This project management plan outlines the relocation of Burnaby Hospital, addressing key aspects such as customer identification, stakeholder analysis, project scope, statement of work, work breakdown structure (WBS), project costs, scheduling, risk management, and quality control. The plan includes a detailed analysis of stakeholders like the Burnaby Hospital Management Team, doctors, nurses, and contractors, along with their respective interests and influences. It defines the project's scope, encompassing the construction of a new hospital, infrastructure upgrades, equipment procurement, and technical requirements. The plan also addresses project limitations, exclusions, and the roles of the project sponsor (Government of Canada and Health Canada) in decision-making and communication. Furthermore, it details the project team's roles, communication strategies, key performance measurements, and procurement processes. The document concludes with health and safety considerations and includes a project charter in the appendix, providing a comprehensive guide for the successful relocation of Burnaby Hospital.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: SCENARIO OF RELOCATING BURNABY HOSPITAL
Comprehensive Project Management Plan: Scenario of Relocating Burnaby Hospital
Name of the Student
Name of the University
Author note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1SCENARIO OF RELOCATING BURNABY HOSPITAL
Executive Summary
The project is based on constructing the Burnaby Hospital. The hospital management team has
decided to build the entire project within a limited budget and time period. The project has been
approved by the Government of Canada and the Healthcare Department of Canada. The
discussion in this report is based on understanding of each of the requirements and necessities of
the project. The building of the new hospital would be highly required for providing various kind
of facilities to the patients. The report discusses about the entire schedule and cost estimation for
the different activities set for the project. The report also discusses about the risks and
contingencies that are concerned with the project. Thus after the completion of the project, the
different requirements based on building of the hospital would be understood.
Document Page
2SCENARIO OF RELOCATING BURNABY HOSPITAL
Statement of Assumptions
The certain assumptions could be made during the preparing of the project plan:
Permission Grant – The permission would be granted by the Government of Canada and
Healthcare Department of Canada. They would understand the project plan and then provide
approval for the project.
Considering various factors – Different factors based on permission of zone would be
approved after discussing with the local administration.
Design – The design layout for the project would be approved after a formal approval
from the project management team and the higher officials.
Social – The construction work over the project could lead to disruption of traffic and
certain check points.
Document Page
3SCENARIO OF RELOCATING BURNABY HOSPITAL
Table of Contents
Executive Summary.........................................................................................................................1
Statement of Assumptions...............................................................................................................2
1. Identification of Potential Customers..........................................................................................5
2. Stakeholder Identification and Analysis......................................................................................5
3. Project Sponsor............................................................................................................................7
4. Scope of the Project.....................................................................................................................8
5. Statement of Work.....................................................................................................................11
6. Work Breakdown Structure (WBS)...........................................................................................16
7. Work Activities (from WBS).....................................................................................................17
8. Project Costs..............................................................................................................................23
9. Project Scheduling.....................................................................................................................24
10. Project Gates............................................................................................................................26
11. Risks........................................................................................................................................26
11.1 Risk identification..............................................................................................................26
11.2 Prioritization......................................................................................................................27
11.4 Risk Matrix........................................................................................................................27
12. Project Team (your group is the team)....................................................................................29
12.1 Importance of Project Team..............................................................................................29
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4SCENARIO OF RELOCATING BURNABY HOSPITAL
12.2 Roles and Responsibilities of the Team Members of the Project......................................30
13. Project Communications – Matrix showing internal and external, types and frequency........32
13.1 Project Communication Matrix.........................................................................................32
14. Key Performance Measurements (KPM’S) specific quantifiable metrics to track success of
the project......................................................................................................................................35
15. Project Procurement.................................................................................................................35
17. Quality Control – inspection (acceptance) criteria for each work activity..............................36
18. Any other issues pertinent to the project.................................................................................40
18.1 Health and Safety Considerations......................................................................................40
Appendix A: Project Charter.........................................................................................................44
Document Page
5SCENARIO OF RELOCATING BURNABY HOSPITAL
1. Identification of Potential Customers
The potential customers who would be benefited and valued from the completion and
success of the project are the patients who would come to the hospital for getting proper
treatment. The patients who would reach to the hospital to get the healthcare assistance would be
benefited from the project. They would be highly valued from the completion of the project as
they would gain better form of assistance from the doctors. They would gain help from the new
and advanced medical equipment that would be procured within the hospital. After the
completion of the project, the patients would receive high form of convenience and comfort at
the hospital. They would also receive state-of-the-art medical technology and thus they would be
highly benefited as the doctors would also be able to serve them in a better manner.
2. Stakeholder Identification and Analysis
The different stakeholder who are involved with the construction project of Burnaby
Hospital are:
1. Burnaby Hospital Management Team – The hospital management team would be
considered as the primary stakeholder who would be assigning the work to the project manager,
construction specialists and other project sponsor. They would be made to understand about the
need for the development of a new hospital that would include the better forms of medical
equipment in order to serve the patients in the best possible manner. They would have the
maximum amount of interest based on developing the project and seeing into each of the affected
costs and outcomes from the project. They have the maximum power of choosing the best form
of contractors who would handle the entire design of the project.
Document Page
6SCENARIO OF RELOCATING BURNABY HOSPITAL
2. Doctors – The doctors would also be considered as the next stakeholder within the
project. They would be affected with each of the major development activity that would take
place within the hospital. The new and efficient medical equipment that would be installed
within the hospital would also be a matter of great satisfaction for the doctors. These new
equipment that would be used by the doctors would also help them to increase the efficiency of
treatment for the patients. Enhanced form of patient services and better access to the needs of the
patients would in turn lead to better engagement with the patients.
3. Nurses – The nurses would also be affected with the development of the new hospital.
They would be benefited after the development of the new hospital as they would be able to
better follow the instructions of the doctors. Although they would have less form of power
during the development work over the construction project but they would have maximum
interest for the development of the project. This would also lead them to understand the exact
concerns of the patients by noting them and conveying them to the doctors. After the proper kind
of instructions from their supervisor doctors, the nurses would bring the new equipment that
would help in serving the patients better and efficiently.
4. Customer Support Team – The customer support team would also have latest
facilities and advanced infrastructure based on understanding the exact needs of the customer by
listening to their problems and resolving their queries. The customer support team would also
have a certain level of interest with the construction of the new hospital. Advanced from of
computing systems would be installed within the hospital that would be highly responsive and
thus they would understand the exact queries and issues raised by the customers. Accordingly,
the customer service representative would be able to identify them and thus redirect them to the
top healthcare specialist in order to solve their issues in real-time scenarios.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7SCENARIO OF RELOCATING BURNABY HOSPITAL
5. Helpdesk Specialists – The helpdesk specialists would be sitting at the reception
section of the hospital. They would also be provided with computers that would be fitted with
new and advanced software. The customers would report to them after arriving at the hospital.
They would directly listen to the customer concerns and hence transfer them to the specialized
department in order to receive further aids. These helpdesk specialists would also be responsible
for connecting the patients with the appropriate doctors who would then serve them with the
most efficient healthcare amenities. Thus they would also have a certain level of interest based
on the development of the new hospital.
6. Contractors – The contractors within the construction department would be highly
interested for performing the work of construction based on the development of the Burnaby
Hospital. The contractors would have the maximum form of interest based on receiving the
tender for the construction project. They would thus be highly responsible for detailing out the
entire aspects of the construction project to the hospital management team. They would also list
the entire list of materials in relation to performing the work of construction.
3. Project Sponsor
The Government of Canada and Health Canada, Ministry of Health and the management
team at Burnaby Hospital would be primarily responsible for sponsoring the entire project. With
the different forms of new requirement based within the infrastructure of the hospital, it would be
highly important for the project sponsor to look into the developmental aspects and the present
situation within the hospital.
The plan of the project based on developing a new hospital at a different new site would
incur a high level of understanding of the needs of patients and the healthcare industry. In order
Document Page
8SCENARIO OF RELOCATING BURNABY HOSPITAL
to develop the project in a well-planned manner, the deliverables, budget and schedule of the
project should be planned accordingly. After the approval of the project plan from the
management team and Health Department, the project would be funded and thus the work over
the project would begin. During the performing of the project, critical decisions would be taken
by the project sponsor in order to move the project in a well-planned manner. The project
sponsor should properly communicate with the various departments in-charge of the construction
work over the project. Hence, they should also show some level of support and thus express their
interest and wide form of commitment for the overall success towards the project.
4. Scope of the Project
The scope of the project could be defined as the entire construction work that would be
performed for delivering a new hospital. The scope of construction of the new hospital is based
on focusing over the entire list of deliverables that would be supplied after the completion of the
project.
The scope of the hospital construction project could be accomplished by following the
certain list of deliverables. These include:
Building of a new hospital at a new site situated at Willingdon and Canada Way
Upgrading of hospital surroundings and supporting infrastructure such as sewer, water,
gas and electricity
Purchasing of new medical equipment and installing them
Purchasing of new furniture, office equipment such as computers and advanced medical
infrastructure
Document Page
9SCENARIO OF RELOCATING BURNABY HOSPITAL
Acquisition of construction site, choosing of the contractors for the supply of goods and
bringing them within the site.
Technical Requirements – In order to prepare the construction project of the Burnaby
Hospital, certain kind of technical requirements would be highly required for the perfect design
of the project. Based on the project of constructing of the Burnaby Hospital, the project manager
along with the construction manager design the specific details in relation with the project.
Design drawings would need to be prepared in order to prepare and set the information
about the design and various procedures that need to be followed for performing the construction
work. In this technical requirement for the project, the construction manager would present a
technical layout of the entire core project based on which the architects would plan for the entire
project.
The project manager should also be responsible for defining the bill of quantities. In this
bill, each of the required materials that would be required for the performing of the project would
be made. Based on the certain list of items, the tenderer would be provided with the appropriate
forms of cost based on the work needed to be performed for the construction work.
The specifications of each material that would be required within the construction project
should be prepared and provided to the construction manager and project manager. They should
be highly efficient for understanding the necessities of the construction project. The requirements
for material testing would also be mentioned by the construction engineer who would be
performing field work. They should check over each of the intrinsic details of the work over the
project.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10SCENARIO OF RELOCATING BURNABY HOSPITAL
Limits – The limits for the construction project include the completion of each of the
necessary milestones set for the project. The project manager and other engineers working over
the project would be bounded within the set limitation of the project. The budget and time that
are estimated for the project could also be defined as the limitations of the project. The project
would be bounded within a certain limited period and the project sponsor would also set a
limited budget for the project.
Exclusions – Every project would incur some kind of exclusions. This is defined as the
kind of work activities that would not be performed beyond the set work limit. Every project
would incur some pre-defined work activities that list out the different tasks in relation to the
project. Such kind of things would be included within the project as per the emerging needs of
the project. However, the certain things that might be provided after the plan of the project has
been defined are defined as exclusions within the project. The certain exclusions within the
construction project are:
The construction manager would not be responsible for performing the interior designs of
the hospital infrastructure
Procurement and installation of the new medical equipment would not be performed by
the construction engineer
The construction manager would not perform any maintenance work after the
construction of the project has been done
The property policy that lists out the safety of equipment and other construction materials
would not be covered within the construction plan. Rather it would be covered within the
project plan that would be defined by the project manager.
Document Page
11SCENARIO OF RELOCATING BURNABY HOSPITAL
Constraints – There could be different kind of constraints in relation the to the
construction project of the hospital. The different kind of constraints in relation to the
construction project could be based within resources, budget and time estimated for the project.
5. Statement of Work
The construction project consist of five primary deliverables that would need to be
summarized within the Statement of Work. This statement would help in explaining the
objectives that would be able to expand the objectives, identify any kind of issues within the
deliverables and thus decide on certain measures for resolving the raised issues.
1. Building of a new hospital situated at Willingdon and Canada Way – The
Government of Canada would have to understand the necessities of the patients based on the
present condition of healthcare. The management team of the hospital would have to analyze the
present situation within the healthcare sector, make a list of the certain equipment and medical
facilities that are provided by the hospital. Based on the certain emerging needs, the hospital
would be built that would comprise of the necessary amenities. The Government should also
select the proper location based on which they would plan for the entire construction project. In
the initial position, the Government should select the proper site over which the construction
would be set.
After the selection of the site, the management team would be informed and based on that
they would take appropriate steps for performing the future works over the project. The
construction manager would be made to understand about the high-level needs of the hospital.
The time period of the completion of the project would also be set during this time. The
Document Page
12SCENARIO OF RELOCATING BURNABY HOSPITAL
excavation work over the project would finally begin after the proper form of approval from the
project sponsor and project manager.
2. Upgrading of hospital and surrounding infrastructure – The primary aim of the
construction of the new hospital would need to include each of the factors that were lacking in
the old infrastructure of the hospital. The new hospital would thus be equipped with each of the
facilities that would be highly needed for providing the best kind of benefits based within the
healthcare department. The supporting infrastructure within the hospital includes the sewage
system, water facilities and other facilities such as gas and electricity. These are defined as the
basic and most useful amenities that would be extremely needed for proper running of the
hospital.
The hospital management team should undertake proper measures in order to contact
with the proper suppliers of such kind of necessary materials. During the building of the new
Burnaby Hospital, it should be highly ensured that each of the upgraded materials should be
based on certain guidelines and specific policies that would be set for the specific industry. After
the construction work would be completely over, the concerned people for fixing the materials in
proper place would hold responsibility to put these places in specific places. The hospital should
also be supported with wide escalators and lift system in order to bring convenience for the
patients. This would also reduce the time of reaching to the proper floor and get their
appointment within the proper time. The escalators should also be situated adjacent to the
stairways.
3. Purchasing of new medical equipment – With the rise of critical ailments that are
concerned with the patients, the purchasing of new medical equipment would be highly
necessary in order to deal with such kind of ailments. The old hospital did not have the advanced
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13SCENARIO OF RELOCATING BURNABY HOSPITAL
medical equipment and thus due to the lack of such kind of equipment they could not afford to
provide such kind of high medical treatment to their patients. This would in turn lead to a bad
reputation for the hospital. Thus the hospital management team should conduct a meeting with
the different healthcare specialists, doctors and nurses who are efficient in dealing with the
patients, understand their concerns and thus recommend the management team to bring special
kind of medical equipment within the hospital infrastructure. The hospital should also be
provided with wheelchair facility for the convenience of certain group of patients.
The Burnaby Hospital would comprise of 400 beds, 2000 staff and 150 hospital
specialists that comprise of doctors and nurses. In an approximate estimation, 90% of the total
number of beds would be situated in singly occupied rooms. The hospital could thus be expected
to handle almost 150,000 exams based on medical imaging, 4150 births, 7000 surgeries and 1900
urgency related pediatric visits on an annual basis. Different other kind of healthcare services
included within the Burnaby Hospital include operating rooms, surgical services, diagnostic
imaging, intensive care units, ambulatory clinics and various forms of acute care units in order to
prevent the spread of various form of infections. The hospital would also collaborate with
leading healthcare service providers in the international market. They would thus provide the
layout of the design for the rooms, perform advanced diagnostics, predictive analytics, alarm
management system and other services based on medical technology. Thus the different form of
managed services that would be described within the contract are procurement of medical
services, installation of those services, integration of medical systems, maintenance and in-time
updates for the medical systems.
4. Purchasing of new furniture and office equipment – With the construction of the
new hospital, the hospital management team would have to strongly think about the basic
Document Page
14SCENARIO OF RELOCATING BURNABY HOSPITAL
infrastructure that would support the entire hospital. New furniture would need to be procured
within the hospital for supporting the patients and the people who would come to hospital for
certain visits. The hospital should be equipped with certain highly furnished furniture that would
suit the needs of the patients and would provide comfort to them.
The new hospital should also be supported by new computing equipment based on the
merging needs of medical and healthcare systems. The different kind of healthcare equipment
that are primarily required within the hospital systems are exam tables, exam lights,
electrosurgical units, laboratory microscopes, surgical headlights, ECG machines and many
others. Such kind of equipment would incur a high cost for the hospital management team and
thus they need to heavily invest for procuring such kind of items. Other kind of equipment for
treatment of patients and which are highly in need for doctors should also be procured before
setting up the entire hospital and opening the hospital before the patients.
5. Acquisition of construction site and choosing of the contractors – In order to
construct the hospital, a proper construction site need to be chosen by the hospital management
team. A certain hectare of land needs to be procured. However, during performing this phase,
different groups of people and other organization could raise disputes against the building of the
hospital. Thus, the hospital management team should take proper support from the Government
of Canada and the Ministry of Health for proper proceeding over the construction phase of the
new hospital. An official approval should be seek from the government officials. The
Government of Canada should fund the entire project for the entire development phase,
procuring of furniture, performing the sanitary works, servicing of materials and procuring
advanced medical equipment within the hospital.
Document Page
15SCENARIO OF RELOCATING BURNABY HOSPITAL
The Government should set a tender before the construction association. A certain budget
would be fixed and bidders would bid for the amount. The government would thus choose the
lowest bidder and thus assign the work of construction to the contractor. They would also need to
sign a certain agreement with the contractors in order to start the work over the project. After the
proper signage over each of the documents, the construction work over the hospital would
proceed accordingly. The materials for construction would be put within the site one week prior
to the start of the project.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16SCENARIO OF RELOCATING BURNABY HOSPITAL
6. Work Breakdown Structure (WBS)
Scenario of Construction of
Burnaby Hospital
Start Project Signing of Agreement and
choosing of hospital site
Preparing a team
meeting with the
different higher
officials
Discussing about
land acquisition
matters
Preparing an initial
document based on
court approval
Approval from the
court
Setting of tender
Acquiring proper
bids
Getting the proper
construction
contractor
Hiring of contractors
Preparing of Project Plan
and Hospital Layout Plan
Preparing of Initial
Project Plan
Preparing of
Financial Plan
Approval of Project
Plan and Financial
Plan
Designing the
Hospital Layout Plan
Approval of Hospital
Layout Plan
Preparing a List of
Equipment required
for Construction work
Preparing for a
Public Awareness
Campaign
Determination of
Certain Risks
Foundation Layout and
Bringing of Construction
Materials
Choosing of proper
supplier of raw
materials
Procuring the raw
materials
Laying out of
foundation of the
site
Informing the local
administration
Bringing of
construction
vehicles and
equipment
Closing the
surrounding area
Laying the materials
Final check over the
construction area
Implementation of
Construction Work
Cleaning of
construction area
Boring of Tunnel
Traffic management
Groundwater
monitoring
Designing integrated
systems and
architectural finishes
Performing
geotechnical review
Reviewing over the
final work done
Property acquisition
Installing of Medical
Equipment and final
Project Sign-off
Preparing the list of
items
Procuring the
medical equipment
Fitting the
equipment
Testing of the
equipment
Survey of the
hospital
Performing
geological
assessment
Making of final
payments
Implementation of
security systems
End Project
(Figure 1: The WBS for the Project)
(Source: Created by author)
Document Page
17SCENARIO OF RELOCATING BURNABY HOSPITAL
7. Work Activities (from WBS)
The different work activities that would be performed for the construction project would
be explained as under:
1. Signing of Agreement and choosing of hospital site
1.1 Preparing a team meeting with the different higher officials – In this stage, the
different higher officials responsible for performing team meetings with the government would
accumulate together. They would discuss about the major needs for the constructing of the new
hospital.
1.2 Discussing about land acquisition matters – In this phase, the government officials
would meet with the land owners and discuss the plans for the construction of the new hospital.
They would need to discuss the issues based on the problems that are faced without a new
hospital.
1.3 Preparing an initial document based on court approval – After the land owners
have given a proper approval from their end, the management team and the government should
prepare a certain proposal paper. This paper would detail out the entire set of plans that would be
put forward. This paper would then be forwarded to the court in order to gain proper approval
from the higher officials.
1.4 Approval from the court – After the paper has been received by the court, they
would understand the motive of the hospital committee and based on that they would approve the
plans for the construction of the hospital.
Document Page
18SCENARIO OF RELOCATING BURNABY HOSPITAL
1.5 Setting of tender – After the gain of approval from the court, the management team
would set tender for the project. The bidders would then bid for the amount based on which they
would be able to complete the project.
1.6 Acquiring proper bids – After the tender has been set, the contractors would bid for
the price within which they could finish the project. However, the contract of construction would
only be provided to the lowest bidder from the various choices.
1.7 Getting the proper construction contractor – After the proper bid has been set,
they would be called and thus an agreement would be signed. The construction manager would
be made to understand about the different necessities of the hospital department.
1.8 Hiring of contractors – The contractors and other labours who would work for the
project would be hired in this phase. They would thus be responsible for following the orders of
the manager and perform further works of construction.
2. Preparing of Project Plan and Hospital Layout Plan
2.1 Preparing of Initial Project Plan – The project manager responsible for leading the
entire management of construction project would design some measures based on preparing the
plan for the project. The plan would help the different stakeholders to understand the basic needs
of constructing the hospital and ensure successful achievement of the project needs.
2.2 Preparing of Financial Plan – The investors within the project who would provide
sponsorship for the project would design the financial plan for the project. This plan would be
helpful for listing out each of the necessities that would be required for the project. The financial
plan would be finally approved by the Government and other higher officials.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19SCENARIO OF RELOCATING BURNABY HOSPITAL
2.3 Approval of Project Plan and Financial Plan – After the preparation of the project
and financial plan, they would be produced to the higher officials for gaining proper form of
approval.
2.4 Designing the Hospital Layout Plan – The construction manager would design the
layout plan for the hospital. They would consider each of the sections that need to be included
within the hospital.
2.5 Approval of Hospital Layout Plan – The layout plan would be finally shown to the
hospital management team. They would thus be responsible for approving the layout plan.
2.6 Preparing a List of Equipment required for Construction work – The project
manager would list the entire equipment list that would be required for performing the
construction works.
2.7 Preparing for a Public Awareness Campaign –After each of the works have been
completed, the project manager would define a public awareness campaign for informing the
public about the latest kind of development.
2.8 Determination of Certain Risks – The project manager would also determine the
certain risks that would overcome towards the project. These risks should be mitigated by
developing a proper plan for risk mitigation.
3. Foundation Layout and Bringing of Construction Materials
3.1 Choosing of proper supplier of raw materials – The project manager would need to
choose the proper supplier of raw materials by estimating the budget.
Document Page
20SCENARIO OF RELOCATING BURNABY HOSPITAL
3.2 Procuring the raw materials - After an agreement have been done, the raw materials
would be brought to the site.
3.3 Laying out of foundation of the site – The foundation for the construction work
would be laid based on the performing of construction work.
3.4 Informing the local administration – The local administration would need to be
informed one week prior to the start of the project.
3.5 Bringing of construction vehicles and equipment – The necessary equipment and
construction vehicles would be brought before the start of the construction project.
3.6 Closing the surrounding area – After the local administration has been informed,
the labors would seal the entire area and thus no person or vehicle would be allowed to enter
within the region.
3.7 Laying the materials – The materials that would be required for the construction
project would be laid.
3.8 Final check over the construction area – After each of the materials would be
procured, the construction managers would finally check over each of the items that have been
procured.
4. Implementation of Construction Work
4.1 Cleaning of construction area – The construction area would need to be cleaned
before the initial start of the work.
4.2 Boring of Tunnel – The construction vehicles would bore the tunnel and thus prepare
for the construction work of the hospital.
Document Page
21SCENARIO OF RELOCATING BURNABY HOSPITAL
4.3 Traffic management – Before the construction work would begin, the construction
workers would perform the final traffic management before the beginning of the construction
phase.
4.4 Groundwater monitoring – The groundwater levels need to be checked during the
construction phase of the project.
4.5 Designing integrated systems and architectural finishes – In this phase, the
different phases of the construction would begin. The construction workers would design the
integrated system and perform the architectural finishes within the hospital. Each of the
necessary details would be built and exact finishes would be made within the hospital.
4.6 Performing geotechnical review – After the construction phase has been made, the
geotechnical team would conduct a final review of the entire construction area and the building.
4.7 Reviewing over the final work done – After the completion of the construction and
the interior works of the building, the final review would be done by the project manager and the
hospital management team.
4.8 Property acquisition – The property would be acquired by the hospital department
after the review phase has been made.
5. Installing of Medical Equipment and final Project Sign-off
5.1 Preparing the list of items – The list of the needed medical equipment would need
to be prepared before the final procurement of items.
5.2 Procuring the medical equipment – After the list has been prepared, the medical
equipment would be procured.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
22SCENARIO OF RELOCATING BURNABY HOSPITAL
5.3 Fitting the equipment – The medical equipment would be fitted in proper place after
they have been procured.
5.4 Testing of the equipment – The medical equipment would be tested for a final
approval from the management team.
5.5 Survey of the hospital – The hospital management team would conduct a final
survey from the doctors and nurses about the appropriateness of the equipment after they have
tested them.
5.6 Performing geological assessment – Geological assessment would also be need to
be done for the final approval of the grant of the hospital and access to patient.
5.7 Making of final payments – The hospital management would complete the final
payment to the construction company after the hospital works have been completed.
5.8 Implementation of security systems – The security systems would also be installed
within the hospital that would mark the completion of the project.
Document Page
23SCENARIO OF RELOCATING BURNABY HOSPITAL
8. Project Costs
Task Name Cost
Scenario of Construction of Burnaby Hospital $1,575,800.00
Signing of Agreement and choosing of hospital site $92,800.00
Preparing of Project Plan and Hospital Layout Plan $176,800.00
Foundation Layout and Bringing of Construction Materials $63,200.00
Implementation of Construction Work $995,200.00
Installing of Medical Equipment and final Project Sign-off $247,800.00
Document Page
24SCENARIO OF RELOCATING BURNABY HOSPITAL
Year of Project
year 0 year1 year 2 year 3 year 4 year 5 TOTALS
Net economic benefit $0.00 $1,000,000.00 $1,000,000.00 $1,000,000.00 $1,000,000.00 $1,000,000.00
Discount Rate 8% 1 0.9259 0.8573 0.7938 0.7350 0.6806
PV Of Benefits $0.00 $925,925.93 $857,338.82 $793,832.24 $735,029.85 $680,583.20
NPV of all BENEFITS $0.00 $925,925.93 $1,783,264.75 $2,577,096.99 $3,312,126.84 $3,992,710.04 $12,591,124.54
One Time Costs $269,600.00
Recurring Costs $0.00 $850,000.00 $850,000.00 $850,000.00 $850,000.00 $850,000.00
Discount Rate 8% 1.0000 0.9259 0.8573 0.7938 0.7350 0.6806
PV Of Recurring Costs $0.00 $787,037.04 $728,738.00 $674,757.40 $624,775.37 $578,495.72
NPV Of All Costs $269,600.00 $1,056,637.04 $1,785,375.03 $2,460,132.44 $3,084,907.81 $3,663,403.53 $12,320,055.86
Overall NPV $271,068.68
Overall ROI = (Overall NPV / NPV Of All Costs 0.02
Break-Even Analysis
Yearly NPV Cash Flow $0.00 $138,888.89 $128,600.82 $119,074.84 $110,254.48 $102,087.48
Overall NPV Cash Flow $269,600.00 ($130,711.11) ($2,110.29) $116,964.55 $227,219.03 $329,306.51
Project break-even occurs between years 2 and 3
Use 1st year of positive cash flow to calculate break-even fraction 2.0177 years
(Figure 2: The Payback Period for the Project)
(Source: Created by author)
9. Project Scheduling
The project schedule would be based on the WBS designed for the project. The project
would begin from the 24th June, 2019 and would end by
The critical path for the project have been highlighted in red color as described within the
Gantt chart from the figure given.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
25SCENARIO OF RELOCATING BURNABY HOSPITAL
ID Outline
Number
Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
0 0 Scenario of Construction of
Burnaby Hospital
1360
days
Mon
24-06-19
Fri
06-09-24
$1,575,800.00
1 1 Start Project 0 days Mon 24-06-19Mon 24-06-19 $0.00
2 2 Signing of Agreement and
choosing of hospital site
49 days Mon
24-06-19
Thu
29-08-19
$92,800.00
3 2.1 Preparing a team meeting with
the different higher officials
8 days Mon
24-06-19
Wed
03-07-19
1 Government of
Canada,Healthcare
Department,Hospital
$25,600.00
4 2.2 Discussing about land
acquisition matters
11 days Thu
04-07-19
Thu
18-07-19
3 Government of
Canada,Healthcare
Department,Hospital
$0.00
5 2.3 Preparing an initial document
based on court approval
6 days Fri
19-07-19
Fri
26-07-19
4 Project
Manager
$19,200.00
6 2.4 Approval from the court 0 days Fri 26-07-19Fri 26-07-195 $0.00
7 2.5 Setting of tender 5 days Mon 29-07-19Fri 02-08-196 Project Manager $16,000.00
8 2.6 Acquiring proper bids 10 days Mon 05-08-19Fri 16-08-197 Project Manager $32,000.00
9 2.7 Getting the proper
construction contractor
3 days Mon
19-08-19
Wed
21-08-19
8 $0.00
10 2.8 Hiring of contractors 6 days Thu 22-08-19Thu 29-08-199 $0.00
11 3 Preparing of Project Plan and
Hospital Layout Plan
32 days Fri
30-08-19
Mon
14-10-19
$176,800.00
12 3.1 Preparing of Initial Project
Plan
8 days Fri
30-08-19
Tue
10-09-19
10 Project
Manager
$25,600.00
13 3.2 Preparing of Financial Plan 7 days Fri 30-08-19Mon 09-09-1910 Project Sponsor $16,800.00
14 3.3 Approval of Project Plan and
Financial Plan
0 days Tue
10-09-19
Tue
10-09-19
12,13 Hospital
Management
Team
$0.00
15 3.4 Designing the Hospital Layout
Plan
16 days Fri
30-08-19
Fri
20-09-19
10 Construction
Manager,Project
Manager
$76,800.00
16 3.5 Approval of Hospital Layout
Plan
0 days Fri
20-09-19
Fri
20-09-19
15,14 $0.00
17 3.6 Preparing a List of Equipment
required for Construction
work
4 days Mon
23-09-19
Thu
26-09-19
16 Construction
Manager,Project
Manager
$19,200.00
18 3.7 Preparing for a Public
Awareness Campaign
5 days Fri
27-09-19
Thu
03-10-19
17 Project
Manager
$16,000.00
19 3.8 Determination of Certain Risks7 days Fri 04-10-19Mon 14-10-1918 Project Manager $22,400.00
20 4 Foundation Layout and
Bringing of Construction
Materials
30 days Tue
15-10-19
Mon
25-11-19
$63,200.00
21 4.1 Choosing of proper supplier
of raw materials
6 days Tue
15-10-19
Tue
22-10-19
19 Project
Manager
$19,200.00
22 4.2 Procuring the raw materials 4 days Wed 23-10-19Mon 28-10-1921 Construction Materials[1]$8,000.00
23 4.3 Laying out of foundation of
the site
7 days Tue
29-10-19
Wed
06-11-19
22 Construction
Manager
$11,200.00
24 4.4 Informing the local
administration
2 days Thu
07-11-19
Fri
08-11-19
23 $0.00
25 4.5 Bringing of construction
vehicles and equipment
7 days Mon
11-11-19
Tue
19-11-19
24 Hospital
Equipment[1]
$12,000.00
26 4.6 Closing the surrounding area 3 days Wed 20-11-19Fri 22-11-1925 $0.00
27 4.7 Laying the materials 4 days Wed 20-11-19Mon 25-11-1925 Project Manager $12,800.00
28 4.8 Final check over the
construction area
0 days Mon
25-11-19
Mon
25-11-19
27 $0.00
29 5 Implementation of
Construction Work
1114
days
Tue
26-11-19
Fri
01-03-24
$995,200.00
30 5.1 Cleaning of construction area 17 days Tue 26-11-19Wed 18-12-1926,27 Labours $13,600.00
31 5.2 Boring of Tunnel 39 days Thu 19-12-19Tue 11-02-2030 Labours $31,200.00
32 5.3 Traffic management 15 days Wed 12-02-20Tue 03-03-2031 Labours $12,000.00
33 5.4 Groundwater monitoring 35 days Wed 04-03-20Tue 21-04-2032 Construction Manager,Labours$84,000.00
34 5.5 Designing integrated systems
and architectural finishes
938 days Wed
22-04-20
Fri
24-11-23
33 Labours $750,400.00
35 5.6 Performing geotechnical
review
65 days Mon
27-11-23
Fri
23-02-24
34 Construction
Manager
$104,000.00
36 5.7 Reviewing over the final work
done
0 days Fri
23-02-24
Fri
23-02-24
35 $0.00
37 5.8 Property acquisition 5 days Mon 26-02-24Fri 01-03-2436 $0.00
38 6 Installing of Medical
Equipment and final Project
Sign-off
135 days Mon
04-03-24
Fri
06-09-24
$247,800.00
39 6.1 Preparing the list of items 8 days Mon 04-03-24Wed 13-03-2437 Project Manager $25,600.00
40 6.2 Procuring the medical
equipment
19 days Thu
14-03-24
Tue
09-04-24
39 Hospital
Equipment[1]
$12,000.00
41 6.3 Fitting the equipment 30 days Wed 10-04-24Tue 21-05-2440 Labours $24,000.00
42 6.4 Testing of the equipment 15 days Wed 22-05-24Tue 11-06-2441 Labours $12,000.00
43 6.5 Survey of the hospital 19 days Wed 12-06-24Mon 08-07-2442 Project Manager $60,800.00
44 6.6 Performing geological
assessment
14 days Tue
09-07-24
Fri
26-07-24
43 Construction
Manager
$22,400.00
45 6.7 Making of final payments 5 days Mon 29-07-24Fri 02-08-2444 Project Manager $16,000.00
46 6.8 Implementation of security
systems
25 days Mon
05-08-24
Fri
06-09-24
45 Security
Specialists,Security
Systems[1]
$75,000.00
47 7 End Project 0 days Fri 06-09-24Fri 06-09-2446 $0.00
24-06
Government of Canada,Healthcare Department,Hospital Management Team,Project Manager
Government of Canada,Healthcare Department,Hospital Management Team
Project Manager
26-07
Project Manager
Project Manager
Project Manager
Project Sponsor
10-09
Construction Manager,Project Manager
20-09
Construction Manager,Project Manager
Project Manager
Project Manager
Project Manager
Construction Materials[1]
Construction Manager
Hospital Equipment[1]
Project Manager
25-11
Labours
Labours
Labours
Construction Manager,Labours
Labours
Construction Manager
23-02
Project Manager
Hospital Equipment[1]
Labours
Labours
Project Manager
Construction Manager
Project Manager
Security Specialists,Security Syst
06-09
02-06 21-07 08-09 27-10 15-12 02-02 22-03 10-05 28-06 16-08 04-10 22-11 10-01 28-02 18-04 06-06 25-07 12-09 31-10 19-12 06-02 27-03 15-05 03-07 21-08 09-10 27-11 15-01 05-03 23-04 11-06 30-07 17-09 05-11 24-12 11-02 31-03 19-05 07-07 25-08 13-10 01-12
11 April 21 July 01 November 11 February 21 May 01 September 11 December 21 March 01 July 11 October 21 January 01 May 11 August 21 November 01 March 11 June 21 September 01 January 11 April 21 July 01 November
(Figure 3: The Schedule for the Project)
(Source: Created by author)
Document Page
26SCENARIO OF RELOCATING BURNABY HOSPITAL
10. Project Gates
The project gates should be set in order to check the status and progress of the project.
This review would be done with the upper management team that would look into each of the
details of the project.
The first project gate would be defined during the initial defining of project plan and
financial plan for the project. In this phase, the plan of the project would be prepared for review
by the hospital management team.
The second project gate would be made during the middle phase of constructing the
project. The project management team would ensure that the construction has been progressing
as per the design layout of the project.
The third project gate would be set after the medical equipment have been fixed in proper
phase. During this phase, the management team would check that each of the medical equipment
have been put in proper place and as per the necessities of the hospital.
11. Risks
11.1 Risk identification
It is quite a known fact that the construction projects are most likely to be subjected to
uncertainties since most of the times it has been found that the risks under which the project is
being propagated has several complexities. It has also been found that the objectives of the
project, which in this case is the construction of the Burnaby General Hospital in a new location
near the corner of the Willingdon and the Canada Way. The identification of risk is extremely
important so that it becomes easy to identify all the implications that would cause problems for
the project team to reach its target. Identifying the sources of all these risks are important so that
Document Page
27SCENARIO OF RELOCATING BURNABY HOSPITAL
proper mitigating factors can be applied to the project so that the essential mitigating factors can
help reaching the project goal without any issues arising.
11.2 Prioritization
The risk prioritization factor enables the identification of the risks according to their
severity on which they might affect the propagation of the project. The ways by which the
prioritization is done makes it easier to differentiate between clustered risks at the same level
based on their severity. The prioritization also helps to respond to the risks according to the
available resources. It would be much helpful if the risk is prioritized for the project for utilizing
the least amount of resources being applied for the mitigation of the risks.
11.3 Cost Contingency
Cost Contingency is a factor that is used for this particular project for setting aside a
specific sum of money for covering any specific incidents that might occur unexpectedly. The
amount of money that the project has reserved for the cost pf contingency can never be allocated
to any specific work area in the project and this is why it has the potential to act as an insurance
for any kind of unforeseen cost.
11.4 Risk Matrix
Identified Risk Potential Hazard Potential Consequences Severity
1. Issues of
accessing the
hospital site
during
construction
The hospital has to
clear out the entire
hospital and also has to
pause the services to
the patients during the
The consequences of this risk can be
severe since the services of the
hospital to the existing patients can
become hampered. The patients
receiving healthcare treatments
Medium
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
28SCENARIO OF RELOCATING BURNABY HOSPITAL
time of the
construction.
would have to be released due to the
construction work or the executive
body would have to look out for any
other way to ensure proper
treatment to the patients.
2. Transportation
of heavy
machinery to
specific floors
There might be
occurrences where the
stairways can be
blocked because of the
relocation of the heavy
machineries to the
specific floors.
The potential consequence that it
can cause is by halting the ongoing
operations that might utilize the
stairways for that point of time
during which the transportation of
the heavy machinery is going on
through the stairways.
Low
3. Health hazards
to the patients
during the
construction
There might be
occurrences where the
construction project
may lead to the initial
hospital being negligent
to the patients or the
previously available
services may be
hampered due to the
ongoing construction
The patients might face adverse
situations regarding their health
where the situations might hamper
the way that the hospital
management and employees be
affected by the inability of serving
the patients.
High
Document Page
29SCENARIO OF RELOCATING BURNABY HOSPITAL
project.
4. Dust and
Infection Control
The construction
project of
reconstructing the
Burnaby Hospital may
lead to the residue of
dust and infection that
might affect the
patients even after the
completion of the
construction project.
Patients can be affected with the
residue dust and infectious particles
left after the construction since there
has not been a proper cleaning of
the construction area being
conducted. This can result severe
health issues to the existing patients
of Burnaby Hospital.
High
12. Project Team (your group is the team)
12.1 Importance of Project Team
The primary responsibility of the Project Manager lies in the detection of the proper
project team that would be resulting as effective to the construction project as a whole. This is
important as it would determine the synergy of the human beings involved within the project and
amplify the skills of every respective individual team member for the project and this would help
in the reaching of the set goal for the project in the most effective way.
Document Page
30SCENARIO OF RELOCATING BURNABY HOSPITAL
12.2 Roles and Responsibilities of the Team Members of the Project
Team Members Roles and Responsibilities
The government of Canada The government of Canada would be in
responsibility of going through the entire
project and understanding the feasibility and
effectivity of the project to be thoroughly
scrutinized by the Government of Health in
Canada by passing onto next.
Government of Health in Canada The Government of Health in Canada is in
responsibility of scrutinizing the details of
the project to understand the overall project
advantages and how effectively it would be
serving the patients in future after the
project completion.
Project Sponsors The Project Sponsors are at the
responsibility of scrutinizing the
requirements of the entire project and look
into the developmental aspects. They would
then be presenting the project for the
relocation and construction of the Burnaby
Hospital in order to provide with financial
help and progress through the project based
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
31SCENARIO OF RELOCATING BURNABY HOSPITAL
on the available resources.
Project Owners The project owners are mostly to be treated
as the head of the business unit who would
be bearing the responsibility of the project
including all the successful implementation
of the project and even the issues occurring.
Project Director The project director would be responsible
for the management of the entire project at a
more strategic level where the project needs
to be handled at a much more perceived
perception.
Project Manager The project Manager would be at the overall
charge of the entire project throughout the
planning and the execution of the relocation
and construction of the project for Burnaby
Hospital.
Contractors The general project Contractors are at the
responsibility of the daily oversight for the
site of the construction for the Burnaby
Hospital and at the same time, would be
responsible for the management of the
Document Page
32SCENARIO OF RELOCATING BURNABY HOSPITAL
people hired as the traders and the vendors.
Project Management Team These would be the people who would have
all the responsibilities of conducting the
progression of the project with individual
roles to play and handle the project as per
the specific skills every individual team
member is capable of.
13. Project Communications – Matrix showing internal and external, types and frequency
The success of any project primarily depends upon the communication and the effective
ways by which the communication can be conducted. The effectiveness of the communication
decides whether the maximization of the success or the minimization of the risks can be made
possible. This is the ways by which the collaboration program for the Burnaby Hospital and its
relocation can be formulated in the most effective way possible including the minimization of all
the above identified risks.
13.1 Project Communication Matrix
Communicati
on Activity
Purpose of
the
Communicati
on
Medium of
Communicati
on
Frequenc
y
Communicati
on Audience
Communicati
on Owner
Project
Kickoff
Introduction
of the entire
Individual or
group meeting
Once The entire
Project Team,
The Project
Director, the
Document Page
33SCENARIO OF RELOCATING BURNABY HOSPITAL
Meeting project and its
purpose to the
project team,
reviewing the
objectives of
the project
and
identifying the
unified goal.
over face to
face followed
by a detailed
“minutes of
meeting”
being both
emailed and
sent to the
project team
as a hard
copy.
the sponsors
and the
internal
stakeholders
of the project
Project
Manager and
the Project
Owner
Team
Meetings
For the review
of the project
status every
passing week
Through face
to face
meeting or
even through
conducted
calls via
conferences
Every
week
Project Team Project
Manager and
Project
Director
Technical
Meetings
Discussion
and review of
all the
technicalities
of the
Individual or
group meeting
via face to
face
communicatio
As per the
requireme
nts
The technical
and
construction
planning and
design team
Project
Manager and
Project
Director
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
34SCENARIO OF RELOCATING BURNABY HOSPITAL
construction
including the
problems
occurred and
finding their
solutions
n for the project
Project Status
Meeting
For updating
the leadership
as per the
developments
made on the
project at
every phase of
the project.
Individual or
group meeting
via face to
face
communicatio
n or even
through
conference
calls
Every
Month
Project
Manager and
the Project
Stakeholders
Project
Manager and
Project
Director
Status reports
for the project
For having the
detailed report
in the status of
the project at
every level of
the project
including all
the
Regular
emails at the
interval
Every
Month
Project
Manager and
the Project
Stakeholders
Project
Manager and
Project
Director
Document Page
35SCENARIO OF RELOCATING BURNABY HOSPITAL
progressions
made in the
project
regarding the
costs incurred
so far, the
issues and the
mitigation
procedure
taken to
mitigate them
and the ways
by which the
severity has
affected the
project.
14. Key Performance Measurements (KPM’S) specific quantifiable metrics to track success
of the project
1. Safety Checklists
2. Performance evaluation of Project Team
3. Duration of the Project
Document Page
36SCENARIO OF RELOCATING BURNABY HOSPITAL
4. Risks mitigation success rate
5. Cost management
6. Usage of the cost contingency
15. Project Procurement
There could be different issues in relation to the procurement of items, persons and other
resources required for the project. These include:
Identification of external resources – The external resources such as the medical
equipment and other raw materials that need to be procured during the construction phase should
be properly identified. The project manager would need to keep a complete check over the
resources that are procured within the department.
Selection of seller details of tendering – The tender would only be marked as successful
after evaluating them against a certain set of metrics. The seller would need to respond to certain
metrics based on an Evaluation Criteria metrics. Hence based on meeting with the requirement of
the criteria, the tender for the project would be set to them.
17. Quality Control – inspection (acceptance) criteria for each work activity
Work Activity Inspection/Acceptance Criteria
Preparing a team meeting with the different
higher officials
Every project stakeholder understands the
project outcomes and the ways by which the
project needs to be progressed
Discussing about land acquisition matters The strategy for making the land owners
agree to the terms are set for the project to
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
37SCENARIO OF RELOCATING BURNABY HOSPITAL
begin
Preparing an initial document based on
court approval
The initial documentation process is set
accordingly without any flaw to be
identified by the court
Approval from the court The court approves the Burnaby Hospital to
be constructed at the new site without any
conditions
Setting of tenders The initial budget is set and the tenders are
handed to the contractors to find out which
contractor quoted the least
Acquiring proper bids Contractors quote accordingly and the bids
are somewhat close to the initial estimated
budget.
Getting the proper construction contractor The contractor that quoted the least and
closest to the initial estimated budget is
selected.
Hiring of contractors Contractor is hired as per the proper
legalized documentation plans
Preparing of Initial Project Plan Initial project plan considers all the project
constrains and project aspects
Preparing of Financial Plan Budget plan is set up accordingly as per the
Document Page
38SCENARIO OF RELOCATING BURNABY HOSPITAL
available resources
Approval of Project Plan and Financial Plan The sponsors agree to the project and the
budget plan set for the initial beginning of
the project.
Designing the Hospital Layout Plan The budget and the project plan are kept in
mind to design the initial layout of the
construction considering the site selected
Approval of Hospital Layout Plan The project owner and the sponsors agree to
the initiated project plan
Preparing a List of Equipment required for
Construction work
The project layout is considered for the
listing of the required equipment as per the
consultation with the contractors
Preparing for a Public Awareness Campaign The external stakeholders understand the
requirement of the project and the goal that
is being targeted with the construction
Determination of Certain Risks All the possible risks are identified
Choosing of proper supplier of raw
materials
Contractors make out the effective suppliers
for the raw materials.
Procuring the raw materials The raw materials according to the project
requirements are acquired
Laying out of foundation of the site The initial project layout is set accordingly
Document Page
39SCENARIO OF RELOCATING BURNABY HOSPITAL
Informing the local administration The local administration is informed
accordingly
Bringing of construction vehicles and
equipment
The equipment and vehicles are set
accordingly
Closing the surrounding area The surrounding area is closed for no
trespassers to enter
Laying the materials Materials are laid out according to the
requirements
Final check over the construction area The construction area is checked out
accordingly
Cleaning of construction area The area is cleaned to perfection for the
construction to begin
Boring of Tunnel The tunnels are effectively bored for the
transportation to follow through flawlessly
Traffic management The adjacent area has no traffic congestions
Groundwater monitoring The water balance is effectively managed
Designing integrated systems and
architectural finishes
The integrated systems and architectural
finishes are designed according to the
project requirements
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
40SCENARIO OF RELOCATING BURNABY HOSPITAL
Performing geotechnical review Geotechnical review is conducted flawlessly
Reviewing over the final work done The review of the final work done has been
conducted as per the assurance of the
project stakeholders
Property acquisition The property for the construction project is
conducted flawlessly.
Preparing the list of items The list of items identifies all the relevant
project requirements
Procuring the medical equipment The medical equipment are according to the
relevant project plan made to develop the
state of the art facilities available at the
Burnaby Hospital
Fitting the equipment The equipment is accordingly fitted
Testing of the equipment The equipment is accordingly tested
Survey of the hospital The hospital is surveyed accordingly
Performing geological assessment Geological assessment is conducted feasibly
Making of final payments All the payment to every project team
member and the suppliers are done
accordingly
Implementation of security systems The security systems are handled properly
Document Page
41SCENARIO OF RELOCATING BURNABY HOSPITAL
with all the risks related to patient
information and health records being
handled accordingly.
18. Any other issues pertinent to the project
18.1 Health and Safety Considerations
The Burnaby Hospital and its relocation can cause a lot of problems regarding the construction
since it is a healthcare center. It may occur that the area or the site chosen for the construction is
not feasible for the patients that are to be admitted to the hospital. It may also occur that the
people in responsibility of the construction might be not effective with cleaning the construction
site, which again can cause health hazards to the overall health of the patients admitted to the
hospital.
Document Page
42SCENARIO OF RELOCATING BURNABY HOSPITAL
Criteria metrics for the Construction Company
Criteria of Evaluation Weightage Score
Previous experiences 30%
Qualification 20%
Safety requirements 20%
Environmental factor consideration 10%
Quality 10%
Price 10%
Criteria metrics for the Hospital Equipment
Criteria of Evaluation Weightage Score
Previous experiences 30%
Qualification 20%
Safety requirements 20%
Environmental factor consideration 10%
Quality 10%
Price 10%
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
43SCENARIO OF RELOCATING BURNABY HOSPITAL
Criteria metrics for the seller performance
Criteria of Evaluation Weightage Score
Previous experiences 30%
Qualification 20%
Safety requirements 20%
Environmental factor consideration 10%
Quality 10%
Price 10%
Document Page
44SCENARIO OF RELOCATING BURNABY HOSPITAL
Appendix A: Project Charter
Project Charter
Project Vision
Burnaby Hospital provides a vast amount of facilities that are in relation to the healthcare
department. The hospital provides different forms of healthcare services that includes surgical,
tertiary, obstetric, psychiatry and medical facilities to different problems in relation to patient
care. The hospital also provides emergency care services and it has been further reported that the
hospital organization serves nearly 80,000 patients on an annual basis. The Burnaby Hospital is
considered as a large community hospital and has been serving customers for a couple of years.
The primary focus of the hospital is to develop different innovative techniques based on the
growing needs of patients. Innovative form of medical techniques would be highly helpful for
driving the owners of the department and thus also enhancing the patient care.
In the recent years, a study conducted by the government had reached to a conclusion that
it would be highly expensive to renovate the Burnaby Hospital. In order to ensure that the entire
project would be cost effective, a new hospital should be built at the corner of Canada Way and
Willingdon. Thus the primary vision of the company is to bring the most effective management
of project management services during the entire construction project. Each of the factors of cost
should be calculated as per the current needs of the hospital. This would be highly needed for
delivering the best forms of healthcare facilities to the patients and thus developing better
relationship with the customers.
Document Page
45SCENARIO OF RELOCATING BURNABY HOSPITAL
Project Objective
The objective based on the project of building a new hospital are:
Determining of the hospital site, surveying and preparing for the construction work.
Constructing the best form of infrastructure based on providing the best form of
healthcare facilities.
Purchasing and installation of high quality medical equipment
Procuring high quality hospital furnishings, office equipment and other non-medical
facilities.
Designing the hospital infrastructure within the proper estimated budget and within
appropriate deadlines.
Problem or Issue
In the present situation, the Burnaby Hospital is facing some serious consequences based
on providing the best form of facilities to the patients. In the present conditions, there is a high
need to develop skills in order to serve the patients in the best possible manner. There are a lot of
technologies that are rapidly growing in the present market. The Burnaby Hospital is currently
facing some critical problems in dealing with the queries of the patients and dealing with critical
medical ailments. Hence, in order to develop better form of healthcare facilities, it would be
highly necessary to implement the best form of medical facilities and equipment that would help
in serving the patients in the best possible manner.
Purpose of the Project
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
46SCENARIO OF RELOCATING BURNABY HOSPITAL
The project is primarily been designed to implement the best form of facilities for serving
the patients with the high quality of medical equipment. Better form of medical equipment is
highly needed to deal with the ever increasing medical ailments and thus increase the quality of
treatment that is provided within the hospital. The old hospital is not efficient for serving the
patients in the best possible manner. Hence, in order to deal with the present situations, the
government has decided to build a new hospital that would be equipped with the best possible
medical equipment. The entire purpose of the project is to serve the patients in the best possible
manner and thus increase the reputation of the company in the healthcare industry.
Project Risks
The different risks in relation to the project include the following:
1. Inflation of costs – There might be certain kind of problems based on inflation of cost
factor.
2. Hazard within Worksite – The work within the worksite could consist of several
form of hazards such as construction period, pollution factors and many others. Such kind of
worksite hazards would lead to problems for the workers and might lead to further disruption of
work procedures.
3. Natural Disasters – Natural disasters such as rain, storm and many others could lead
to disruption in the work over the project. These kind of disasters would lead to disruption of
work and lead to delay in the work over the project.
chevron_up_icon
1 out of 47
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]