This assignment provides a comprehensive project plan and review for a healthcare initiative focused on introducing a new pressure ulcer monitoring device for older adults within Peninsula Community Health Services. The project plan outlines the scope, rationale, triple constraint, and lifecycle approach, incorporating agile methodologies. A work breakdown structure (WBS) summarizes project tasks, while risk identification and mitigation strategies address potential financial and technological challenges. The assignment further analyzes stakeholder engagement using the Mendelow matrix, defines stakeholder roles and responsibilities, and evaluates legal and non-legal solutions for risk mitigation. Finally, it explores team expansion theories and conflict resolution strategies to ensure project goal achievement.
Document Page
Healthcare Management Top UP
Project Management and Risk
This is a Project Plan/Review Assignment
STU99221
4000
Table of Contents
INTRODUCTION......................................................................................................................3
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
TASK 1......................................................................................................................................3
Scope of project with rationale ..............................................................................................3
Triple constraint and baseline for project...............................................................................4
Project life cycle approach.....................................................................................................4
Project methodologies............................................................................................................5
Summary of work breakdown structure ................................................................................6
Risk identification and mitigation strategies..........................................................................9
Task 2.......................................................................................................................................11
Mendelow matrix this task is about t ...................................................................................11
Key stakeholder and their relative interest in the project.....................................................12
Roles and responsibility of the stakeholders the stakeholders here should be stakeholders
that will be directly involved in the project. Be specific and refer to the case study...........13
TASK 3....................................................................................................................................14
Evaluation of the legal and non-legal solution to mitigate the project risk .........................14
Your focus in this question should be on the legal and non -legal solutions for the risks
than will occur. I.e think about some of the ways the risks can be solved, whether legally or
non legally............................................................................................................................14
TASK 4....................................................................................................................................16
Team expansion theories for project goal achievement.......................................................16
Think of conflict and conflict resolution..................................................................................18
CONCLUSION........................................................................................................................18
REFERENCES.........................................................................................................................18
Document Page
INTRODUCTION
Project management is the essential tool which is required for the successful completion of
any project. It involves proper strategies and planning to initiate with (Meredith and et.al
2017). Therefore, for all the project it is required to proceed with scope and aim for the good
outcomes of the project. This assignment will describe about the scenario in which Peninsula
community health which aim to introduce the new pressure ulcer monitoring device for the
older people. This assignment will cover the critical discussion about the rationale and project
scope which describe about the project life cycle, it further includes the Mendelow matrix to
identify the behaviour of various stakeholders who can show the interest in the project.
Report also includes the legal and non-legal solution or risk management strategies to
mitigate the risk. It finally includes the Tuckman and McClelland process.
TASK 1
Scope of project with rationale
The project by peninsula community health services is to help the people of UK to deal with
the pressure of ulcer (Fashina, Abdilahi and Fakunle, 2020). As the majority of UK
population is facing the issues of ulcer and with this project the patients will get help and the
people also going to be more aware about the serious issue of ulcer. This project will be
having a wider scope in UK as the issues is getting more server and with this project all the
patients will get the treatment to overcome from ulcer.
Rationale
The issues of ulcer is continuously increasing the population of UK and people with
underlying healthy condition are having higher risk with this diseases. There are many
regions like Cornwall where the elder population is having pressure of ulcers every month.
So, this project will going to help the people who are facing this issue and also help the other
people to be aware of this serious disease. With the project the different hospital facilities
such as electronic health records in which patients that could keep the support for sharing the
data, test results, robotics and diagnostics technology are going to be provided to the
suffering people and continue monitor their condition with different technologies. In this
project there will be 50 patients across the Cornwall further they are being provided required
treatment peninsula community health services and their progress will be measured with
different aspects. The aim of this project is to help this people to overcome from the ulcer and
Document Page
aware the population to take precautions so that the pressure of ulcer can be avoided and try
to ensure about the various peninsula community health services.
In this project the staff will going to help the patients for around 18 month in which they will
regularly monitor the condition of patients (Corvello, Javernick-Will and Ratta, 2017). The
investigation of change of pressure ulcer and formation of ulcer, carer engagement to prevent
and the behaviour of patients are also being inspected accordingly. The access to this facility
is also easy for the patient as they need to register their names and diseases document by their
doctors there is no additional formalities. In this different monitoring tools are being used for
the patients of ulcer to know the hot spots regarding the pressure any of patient is sitting on
an particular place for long time. As this disease is occur when the people are not move for
long time and their mobility is less throughout the day (Althiyabi and Qureshi, 2021).
Triple constraint and baseline for project
This is an effective way through find out the three main elements related to the project by
peninsula community health services. As there are three main aspects and boundary
according to which a project operates its activities this are:
Scope: the project to help the underlying health condition people of Cornwall so that they can
overcome from the issue. This is having wider scope as they are taking patients from big
unitary and providing the facilities so that they can overcome from this issue. A primary
research that have been conducted for collection of data or gathering that could be based on
research, recommendation will be provided.
Time/ schedule: This project is going to operate in Cornwall for around 18 months and the
patients are provided help in this period so that they can overcome from this issue.
Budget/ cost: As the project is going to operate on an large area and there are also making use
of different innovative technologies and the nurses facilities are also provided. This project
will be going to work on a big budget (Akhwaba, Bowa and Keiyoro, 2020). while this can be
estimated about the 4565 pounds
Project life cycle approach
According to this cycle the project may include number of levels to successfully manage its
activities.
Initiation: In this level the scope, budget requirement and time needed to complete the
project activities are evaluated. There are problems also which need to fix so the problem
statement will help to know the issues and the project can be able to work effectively. while
the scope for the project that have been increased and cost that have been taken the longer
steps for which cost and schedule which must be important for the nurses working in
evaluating the given project opportunities.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Planning: When the objective of the project clear and time need to perform the task are
identified then make sure the activities and role and responsibilities within the project. The
budget is also prepared in this to organise the task. Schedule all the task and effective chain
of duties that will be followed throughout the project (Sanghera, 2019).
Execution: In this the activities which are planned are being implemented and staff are
allotted their work so that they can perform their duties. The managers will also coordinate
with the staff and help them to perform their activities more effectively.
project management monitoring and controlling that could keep the involvement about how the
actively reviewing the status for the potential, evaluating potential obstacles and also implementation
more changes which might be necessary for the completing of the project management.
Closure: in the closure the monitoring of all the task and activities are done by manager and
leaders so that the potential and target goal can be matched. When the project manager will
get any difference then they will make the required action so that situation get controlled. In
the closure is done after all the tasks are completed (Tariq, Ahmad, Ashraf, Alghamdi and
Alfakeeh, 2020). While this could be taken through using formal acceptance of the project
and project deliverables which are taken by the customer. While this could be presented for
the patients which have been states about the completed and make sure about how usually
this could work for them.
Project methodologies
This is one of the important management practise for the project and in this all the activities
are listed to deliver the project more appropriately.
Document Page
Waterfall methodology: this is one of the project management approach which emphasis
linear advance from starting task to end of the project. In this manager have to develop a plan
and then without making any change work accordingly to that plan (Hoehn and et. al., 2020).
Agile methodology: This is an effective refers to group to develop the software which is
based on iterative development. The manager in this can develop a plan and when they
complete any of the task further in this, they can make change to the previously done
activities (Beerbaum, 2021). Agile is one of the flexible approaches for the project in its
progression.
Prince2 methodology: this is used in the wider range of companies and industry which help to
manage the activities of the project (Esteki, Gandomani and Farsani, 2020). This helps the
manager to manage the project and bring them on time with the respective budget.
Form the above discussed methodologies for the project the agile is most appropriate
methodology that can be used in the project of peninsula community health services. As they
are operating this project on comparatively small scale and for this project, they are taking the
50 patients of Cornwall. The agile is flexible and when there is any kind of mistake happen
then manager is able to make the change.
Summary of work breakdown structure
For this project the work is divided into different part so that all the task related to the project
get accomplish effective by group work (Heusala and et. al., 2020). The project manager will
coordinate all the activities related to the project then the task of initiation, planning,
execution, control and closure and the 30 staff members are equally divided in all the stage to
perform their individual and group duties.
Serial
Nos.
Task Name Duration Start Finish Predecessors
1 Creation of Online
Platform for patients
221 days Fri 10/1/21 Fri 8/5/22
2 Project Initiation 18 days Fri 10/1/21 Tue
10/26/21
3 Setting Aim and Objectives 1 day Fri 10/1/21 Fri 10/1/21
4 Developing timeline 2 days Mon
10/4/21
Tue 10/5/21 3
Document Page
5 Proposing the Idea 15 days Wed
10/6/21
Tue
10/26/21
3,4
6 Project Planning 40 days Wed
10/27/21
Tue
12/21/21
7 Creating Budget 5 days Wed
10/27/21
Tue 11/2/21 3,5
8 Selection of experts and
vendors
10 days Wed
11/3/21
Tue
11/16/21
7
9 Getting investors 25 days Wed
11/17/21
Tue
12/21/21
8
10 Project Implementation 61 days Wed
12/22/21
Wed
3/16/22
11 Designing website 35 days Wed
12/22/21
Tue 2/8/22 7,9
12 Content Writing 10 days Wed 2/9/22 Tue 2/22/22 11
13 Coding 15 days Wed
2/23/22
Tue 3/15/22 12
14 Launching the website 1 day Wed
3/16/22
Wed
3/16/22
13
15 Project Monitoring 100 days Thu
3/17/22
Wed 8/3/22
16 Testing 50 days Thu 3/17/22 Wed
5/25/22
14
17 Maintenance 10 days Thu 5/26/22 Wed 6/8/22 16
18 Identifying and removing
bugs
40 days Thu 6/9/22 Wed 8/3/22 17
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Figure : Gantt Chart
Figure : Network Diagram
Document Page
Risk identification and mitigation strategies
Risk Likeliho
od of
risk to
occur
Impact of risk if occur Severit
y
Mitigation action
Financial risk Medium When the finance is not
adequate then the process
to provide different
facilities to the patient is
not complete properly and
they will not be able to get
over from issue.
High The project manager needs
to make sure that they have
adequate amount of fund so
that all the tasks effectively
done.
Document Page
Technological
risk
low The patient involved in this
project will not get the
right services and they are
unable to get normal
(Goldsworthy and Ellams,
2019). The staff are also
not going to have an
effective communication as
well as collaboration. The
project manager also not
able to work effectively
with this.
medium The project manager will
secure all the data and the
system in which the
information is getting
recorded of the patient’s
recovery from the ulcer.
The manager must check
that all the tool which are
used in the process to help
the patients are effectively
working and assisting them
so that they can recover
from the issues
Performance
risk
High The patients and the people
of the Cornwall will not be
able to know about the
issue that is faced by their
area. They will not be able
to understand what the
project need to tell them.
The patients are also not
going to overcome from
their diseases and result of
the project is not effective
and totally wastage of time
and money.
High The project manager will
avoid this risk by optimum
utilisation of resources
within the project. The
manager will inspect the
need of resource which is
needed to perform the
particular task this will
assist to identify the project
ways to avoid the risk.
Strategic risk Medium When an strategies risk
occurs in this project then
the patient that are
included in this project will
not get the appropriate
facilities and nurse are also
not helping them to get
High To mitigate this risk the
manager should monitor all
the activities and task that
are assigned to individual
person involved in this
project. All the action
related to the project are
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
away from the issues of
ulcer. The result of the
project are not effective
and patient are also not
satisfied with this project.
measured and manager
further make the controlling
to the task so that activities
can done optimally.
Manager will prioritise the
task for the project and
make effort to complete that
first.
Task 2
Mendelow matrix this task is about t
Mendelow matrix is the important tool which is mainly used by the organization to know
about the behaviour of their stakeholders in terms of their attitude, knowledgeable approach
to start any project. This matrix involves the level of understanding of the stakeholders in the
organizational strategies or organization uses their approaches to enable the stakeholders to
invest or consider their project.
Structure of Mendelow matrix:
This matrix is generally consisting of four parts as
Minimal efforts:
This part of the matrix involves the stakeholders which are not interested in the planning or
project of the organization. In this category the stakeholder will be the supplier who have no
longer interest in business (Buganová and Šimíčková, 2019). Their only work is to supply
the raw materials, therefore project leader for treating the Ulcer patient, they need to use the
resources well in order to deal with the suppliers, or they also proceed to develop a
connection with other suppliers so that they can negotiate the price for raw materials required
in project.
Keep informed:
In this stage member of the project can be a major stakeholder as they have more interest to
indulge in project process. As they are the key holders who can work out to give positive
outcome of the project.
Keep Satisfied:
Document Page
In this the stakeholder will be a large supplier or governmental agencies who can play a
essential role in success of the project. Therefore, the project leader for ulcer require to
satisfy the stakeholders in order to get successful evaluation of their project (Harrison and
Lock, 2017).
Key players:
This stage includes the customer as a stakeholder as they are the key player who decides the
success or failure ratio of any project. Therefore, project leader needs to develop all the
strategies before introducing their project to the audience so that it enables the audience to
take part in the project.
Key stakeholder and their relative interest in the project
Stakeholder plays an important role in the funding process for every project, therefore for the
cure of Ulcer in Cornwall the peninsula community health will have to involve the effective
participation of the stakeholder in order to get better result. Their projects key stakeholder
will be-
Clinical staff as a stakeholder:
Clinical staff will be the major anticipated stakeholder for the project as projects' aim is to
provide awareness about the pressure ulcer to mitigate its risk at early stage or to enable the
patient for self-management of this disease. Clinical staff can educate the patient by giving
them a knowledge to mitigate its risk or to take precautions to protect from this disease
(Bredillet, C., Tywoniak and Tootoonchy, 2018).
Government as a stakeholder:
For every project it is important to involve the government legal factor in the project to
protect from any kind of future legal activities, as they collect the taxes therefore for every
project it is required to done all the legal activities before initiating the project as it will help
to secure from any legal procedures.
Businessman as a stakeholder:
For every project it is required to manage all the funds related procedures as for the project
initiation it requires an investment to arrange all the resources. Therefore, it is the major
responsibility for the project leader to make an effective strategy so that it will influence the
stakeholders to take effective part in the project.