Detailed Green Building Assessment and Green Mark Certification Report
VerifiedAdded on 2021/04/24
|28
|3024
|83
Report
AI Summary
This report assesses the feasibility of obtaining Green Mark Gold certification for a headquarters building, focusing on energy efficiency. The report begins by identifying the appropriate BCA Green Mark assessment criteria and the certification process, emphasizing the importance of energy efficiency, lighting power, tenant awareness, environmental policies, and management involvement. It includes a detailed assessment of current and targeted Green Mark score points, providing calculations for energy savings, replacement of electricity by renewable energy, and Energy Efficiency Index based on the provided monthly electricity consumption data. The report also provides a breakdown of the targeted scoring to achieve the Green Mark Gold award, explaining the necessary reasons for all categories under the Green Mark framework, and includes calculations such as percentage savings to derive the points scored. Appendix A provides building information, including monthly electricity consumption, cooling load profile, air-conditioning system efficiency, and equipment details, to support the assessment. The report aims to provide a comprehensive guide to sustainable building practices and the Green Mark certification process.

Module: Green Building Assessment Standards
Question 1
You are required to demonstrate your understanding of what was learnt in your GMFM course
by submitting the application with relevant supporting documents for Green Mark certification.
As the project leader, assess and recommend an appropriate version of BCA Green Mark
assessment criteria for the headquarter building.
The assessment criteria that will be used for headquarter building will be energy efficiency,
which will comprise of ensuring that the following areas have the highest scores for it to be
able to win the Green mark gold, the area under consideration will include, monthly electrical
meter monitory through reading it, the performance based on the thermal on the envelope of the
building, thermal parameters, system of air conditioning, density of light, lifts having efficiency
of energy, management of energy, energy efficient renewed and finally artificial lighting.
(5 marks)
Question 1
You are required to demonstrate your understanding of what was learnt in your GMFM course
by submitting the application with relevant supporting documents for Green Mark certification.
As the project leader, assess and recommend an appropriate version of BCA Green Mark
assessment criteria for the headquarter building.
The assessment criteria that will be used for headquarter building will be energy efficiency,
which will comprise of ensuring that the following areas have the highest scores for it to be
able to win the Green mark gold, the area under consideration will include, monthly electrical
meter monitory through reading it, the performance based on the thermal on the envelope of the
building, thermal parameters, system of air conditioning, density of light, lifts having efficiency
of energy, management of energy, energy efficient renewed and finally artificial lighting.
(5 marks)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Question 2
Prior to assessing the building’s current score, explain and discuss with the management the
certification process with BCA in order to obtain Green Mark Gold for the Green Mark criteria
recommended.
In order to achieve Green Mark Gold then the management should ensure that the following
areas or sections will have to achieve the stipulated points.
i. Under the energy efficiency management should ensure that it is possible for it to
achieve a minimum of four points.
ii. Under lighting power the budget should be able to achieve a minimum of 24%
iii. Creation of awareness on the building tenants regarding the sustainable
environment, the management should ensure this section achieves three points.
iv. Achievement of three points by ensuring that environmental policies and review on
it.
v. Setting up a reminder that is capable of maintaining air conditioning at 240 point.
vi. Achievement of two points on the involvement of management in all the activities.
vii. Achieving two points by providing a green corner in each house unit with enough
house working material.
viii. Appoint in each and every floor an environmental chairman to ensure every sector
that involvement environment in each floor is totally addressed to the management
in time.
(10 marks)
Prior to assessing the building’s current score, explain and discuss with the management the
certification process with BCA in order to obtain Green Mark Gold for the Green Mark criteria
recommended.
In order to achieve Green Mark Gold then the management should ensure that the following
areas or sections will have to achieve the stipulated points.
i. Under the energy efficiency management should ensure that it is possible for it to
achieve a minimum of four points.
ii. Under lighting power the budget should be able to achieve a minimum of 24%
iii. Creation of awareness on the building tenants regarding the sustainable
environment, the management should ensure this section achieves three points.
iv. Achievement of three points by ensuring that environmental policies and review on
it.
v. Setting up a reminder that is capable of maintaining air conditioning at 240 point.
vi. Achievement of two points on the involvement of management in all the activities.
vii. Achieving two points by providing a green corner in each house unit with enough
house working material.
viii. Appoint in each and every floor an environmental chairman to ensure every sector
that involvement environment in each floor is totally addressed to the management
in time.
(10 marks)

Question 3
Please also assess and compute the assessment fee (including GST) in your briefing to the
management. Include a screen shot of the assessment fee guide from BCA website that you
have made reference to.
(10 marks)
Size Existing HQ building
GFA: square metre
Assessment fee for
certification
Medium and above 37,800 = $8,900 for the first 15,
000 m2
= $0.15 *(37800 – 15000)
= $3,420
Total = $8900 + $34200 =
$12,320
GTS = 7% * $12,320
= $862.40
Net cost = $8900 + $34200
+ $862.40 = $13,182.40
Please also assess and compute the assessment fee (including GST) in your briefing to the
management. Include a screen shot of the assessment fee guide from BCA website that you
have made reference to.
(10 marks)
Size Existing HQ building
GFA: square metre
Assessment fee for
certification
Medium and above 37,800 = $8,900 for the first 15,
000 m2
= $0.15 *(37800 – 15000)
= $3,420
Total = $8900 + $34200 =
$12,320
GTS = 7% * $12,320
= $862.40
Net cost = $8900 + $34200
+ $862.40 = $13,182.40
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Question 4
After you have completed your assessment, you are required to appraise and present to the
management of the company current Green Mark score points of the existing headquarter office
building based on the preliminary findings. (Preliminary findings are provided in Appendix A)
Category Available
Points
Curre
nt
Points
(Q4)
Propo
sed
Additio
nal
Points
(Q5)
Total
Points
(Q4+Q5)
Reasons
(Q6)
Energy Efficiency
1-1 Thermal performance of
building envelope
Maximum
permissible
REVT = 30
W/m2
10 5
15
REVT should
be less or
equal to 22
W/m2
1-2 System of air
conditioning
a) Ac having a unit
of condensing
model and
coefficient of
performance
b) An A/c system
efficiency
Air
12 10 22 Energy
reduction by
ensuring that
efficient
system of air
conditioning
is used.
Point scored
= 0.2 *
percentage
After you have completed your assessment, you are required to appraise and present to the
management of the company current Green Mark score points of the existing headquarter office
building based on the preliminary findings. (Preliminary findings are provided in Appendix A)
Category Available
Points
Curre
nt
Points
(Q4)
Propo
sed
Additio
nal
Points
(Q5)
Total
Points
(Q4+Q5)
Reasons
(Q6)
Energy Efficiency
1-1 Thermal performance of
building envelope
Maximum
permissible
REVT = 30
W/m2
10 5
15
REVT should
be less or
equal to 22
W/m2
1-2 System of air
conditioning
a) Ac having a unit
of condensing
model and
coefficient of
performance
b) An A/c system
efficiency
Air
12 10 22 Energy
reduction by
ensuring that
efficient
system of air
conditioning
is used.
Point scored
= 0.2 *
percentage

conditione
rs
Unitary
improvement
= 0.2 * 1.08 =
0.216%
1-3 Daylight 4 2 6 To obtain a
maximum
power budget
of lighting for
either artificial
light or
control lights
will comply
with 530:
2014.
1-4 Energy efficient index 3 4 7
1-5 System artificial of
lighting
3 7 10 To obtain a
maximum
power budget
of lighting for
either artificial
light or
control lights
will comply
with 530:
2014.
1-6 Ventilation in carpark 4 2 6 Use to reduce
the energy
that will
needed for
operation of
car park.
rs
Unitary
improvement
= 0.2 * 1.08 =
0.216%
1-3 Daylight 4 2 6 To obtain a
maximum
power budget
of lighting for
either artificial
light or
control lights
will comply
with 530:
2014.
1-4 Energy efficient index 3 4 7
1-5 System artificial of
lighting
3 7 10 To obtain a
maximum
power budget
of lighting for
either artificial
light or
control lights
will comply
with 530:
2014.
1-6 Ventilation in carpark 4 2 6 Use to reduce
the energy
that will
needed for
operation of
car park.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Point scored
= 0.05 *
percentage
from baseline
= 0.05 * 1.08
= 0.054%
1-7 Lift 0 1 1 The lift will
be required to
be equipped
with a variable
AC voltage,
features of
sleep mode
and variable
frequency
(VVVF).
1-8 Renewable energy
Encouragement on
applying sources of
renewable energy in HQ
building
use of solar
energy
use of sun pipes
use of system that
recover heat
8 12 20 Encourage use
of renewable
energy
= 0.05 *
percentage
from baseline
= 0.05 * 1.08
= 0.054%
1-7 Lift 0 1 1 The lift will
be required to
be equipped
with a variable
AC voltage,
features of
sleep mode
and variable
frequency
(VVVF).
1-8 Renewable energy
Encouragement on
applying sources of
renewable energy in HQ
building
use of solar
energy
use of sun pipes
use of system that
recover heat
8 12 20 Encourage use
of renewable
energy
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

use of lifts that
are regenerative
use of light
shelves
use of heat pumps
(20 marks)
Question 5
Next, demonstrate your detailed breakdown of the targeted scoring of the building, in order to
obtain the Green Mark Gold award. You are also advised to include additional points in your
proposal for buffer.
Note : In your proposal, you are required to estimate the energy savings, replacement of
electricity by renewable energy and Energy Efficiency Index based on the Monthly Electricity
Consumption (kWh) provided in Appendix A.
Energy efficiency Points
Thermal performance of building
envelope
REVT reduced to 22 W/m2 or less.
Target point awarded = 15 points
are regenerative
use of light
shelves
use of heat pumps
(20 marks)
Question 5
Next, demonstrate your detailed breakdown of the targeted scoring of the building, in order to
obtain the Green Mark Gold award. You are also advised to include additional points in your
proposal for buffer.
Note : In your proposal, you are required to estimate the energy savings, replacement of
electricity by renewable energy and Energy Efficiency Index based on the Monthly Electricity
Consumption (kWh) provided in Appendix A.
Energy efficiency Points
Thermal performance of building
envelope
REVT reduced to 22 W/m2 or less.
Target point awarded = 15 points

Energy efficiency
i) Calculation of
energy utilisation
index in
kWh/m2/year
ii) Calculation of Energy index
per occupant person
(kWh/person/year)
a) Secondary energy utilisation
in kWh/m2/year
Points Secondary
8 ≤ 27
7 ≤ 32
6 ≤ 35
5 ≤ 40
4 ≤ 74
Prior requirement: ensure there is an
achievement of 8 point
b) The secondary energy index
per person per year
Points Secondary
7 ≤ 487
6 ≤ 576
5 ≤ 677
4 ≤ 1034
3 ≤ 4370
Prior requirement: ensure there is an
i) Calculation of
energy utilisation
index in
kWh/m2/year
ii) Calculation of Energy index
per occupant person
(kWh/person/year)
a) Secondary energy utilisation
in kWh/m2/year
Points Secondary
8 ≤ 27
7 ≤ 32
6 ≤ 35
5 ≤ 40
4 ≤ 74
Prior requirement: ensure there is an
achievement of 8 point
b) The secondary energy index
per person per year
Points Secondary
7 ≤ 487
6 ≤ 576
5 ≤ 677
4 ≤ 1034
3 ≤ 4370
Prior requirement: ensure there is an
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

achievement of 7 point
Total point targeted = 15 points
System of air conditioning
a) Ac having a unit of
condensing model and
coefficient of
performance
b) An A/c system efficiency
Air conditioners
Unitary
Prior requirement: ensure there is an
achievement of 11 point
i. Cooling load of more
than 500RT
Achievement efficiency of 1.1
kW/ton will result to 4 points
The improvement of percentage in
the efficiency of the Chiller plant that
is better than 1.0 kW/ton will achieve
0.2 points
Scored point = 0.2 * the percentage
of improvement.
ii. Cooling load of less than
500RT
Achievement efficiency of 1.0
Total point targeted = 15 points
System of air conditioning
a) Ac having a unit of
condensing model and
coefficient of
performance
b) An A/c system efficiency
Air conditioners
Unitary
Prior requirement: ensure there is an
achievement of 11 point
i. Cooling load of more
than 500RT
Achievement efficiency of 1.1
kW/ton will result to 4 points
The improvement of percentage in
the efficiency of the Chiller plant that
is better than 1.0 kW/ton will achieve
0.2 points
Scored point = 0.2 * the percentage
of improvement.
ii. Cooling load of less than
500RT
Achievement efficiency of 1.0
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

High temperature on the rooms
kW/ton will result to 4 points
The improvement of percentage in
the efficiency of the Chiller plant that
is better than 1.0 kW/ton will achieve
0.25 points
Scored point = 0.25 * the percentage
of improvement.
Achievement of up to 1 point
Total point targeted = 22 points
Artificial system of lighting
a) Power budget
Awarding of 0.25 points for an
improvement percentage on power
budget lighting
Scored point = 0.25 * the percentage
of improvement that will be better
than LPB
Prior requirement will award 5 points
Coverage extension of at least 90%
kW/ton will result to 4 points
The improvement of percentage in
the efficiency of the Chiller plant that
is better than 1.0 kW/ton will achieve
0.25 points
Scored point = 0.25 * the percentage
of improvement.
Achievement of up to 1 point
Total point targeted = 22 points
Artificial system of lighting
a) Power budget
Awarding of 0.25 points for an
improvement percentage on power
budget lighting
Scored point = 0.25 * the percentage
of improvement that will be better
than LPB
Prior requirement will award 5 points
Coverage extension of at least 90%

b) Photon light sensors in
i) Toilets
ii) Staircases
iii) Controlling of lights
on areas which are applicable
Awarding of 0.5 points on each area
which are applicable.
Tenant adjusting light to their
comfortable use.
Less than 50% of light control award
(1 point)
Less than 90% of light control award
(2 point)
Total targeted awarded points = 10
points
Ventilation in;
i) Toilets
ii) Staircases
iii) Corridors
Natural ventilation award 1 point
Mechanical ventilation award 0.5
points
Total target point awarded = 6 points
Lift Total targeted point of 1 point for well
working installed lift
Renewable energy
Awarding of 3 points if 1% energy
i) Toilets
ii) Staircases
iii) Controlling of lights
on areas which are applicable
Awarding of 0.5 points on each area
which are applicable.
Tenant adjusting light to their
comfortable use.
Less than 50% of light control award
(1 point)
Less than 90% of light control award
(2 point)
Total targeted awarded points = 10
points
Ventilation in;
i) Toilets
ii) Staircases
iii) Corridors
Natural ventilation award 1 point
Mechanical ventilation award 0.5
points
Total target point awarded = 6 points
Lift Total targeted point of 1 point for well
working installed lift
Renewable energy
Awarding of 3 points if 1% energy
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 28
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2026 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.