CIS8010 Project: 5G Technology Implementation in Healthcare, S2 2019
VerifiedAdded on 2022/10/17
|23
|4144
|330
Project
AI Summary
This project management assignment focuses on implementing 5G technology within Gosford Private Hospital in Australia. The project includes a detailed plan, addressing the business assumptions, expanding the ICT unit, and estimating costs and resources. The project plan incorporates quality assurance, cost and resource structures, timelines, and milestones. The report contains a cost-benefit analysis, recommendations for managing the project and integration, an implementation plan, and a post-implementation plan. Key components include a PERT chart, Gantt chart, and cost structure analysis, demonstrating the project's feasibility and potential benefits such as improved telemedicine and patient care. The project aims to enhance the hospital's processes and attract more customers through faster data transmission and improved communication capabilities using 5G technology.

Running head: PROJECT MANAGEMENT
Implementation of 5G technologies in health care center
Name of Student-
Name of University-
Author’s Note-
Implementation of 5G technologies in health care center
Name of Student-
Name of University-
Author’s Note-
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1PROJECT MANAGEMENT
Executive Summary
This project deals with implementing 5G technology in the working process of Gosford Private
Hospital. The organization wants to improve its business process so that it can attract more
customers from national as well as international customers. The organization wants to speed up
their processes by implementing 5G technology and wants to have the opportunity to provide its
service in the remotes areas as well. To speed up their network and to increase customer
retention, 5G technologies will be implemented in the system of the hospital. This report states
detailed project plan for implementing the process in the system.
Executive Summary
This project deals with implementing 5G technology in the working process of Gosford Private
Hospital. The organization wants to improve its business process so that it can attract more
customers from national as well as international customers. The organization wants to speed up
their processes by implementing 5G technology and wants to have the opportunity to provide its
service in the remotes areas as well. To speed up their network and to increase customer
retention, 5G technologies will be implemented in the system of the hospital. This report states
detailed project plan for implementing the process in the system.

2PROJECT MANAGEMENT
Table of Contents
Assignment 3: (Part 1) Project Plan.................................................................................................2
1. Assumptions of business and incorporating 5G technologies:................................................2
2. Expanding ICT unit to 5G technologies to business:..............................................................2
3. Quality, Cost and Resource Estimation...................................................................................3
4. Time sheet with milestone and slack.......................................................................................7
5. Project Plan..............................................................................................................................9
Assignment 3: (Part 2) Written Report..........................................................................................12
1. Cost Benefit Analysis............................................................................................................12
2. Recommendations for managing the project.........................................................................13
3. Recommendations for managing project integration.............................................................14
4. Implementation plan..............................................................................................................15
5. Post Implementation plan......................................................................................................16
Recommendation and Conclusion.................................................................................................17
References......................................................................................................................................19
Table of Contents
Assignment 3: (Part 1) Project Plan.................................................................................................2
1. Assumptions of business and incorporating 5G technologies:................................................2
2. Expanding ICT unit to 5G technologies to business:..............................................................2
3. Quality, Cost and Resource Estimation...................................................................................3
4. Time sheet with milestone and slack.......................................................................................7
5. Project Plan..............................................................................................................................9
Assignment 3: (Part 2) Written Report..........................................................................................12
1. Cost Benefit Analysis............................................................................................................12
2. Recommendations for managing the project.........................................................................13
3. Recommendations for managing project integration.............................................................14
4. Implementation plan..............................................................................................................15
5. Post Implementation plan......................................................................................................16
Recommendation and Conclusion.................................................................................................17
References......................................................................................................................................19

3PROJECT MANAGEMENT
Assignment 3: (Part 1) Project Plan
1. Assumptions of business and incorporating 5G technologies:
The private health care organization that wants to implement 5G technologies in its
business process is Gosford Privet Hospital situated in the NSW of Australia. The business has
many modern technologies that has improved the health care services in Australia and recently
the organization wants to implement 5G technology to enhance the working speed and the
features of the application that are used to diagnose the health of the patients (Hossain and
Muhammad 2017). 5G technology is an extension of 3G and 4G this emerging network
capitalize in all interface variety. With the 5G connected device, the patients and the employees
working in the private hospital and get experience more enhance services. The 5G technologies
would improve the patient care and diagnosis process and includes changes in the models of
health care. This report states the details of implementing the 5G technology in the private
hospital.
2. Expanding ICT unit to 5G technologies to business:
In the private health care hospital, the implementation of 5G technology helps people to
communicate well with the private hospitals even from the rural areas (Thuemmler et al. 2018).
Expanding the business process to 5G will expand the services to suburb areas of Australia and
thus can save time for treatment. 5G system will help to monitor patients from different
locations. With the 5G technology implementation in the business working process, the business
will get following advantages:
1. Quickly transmit the large file that might consists of patient’s data or some diagnosis
report that are needed by the doctors immediately (Magsi et al. 2018). Adding the 5G
Assignment 3: (Part 1) Project Plan
1. Assumptions of business and incorporating 5G technologies:
The private health care organization that wants to implement 5G technologies in its
business process is Gosford Privet Hospital situated in the NSW of Australia. The business has
many modern technologies that has improved the health care services in Australia and recently
the organization wants to implement 5G technology to enhance the working speed and the
features of the application that are used to diagnose the health of the patients (Hossain and
Muhammad 2017). 5G technology is an extension of 3G and 4G this emerging network
capitalize in all interface variety. With the 5G connected device, the patients and the employees
working in the private hospital and get experience more enhance services. The 5G technologies
would improve the patient care and diagnosis process and includes changes in the models of
health care. This report states the details of implementing the 5G technology in the private
hospital.
2. Expanding ICT unit to 5G technologies to business:
In the private health care hospital, the implementation of 5G technology helps people to
communicate well with the private hospitals even from the rural areas (Thuemmler et al. 2018).
Expanding the business process to 5G will expand the services to suburb areas of Australia and
thus can save time for treatment. 5G system will help to monitor patients from different
locations. With the 5G technology implementation in the business working process, the business
will get following advantages:
1. Quickly transmit the large file that might consists of patient’s data or some diagnosis
report that are needed by the doctors immediately (Magsi et al. 2018). Adding the 5G
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4PROJECT MANAGEMENT
technology to the network, medical imagery as well as data files can be transferred that would
improve the process of patient care in the system.
2. This would also improve the telemedicine help for the hospital. Telemedicine needs a
high speed network that is capable of providing high video quality and this technology also
includes mobile networks for handling the appointments that are made through telemedicine
(Lema et al. 2017). This would help to make the treatment process faster.
3. The implementation of 5G technology in the private hospital also helps to improve the
AR, spatial computing as well as include VR in the system (Chen et al. 2017). Implementation
of 5G would help to enhance the ability of the doctor so that they can get innovative as well as
less treatments that are invasive.
4. This system would provide remote monitoring for the patients and helps to gather
some data that helps to improve the preventive care as well as the personalized care for the
patients (West 2016).
3. Quality, Cost and Resource Estimation
3.1 Quality Structure:
There is 10 significant ways for improving quality of the project. The quality of the
project matters in completing the project and the aim is also to maintain the quality of the project
as well as deliver the project within the budget. For maintaining project quality, the following
processes are to be carried out.
1. Define the project quality: Before starting the project, the quality of the project is to be
defined which states the degree of the project that is to be set in the project (Chofreh et al.
technology to the network, medical imagery as well as data files can be transferred that would
improve the process of patient care in the system.
2. This would also improve the telemedicine help for the hospital. Telemedicine needs a
high speed network that is capable of providing high video quality and this technology also
includes mobile networks for handling the appointments that are made through telemedicine
(Lema et al. 2017). This would help to make the treatment process faster.
3. The implementation of 5G technology in the private hospital also helps to improve the
AR, spatial computing as well as include VR in the system (Chen et al. 2017). Implementation
of 5G would help to enhance the ability of the doctor so that they can get innovative as well as
less treatments that are invasive.
4. This system would provide remote monitoring for the patients and helps to gather
some data that helps to improve the preventive care as well as the personalized care for the
patients (West 2016).
3. Quality, Cost and Resource Estimation
3.1 Quality Structure:
There is 10 significant ways for improving quality of the project. The quality of the
project matters in completing the project and the aim is also to maintain the quality of the project
as well as deliver the project within the budget. For maintaining project quality, the following
processes are to be carried out.
1. Define the project quality: Before starting the project, the quality of the project is to be
defined which states the degree of the project that is to be set in the project (Chofreh et al.

5PROJECT MANAGEMENT
2018). It is needed to check the project and define the criteria of quality that is to be carried out
in the project.
2. Stick to requirements of project: The project requirement are to be defined at the
starting of the project and till the project ends, the project requirements are to be followed to
complete the project successfully.
3. Include quality assurance: The plan for quality management is to be defined within the
project including the project processes as well as standards of the project that are initially stated
for the project (Heerden, Kleingeld, and Vosloo 2015).
4. Control project quality: The quality of the project is to be controlled by ensuring that
the deliverables of the project are correct and they do not have any defects when they are
included in the project.
5. Following project processes: Follow all the processes as well as the tasks that are
included in the initial project plan. More way to complete the project with high quality should be
included for implementing the 5G technology in the system.
3.2 Cost Structure:
Task Name Cost
Implementing 5G Technology $181,000.00
Project Planning $54,840.00
Get Stakeholder Research $15,360.00
Interview the Stakeholders $8,160.00
Stakeholder Analysis $7,200.00
Initial plan for implementation $39,480.00
Select the processes $4,000.00
2018). It is needed to check the project and define the criteria of quality that is to be carried out
in the project.
2. Stick to requirements of project: The project requirement are to be defined at the
starting of the project and till the project ends, the project requirements are to be followed to
complete the project successfully.
3. Include quality assurance: The plan for quality management is to be defined within the
project including the project processes as well as standards of the project that are initially stated
for the project (Heerden, Kleingeld, and Vosloo 2015).
4. Control project quality: The quality of the project is to be controlled by ensuring that
the deliverables of the project are correct and they do not have any defects when they are
included in the project.
5. Following project processes: Follow all the processes as well as the tasks that are
included in the initial project plan. More way to complete the project with high quality should be
included for implementing the 5G technology in the system.
3.2 Cost Structure:
Task Name Cost
Implementing 5G Technology $181,000.00
Project Planning $54,840.00
Get Stakeholder Research $15,360.00
Interview the Stakeholders $8,160.00
Stakeholder Analysis $7,200.00
Initial plan for implementation $39,480.00
Select the processes $4,000.00

6PROJECT MANAGEMENT
Documenting the project management $22,680.00
Developing Project Charter $3,200.00
Defining Project Scope $5,120.00
Develop Project Plan $5,280.00
Analyze the Risks $3,960.00
Include communication strategy $5,120.00
Implement KPI Metrics $5,120.00
Develop Business Case $7,680.00
Designing Phase $12,800.00
Analyzing the system $3,200.00
Designing the network diagram $3,840.00
Gathering equipment $5,760.00
Implementing Phase $39,760.00
Set up new systems $6,000.00
Network Design $12,200.00
Connecting subnet $21,560.00
Testing Phase $29,520.00
Testing the systems $8,200.00
Testing sub-nets $6,560.00
Integrate the tested systems $6,560.00
Document the testing $8,200.00
Maintenance phase $21,920.00
Train the employees $7,200.00
Maintain the networks $7,360.00
Implement secure encryption technique $7,360.00
Checklist on testing $0.00
Documenting the project management $22,680.00
Developing Project Charter $3,200.00
Defining Project Scope $5,120.00
Develop Project Plan $5,280.00
Analyze the Risks $3,960.00
Include communication strategy $5,120.00
Implement KPI Metrics $5,120.00
Develop Business Case $7,680.00
Designing Phase $12,800.00
Analyzing the system $3,200.00
Designing the network diagram $3,840.00
Gathering equipment $5,760.00
Implementing Phase $39,760.00
Set up new systems $6,000.00
Network Design $12,200.00
Connecting subnet $21,560.00
Testing Phase $29,520.00
Testing the systems $8,200.00
Testing sub-nets $6,560.00
Integrate the tested systems $6,560.00
Document the testing $8,200.00
Maintenance phase $21,920.00
Train the employees $7,200.00
Maintain the networks $7,360.00
Implement secure encryption technique $7,360.00
Checklist on testing $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
Project closing phase $22,160.00
Checklist all the activities $5,760.00
Document project plan $16,400.00
Project Sign off $0.00
Table 1: Cost Structure
(Source: Created by Author)
3.3 Resource Structure:
Resource Name Type Material
Label Initials Group Max.
Units Std. Rate
Project manager Work P 100% $100.00/hr
Finance manager Work F 100% $90.00/hr
Team leader Work T 100% $80.00/hr
Network analyst Work N 100% $80.00/hr
Network workers Work N 100% $80.00/hr
Technicians Work T 100% $80.00/hr
Subject matter
Experts Work S 100% $50.00/hr
System analyst Work S 100% $70.00/hr
Quality analyst Work Q 100% $75.00/hr
Sponsors Work S 100% $95.00/hr
Table 2: Resource Structure
(Source: Created by Author)
Project closing phase $22,160.00
Checklist all the activities $5,760.00
Document project plan $16,400.00
Project Sign off $0.00
Table 1: Cost Structure
(Source: Created by Author)
3.3 Resource Structure:
Resource Name Type Material
Label Initials Group Max.
Units Std. Rate
Project manager Work P 100% $100.00/hr
Finance manager Work F 100% $90.00/hr
Team leader Work T 100% $80.00/hr
Network analyst Work N 100% $80.00/hr
Network workers Work N 100% $80.00/hr
Technicians Work T 100% $80.00/hr
Subject matter
Experts Work S 100% $50.00/hr
System analyst Work S 100% $70.00/hr
Quality analyst Work Q 100% $75.00/hr
Sponsors Work S 100% $95.00/hr
Table 2: Resource Structure
(Source: Created by Author)

8PROJECT MANAGEMENT
4. Time sheet with milestone and slack
4.1 Milestones in the project plan
Task Name Duration Start Finish
Develop Business Case 3 days Mon 2/09/19 Wed 4/09/19
Connecting subnet 7 days Thu 26/09/19 Fri 4/10/19
Document the testing 5 days Thu 24/10/19 Wed 30/10/19
Checklist on testing 0 days Fri 15/11/19 Fri 15/11/19
Project Sign off 0 days Tue 26/11/19 Tue 26/11/19
Table 3: Milestone in project plan
(Source: Created by Author)
4.2 Slack Time for each activity
Task Name Slack Time
Interview the Stakeholders 0 days
Stakeholder Analysis 0 days
Select the processes 0 days
Developing Project Charter 0 days
Defining Project Scope 0 days
Develop Project Plan 0 days
Analyze the Risks 0 days
Include communication strategy 1 days
Implement KPI Metrics 0 days
Develop Business Case 0 days
Analyzing the system 3 days
Designing the network diagram 0 days
4. Time sheet with milestone and slack
4.1 Milestones in the project plan
Task Name Duration Start Finish
Develop Business Case 3 days Mon 2/09/19 Wed 4/09/19
Connecting subnet 7 days Thu 26/09/19 Fri 4/10/19
Document the testing 5 days Thu 24/10/19 Wed 30/10/19
Checklist on testing 0 days Fri 15/11/19 Fri 15/11/19
Project Sign off 0 days Tue 26/11/19 Tue 26/11/19
Table 3: Milestone in project plan
(Source: Created by Author)
4.2 Slack Time for each activity
Task Name Slack Time
Interview the Stakeholders 0 days
Stakeholder Analysis 0 days
Select the processes 0 days
Developing Project Charter 0 days
Defining Project Scope 0 days
Develop Project Plan 0 days
Analyze the Risks 0 days
Include communication strategy 1 days
Implement KPI Metrics 0 days
Develop Business Case 0 days
Analyzing the system 3 days
Designing the network diagram 0 days

9PROJECT MANAGEMENT
Gathering equipment 0 days
Set up new systems 0 days
Network Design 0 days
Connecting subnet 0 days
Testing the systems 0 days
Testing sub-nets 0 days
Integrate the tested systems 0 days
Document the testing 0 days
Train the employees 0 days
Maintain the networks 0 days
Implement secure encryption technique 0 days
Checklist on testing 0 days
Checklist all the activities 0 days
Document project plan 0 days
Project Sign off 0 days
Table 4: Slack Time for all activities
(Source: Created by Author)
Gathering equipment 0 days
Set up new systems 0 days
Network Design 0 days
Connecting subnet 0 days
Testing the systems 0 days
Testing sub-nets 0 days
Integrate the tested systems 0 days
Document the testing 0 days
Train the employees 0 days
Maintain the networks 0 days
Implement secure encryption technique 0 days
Checklist on testing 0 days
Checklist all the activities 0 days
Document project plan 0 days
Project Sign off 0 days
Table 4: Slack Time for all activities
(Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10PROJECT MANAGEMENT
5. Project Plan
5.1 Critical path method/PERT chart
Figure 1: PERT Chart
(Source: Created by Author using Visio)
Interpretation: The above diagram shows the Critical path method of the pert chart that is
associated with project plan. Each activity of the project plan includes early start (ES), early
5. Project Plan
5.1 Critical path method/PERT chart
Figure 1: PERT Chart
(Source: Created by Author using Visio)
Interpretation: The above diagram shows the Critical path method of the pert chart that is
associated with project plan. Each activity of the project plan includes early start (ES), early

11PROJECT MANAGEMENT
finish (EF), late start (LS), and late finish (LF) along with activity name, duration of the activity
and the float of the activity. The calculation of each of the activity is shown in the diagram
above.
Implication: From this calculation, the slack/float of the project can be calculated from
which the critical path of the project can be determined. The critical path method includes the
project manager to identify the time necessary a particular activity and also shows the
dependencies of the activity on each.
finish (EF), late start (LS), and late finish (LF) along with activity name, duration of the activity
and the float of the activity. The calculation of each of the activity is shown in the diagram
above.
Implication: From this calculation, the slack/float of the project can be calculated from
which the critical path of the project can be determined. The critical path method includes the
project manager to identify the time necessary a particular activity and also shows the
dependencies of the activity on each.

12PROJECT MANAGEMENT
5. 2 Gantt chart
Figure 2: Gantt chart
(Source: Created by Author using Visio)
Interpretation: The above diagram shows the Gantt chart that is the plan of incorporating
5G technology in Gosford Private Hospital in Australia. Gantt chart above shows the details of
how project will proceed and the activities that are to be carried out for implementing the new
5. 2 Gantt chart
Figure 2: Gantt chart
(Source: Created by Author using Visio)
Interpretation: The above diagram shows the Gantt chart that is the plan of incorporating
5G technology in Gosford Private Hospital in Australia. Gantt chart above shows the details of
how project will proceed and the activities that are to be carried out for implementing the new
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13PROJECT MANAGEMENT
network. The Gantt chart also shows the duration, the staring date as well as the ending date of a
particular activity and the resources associated with the project.
Implication: From the Gantt chart, the project manager can manage the completion time
of the project and can check the milestones if they are completed within that particular time
period.
Assignment 3: (Part 2) Written Report
1. Cost Benefit Analysis
RMO Cost/Benefit Analysis for Implementing 5G network in a
private health care
Total Cost of project
Cost of
Implementation 181000
Total Cost for the
project 181000
Year of
Project
year 0 year1 year 2 year 3 year 4 year 5 TOTALS
Total economic benefit $0.00
$50,000.0
0 $50,000.00
$50,000.
00
$50,000.
00
$50,000.
00
10% Discount Rate 1 0.9091 0.8264 0.7513 0.6830 0.6209
PV Of Benefits $0.00
$45,454.5
5 $41,322.31
$37,565.
74
$34,150.
67
$31,046.
07
NPV of all BENEFITS $0.00
$45,454.5
5 $86,776.86
$124,34
2.60
$158,49
3.27
$189,53
9.34
$604,606.
62
One Time Costs
$181,000.
00
Recurring Costs $0.00 $1,000.00 $1,000.00
$1,000.0
0
$1,000.0
0
$1,000.0
0
10% Discount Rate 1.0000 0.9091 0.8264 0.7513 0.6830 0.6209
PV Of Recurring Costs $0.00 $909.09 $826.45 $751.31 $683.01 $620.92
NPV Of All Costs
$181,000.
00
$181,909.
09
$182,735.5
4
$183,48
6.85
$184,16
9.87
$184,79
0.79
$1,098,09
2.13
network. The Gantt chart also shows the duration, the staring date as well as the ending date of a
particular activity and the resources associated with the project.
Implication: From the Gantt chart, the project manager can manage the completion time
of the project and can check the milestones if they are completed within that particular time
period.
Assignment 3: (Part 2) Written Report
1. Cost Benefit Analysis
RMO Cost/Benefit Analysis for Implementing 5G network in a
private health care
Total Cost of project
Cost of
Implementation 181000
Total Cost for the
project 181000
Year of
Project
year 0 year1 year 2 year 3 year 4 year 5 TOTALS
Total economic benefit $0.00
$50,000.0
0 $50,000.00
$50,000.
00
$50,000.
00
$50,000.
00
10% Discount Rate 1 0.9091 0.8264 0.7513 0.6830 0.6209
PV Of Benefits $0.00
$45,454.5
5 $41,322.31
$37,565.
74
$34,150.
67
$31,046.
07
NPV of all BENEFITS $0.00
$45,454.5
5 $86,776.86
$124,34
2.60
$158,49
3.27
$189,53
9.34
$604,606.
62
One Time Costs
$181,000.
00
Recurring Costs $0.00 $1,000.00 $1,000.00
$1,000.0
0
$1,000.0
0
$1,000.0
0
10% Discount Rate 1.0000 0.9091 0.8264 0.7513 0.6830 0.6209
PV Of Recurring Costs $0.00 $909.09 $826.45 $751.31 $683.01 $620.92
NPV Of All Costs
$181,000.
00
$181,909.
09
$182,735.5
4
$183,48
6.85
$184,16
9.87
$184,79
0.79
$1,098,09
2.13

14PROJECT MANAGEMENT
Overall NPV
($493,485
.52)
Overall ROI = (Overall NPV / NPV
Of All Costs -0.45
Break-Even Analysis
Yearly NPV Cash
Flow $0.00
$44,545.4
5 $40,495.87
$36,814.
43
$33,467.
66
$30,425.
14
Overall NPV Cash
Flow
$181,000.
00
($136,454
.55)
($95,958.68
)
($59,144
.25)
($25,676
.59)
$4,748.5
5
Project break-even occurs between
years 6 and 7
Use 1st year of positive cash flow to calculate
break-even fraction 6.6066 years
Explanation: The above calculation shows the analysis of cost for implementing the 5G
technology in the Gosford Private Hospital. The total cost of implementation of the project is
$181000 and the net economic benefit and the recurring cost of the project is calculated above.
Five years plan are shown in the above calculation and the discount rate that is provided by the
hospital is 10%. The break even for the project occurs after 6 years that is the organization would
be able to cover up the variable cost and the fixed cost at 6.6066 years after implementation.
2. Recommendations for managing the project
For implementing 5G technology in the Gosford Private Hospital with the help of project
management, there are many difficulties that are faced by project manager to complete the
project that is on track and complete it within the project budget (Colebatch and Lockwood
2019). The recommendations to manage the project are
Overall NPV
($493,485
.52)
Overall ROI = (Overall NPV / NPV
Of All Costs -0.45
Break-Even Analysis
Yearly NPV Cash
Flow $0.00
$44,545.4
5 $40,495.87
$36,814.
43
$33,467.
66
$30,425.
14
Overall NPV Cash
Flow
$181,000.
00
($136,454
.55)
($95,958.68
)
($59,144
.25)
($25,676
.59)
$4,748.5
5
Project break-even occurs between
years 6 and 7
Use 1st year of positive cash flow to calculate
break-even fraction 6.6066 years
Explanation: The above calculation shows the analysis of cost for implementing the 5G
technology in the Gosford Private Hospital. The total cost of implementation of the project is
$181000 and the net economic benefit and the recurring cost of the project is calculated above.
Five years plan are shown in the above calculation and the discount rate that is provided by the
hospital is 10%. The break even for the project occurs after 6 years that is the organization would
be able to cover up the variable cost and the fixed cost at 6.6066 years after implementation.
2. Recommendations for managing the project
For implementing 5G technology in the Gosford Private Hospital with the help of project
management, there are many difficulties that are faced by project manager to complete the
project that is on track and complete it within the project budget (Colebatch and Lockwood
2019). The recommendations to manage the project are

15PROJECT MANAGEMENT
a. Nailing down the project: Before starting the project the project manager should make
sure that the project includes a solid foundation and all the stakeholders that are in the project.
The project plan is to be develop for managing a project properly.
b. Project identification and requirement of team: The project identification is to be
defined in the project (Bourne 2016). This includes the need of carrying out the project and
includes to assemble as well as organize the resources that are available.
c. Include a project leader: The main aim of the project is to include a project leader to
manage the project. There should be proper team dynamics and there should be a supervisor who
can manage the project successfully.
d. Defining the project milestones: The project milestones are to be defined that is
included in project plan of developing the project (Stark 2015). In implementing the 5G
technology in the Gosford Private hospital, the project plan includes milestones that are to be
completed within the time scheduled for the project.
e. Open communication plan: The project manager includes communication plan so that
the project managers are capable of establishing proper communication with the team members
and listen to the advice they provide for the project.
3. Recommendations for managing project integration
The project Integration management is the process collection that requires ensuring
different elements that are included in project and the activities are coordinated well. Integration
management includes trade-offs in the project objective and as well as includes alternatives that
are needed to meet the expectation of the users (Kerzner 2019). The recommendations that are to
be included for project integration is:
a. Nailing down the project: Before starting the project the project manager should make
sure that the project includes a solid foundation and all the stakeholders that are in the project.
The project plan is to be develop for managing a project properly.
b. Project identification and requirement of team: The project identification is to be
defined in the project (Bourne 2016). This includes the need of carrying out the project and
includes to assemble as well as organize the resources that are available.
c. Include a project leader: The main aim of the project is to include a project leader to
manage the project. There should be proper team dynamics and there should be a supervisor who
can manage the project successfully.
d. Defining the project milestones: The project milestones are to be defined that is
included in project plan of developing the project (Stark 2015). In implementing the 5G
technology in the Gosford Private hospital, the project plan includes milestones that are to be
completed within the time scheduled for the project.
e. Open communication plan: The project manager includes communication plan so that
the project managers are capable of establishing proper communication with the team members
and listen to the advice they provide for the project.
3. Recommendations for managing project integration
The project Integration management is the process collection that requires ensuring
different elements that are included in project and the activities are coordinated well. Integration
management includes trade-offs in the project objective and as well as includes alternatives that
are needed to meet the expectation of the users (Kerzner 2019). The recommendations that are to
be included for project integration is:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

16PROJECT MANAGEMENT
a. Developing a project plan for developing the project.
b. A proper knowledge area is to be defined for completing the project that includes
seven different processes of project managemenst (Carnall 2018).
c. For integration a project, project charter is to be involved including input, tools, as well
as techniques that are included in the system.
d. In the project execution of the project, the project focuses to complete the task that is
assigned.
e. There should be tools, techniques as well as inputs that are to be included in the
project.
4. Implementation plan
For developing a project proper implementation plan should be introduced. Project
implementation plan includes details of project plan as well as activities that are included in the
system (Nanda 2016). There are some plan of project implementation that are carried out for
developing a project.
a. Preparing project infrastructure: The project implementation plan should be carried
out in the organization where it should be used (Kerzner 2017). It is not right to test the solution
in some other place and implement it in some other place.
b. Coordinate all organization included in implementation: All the other organization is
associated with a particular project are to be implemented when the project is being developed.
c. Implementing training process: To use the process, trained professional are required
who will be able to handle the system.
a. Developing a project plan for developing the project.
b. A proper knowledge area is to be defined for completing the project that includes
seven different processes of project managemenst (Carnall 2018).
c. For integration a project, project charter is to be involved including input, tools, as well
as techniques that are included in the system.
d. In the project execution of the project, the project focuses to complete the task that is
assigned.
e. There should be tools, techniques as well as inputs that are to be included in the
project.
4. Implementation plan
For developing a project proper implementation plan should be introduced. Project
implementation plan includes details of project plan as well as activities that are included in the
system (Nanda 2016). There are some plan of project implementation that are carried out for
developing a project.
a. Preparing project infrastructure: The project implementation plan should be carried
out in the organization where it should be used (Kerzner 2017). It is not right to test the solution
in some other place and implement it in some other place.
b. Coordinate all organization included in implementation: All the other organization is
associated with a particular project are to be implemented when the project is being developed.
c. Implementing training process: To use the process, trained professional are required
who will be able to handle the system.

17PROJECT MANAGEMENT
d. Installing production solution: The solution or the application that is to be made are to
be changed to the developed phase (Archibald and Archibald 2016). In this phase, the production
solution is made.
e. Converting the data: Data conversion is needed which include changing of data that
are included in the infrastructure of the system.
f. Performing verification in the production process: This includes combination of
development as well as include client personnel with the project (Tupa, Simota, and Steiner
2017). This verification technique checks if all the things going on the right path.
g. Implement necessary processes: All the processes needed for developing the system
should be included in this implementation process.
h. Monitoring solution: All the solution should be monitored that are on the process and
the process that are already being completed.
5. Post Implementation plan
In the post implementation method, the reviews of the users or the clients are to be taken
to get the working condition of the system or product (Permana 2015). To capture the learning
process as well as make the information that are available are included in the organization. Post
implementation plan is generally organized by project manager. Associated project manager
should look after the customer gain, the benefits of the customers, as well as include detailed
business case that are included in the project (Heagney 2016). This post implementation plan is
considered to be extra phase in developing a project. To implement the post-implementation
review, generally the project manager needs to provide six months to one year to complete the
project.
d. Installing production solution: The solution or the application that is to be made are to
be changed to the developed phase (Archibald and Archibald 2016). In this phase, the production
solution is made.
e. Converting the data: Data conversion is needed which include changing of data that
are included in the infrastructure of the system.
f. Performing verification in the production process: This includes combination of
development as well as include client personnel with the project (Tupa, Simota, and Steiner
2017). This verification technique checks if all the things going on the right path.
g. Implement necessary processes: All the processes needed for developing the system
should be included in this implementation process.
h. Monitoring solution: All the solution should be monitored that are on the process and
the process that are already being completed.
5. Post Implementation plan
In the post implementation method, the reviews of the users or the clients are to be taken
to get the working condition of the system or product (Permana 2015). To capture the learning
process as well as make the information that are available are included in the organization. Post
implementation plan is generally organized by project manager. Associated project manager
should look after the customer gain, the benefits of the customers, as well as include detailed
business case that are included in the project (Heagney 2016). This post implementation plan is
considered to be extra phase in developing a project. To implement the post-implementation
review, generally the project manager needs to provide six months to one year to complete the
project.

18PROJECT MANAGEMENT
This phase is generally included in the last phase after the implementation process is
being completed (Uhl and Gollenia 2016). The common mistakes that are committed in the post
implementation plan that occurs in the system planning.
Recommendation and Conclusion
From the above discussion, it can be cleared that 5G technologies will help to improve
the condition of health care and will also improve the medical service that health care centres
provides. With eth fastest speed and because of its intelligent design of the systems of 5G
technology is helping system developers to design new applications as well as devices which
have potential to change the way of diagnosis of health. 5G technology provides wide range of
possibility so that they can connect different health care centres in different creative ways. The
technology of 5G is increasing the ability to use equipment of remote monitoring, sensors as well
as mobile devices and the patient’s diagnosis system, receiving images as well as changing the
treatment process via digital technology. As Gosford Private Hospital in NSW Australia wants to
implement 5G technology in its business process for expanding the technological opportunities,
some number of steps are recommended before incorporating 5G technology in its system
applications.
1. Proper infrastructure is needed for incorporating 5G technology and there is a need of
trained professionals to handle the system.
2. The spectrum of the 5G technology are to be harmonized which should include
combination of the licensed, licensed shared as well as unlicensed spectrum. Applications require
different range of spectrums.
This phase is generally included in the last phase after the implementation process is
being completed (Uhl and Gollenia 2016). The common mistakes that are committed in the post
implementation plan that occurs in the system planning.
Recommendation and Conclusion
From the above discussion, it can be cleared that 5G technologies will help to improve
the condition of health care and will also improve the medical service that health care centres
provides. With eth fastest speed and because of its intelligent design of the systems of 5G
technology is helping system developers to design new applications as well as devices which
have potential to change the way of diagnosis of health. 5G technology provides wide range of
possibility so that they can connect different health care centres in different creative ways. The
technology of 5G is increasing the ability to use equipment of remote monitoring, sensors as well
as mobile devices and the patient’s diagnosis system, receiving images as well as changing the
treatment process via digital technology. As Gosford Private Hospital in NSW Australia wants to
implement 5G technology in its business process for expanding the technological opportunities,
some number of steps are recommended before incorporating 5G technology in its system
applications.
1. Proper infrastructure is needed for incorporating 5G technology and there is a need of
trained professionals to handle the system.
2. The spectrum of the 5G technology are to be harmonized which should include
combination of the licensed, licensed shared as well as unlicensed spectrum. Applications require
different range of spectrums.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

19PROJECT MANAGEMENT
3. The network of the system should have security as well as include interoperability. The
data networks used in the system should be maintained and the information exchange through 5G
network should be trusted.
4. The Gosford Private hospital should also follow the updated policy of reimbursement
so that they can apply advance application in the area of digital medicine.
3. The network of the system should have security as well as include interoperability. The
data networks used in the system should be maintained and the information exchange through 5G
network should be trusted.
4. The Gosford Private hospital should also follow the updated policy of reimbursement
so that they can apply advance application in the area of digital medicine.

20PROJECT MANAGEMENT
References
Archibald, R.D. and Archibald, S., 2016. Leading and Managing Innovation: What Every
Executive Team Must Know about Project, Program, and Portfolio Management. Auerbach
Publications.
Bourne, L., 2016. Stakeholder relationship management: a maturity model for organisational
implementation. Routledge.
Carnall, C., 2018. Managing change. Routledge.
Chen, M., Yang, J., Hao, Y., Mao, S. and Hwang, K., 2017. A 5G cognitive system for
healthcare. Big Data and Cognitive Computing, 1(1), p.2.
Chofreh, A.G., Goni, F.A. and Klemeš, J.J., 2018. A roadmap for Sustainable Enterprise
Resource Planning systems implementation (part III). Journal of cleaner production, 174,
pp.1325-1337.
Colebatch, E. and Lockwood, C., 2019. Enhanced perioperative nutritional care for patients
undergoing elective colorectal surgery at Calvary North Adelaide Hospital: a best practice
implementation project. JBI database of systematic reviews and implementation reports.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Hossain, M.S. and Muhammad, G., 2017. Emotion-aware connected healthcare big data towards
5G. IEEE Internet of Things Journal, 5(4), pp.2399-2406.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
References
Archibald, R.D. and Archibald, S., 2016. Leading and Managing Innovation: What Every
Executive Team Must Know about Project, Program, and Portfolio Management. Auerbach
Publications.
Bourne, L., 2016. Stakeholder relationship management: a maturity model for organisational
implementation. Routledge.
Carnall, C., 2018. Managing change. Routledge.
Chen, M., Yang, J., Hao, Y., Mao, S. and Hwang, K., 2017. A 5G cognitive system for
healthcare. Big Data and Cognitive Computing, 1(1), p.2.
Chofreh, A.G., Goni, F.A. and Klemeš, J.J., 2018. A roadmap for Sustainable Enterprise
Resource Planning systems implementation (part III). Journal of cleaner production, 174,
pp.1325-1337.
Colebatch, E. and Lockwood, C., 2019. Enhanced perioperative nutritional care for patients
undergoing elective colorectal surgery at Calvary North Adelaide Hospital: a best practice
implementation project. JBI database of systematic reviews and implementation reports.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Hossain, M.S. and Muhammad, G., 2017. Emotion-aware connected healthcare big data towards
5G. IEEE Internet of Things Journal, 5(4), pp.2399-2406.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.

21PROJECT MANAGEMENT
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. Wiley.
Lema, M.A., Laya, A., Mahmoodi, T., Cuevas, M., Sachs, J., Markendahl, J. and Dohler, M.,
2017. Business case and technology analysis for 5G low latency applications. IEEE Access, 5,
pp.5917-5935.
Magsi, H., Sodhro, A.H., Chachar, F.A., Abro, S.A.K., Sodhro, G.H. and Pirbhulal, S., 2018,
March. Evolution of 5G in Internet of medical things. In 2018 International Conference on
Computing, Mathematics and Engineering Technologies (iCoMET) (pp. 1-7). IEEE.
Nanda, V., 2016. Quality management system handbook for product development companies.
CRC press.
Permana, P.A.G., 2015. Scrum method implementation in a software development project
management. International Journal of Advanced Computer Science and Applications, 6(9),
pp.198-204.
Stark, J., 2015. Product lifecycle management. In Product lifecycle management (Volume 1) (pp.
1-29). Springer, Cham.
Thuemmler, C., Paulin, A., Jell, T. and Lim, A.K., 2018. Information technology–next
generation: the impact of 5G on the evolution of health and care services. In Information
Technology-New Generations (pp. 811-817). Springer, Cham.
Tupa, J., Simota, J. and Steiner, F., 2017. Aspects of risk management implementation for
Industry 4.0. Procedia Manufacturing, 11, pp.1223-1230.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. Wiley.
Lema, M.A., Laya, A., Mahmoodi, T., Cuevas, M., Sachs, J., Markendahl, J. and Dohler, M.,
2017. Business case and technology analysis for 5G low latency applications. IEEE Access, 5,
pp.5917-5935.
Magsi, H., Sodhro, A.H., Chachar, F.A., Abro, S.A.K., Sodhro, G.H. and Pirbhulal, S., 2018,
March. Evolution of 5G in Internet of medical things. In 2018 International Conference on
Computing, Mathematics and Engineering Technologies (iCoMET) (pp. 1-7). IEEE.
Nanda, V., 2016. Quality management system handbook for product development companies.
CRC press.
Permana, P.A.G., 2015. Scrum method implementation in a software development project
management. International Journal of Advanced Computer Science and Applications, 6(9),
pp.198-204.
Stark, J., 2015. Product lifecycle management. In Product lifecycle management (Volume 1) (pp.
1-29). Springer, Cham.
Thuemmler, C., Paulin, A., Jell, T. and Lim, A.K., 2018. Information technology–next
generation: the impact of 5G on the evolution of health and care services. In Information
Technology-New Generations (pp. 811-817). Springer, Cham.
Tupa, J., Simota, J. and Steiner, F., 2017. Aspects of risk management implementation for
Industry 4.0. Procedia Manufacturing, 11, pp.1223-1230.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

22PROJECT MANAGEMENT
Uhl, A. and Gollenia, L.A. eds., 2016. A handbook of business transformation management
methodology. Routledge.
van Heerden, M., Kleingeld, M. and Vosloo, J.C., 2015, August. Improving DSM project
implementation and sustainability through ISO standards. In 2015 International Conference on
the Industrial and Commercial Use of Energy (ICUE) (pp. 123-128). IEEE.
West, D.M., 2016. How 5G technology enables the health internet of things. Brookings Center
for Technology Innovation, 3, pp.1-20.
Uhl, A. and Gollenia, L.A. eds., 2016. A handbook of business transformation management
methodology. Routledge.
van Heerden, M., Kleingeld, M. and Vosloo, J.C., 2015, August. Improving DSM project
implementation and sustainability through ISO standards. In 2015 International Conference on
the Industrial and Commercial Use of Energy (ICUE) (pp. 123-128). IEEE.
West, D.M., 2016. How 5G technology enables the health internet of things. Brookings Center
for Technology Innovation, 3, pp.1-20.
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.