This document presents a comprehensive project management solution for the Hucks case study, focusing on the development of additional production capacity. It includes a detailed project schedule summary, outlining initiation, planning, execution, and closure phases. The solution provides a Work Breakdown Structure (WBS), resource loading with cost and duration estimates, a network diagram, and a Gantt chart for visual representation. Furthermore, it defines roles and responsibilities, a resource assignment matrix (RAM and RACI), deliverable milestones, and a schedule for monitoring and control methods. The document also addresses mechanisms for measuring progress, change management processes, contingency planning, and decision-making processes. Additional sections cover planning tasks, critical path analysis, tools and techniques for time management, and an evaluation of project time management effectiveness for future projects.

Running head: PROJECT MANAGEMENT
Project Management: Hucks Case Study
Name of the Student:
Name of the University:
Project Management: Hucks Case Study
Name of the Student:
Name of the University:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
Part A: Project Schedule..................................................................................................................3
1. Project schedule summary/project time in the organization....................................................3
2. Detailed and complete WBS....................................................................................................4
3. Resource loading/Estimating task cost and duration...............................................................5
3.1 Network diagram...............................................................................................................7
3.2 Gantt chart.........................................................................................................................8
4. Roles and responsibilities........................................................................................................9
5. Resource assignment matrix (RAM and RACI)....................................................................12
5.1 Required resources over specific timeframe....................................................................13
6. Deliverable milestones...........................................................................................................14
7. Schedule for monitoring and control methods.......................................................................14
8. Mechanisms to be used to measure, record and report progress against the project schedule
...................................................................................................................................................15
9. Process to manage changes and issues..................................................................................15
10. Contingency in schedule......................................................................................................16
11. Decision making process.....................................................................................................16
Part B: Additional questions..........................................................................................................17
1. Planning tasks performed as part of the project time management.......................................17
2. Critical path for the project....................................................................................................18
Table of Contents
Part A: Project Schedule..................................................................................................................3
1. Project schedule summary/project time in the organization....................................................3
2. Detailed and complete WBS....................................................................................................4
3. Resource loading/Estimating task cost and duration...............................................................5
3.1 Network diagram...............................................................................................................7
3.2 Gantt chart.........................................................................................................................8
4. Roles and responsibilities........................................................................................................9
5. Resource assignment matrix (RAM and RACI)....................................................................12
5.1 Required resources over specific timeframe....................................................................13
6. Deliverable milestones...........................................................................................................14
7. Schedule for monitoring and control methods.......................................................................14
8. Mechanisms to be used to measure, record and report progress against the project schedule
...................................................................................................................................................15
9. Process to manage changes and issues..................................................................................15
10. Contingency in schedule......................................................................................................16
11. Decision making process.....................................................................................................16
Part B: Additional questions..........................................................................................................17
1. Planning tasks performed as part of the project time management.......................................17
2. Critical path for the project....................................................................................................18

2PROJECT MANAGEMENT
3. Tools and techniques used to track and manage the time in project.....................................20
4. Evaluate effectiveness of project time management to future projects.................................20
Learning journal.............................................................................................................................22
References......................................................................................................................................24
Bibliography..................................................................................................................................27
3. Tools and techniques used to track and manage the time in project.....................................20
4. Evaluate effectiveness of project time management to future projects.................................20
Learning journal.............................................................................................................................22
References......................................................................................................................................24
Bibliography..................................................................................................................................27
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
Part A: Project Schedule
1. Project schedule summary/project time in the organization
The project plan is based on development of additional production capacity in Hucks.
Due to lack of space in the organization, the business organizations want to expand their
production capacity by expansion of their business. In order to resolve issues related to the
organization, Hucks is required to develop new production capacity in the organization.
Following is the summary for the project schedule:
Task Name Duration Start Finish
Initiation phase 76 days Mon 12/3/18 Mon 3/18/19
Planning phase 104 days Tue 3/19/19 Fri 8/9/19
Execution phase 340 days Thu 7/4/19 Wed 10/21/20
Closure phase 47 days Thu 10/22/20 Fri 12/25/20
From the above project schedule summary table, it is concluded that the start date of the
project plan is 12/3/18 and end date is 12/25/20. Therefore, the total duration for the project plan
is 540 days.
Part A: Project Schedule
1. Project schedule summary/project time in the organization
The project plan is based on development of additional production capacity in Hucks.
Due to lack of space in the organization, the business organizations want to expand their
production capacity by expansion of their business. In order to resolve issues related to the
organization, Hucks is required to develop new production capacity in the organization.
Following is the summary for the project schedule:
Task Name Duration Start Finish
Initiation phase 76 days Mon 12/3/18 Mon 3/18/19
Planning phase 104 days Tue 3/19/19 Fri 8/9/19
Execution phase 340 days Thu 7/4/19 Wed 10/21/20
Closure phase 47 days Thu 10/22/20 Fri 12/25/20
From the above project schedule summary table, it is concluded that the start date of the
project plan is 12/3/18 and end date is 12/25/20. Therefore, the total duration for the project plan
is 540 days.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
2. Detailed and complete WBS
Figure 1: Work Breakdown Structure
(Source: Created by author)
2. Detailed and complete WBS
Figure 1: Work Breakdown Structure
(Source: Created by author)

5PROJECT MANAGEMENT
3. Resource loading/Estimating task cost and duration
Resource Name Work Start Finish % Work
Complete Cost
Project Manager 640hrs Mon 12/3/18 Fri 12/25/20 23% $ 76,800.00
Development of
business case 144 hrs Mon 12/3/18 Wed 12/26/18 100% $ 17,280.00
Development of the
project plan 120 hrs Tue 3/19/19 Mon 4/8/19 0% $ 14,400.00
Stakeholder sign off 184 hrs Thu 10/22/20 Mon 11/23/20 0% $ 22,080.00
Documentation 160 hrs Tue 11/24/20 Mon 12/21/20 0% $ 19,200.00
Project closure 32 hrs Tue 12/22/20 Fri 12/25/20 0% $ 3,840.00
Project planner 232 hrs Mon 1/21/19 Fri 12/25/20 0% $ 23,200.00
Establishing project
charter 200 hrs Mon 1/21/19 Fri 2/22/19 0% $ 20,000.00
Project closure 32 hrs Tue 12/22/20 Fri 12/25/20 0% $ 3,200.00
Financial manager 296 hrs Thu 12/27/18 Mon 6/3/19 3% $ 29,600.00
Undertaking feasibility
study 136 hrs Thu 12/27/18 Fri 1/18/19 6% $ 13,600.00
Development of
financial plan 160 hrs Tue 5/7/19 Mon 6/3/19 0% $ 16,000.00
Human resource
manager 288 hrs Mon 2/25/19 Mon 5/6/19 0% $ 28,800.00
Appointing team
members 128 hrs Mon 2/25/19 Mon 3/18/19 0% $ 12,800.00
Development of
resource plan 160 hrs Tue 4/9/19 Mon 5/6/19 0% $ 16,000.00
Quality manager 176 hrs Tue 6/4/19 Wed 7/3/19 0% $ 176,000.00
3. Resource loading/Estimating task cost and duration
Resource Name Work Start Finish % Work
Complete Cost
Project Manager 640hrs Mon 12/3/18 Fri 12/25/20 23% $ 76,800.00
Development of
business case 144 hrs Mon 12/3/18 Wed 12/26/18 100% $ 17,280.00
Development of the
project plan 120 hrs Tue 3/19/19 Mon 4/8/19 0% $ 14,400.00
Stakeholder sign off 184 hrs Thu 10/22/20 Mon 11/23/20 0% $ 22,080.00
Documentation 160 hrs Tue 11/24/20 Mon 12/21/20 0% $ 19,200.00
Project closure 32 hrs Tue 12/22/20 Fri 12/25/20 0% $ 3,840.00
Project planner 232 hrs Mon 1/21/19 Fri 12/25/20 0% $ 23,200.00
Establishing project
charter 200 hrs Mon 1/21/19 Fri 2/22/19 0% $ 20,000.00
Project closure 32 hrs Tue 12/22/20 Fri 12/25/20 0% $ 3,200.00
Financial manager 296 hrs Thu 12/27/18 Mon 6/3/19 3% $ 29,600.00
Undertaking feasibility
study 136 hrs Thu 12/27/18 Fri 1/18/19 6% $ 13,600.00
Development of
financial plan 160 hrs Tue 5/7/19 Mon 6/3/19 0% $ 16,000.00
Human resource
manager 288 hrs Mon 2/25/19 Mon 5/6/19 0% $ 28,800.00
Appointing team
members 128 hrs Mon 2/25/19 Mon 3/18/19 0% $ 12,800.00
Development of
resource plan 160 hrs Tue 4/9/19 Mon 5/6/19 0% $ 16,000.00
Quality manager 176 hrs Tue 6/4/19 Wed 7/3/19 0% $ 176,000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
Development of quality
plan 176 hrs Tue 6/4/19 Wed 7/3/19 0% $ 176,000.00
Risk analyst 216 hrs Thu 7/4/19 Fri 8/9/19 0% $ 21,600.00
Development of risk
management plan 216 hrs Thu 7/4/19 Fri 8/9/19 0% $ 21,600.00
Supervisor 448 hrs Wed 3/18/20 Wed 6/3/20 0% $ 49,280.00
Finishing shop
completion 448 hrs Wed 3/18/20 Wed 6/3/20 0% $ 49,280.00
Contractor 1,032 hrs Thu 7/4/19 Tue 3/17/20 0% $ 113,520.00
Adding existing floor 520 hrs Thu 7/4/19 Wed 10/2/19 0% $ 57,200.00
Dust-free paint 512 hrs Thu 12/19/19 Tue 3/17/20 0% $ 56,320.00
Sub-contractor 0 hrs NA NA 0% $ 0.00
Construction manager 1,480 hrs Thu 7/4/19 Wed 6/3/20 0% $ 162,800.00
Adding existing floor 520 hrs Thu 7/4/19 Wed 10/2/19 0% $ 57,200.00
Dust-free paint 512 hrs Thu 12/19/19 Tue 3/17/20 0% $ 56,320.00
Finishing shop
completion 448 hrs Wed 3/18/20 Wed 6/3/20 0% $ 49,280.00
IT manger 800 hrs Thu 6/4/20 Wed 10/21/20 0% $ 88,000.00
AutoCAD woodworking
production train 400 hrs Thu 6/4/20 Wed 8/12/20 0% $ 44,000.00
Installation of
hardware 400 hrs Thu 8/13/20 Wed 10/21/20 0% $ 44,000.00
Workers 872 hrs Thu 10/3/19 Tue 8/18/20 0% $ 95,920.00
Installation of air-
conditioning 440 hrs Thu 10/3/19 Wed 12/18/19 0% $ 48,400.00
Installation of software 432 hrs Thu 6/4/20 Tue 8/18/20 0% $ 47,520.00
Development of quality
plan 176 hrs Tue 6/4/19 Wed 7/3/19 0% $ 176,000.00
Risk analyst 216 hrs Thu 7/4/19 Fri 8/9/19 0% $ 21,600.00
Development of risk
management plan 216 hrs Thu 7/4/19 Fri 8/9/19 0% $ 21,600.00
Supervisor 448 hrs Wed 3/18/20 Wed 6/3/20 0% $ 49,280.00
Finishing shop
completion 448 hrs Wed 3/18/20 Wed 6/3/20 0% $ 49,280.00
Contractor 1,032 hrs Thu 7/4/19 Tue 3/17/20 0% $ 113,520.00
Adding existing floor 520 hrs Thu 7/4/19 Wed 10/2/19 0% $ 57,200.00
Dust-free paint 512 hrs Thu 12/19/19 Tue 3/17/20 0% $ 56,320.00
Sub-contractor 0 hrs NA NA 0% $ 0.00
Construction manager 1,480 hrs Thu 7/4/19 Wed 6/3/20 0% $ 162,800.00
Adding existing floor 520 hrs Thu 7/4/19 Wed 10/2/19 0% $ 57,200.00
Dust-free paint 512 hrs Thu 12/19/19 Tue 3/17/20 0% $ 56,320.00
Finishing shop
completion 448 hrs Wed 3/18/20 Wed 6/3/20 0% $ 49,280.00
IT manger 800 hrs Thu 6/4/20 Wed 10/21/20 0% $ 88,000.00
AutoCAD woodworking
production train 400 hrs Thu 6/4/20 Wed 8/12/20 0% $ 44,000.00
Installation of
hardware 400 hrs Thu 8/13/20 Wed 10/21/20 0% $ 44,000.00
Workers 872 hrs Thu 10/3/19 Tue 8/18/20 0% $ 95,920.00
Installation of air-
conditioning 440 hrs Thu 10/3/19 Wed 12/18/19 0% $ 48,400.00
Installation of software 432 hrs Thu 6/4/20 Tue 8/18/20 0% $ 47,520.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
3.1 Network diagram
Figure 2: Network diagram
(Source: Created using Ms Project)
3.1 Network diagram
Figure 2: Network diagram
(Source: Created using Ms Project)

8PROJECT MANAGEMENT
3.2 Gantt chart
Figure 3: Gantt chart
(Source: Created using Ms Project)
3.2 Gantt chart
Figure 3: Gantt chart
(Source: Created using Ms Project)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
4. Roles and responsibilities
Role of the human
resources
Responsibilities
Huck’s Project
Manager
Manage the progress of the project deliverables
Development of contingency plan to manage the project risks
Using scheduling software to spot bottlenecks in the plan
Project Planner Recommend of modifications to achieve the project milestones
Prepare short as well as long term allocation of resources
Identify changes in the scope of project plan
Update the project schedule and develop schedule forecast
Financial Manager Prepare the financial statements and reports and review the financial
reports to reduce the cost
Develop plan to meet long term financial goals
Human Resource
Manager
Recruit and select the employees for the project work
Maintain the human resources by counseling
Planning and monitoring the job results
Quality Manager Review the quality of raw materials used for the production work
Improve organizational profitability
Coordinating the quality assurance program
Risk Analyst Assess the project risks in the organization
Review likelihood of project events and its impact on organization
4. Roles and responsibilities
Role of the human
resources
Responsibilities
Huck’s Project
Manager
Manage the progress of the project deliverables
Development of contingency plan to manage the project risks
Using scheduling software to spot bottlenecks in the plan
Project Planner Recommend of modifications to achieve the project milestones
Prepare short as well as long term allocation of resources
Identify changes in the scope of project plan
Update the project schedule and develop schedule forecast
Financial Manager Prepare the financial statements and reports and review the financial
reports to reduce the cost
Develop plan to meet long term financial goals
Human Resource
Manager
Recruit and select the employees for the project work
Maintain the human resources by counseling
Planning and monitoring the job results
Quality Manager Review the quality of raw materials used for the production work
Improve organizational profitability
Coordinating the quality assurance program
Risk Analyst Assess the project risks in the organization
Review likelihood of project events and its impact on organization
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
Perform a risk management plan
IT Manager Supervise and develop the IT system with staffing of IT team
Review performance of information networks and also software
applications
Perform regular meetings with the stakeholders for updating IT
actions
Steel fabricators and
installers
Fabrication and utilization of technical drawings and blueprints
Review of specifications for construction of metal products
Install the equipments in the organizational premises
Construction
Manager
Determination of labor needs and dispatch the workers to the
construction sites
Inspect as well as review the project work for monitoring compliance
with safety codes
Schedule the plan and budget necessary to meet the project deadlines
Mechanical
contractors
Responsible to review ongoing maintenance of the system they are
installed
Oversee the mechanical works in the project plan
Design, install and maintain mechanical machinery and tools
Electrical contractors Design, install and maintain the electrical system
Understanding the building structure and requirements based on the
electrical services
Diagnose the circuits and electrical components
Equipment suppliers Supply of raw materials to the project organization
Perform a risk management plan
IT Manager Supervise and develop the IT system with staffing of IT team
Review performance of information networks and also software
applications
Perform regular meetings with the stakeholders for updating IT
actions
Steel fabricators and
installers
Fabrication and utilization of technical drawings and blueprints
Review of specifications for construction of metal products
Install the equipments in the organizational premises
Construction
Manager
Determination of labor needs and dispatch the workers to the
construction sites
Inspect as well as review the project work for monitoring compliance
with safety codes
Schedule the plan and budget necessary to meet the project deadlines
Mechanical
contractors
Responsible to review ongoing maintenance of the system they are
installed
Oversee the mechanical works in the project plan
Design, install and maintain mechanical machinery and tools
Electrical contractors Design, install and maintain the electrical system
Understanding the building structure and requirements based on the
electrical services
Diagnose the circuits and electrical components
Equipment suppliers Supply of raw materials to the project organization

11PROJECT MANAGEMENT
Deliver the equipments and services at scheduled timeline
Perform daily basis management of the project process
Project management
consultants
Manage project related to project activities in constraints of time and
cost
Ensure for project scope and schedule and allocate of work as per
team members
Deliver the equipments and services at scheduled timeline
Perform daily basis management of the project process
Project management
consultants
Manage project related to project activities in constraints of time and
cost
Ensure for project scope and schedule and allocate of work as per
team members
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 29
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.