Professional Diploma in Innovation: Graduation Ceremony Project Plan

Verified

Added on  2022/12/29

|21
|2880
|41
Project
AI Summary
This project plan outlines the comprehensive management of a graduation ceremony hosted by the Bloomsbury Institute in November 2021. The plan, developed by a project manager, details scope management, including project description, objectives, and constraints, such as a £7000 budget and a three-month timeframe. Time management is addressed through a project activity table, network diagram, and Gantt chart, mapping out activities from initiation to closing. The cost management section provides a budget breakdown and baseline, while the communication plan identifies stakeholders and outlines a communication strategy. Finally, a risk management plan details potential risks and mitigation strategies. The plan aims to successfully organize the graduation ceremony, ensuring high-quality services and proper marketing to maximize student attendance.
Document Page
Professional Diploma in Innovation
Management
Table of Contents
Section 1. Scope Management Plan.................................................................................................4
1.1 Project Description.................................................................................................................4
1.2 Project Scope.........................................................................................................................4
1.3 Assumptions
.....................................................................................................................................................5
1.4 Constraints.............................................................................................................................5
1.5 Project Roles and Responsibilities
......................................................................................................................................................6
1.7 Project Work-breakdown Structure (WBS)...........................................................................7
Section 2. Time Management Plan..................................................................................................7
2.2 Project Activity/Time/Dependency base table ......................................................................7
2.3Project Network Diagram.......................................................................................................9
2.3 Gantt chart ...........................................................................................................................11
Section 3. Cost Management Plan.............................................................................................16
3.1 Cost Breakdown and Budget...............................................................................................16
3.2 Project Cost Baseline........................................................................................................16
Section 4. Communication Management Plan...............................................................................17
4.1 Project Stakeholders.......................................................................................................17
4.2 Stakeholder Communication Plan........................................................................................17
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Section 5. Risk Management Plan.................................................................................................18
5.1 Risk Identification, Analysis and Action Plan ....................................................................18
REFERENCES..............................................................................................................................21
Document Page
Project Plan
Template
Project Manager
Name: ID Number:
Expected Project Start Date: Expected Project Close Date:
Document Page
Section 1. Scope Management Plan
1.1 Project Description
Project management is the process, knowledge, method, skill and experience to
accomplish the project objective according to the project acceptance criteria within the specific
agreed parameters. Project manager is responsible to plan the project effectively, and it covers
planning, expectation, scope, resources , activities and schedule (Babar., Oracle International
Corp, 2019). all the roles and responsibility will be assigned and it role of project member's will
be clear so their will be no thought in their mind that what they have to do in the graduation
ceremony event.
This project is based on graduation ceremony and it is host by the Bloomsbury institute.
The ceremony will be placed on November 2021 where project manager will plan whole project
and implement. Project manager will take around 3 moths to complete this project and host have
provide budget around £7000 to complete and organize the ceremony effectively.
1.1.1 Project Objectives
To organize graduation ceremony within the campus of Bloomsbury Institute
To ensure proper marketing of the graduation ceremony
To make sure high quality of services are provided to the student's within
graduation ceremony.
1.2 Project Scope
Project management scope refers to the set of feature within the project. The deliverable
are distributed from the requirements of the project. The main scope of the project is that the
work need to be accomplished within the given times, budget or result with the specified features
and functions.
This project has higher scope to attend the graduation ceremony by the student's, The
advertisement will be done thorough the Posters and project manager will ensure that marketing
of the graduation ceremony can be doe properly so more and more students can attend
graduation ceremony. Venue time sis decide from the morning 10 Pm and according to the
assumptions it will e over till the 5 O clock and last 6 O clock (de Melo and et.al., 2020). The
hall will be booked for the whole day so the time can be expanded easily without any problem.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1.3 Assumptions
The project planning of the Graduation Ceremony will be start before the three
month and it will be finished before the Novembers end of 2021.
all the roles and responsibility will be assigned and it role of project member's
will be clear so their will be no thought in their mind that what they have to do in
the graduation ceremony event.
Facilities within the graduation ceremony will be implemented life all the
equipment, lunch, water battles etc.
It is being assumed that around 120-150 students will be participating and rest of
people will include around 400-500 including parents, staff employees at various
other.
Resource that will be needed on the graduation ceremony will arrive after 20 to
25 days and may be the project arrangement at the campus will start after 21 to 25
days.
1.4 Constraints
There are some things that are important within the project event of Graduation Ceremony-
Bloomsbury institute has given limited time of 3 months which means project
manager have to ensure that they complete the project within the given time.
Bloomsbury institute provided the budget of £7000 and project manager ha to
complete all the activities and arrangement.
Special skill will be needed in the staff who will work on the ground because ordinary
people cannot do those things like, Stage work where employees who know how to
make the stage can also do it.
who will organise the ceremony in fruitful manner (Nijhuis, Vrijhoef and Kessels.,
2018). This will include volunteers from current batch which will be participating in
the event. This will leads to ascertainment of various finances being available to meet
the needs of conducting the event. It will leads with various sponsors which will leads
to building with their own brand image. It will thus leads with getting finance to
organise the event huge level.
Document Page
1.5 Project Roles and Responsibilities
Project manager It contributes by handling any changes made in
the project and to address the constraints and
the requirements identified by the leaders. It
must be abreast of decisions and review all the
activities.
Supervisor Supervisor will be responsible to report all the
activities about work process to project
manager.
Engineers Engineer will design the all the stages and
within the graduation ceremony.
Staff Staff and employees will work on the ground
and their work is make stage and arrange
chairs.
Document Page
1.7 Project Work-breakdown Structure (WBS)
Section 2. Time Management Plan
2.2 Project Activity/Time/Dependency base table
Activities Time line (days)
Initiation 27
Setting up of goals and objectives 5
Setting up of team 7
Assignment of roles and responsibilities 3
Stakeholder identification 10
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Conducting feasibility study 2
Planning of event 9
Budget development 2
Development of timeline 5
Promotional mechanism 2
Execution and implementation 11
Preparation of itenary 6
Selecting of venues 5
Monitoring and control 13
Rehearsal of itinerary 8
Registration of participants 5
Closing 1
Thanking ceremony 1
2.3 Project Network Diagram
A Network Diagram is visualize schedule of the visual and sequential and logical
relationship between task of the project setting. A Network Diagram within this project will help
the project manager to understand when and how the activities will start, and they will able to
measure the progress including their time. This network diagram has inserted activities from the
start to end, including its times and covered within 3 months.
The event initiation was started on 16 /2/21 that is Monday and finish at 8/3/21 that is
Friday. Then, planning was started at 9/3/21 Monday and finished at 5/4/21 Thursday. The
execution started at 6/4/21 Friday and finished at 19/4/21 Thursday. The monitoring was
started at Friday 20/4/21 and finished at 28/4/21 Tuesday. At last closing started at Tuesday
29/4/21 and finished on 3/05/21.
Document Page
Document Page
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Document Page
chevron_up_icon
1 out of 21
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]