Project Management Report: i-Crop Application for Globex and Virtucon
VerifiedAdded on 2020/10/05
|11
|3100
|137
Project
AI Summary
This project management report presents a comprehensive case study on the i-Crop project, a collaborative venture between Globex Corporation and Virtucon. The assignment details the project's introduction, objectives, and the development of a project management team, outlining each member's roles and responsibilities. It includes a team charter, detailing skills, communication strategies, and ethical considerations. The report further explores the learning cycle, defining roles for team meetings, and analyzing the project's stakeholders, including suppliers, clients, and investors. A communication plan is also developed to facilitate information flow among stakeholders, ensuring effective project management. The analysis provides insights into the application's features, technological aspects, and the overall goal of enhancing farming solutions through an online interface.

Project Management
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Table of Contents
INTRODUCTION...........................................................................................................................1
PART 1............................................................................................................................................1
PART 2............................................................................................................................................4
PART 3............................................................................................................................................5
PART 4............................................................................................................................................6
CONCLUSION ...............................................................................................................................7
REFERENCES................................................................................................................................8
INTRODUCTION...........................................................................................................................1
PART 1............................................................................................................................................1
PART 2............................................................................................................................................4
PART 3............................................................................................................................................5
PART 4............................................................................................................................................6
CONCLUSION ...............................................................................................................................7
REFERENCES................................................................................................................................8

INTRODUCTION
Project management is the process of managing a set of activities such as planning,
executing, controlling and directing which are used in completion of a project. This provides a
proper framework about principles, techniques, methods and tools which can help the project
manager to finish each activity of the project within the stimulated time frame. A project is
managed by a highly productive and efficient members who devote themselves in their job. In
this report, a case study on Globex Corporation and Virtucon is studied in order to understand
the concept of Project management. Main objective of this assignment is to conduct a project
management by considering given case scenario. A team along with its members is developed to
describe their key individual roles and responsibilities. A learning cycle along with
communication plan is also prepared in order to develop a reflective experience (Besner and
Hobbs, 2013).
PART 1
Project name – This is the tittle of a project management team by which they are
recognised and can have a unique identity among others. For this team, name which is
considered as suitable is “Project i-Crop Globex and Virtucon”. The reason behind selecting
this tittle is it includes various variables which indicate involved organisations and the new
innovation which is been introduced by these business entities.
List of all team members along with their contact details:
Name Code Address Contact no.
Chandler Tribianni 1 235, 1 Avenue street, New South Wales,
Australia
0421005177
Jospeh Green 2 25, Muscle Creek, New South Wales, Australia 0421006187
Jack Geller 3 A15, Bowmans Creek, New South Wales,
Australia
0421007548
Phoebhe Mathew 4 B84, Falbrook, NSW, Australia 0421005458
Mike Stephen 5 662, Denman street, NSW, Australia 0421007569
Monica Bing 6 56, Yarrawa, NSW, Australia 0421001256
1
Project management is the process of managing a set of activities such as planning,
executing, controlling and directing which are used in completion of a project. This provides a
proper framework about principles, techniques, methods and tools which can help the project
manager to finish each activity of the project within the stimulated time frame. A project is
managed by a highly productive and efficient members who devote themselves in their job. In
this report, a case study on Globex Corporation and Virtucon is studied in order to understand
the concept of Project management. Main objective of this assignment is to conduct a project
management by considering given case scenario. A team along with its members is developed to
describe their key individual roles and responsibilities. A learning cycle along with
communication plan is also prepared in order to develop a reflective experience (Besner and
Hobbs, 2013).
PART 1
Project name – This is the tittle of a project management team by which they are
recognised and can have a unique identity among others. For this team, name which is
considered as suitable is “Project i-Crop Globex and Virtucon”. The reason behind selecting
this tittle is it includes various variables which indicate involved organisations and the new
innovation which is been introduced by these business entities.
List of all team members along with their contact details:
Name Code Address Contact no.
Chandler Tribianni 1 235, 1 Avenue street, New South Wales,
Australia
0421005177
Jospeh Green 2 25, Muscle Creek, New South Wales, Australia 0421006187
Jack Geller 3 A15, Bowmans Creek, New South Wales,
Australia
0421007548
Phoebhe Mathew 4 B84, Falbrook, NSW, Australia 0421005458
Mike Stephen 5 662, Denman street, NSW, Australia 0421007569
Monica Bing 6 56, Yarrawa, NSW, Australia 0421001256
1
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Rose Buffay 7 B58, Goorangoola street, NSW, Australia 0421005658
Jennefir Cox 8 1, Kayuga circle, NSW, Australia 0421006254
Matt Schwimmer 9 6, Wybong circle, NSW, Australia 0421001123
David Perry 10 25, Sandy Hollow street, NSW, Australia 0421005256
Overview of the project – Globex Corporation is a business organisation which was
incorporated in 2013 and operates in several locations such as Albury, griffith and Wagga
Wagga. This case scenario is concerned with the introduction of new application i-Corp which is
planned to be developed by Virtucon, this organisation is known for providing reliable solutions
for information technology and apps in house. Globex has recently opened an office at Orange so
that they can capture the market of Central West and can fulfil the requirements of Stud farms in
that region. This application is planned to be developed due to bring simplicity and convenience
in getting solutions related to farming. By the way of i-Crop, this organisation is planning to
provide them other services also, some of them includes offers, bids, seasonal sales, procuring
market information and others.
Project description – Globex Corporation is an organisation which provides solutions
for farming and agriculture that are reliable and cost effective. This organisation is planning to
introduce an online interface by the way of website and application. This application is planned
to named as i-Crop, in order to develop this application organisation has contracted with an IT
solution company named as Virtucon. The main aim of introducing this innovative website is to
serve their clients a convenience about ordering crops sample and various kinds of pesticides,
this application will also assist farmers to find solutions for their agriculture related queries.
Features and functions that are expected by Globex from i-Crop are required to be fulfilled by
Virtucon.
This organisation wants that i-Crop will enable the clients to be facilitated by the
transactional features such as offers and bids in which they can set the selling price of their grain
and sellers can offer them various bids. Another major feature which is needed to be
incorporated in this website is the facility to assess information related to market and site.
Technological factors which are Globex wants in i-Crop are that the application will be free of
cost and only network charges should be applicable on users. Another important aspect of i-Crop
is that users should be able to switch their roles from buyer to grower so that they can get reliable
2
Jennefir Cox 8 1, Kayuga circle, NSW, Australia 0421006254
Matt Schwimmer 9 6, Wybong circle, NSW, Australia 0421001123
David Perry 10 25, Sandy Hollow street, NSW, Australia 0421005256
Overview of the project – Globex Corporation is a business organisation which was
incorporated in 2013 and operates in several locations such as Albury, griffith and Wagga
Wagga. This case scenario is concerned with the introduction of new application i-Corp which is
planned to be developed by Virtucon, this organisation is known for providing reliable solutions
for information technology and apps in house. Globex has recently opened an office at Orange so
that they can capture the market of Central West and can fulfil the requirements of Stud farms in
that region. This application is planned to be developed due to bring simplicity and convenience
in getting solutions related to farming. By the way of i-Crop, this organisation is planning to
provide them other services also, some of them includes offers, bids, seasonal sales, procuring
market information and others.
Project description – Globex Corporation is an organisation which provides solutions
for farming and agriculture that are reliable and cost effective. This organisation is planning to
introduce an online interface by the way of website and application. This application is planned
to named as i-Crop, in order to develop this application organisation has contracted with an IT
solution company named as Virtucon. The main aim of introducing this innovative website is to
serve their clients a convenience about ordering crops sample and various kinds of pesticides,
this application will also assist farmers to find solutions for their agriculture related queries.
Features and functions that are expected by Globex from i-Crop are required to be fulfilled by
Virtucon.
This organisation wants that i-Crop will enable the clients to be facilitated by the
transactional features such as offers and bids in which they can set the selling price of their grain
and sellers can offer them various bids. Another major feature which is needed to be
incorporated in this website is the facility to assess information related to market and site.
Technological factors which are Globex wants in i-Crop are that the application will be free of
cost and only network charges should be applicable on users. Another important aspect of i-Crop
is that users should be able to switch their roles from buyer to grower so that they can get reliable
2
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

cost estimation and budgeted costs. Grain sales statistics and usage data are also few
characteristics of this application.
The main aim of Globex is to serve their clients and earn profit by contributing towards
farmers so that they can get accurate prices against their grains. The objective of selecting this
case scenario by the project management team is to develop a better understanding towards
various aspects such as online applications and websites, merging of organisations, agriculture
industry and introduction of an innovative idea.
Team charter:
A team charter is a professional document which states various aspects about a project
management team, these aspects can include skills and knowledge required, responsibilities of
members, communication factors and others. The main aim of this project is to provide a clarity
in direction and roles of different members (Team Charter, 2018).
Team Charter Canvas
Skills and Knowledge Inventory:
IT information about website designing
and application functioning.
Effective communications skills to
communicate various ideas among the
team members.
Leadership and motivational skills
which will encourage team members to
work better.
Roles and Responsibilities:
Manager – Development of project plan,
lead and manage members, ascertain
methodologies, assigning of tasks etc.
Team members – Contribution towards
project objective, provide expertise
knowledge, documenting whole process.
Various members are responsible for
different functions such as research,
information technology etc.
Team Communication:
Meetings Timings & location:
Objectives determination of project on
first day of week 35 at 1500 hours.
Assessment and evaluation of project
themes on third way of week 35 at 1300
hours. Drawing conclusions, recommendations
Team Rules & Expectations:
Experiences:
Working in a team can be positive and
negative. Positive aspects that I experienced
are the ideas of various team members which
can result into effective research and due to an
efficient team manager all team members can
get motivated to work batter. Negative aspect
3
characteristics of this application.
The main aim of Globex is to serve their clients and earn profit by contributing towards
farmers so that they can get accurate prices against their grains. The objective of selecting this
case scenario by the project management team is to develop a better understanding towards
various aspects such as online applications and websites, merging of organisations, agriculture
industry and introduction of an innovative idea.
Team charter:
A team charter is a professional document which states various aspects about a project
management team, these aspects can include skills and knowledge required, responsibilities of
members, communication factors and others. The main aim of this project is to provide a clarity
in direction and roles of different members (Team Charter, 2018).
Team Charter Canvas
Skills and Knowledge Inventory:
IT information about website designing
and application functioning.
Effective communications skills to
communicate various ideas among the
team members.
Leadership and motivational skills
which will encourage team members to
work better.
Roles and Responsibilities:
Manager – Development of project plan,
lead and manage members, ascertain
methodologies, assigning of tasks etc.
Team members – Contribution towards
project objective, provide expertise
knowledge, documenting whole process.
Various members are responsible for
different functions such as research,
information technology etc.
Team Communication:
Meetings Timings & location:
Objectives determination of project on
first day of week 35 at 1500 hours.
Assessment and evaluation of project
themes on third way of week 35 at 1300
hours. Drawing conclusions, recommendations
Team Rules & Expectations:
Experiences:
Working in a team can be positive and
negative. Positive aspects that I experienced
are the ideas of various team members which
can result into effective research and due to an
efficient team manager all team members can
get motivated to work batter. Negative aspect
3

and suggestions on last day of week 25
at 1400 hours. All these meetings need
to be conducted at Mosaic conference
hall.
Communication method – Ideas and comments
on the project will be communicated using open
discussion conference where two of the
members will be assigned to record all the
minutes and document it in a specified log table
so that there can be an ease while assessing that
information.
that I experienced and observed is that the
personal goals can effect team goals and
thought process of every member is different
due to which conflicts may occur. Overall
team goal of this project management team is
to conduct efficient and effective research
about this case.
Codes of ethics:
Integrity, transparency, respect and
professionalism are few of the pillars of this
team and every member as to behave by
considering all this codes.
Rules & expectations:
Regulations of this project includes proper
participation, cooperation, communication
and decision making. Few rules of this team
includes that vote of every member must be
equally considered and decision making
process should include every member.
Team Values:
Every member in the team should listen to each
others ideas and share knowledge, information
and experience. Concerns must be freely
expressed and a sense of integrity and
responsibility must to adapted.
Signature:
PART 2
Learning cycle:
Every role and responsibility should be rotated among the team members to ensure their
equal participation. Roles for the next team meeting classified as “Organiser” and “Scribe” is
described below (Learning cycle, 2011):
4
at 1400 hours. All these meetings need
to be conducted at Mosaic conference
hall.
Communication method – Ideas and comments
on the project will be communicated using open
discussion conference where two of the
members will be assigned to record all the
minutes and document it in a specified log table
so that there can be an ease while assessing that
information.
that I experienced and observed is that the
personal goals can effect team goals and
thought process of every member is different
due to which conflicts may occur. Overall
team goal of this project management team is
to conduct efficient and effective research
about this case.
Codes of ethics:
Integrity, transparency, respect and
professionalism are few of the pillars of this
team and every member as to behave by
considering all this codes.
Rules & expectations:
Regulations of this project includes proper
participation, cooperation, communication
and decision making. Few rules of this team
includes that vote of every member must be
equally considered and decision making
process should include every member.
Team Values:
Every member in the team should listen to each
others ideas and share knowledge, information
and experience. Concerns must be freely
expressed and a sense of integrity and
responsibility must to adapted.
Signature:
PART 2
Learning cycle:
Every role and responsibility should be rotated among the team members to ensure their
equal participation. Roles for the next team meeting classified as “Organiser” and “Scribe” is
described below (Learning cycle, 2011):
4
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Meeting: Objectives determination of project on first day of week 35 at 1500 hours
Organiser: For this team meeting, Organiser is the team member having “code 1”, which
should be changed in every future meeting.
Roles of Organiser includes:
As an organiser, I will make sure that every idea must considered and
voice of every member is heard.
Seeks feedback from other team members about ideas.
I will try to resolve disputes by keeping a constant positive attitude.
Update all the team members and provide clear vision and direction.
I will convey the ideas related to features and characteristics of i-Crop
along by identifying alternatives of this application and website.
I will consider ideas related to offers, bids and preferred buyers
introducing by Globex.
Scribe: Scribe are the other team members of the team which should also be rotated.
Roles of Scribe includes:
Scribe are the other team members for example, team members
having code 2-10 are scribes which needs to record all the important
information from the meeting.
They transact all the ideas discussed in the meeting and action points.
They take notes during the meeting which encourages me as an
organiser to focus on the discussion.
Minutes prepared by Scribe uses a specific template and covers all the
objectives along with action items.
Scribe take notes of all new innovative features which can be added
in i-Crop application and suggest measures for its improvement.
After completion of every meeting, Organiser will be changed. At the beginning of next
meeting that is Assessment of project meeting, organiser will be team member having code 2 and
so on.
5
Organiser: For this team meeting, Organiser is the team member having “code 1”, which
should be changed in every future meeting.
Roles of Organiser includes:
As an organiser, I will make sure that every idea must considered and
voice of every member is heard.
Seeks feedback from other team members about ideas.
I will try to resolve disputes by keeping a constant positive attitude.
Update all the team members and provide clear vision and direction.
I will convey the ideas related to features and characteristics of i-Crop
along by identifying alternatives of this application and website.
I will consider ideas related to offers, bids and preferred buyers
introducing by Globex.
Scribe: Scribe are the other team members of the team which should also be rotated.
Roles of Scribe includes:
Scribe are the other team members for example, team members
having code 2-10 are scribes which needs to record all the important
information from the meeting.
They transact all the ideas discussed in the meeting and action points.
They take notes during the meeting which encourages me as an
organiser to focus on the discussion.
Minutes prepared by Scribe uses a specific template and covers all the
objectives along with action items.
Scribe take notes of all new innovative features which can be added
in i-Crop application and suggest measures for its improvement.
After completion of every meeting, Organiser will be changed. At the beginning of next
meeting that is Assessment of project meeting, organiser will be team member having code 2 and
so on.
5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

PART 3
Stakeholders is an individual or a group of persons who has interest in an organisation
and whose support is important for the functioning of the business operations. These
stakeholders can be internal and external, in this case scenario of Globex i-Crop various
stakeholders are mentioned below:
Suppliers – These are the vendors who sell goods to the business. These stakeholders are
impacted by the introduction of i-Crop as now they can receive order by using a simple interface.
Clients – These are the customers of an organisation and in this case farmers are the
clients of Globex Corporation who seek the advise of this business related to agricultural issues.
After introduction of i-Crop, these clients will be positively influenced as they can solve their
queries by a single click.
Designers – These are the website and app designers of Globex which are influenced by
the introduction of i-Crop as they have to develop efficient application and website which can
fulfil all the requirements of their clients.
Employees – These are the personnel of Globex Corporation which conducts all the
operations of their business. Due to introduction of this new innovative application, their efforts
has to be multiplied.
Investors – These are the external related parties who invest money in the business of
Globex so that they can attain growth and development.
Creditors and debtors – Creditors and debtors are the lenders and receivers which helps
in the business operations of Globex. Their interest is also impacted by the introduction of i-corp.
Government regulators – As Globex corporation deals in agricultural practices,
interference of government regulatory bodies is necessary.
In order to communicate future aspects and developments of the organisation,
Communication plan for Globex is developed below:
Purpose of the communication is to convey and convince all the stakeholders of Globex
corporation about introduction of new website and application of i-Crop in which all the
related aspect of this change is required to be communicated.
Audience of this plan is all the stakeholders including employees, investors, government
regulatory bodies, creditors, debtors, suppliers, clients and many others.
Message for stakeholders is “i-Crop is a website and application which will provide a
6
Stakeholders is an individual or a group of persons who has interest in an organisation
and whose support is important for the functioning of the business operations. These
stakeholders can be internal and external, in this case scenario of Globex i-Crop various
stakeholders are mentioned below:
Suppliers – These are the vendors who sell goods to the business. These stakeholders are
impacted by the introduction of i-Crop as now they can receive order by using a simple interface.
Clients – These are the customers of an organisation and in this case farmers are the
clients of Globex Corporation who seek the advise of this business related to agricultural issues.
After introduction of i-Crop, these clients will be positively influenced as they can solve their
queries by a single click.
Designers – These are the website and app designers of Globex which are influenced by
the introduction of i-Crop as they have to develop efficient application and website which can
fulfil all the requirements of their clients.
Employees – These are the personnel of Globex Corporation which conducts all the
operations of their business. Due to introduction of this new innovative application, their efforts
has to be multiplied.
Investors – These are the external related parties who invest money in the business of
Globex so that they can attain growth and development.
Creditors and debtors – Creditors and debtors are the lenders and receivers which helps
in the business operations of Globex. Their interest is also impacted by the introduction of i-corp.
Government regulators – As Globex corporation deals in agricultural practices,
interference of government regulatory bodies is necessary.
In order to communicate future aspects and developments of the organisation,
Communication plan for Globex is developed below:
Purpose of the communication is to convey and convince all the stakeholders of Globex
corporation about introduction of new website and application of i-Crop in which all the
related aspect of this change is required to be communicated.
Audience of this plan is all the stakeholders including employees, investors, government
regulatory bodies, creditors, debtors, suppliers, clients and many others.
Message for stakeholders is “i-Crop is a website and application which will provide a
6

simpler interface so that it can facilitate all the customers and other related users.”
Media of communication is meeting and focus group.
Feedback for the introduction of i-Crop will be taken to ensure all the concerns of
stakeholders.
Follow up
To communicate the whole plan with stakeholders using above steps, communication plan is
developed below:
Stakeholder Information Phase Mode When
Suppliers Progress report Implementation Meeting Before launching
i-Crop
Clients Evaluation
document
Implementation Meeting Before launching
i-Crop
Designers Updated schedule Implementation Meeting Before launching
i-Crop
Employees Updated schedule Implementation Meeting Before launching
i-Crop
Investors Growth rate
report
Implementation Email Before launching
i-Crop
Creditors and
debtors
Course invitation Implementation Meeting Before launching
i-Crop
Government
regulators
Financial audited
report
Evaluation Email Annually
PART 4
According to me leadership qualities are the support system of managing a project
effectively. Various skills which a organiser or leader should possess are excellent
communication and interpersonal skills, positive attitude and enthusiasm towards project work.
While conducting this project, I experienced that view points of various team members vary
from each other due to which several conflicts arise which were complicated to be resolved by
7
Media of communication is meeting and focus group.
Feedback for the introduction of i-Crop will be taken to ensure all the concerns of
stakeholders.
Follow up
To communicate the whole plan with stakeholders using above steps, communication plan is
developed below:
Stakeholder Information Phase Mode When
Suppliers Progress report Implementation Meeting Before launching
i-Crop
Clients Evaluation
document
Implementation Meeting Before launching
i-Crop
Designers Updated schedule Implementation Meeting Before launching
i-Crop
Employees Updated schedule Implementation Meeting Before launching
i-Crop
Investors Growth rate
report
Implementation Email Before launching
i-Crop
Creditors and
debtors
Course invitation Implementation Meeting Before launching
i-Crop
Government
regulators
Financial audited
report
Evaluation Email Annually
PART 4
According to me leadership qualities are the support system of managing a project
effectively. Various skills which a organiser or leader should possess are excellent
communication and interpersonal skills, positive attitude and enthusiasm towards project work.
While conducting this project, I experienced that view points of various team members vary
from each other due to which several conflicts arise which were complicated to be resolved by
7
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

the organiser of that meeting. Other leadership quality of a leader include integrity, competence,
patience, calmness and team builder which I experienced that is lacking somewhere due to lack
of competence and time. My experience compared to my understanding has deviations some
where and these variations are the result of real world problems which includes conflicts and
surrounding situations.
As per my perspective, techniques and skills which are required by an Information
Communications technology manager are leadership, motivation, organisation, prioritisation and
adaptability as these skills can ensure efficient working of IT department of an organisation. In
this case scenario, Globex Corporation is planning to launch a new website and application
named as i-Crop in which there is a wide scope of Information technology. While conducting
this project, I experienced that due to low knowledge of IT, organisation has to face various
issues and by this statement it can be said that Globex has done a right thing by hiring Virtucon
to design and develop their website and application. By successfully achieving goals of this
project, I can say that problem solving and prioritisation are the most aspects of leadership.
CONCLUSION
From the above assignment, it can be concluded that Globex Corporation is introducing a
website and application named as i-Crop on which a project is managed by a project
management team. The main aim of this report of conducting a Project Management is
successfully achieved by developing a proper communication plan along with team carter
canvas. Project management is the most important branch of business while introducing any new
product, policy, method or innovation.
8
patience, calmness and team builder which I experienced that is lacking somewhere due to lack
of competence and time. My experience compared to my understanding has deviations some
where and these variations are the result of real world problems which includes conflicts and
surrounding situations.
As per my perspective, techniques and skills which are required by an Information
Communications technology manager are leadership, motivation, organisation, prioritisation and
adaptability as these skills can ensure efficient working of IT department of an organisation. In
this case scenario, Globex Corporation is planning to launch a new website and application
named as i-Crop in which there is a wide scope of Information technology. While conducting
this project, I experienced that due to low knowledge of IT, organisation has to face various
issues and by this statement it can be said that Globex has done a right thing by hiring Virtucon
to design and develop their website and application. By successfully achieving goals of this
project, I can say that problem solving and prioritisation are the most aspects of leadership.
CONCLUSION
From the above assignment, it can be concluded that Globex Corporation is introducing a
website and application named as i-Crop on which a project is managed by a project
management team. The main aim of this report of conducting a Project Management is
successfully achieved by developing a proper communication plan along with team carter
canvas. Project management is the most important branch of business while introducing any new
product, policy, method or innovation.
8
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

REFERENCES
Books and Journals:
Besner, C. and Hobbs, B., 2013. Contextualized project management practice: A cluster analysis
of practices and best practices. Project Management Journal. 44(1). pp.17-34.
Fortune, J., and et. al., 2011. Looking again at current practice in project management.
International Journal of Managing Projects in Business. 4(4). pp.553-572.
Kerzner, H. and Kerzner, H. R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E. W., and et. al., 2014. Project management: The managerial process (Vol. 6).
Grandview Heights, OH: McGraw-Hill Education.
Meredith, J. R. and Mantel Jr, S. J., 2011. Project management: a managerial approach. John
Wiley & Sons.
Tadeu de Oliveira Lacerda, R., Ensslin, L. and Rolim Ensslin, S., 2011. A performance
measurement view of IT project management. International Journal of Productivity and
Performance Management. 60(2). pp.132-151.
Turner, J. R., 2014. Handbook of project-based management (Vol. 92). New York, NY:
McGraw-hill.
Wysocki, R. K., 2011. Effective project management: traditional, agile, extreme. John Wiley &
Sons.
Online
Team Charter. 2018. [online]. Available through:
<https://www.thomasinternational.net/en-gb/blog/june-2017/team-charter-how-to/>
Learning cycle. 2011. [online]. Available through:
<https://www.pmi.org/learning/library/learning-framework-pm-2018>
9
Books and Journals:
Besner, C. and Hobbs, B., 2013. Contextualized project management practice: A cluster analysis
of practices and best practices. Project Management Journal. 44(1). pp.17-34.
Fortune, J., and et. al., 2011. Looking again at current practice in project management.
International Journal of Managing Projects in Business. 4(4). pp.553-572.
Kerzner, H. and Kerzner, H. R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E. W., and et. al., 2014. Project management: The managerial process (Vol. 6).
Grandview Heights, OH: McGraw-Hill Education.
Meredith, J. R. and Mantel Jr, S. J., 2011. Project management: a managerial approach. John
Wiley & Sons.
Tadeu de Oliveira Lacerda, R., Ensslin, L. and Rolim Ensslin, S., 2011. A performance
measurement view of IT project management. International Journal of Productivity and
Performance Management. 60(2). pp.132-151.
Turner, J. R., 2014. Handbook of project-based management (Vol. 92). New York, NY:
McGraw-hill.
Wysocki, R. K., 2011. Effective project management: traditional, agile, extreme. John Wiley &
Sons.
Online
Team Charter. 2018. [online]. Available through:
<https://www.thomasinternational.net/en-gb/blog/june-2017/team-charter-how-to/>
Learning cycle. 2011. [online]. Available through:
<https://www.pmi.org/learning/library/learning-framework-pm-2018>
9
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.