 days Wed 1/05/19 Fri 10/05/19
Defining scope 5 days Mon 13/05/19 Fri 17/05/19
Scope management plan 8 days Mon 20/05/19 Wed 29/05/19
Establish team for project development 5 days Thu 30/05/19 Wed 5/06/19
Developing WBS 5 days Thu 6/06/19 Wed 12/06/19
Defining project schedule 5 days Thu 13/06/19 Wed 19/06/19
Establishing budget 5 days Thu 20/06/19 Wed 26/06/19
Performing Analysis of Risks 5 days Thu 27/06/19 Wed 3/07/19
Quality management 5 days Thu 4/07/19 Wed 10/07/19
Checklists 0 days Wed 10/07/19 Wed 10/07/19
System Development 30 days Thu 11/07/19 Wed 21/08/19
Developing the coding 15 days Thu 11/07/19 Wed 31/07/19
Debugging the coding 15 days Thu 1/08/19 Wed 21/08/19
System testing 39 days Thu 22/08/19 Tue 15/10/19
Carrying out unit testing 15 days Thu 22/08/19 Wed 11/09/19
Component testing 8 days Thu 12/09/19 Mon 23/09/19
Implementing integration testing 8 days Tue 24/09/19 Thu 3/10/19
User Testing 5 days Fri 4/10/19 Thu 10/10/19
Acceptance Testing 3 days Fri 11/10/19 Tue 15/10/19
Checklists 0 days Tue 15/10/19 Tue 15/10/19
System installation 23 days Wed 16/10/19 Fri 15/11/19
Deploying the system 2 days Wed 16/10/19 Thu 17/10/19
Employee training 10 days Fri 18/10/19 Thu 31/10/19
Provide training materials 1 day Fri 1/11/19 Fri 1/11/19
Maintenance 10 days Mon 4/11/19 Fri 15/11/19
Checklists 0 days Fri 15/11/19 Fri 15/11/19
Project Closure 18 days Mon 18/11/19 Wed 11/12/19
Checking all constraints 10 days Mon 18/11/19 Fri 29/11/19
Documentation 8 days Mon 2/12/19 Wed 11/12/19
Project sign off 0 days Wed 11/12/19 Wed 11/12/19
Handing over the project 0 days Wed 11/12/19 Wed 11/12/19
5. Project Budget
Task Name Cost
Document Page
11ICT PROJECT MANAGEMENT
Development of Mobile Application $471,180.00
System Design $119,472.00
Requirement Specification $20,960.00
Analysis of requirement $20,960.00
Designing interface prototype $20,960.00
Defining features of prototype $31,440.00
Accessing roles prototype $25,152.00
Finalizing the prototype $0.00
Project Initiation $117,920.00
Developing the project charter $10,400.00
Project sign in $0.00
Project planning $16,640.00
Defining scope $10,400.00
Scope management plan $16,640.00
Establish team for project development $10,400.00
Developing WBS $10,400.00
Defining project schedule $10,400.00
Establishing budget $10,880.00
Performing Analysis of Risks $10,880.00
Quality management $10,880.00
Checklists $0.00
System Development $46,700.00
Developing the coding $25,100.00
Debugging the coding $21,600.00
System testing $93,600.00
Carrying out unit testing $36,000.00
Component testing $19,200.00
Implementing integration testing $19,200.00
User Testing $12,000.00
Acceptance Testing $7,200.00
Checklists $0.00
System installation $59,248.00
Deploying the system $5,152.00
Employee training $25,760.00
Provide training materials $2,576.00
Maintenance $25,760.00
Checklists $0.00
Project Closure $34,240.00
Checking all constraints $20,160.00
Documentation $14,080.00
Project sign off $0.00