This report provides a comprehensive analysis of stakeholder management within the Highway 99 upgradation project, also known as Burns Road, in Homer city. The project aims to alleviate traffic congestion and improve commercial transportation efficiency. The report outlines the project's scope, objectives, benefits (such as reduced traffic and increased commercial activity), and potential constraints, risks (environmental hazards, political issues), and assumptions. It identifies and analyzes key stakeholders, categorizing them based on their power and interest levels, and proposes a communication plan to ensure effective information flow. Requirement gathering tools, including surveys, questionnaires, and focus groups, were employed to gather data from residents, businesses, and other stakeholders. The analysis of gathered data revealed significant support for the project. The report concludes with solution strategies and recommendations for successful project execution, highlighting lessons learned and emphasizing the importance of stakeholder engagement and communication. The appendices include a questionnaire and further details on stakeholder management.
Document Page
Running head: STAKEHOLDER MANAGEMENT IN PROJECT
STAKEHOLDER MANAGEMENT IN PROJECT
Name of the Student
Name of the University
Author note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1STAKEHOLDER MANAGEMENT IN PROJECT
Executive Summary:
Aim of the project is to analyse the project scope and benefits, risks and assumptions,
stakeholder management of the given project. The project is related to the upgradation of
Highway 99, else known as Burns Road in the city of Homer. This upgradation is necessary
as it is one of the major commercial transportation route of the city and facing many
problems like traffic jams and tie delay in transportation. A communication plan and a survey
has been done to achieve progress in the project. The report is concluded with a business
outline of the project from the viewpoint of a project manager to help the sponsors.
Document Page
2STAKEHOLDER MANAGEMENT IN PROJECT
Table of Contents
Project Scopes and Objectives:......................................................................................4
Project Benefits:.............................................................................................................4
Project Constraints, Risks and Assumptions:.................................................................5
Stakeholders:..................................................................................................................5
Stakeholder Identification and Analysis:.......................................................................6
Stakeholder Power Grid and Engagement Matrix:........................................................7
Actively Engaged:......................................................................................................9
Keep Informed:..........................................................................................................9
Keep Satisfied:...........................................................................................................9
Monitor:......................................................................................................................9
Project Communication Plan:........................................................................................9
Requirement Gathering Tools:.....................................................................................10
Surveys and Questionnaire:......................................................................................10
Focus Groups:..........................................................................................................10
Target Population:................................................................................................11
Analysis:.......................................................................................................................11
Solution Strategies:......................................................................................................11
Project Budget:.............................................................................................................13
Recommendations:.......................................................................................................13
Lessons Learned:..........................................................................................................14
References:...................................................................................................................15
Appendices:..................................................................................................................18
Questionnaire:..........................................................................................................18
Stakeholder Management:........................................................................................19
Document Page
3STAKEHOLDER MANAGEMENT IN PROJECT
Project Scopes and Objectives:
There are certain scopes and objectives related to the project. The first and most
important scope is to arrange the sponsor for funding the project (De Schepper, Dooms &
Haezendonck, 2014). Next scope is to ensure the construction of dual carriageway along with
three traffic lanes in either direction in the upgraded road. Following scopes are installation
of street lighting poles with neon lights and electronic gantry signs all over the main
carriageways. These neon lights are the upgraded version of traffic lights. After that comes
the new limitation of speed and restriction rules for cyclists, pedestrians and animals near
these roads. The restriction rules are developed following only one goal and that is safety and
security for public and animals (Kendrick, 2015). Next scopes of the project are to raise the
busiest sections of the Burns Road and utilization of freeway style ramps for exiting the
highway. The planning of this raise has been done so that it goes over the railway the railway
lines not causing any traffic jams near the railway level crossings (Fewings, 2013). Other
scopes related with the project are 5 km diversion of the highway near Wiggum Regional
Park and construction of 24/7 service station inside the park. The last but one of the most
important scope is to relocate the existing power substation and replace it with another
suitable electrical substation and depot for maintenance on the residential grounds. High
voltage poles have to be removed in this case.
Project Benefits:
Major benefit that can be obtained from this project is reduction of traffic jams and
time delay (Eskerod & Jepsen, 2013). This project will also expand the highway, therefore
allowing a swift movement of heavy vehicles. Construction of 24/7 service station inside the
Regional; Park will provide the drivers necessary requirements and reduce the amount of
stops. 5 Km diversion of the road will reduce the traffic congestion around the intersection of
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4STAKEHOLDER MANAGEMENT IN PROJECT
Burns Road and Waylon Way. Neon street lighting and electronic gantry signs will increase
driver awareness and visibility. Expansion of the road will increase the commercial activity
within the city. Traffic jams will get reduce in congested intersections.
Project Constraints, Risks and Assumptions:
The major risks which are associated with the project are environmental hazards,
political issues, discontent among the stakeholders and cost-benefit issues. Increase in taxes
and attraction of more businesses are the primary goals of this project and the comparison
between project cost and benefit will always be a doubtful subject before the completion of
the project (De Brucker, Macharis & Verbeke, 2013). Demolition of buildings and required
construction will impact the environment so that is another risk. Political issues can be
considered as a risk too. Moreover, discontent among stakeholders in some part of the project
is a risk regarding time and money both (Haimes, 2015).
Project constraints are the restrictions present in the pathway of project action. The
general project constraints are risk, quality, cost, resource, scope and time. For the given
project time, cost, risks and quality are the major constraints (Burke, 2013). The project will
definitely cause environmental hazards so proper measures should be ready. Apart from that
the resources are need to be imported from other cities as all the resources are not present
within the city. More time the project will linger on, more time delays and losses in
commercial transportation will occur (Kendrick, 2015).
Stakeholders:
Stakeholder is a person or a group of person or even an organisation that takes interest
in the business of an organisation. Any business has constant interaction with its stakeholders
that either affects the business or affects the stakeholders (Doh & Quigley, 2014). Any
Document Page
5STAKEHOLDER MANAGEMENT IN PROJECT
business contains three fundamental stakeholders, who are employees, investors and
consumers (Moura-Leite, Padgett & Galán, 2014). These stakeholders can be either internal
or external depending upon their connection with the business (Minoja, 2012). Investors are
the example of internal stakeholders where creditors and suppliers are the example of
external stakeholders (Freeman & Moutchnik, 2013).
Stakeholder Identification and Analysis:
Stakeholders in this road upgradation projects are the people who are actively
involved with the project, directly or indirectly. They are facility owners and users,
shareholders, project managers and facilities managers, suppliers, employees, sub-
contractors, service providers, legal authorities, community representatives, banks, media,
business establishments, general public, government and natural environment (El Abboubi &
Cornet, 2012).
Analysing the stakeholders according to their importance, responsibility, integration
and interests, a categorization of primary and secondary stakeholders has been obtained.
Project managers, general managers, functional managers are the primary stakeholders in the
project action plan. On the other hand contractors, suppliers and unions are also directly
involved with the project (Davis, 2014). Finally shareholders, employees and legal
organisations come into the category of primary stakeholders as the impact of the project will
directly upon them (Carpenter, 2014). These stakeholders influence the decisions and
direction of the project. And they have contractual relationship with the project. Secondary
stakeholders are general public, residents, social and professional organisations, media, local
communities and some others. They do not have a contractual relationship with the project
but they have interests and they receive the impacts (Lam, 2014).
Document Page
6STAKEHOLDER MANAGEMENT IN PROJECT
Stakeholder Power Grid and Engagement Matrix:
A grouping can be created among the stakeholders on the basis of their power and
level of interests regarding the outcomes of the project. Project manager is the main designer
and controller of the project (Eskerod & Jepsen, 2013). Main contractor transform the project
model to a reality and sub-contractor follows the orders of main contractor like supplying of
materials and other tasks. Financer are main source of funding of project. Shareholders are
persons to maintain the cost-benefit structure of the project (De Schepper, Dooms &
Haezendonck, 2014). Legal organisations holds the authorities of the project. Social, political
and professional organisations become involve in the project activities as they face the
Impact. Business is the main objective of the project and the residents and the environment
are the ones who are subjected to face the primary impacts of the projects (Minoja, 2012).
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7STAKEHOLDER MANAGEMENT IN PROJECT
(Political and professional
organisations, NGO, Unions)
Keep satisfied
(Financers, Project managers,
contractors, Suppliers
employees, service providers, )
Actively engaged
(Legal organisations, functional
managers, Competitor groups,
residents, environmentalists)
Monitor
(Shareholders, social and
political organisations, media,
general public )
Keep Informed
Different stakeholder has variable interests in this project of road upgradation. With
the progress of the upgradation the interests still remain variable (Von Meding et al., 2013).
Different stakeholders focus on different stage of the project. A power versus interest grid
matrix has been prepared for classification of power and interest on the basis on engagement
of stakeholders in the project.
Actively Engaged:
They are the most significant stakeholders of this project and control all the matters of
the projects. All the decisions like gathering of financial resources, demolition of buildings,
P
p
O
W
E
R
I N T E R E S T
Document Page
8STAKEHOLDER MANAGEMENT IN PROJECT
construction of dual carriageway, installation of neon street lights and electronic gantry signs,
construction of 24/7 service station are made by these stakeholders (Doh & Quigley, 2014).
Keep Informed:
These stakeholders requires information of every progress in the project. They
possesses high interest in the project but their decision making power is low (Fewings, 2013).
Some stakeholders among them have influences on some decision of the project. These
stakeholders also faces the direct impact of the project.
Keep Satisfied:
These people are the stakeholders who possesses high power but low interest on the
project (Mok, Shen & Yang, 2015).
Monitor:
These stakeholders are mainly government and other legal organisations who manage
the legal and social procedures of the projects (Gatti, 2013).
Project Communication Plan:
To complete a project of road upgradation this big, communication must be
maintained among the project sponsors, project managers, stakeholders, government and
construction workers. From the perspective of a project manager, communication between
the stakeholders and workers are the most important thing, else the project will not proceed
accordingly. Any problems should be solved right away as this is the major communication
pathway for the city. Main contractor and sub-contractors must be always in touch with the
project manager and supervisors (De Brucker, Macharis & Verbeke, 2013). Daily schedule
should be followed all the time. Several communication tools can be used in this case like
official presentations, newsletters, internet, emails, status reports and others. Construction
Document Page
9STAKEHOLDER MANAGEMENT IN PROJECT
workers should be well connected with the environmentalists to maintain that environmental
hazards remain limited.
Goals of this communication plan is to gather general information, estimation of the
efficiency of new transport system, advertisement and public awareness, information
gathering regarding impact on nature (Weiss, 2014).
Requirement Gathering Tools:
The process of discovery, documentation and management of stakeholders to satisfy
the objectives and scopes of the project. Key information of the project is discovered by a lot
of information gathering tools. For this case the two tools those have been used are surveys
and questionnaire and focus groups.
Surveys and Questionnaire:
This techniques are effective to obtain the perspectives of the users. Using these
techniques stakeholders are able to understand the viewpoints of the residents and the local
businessmen (Moura-Leite, Padgett & Galán, 2014). This method have positive benefits
reasonable cost and low processing time, integration of the viewpoints of a large population,
low amount of training and other benefits regarding data collection method.
Focus Groups:
Focus group can be called a portal of homogeneous of heterogeneous stakeholders
who can develop ideas for new products or improvisation for old ones. User-base view, the
most important factor for a social and economic project can be obtained by applying the
principle of a focus group (Fassin, 2012). This method of data gathering is efficient when the
target population is large.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10STAKEHOLDER MANAGEMENT IN PROJECT
Target Population:
Target population includes residents of the whole, businessmen, students,
environmentalists, professionals and office workers (Freeman & Moutchnik, 2013). The
project management team went to different houses, commercial stores and community centres
to gather the data. More than 50 focus group session have been performed.
Analysis:
Information that has been gathered using all the requirement tools are analysed in this
section. Almost 70% of the local residents have complained about the traffic jams and gave
positive answers for the project of upgradation of the road. Almost 85% of the businessmen
have agreed with the upgradation plan as highway 99 is the major commercial route in
Homer city. 60% of the environmentalists have agreed with the upgradation project plan
despite of the harmful effects on nature. Near about 60% of the members of social and
professional organisations are content with the objective the planning of the project. Finally
80% of the financers and 95% of the stakeholders are on the same page in this project.
Solution Strategies:
Major solution strategies of the problems in the projects are discussed here. Gathering
of financial resources is the solution to start the project of upgradation highway 99, else
known as Burns Road. To complete this objective the major activity will be to gather as many
sponsors as possible for proper funding. Next solution is demolition of buildings and
subsidiaries in a proper way and a fair compensation to the natives so they can settle down on
another place. Next to reduce the traffic jams dual carriageway should be formed along with
three lanes in each section and construction of emergency lanes. To maintain the traffic
visibility at night and aware the drivers about entry and exit neon street lights and electric
gantry signs should be placed where necessary (Bal et al., 2013). To maintain the safety
Document Page
11STAKEHOLDER MANAGEMENT IN PROJECT
among the residents, animals and cyclists some road limitations and penalties for violating
them should be set by the legal department. Busiest part of the road should be raised to form
a bridge and this way traffic jam near the railway level crossings can be avoided. To decrease
the congestion at the intersection of Burns Road and Waylon Way a diversion of 5 Km
should be constructed. A 24/7 service stations should be made beside the highway so that
people do not have to move far away from the road to get refreshment or fuel (Doloi, 2012).
Lastly an electricity substation and depot for maintenance should be established as soon as
possible, replacing the old one.
Document Page
12STAKEHOLDER MANAGEMENT IN PROJECT
Project Budget:
Estimating your start-up costs
Equipment & assets
Extra equipment e.g., vehicles, cleaning equipment $ 20,000 2
Extra office equipment, e.g., computer, photocopier $ 10,000 3
Fitting out, e.g., fittings, interior and exterior design $ 56,000 4
Other 'one off' costs
Initial stock, e.g., merchandise, components $ 54,000
Initial lease payments (new equipment etc) $ 34,000
Licence fees $ 56,000
Stationery e.g, letterhead, pens, pencils, paper $ 67,000
Initial promotion costs, e.g, web design, signs, brochures $ 76,000
Public relations fees $ 1,000
Adviser fees, e.g., consultant charges, accountant fees $ 340
Training costs. e.g., TAFE course fees $ 5,000
Additional insurance $ 45,000
Other $ 23,000
Purchase cost of existing venture (include legal fees etc) $ 12,000
Franchise and other fees to be paid $ 12,000
Total Capital costs $ 471,340
Life span
(years)
Please note that this is a guide only and should neither replace competent advice, nor be taken, or relied upon, as financial or professional
advice. Seek professional advice before making any decision that could affect your business.
Start-up costs
Complete the details in the boxes to calculate your
start-up costs.
This spreadsheet calculates the set up costs of your
idea. These are what you will you need to buy or
pay for before you can get your idea to the market.
It is important to estimate these as realistically as
you can. It may be that you need to go away and
research some of these costs before you can
complete the table.
Many of these costs listed may not apply to your
idea - in which case just leave the field blank or
change the descriptions.
www.tsbc.comIn association with The Small Business Company Limited.
Recommendations:
The major recommendation that can be given in this project is the fundamental
objective of the project of road upgradation should not be based the commercial needs of the
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13STAKEHOLDER MANAGEMENT IN PROJECT
city. The requirement of the residential and the safety of the environment should be
considered as well. Regarding the issues of the stakeholders, it can be said that the project
must be start after all the stakeholders can come to a same agreement. The communication
process among the project team must be maintained throughout the project. Expansion of the
road with construction of more lanes is better plan than digging a tunnel. For safety
measurements, appropriate amount of street lights and electrical gantry signs should be
placed. Overbridge section of the highway should be properly balanced. Lastly, transportation
system should be managed by experience traffic guards to prevent any mishap.
Lessons Learned:
The lessons those have been learned from the project are the utilisation of various
methods to analyse stakeholder issues and management, different information gathering
techniques help to obtain a common perspective, identification method of objectives and
scopes of a project and the insight of the techniques to deal with people from different
background, personal and professional.
Document Page
14STAKEHOLDER MANAGEMENT IN PROJECT
References:
Bal, M., Bryde, D., Fearon, D., & Ochieng, E. (2013). Stakeholder engagement: Achieving
sustainability in the construction sector. Sustainability, 5(2), 695-710.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Carpenter, J. (2014). Library project funding: a guide to planning and writing proposals.
Elsevier.
Davis, K. (2014). Different stakeholder groups and their perceptions of project
success. International Journal of Project Management, 32(2), 189-201.
De Brucker, K., Macharis, C., & Verbeke, A. (2013). Multi-criteria analysis and the
resolution of sustainable development dilemmas: A stakeholder management
approach. European journal of operational research, 224(1), 122-131.
De Schepper, S., Dooms, M., & Haezendonck, E. (2014). Stakeholder dynamics and
responsibilities in Public–Private Partnerships: A mixed experience. International
Journal of Project Management, 32(7), 1210-1222.
Doh, J. P., & Quigley, N. R. (2014). Responsible leadership and stakeholder management:
Influence pathways and organizational outcomes. The Academy of Management
Perspectives, 28(3), 255-274.
Doloi, H. (2012). Cost overruns and failure in project management: Understanding the roles
of key stakeholders in construction projects. Journal of construction engineering and
management, 139(3), 267-279.
Document Page
15STAKEHOLDER MANAGEMENT IN PROJECT
El Abboubi, M., & Cornet, A. (2012). Towards a dynamic stakeholder management
framework for CSR certifications. International Journal Of Business And Social
Science, 3(4).
Eskerod, P., & Jepsen, A. L. (2013). Project stakeholder management. Gower Publishing,
Ltd..
Fassin, Y. (2012). Stakeholder management, reciprocity and stakeholder
responsibility. Journal of Business Ethics, 109(1), 83-96.
Fewings, P. (2013). Construction project management: an integrated approach. Routledge.
Freeman, E., & Moutchnik, A. (2013). Stakeholder management and CSR: questions and
answers. uwf UmweltWirtschaftsForum, 21(1-2), 5-9.
Gatti, S. (2013). Project finance in theory and practice: designing, structuring, and financing
private and public projects. Academic Press.
Haimes, Y. Y. (2015). Risk modeling, assessment, and management. John Wiley & Sons.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-
proofing your project. AMACOM Div American Mgmt Assn.
Lam, J. (2014). Enterprise risk management: from incentives to controls. John Wiley & Sons.
Minoja, M. (2012). Stakeholder management theory, firm strategy, and
ambidexterity. Journal of Business Ethics, 109(1), 67-82.
Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega
construction projects: A review and future directions. International Journal of Project
Management, 33(2), 446-457.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16STAKEHOLDER MANAGEMENT IN PROJECT
Moura-Leite, R. C., Padgett, R. C., & Galán, J. I. (2014). Stakeholder management and
nonparticipation in controversial business. Business & Society, 53(1), 45-70.
Von Meding, J., McAllister, K., Oyedele, L., & Kelly, K. (2013). A framework for
stakeholder management and corporate culture. Built Environment Project and Asset
Management, 3(1), 24-41.
Weiss, J. W. (2014). Business ethics: A stakeholder and issues management approach.
Berrett-Koehler Publishers
Document Page
17STAKEHOLDER MANAGEMENT IN PROJECT
Appendices:
Questionnaire:
This survey has been conducted to evaluate the relevance and impacts of the
upgradation project of Highway 99 in Homer city:
Gender:
a. Male b. Female
Occupation:
Primary means of Transport:
A. Bus B. Private Car C. Cab D. Train
Daily Traffic Conditions:
A. Smooth Traffic B. Low Traffic C. Moderate Traffic D. Huge Traffic
Congestion
Requirement for Upgradation of Highway 99:
A. Yes B. No C. Maybe
Process of Upgradation:
A. Tunnel beneath Wiggum Regional Park B. Expansion of the highway
with two carriageways
Will upgradation of the road help in improvement of Commercial
Transport?
A. Yes B. No C. Maybe
Document Page
18STAKEHOLDER MANAGEMENT IN PROJECT
Will 5 Km diversion of Burns road near Wiggum Regional Park reduce
traffic congestion at the intersection of Burns Road and Waylon Way?
A. Yes B. No C. Maybe
Will Neon street lights and Electrical Gantry signs help in improvement of
visualization?
A. Yes B. No C. Maybe
Will the road be raised over the railway level crossing?
A. Yes B. No C. Maybe
Will a 24/7 service station be made inside Wiggum Regional Park?
A. Yes B. No C. Maybe
Stakeholder Management:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19STAKEHOLDER MANAGEMENT IN PROJECT
chevron_up_icon
1 out of 20
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]