Project Charter: I-Crop Platform Website and Application Development
VerifiedAdded on 2023/06/04
|21
|3882
|190
Project
AI Summary
This document presents a project charter for the development of the I-Crop platform, an online cash marketplace designed to support Globex's existing services by connecting buyers and growers of warehoused grain. The charter outlines the project's measurable organizational value (MOV), including its strategic, customer-centric, financial, operational, and social impacts, with specific metrics and timeframes for achievement. It defines the project scope, both in and out of scope, and details the resources required for development. Furthermore, the charter includes a project schedule with milestones, activities, and resource assignments, along with a project budget, risk analysis, and a quality management plan. The document concludes with a closure and evaluation plan to ensure project success. Desklib provides access to this and other solved assignments for students.

Running head: PROJECT MANAGEMENT
Project Management: Website and Application Development Project for I-Crop
Student Name:
University Name:
Project Management: Website and Application Development Project for I-Crop
Student Name:
University Name:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
1. Project Description.................................................................................................................3
2. Part One: MOV - Measurable Organisational Value.............................................................3
2.1 Desired area of impact.....................................................................................................3
2.2 Types of Value.................................................................................................................4
2.3 Involvement of stakeholders in the project......................................................................4
2.4 Target metric and timeframe............................................................................................5
3. Part Two: Define Scope and produce a Scope Management Plan.........................................5
3.1 Scope definition and scope management.........................................................................5
3.2 List of Resources..............................................................................................................6
4. Part Three: Schedule for the project.......................................................................................6
4.1 Milestones for each phase and Deliverable......................................................................6
4.2 Activities / Tasks for the project......................................................................................7
4.3 Resource Assignments.....................................................................................................8
4.4 Estimates for Each Activity / Task...................................................................................9
4.5 Project Budget..................................................................................................................9
5. Part Four: Project Risk Analysis and Plan...........................................................................11
5.1 Assumptions...................................................................................................................11
5.2 Risk Assessment.............................................................................................................11
6. Part Five: Quality Management Plan...................................................................................13
7. Part Six: Closure and Evaluation.........................................................................................15
7.1 Closure Checklist...........................................................................................................15
7.2 Project Evaluation Plan..................................................................................................15
Bibliography.............................................................................................................................16
Appendix - Annotated Bibliography........................................................................................19
Table of Contents
1. Project Description.................................................................................................................3
2. Part One: MOV - Measurable Organisational Value.............................................................3
2.1 Desired area of impact.....................................................................................................3
2.2 Types of Value.................................................................................................................4
2.3 Involvement of stakeholders in the project......................................................................4
2.4 Target metric and timeframe............................................................................................5
3. Part Two: Define Scope and produce a Scope Management Plan.........................................5
3.1 Scope definition and scope management.........................................................................5
3.2 List of Resources..............................................................................................................6
4. Part Three: Schedule for the project.......................................................................................6
4.1 Milestones for each phase and Deliverable......................................................................6
4.2 Activities / Tasks for the project......................................................................................7
4.3 Resource Assignments.....................................................................................................8
4.4 Estimates for Each Activity / Task...................................................................................9
4.5 Project Budget..................................................................................................................9
5. Part Four: Project Risk Analysis and Plan...........................................................................11
5.1 Assumptions...................................................................................................................11
5.2 Risk Assessment.............................................................................................................11
6. Part Five: Quality Management Plan...................................................................................13
7. Part Six: Closure and Evaluation.........................................................................................15
7.1 Closure Checklist...........................................................................................................15
7.2 Project Evaluation Plan..................................................................................................15
Bibliography.............................................................................................................................16
Appendix - Annotated Bibliography........................................................................................19

2PROJECT MANAGEMENT
1. Project Description
This project is based on developing a new online cash marketplace platform “i-Crop”
to support the existing services of Globex. In this project, a website and application will be
developed to meet the requirements of organization as well as clients. The platform will help
to bring the buyers and growers together in a single platform. This project will facilitate
convenient and easy management along with selling or buying of warehoused grain.
2. Part One: MOV - Measurable Organisational Value
2.1 Desired area of impact
Strategy: It has been identified that development of the Website and Application for i-
Crop will help to the keep track of the various type of information and details about
customers.
Customer: The development of the Website and the Application for i-Crop will help
the customers to resolve their queries and get required information. The clients will be
able to access i-Crop through any web browser or an application.
Financial: The platform that will be developed for the Globex will help the
organization to achieve desired profits and gain excellence in their business process.
The return on investment that will be achieved through the platform will be high for
the business organization.
Operational: It has been determined that the development and implementation of the
platform “i-Crop” will help to achieve the desired profit range. The development of
the platform will ensure that the operations can be easily carried out within the
business organization.
1. Project Description
This project is based on developing a new online cash marketplace platform “i-Crop”
to support the existing services of Globex. In this project, a website and application will be
developed to meet the requirements of organization as well as clients. The platform will help
to bring the buyers and growers together in a single platform. This project will facilitate
convenient and easy management along with selling or buying of warehoused grain.
2. Part One: MOV - Measurable Organisational Value
2.1 Desired area of impact
Strategy: It has been identified that development of the Website and Application for i-
Crop will help to the keep track of the various type of information and details about
customers.
Customer: The development of the Website and the Application for i-Crop will help
the customers to resolve their queries and get required information. The clients will be
able to access i-Crop through any web browser or an application.
Financial: The platform that will be developed for the Globex will help the
organization to achieve desired profits and gain excellence in their business process.
The return on investment that will be achieved through the platform will be high for
the business organization.
Operational: It has been determined that the development and implementation of the
platform “i-Crop” will help to achieve the desired profit range. The development of
the platform will ensure that the operations can be easily carried out within the
business organization.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
Social: The development of the platform will help to support communications
between the clients so that buyers and growers can easily communicate for buying or
selling warehoused grains.
2.2 Types of Value
Better: It has been determined that the new system will help to provide better services
to both organization as well as clients rather than the existing system. It has been
found that new system will help to enhance business operations of the organization.
Cheaper: The implementation of the new system will help to reduce the costs
associated with resource as well as materials for business operations within the
organization.
Faster: The new system will help to improve the response time required for clients
and delay in the business process due to the time required for executing activities
within the organization.
2.3 Involvement of stakeholders in the project
The below table illustrates the stakeholders that are associated with the project for
developing the new system:
Social: The development of the platform will help to support communications
between the clients so that buyers and growers can easily communicate for buying or
selling warehoused grains.
2.2 Types of Value
Better: It has been determined that the new system will help to provide better services
to both organization as well as clients rather than the existing system. It has been
found that new system will help to enhance business operations of the organization.
Cheaper: The implementation of the new system will help to reduce the costs
associated with resource as well as materials for business operations within the
organization.
Faster: The new system will help to improve the response time required for clients
and delay in the business process due to the time required for executing activities
within the organization.
2.3 Involvement of stakeholders in the project
The below table illustrates the stakeholders that are associated with the project for
developing the new system:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
2.4 Target metric and timeframe
Rank Impact Metrics Timeframe
1 Operationa
l
This project would decrease the time and cost required
for business operations within the organization.
2 months
2 Strategy This project will help to keep track of the client details
and requirements thus decrease of money.
1 month
3 Customer This project will help in reducing the response time thus
decrease of money.
1 month
4 Social This project will help to develop proper communications
between the client and organization thus there will be
decrease of money.
2 months
5. Financial This project will help to achieve high return on
investment and thus there will be increase of money.
6 months
3. Part Two: Define Scope and produce a Scope Management Plan
3.1 Scope definition and scope management
The scope of this project is development of a new online cash marketplace platform
“i-Crop” to support the business operations of Globex. The new system will help to bring the
buyers and growers together in a single platform.
In scope: The system will help to keep track and record details of the clients such as
Name, Contact and other relevant information so that the response time could be easily
reduced and business efficiency can be increased.
2.4 Target metric and timeframe
Rank Impact Metrics Timeframe
1 Operationa
l
This project would decrease the time and cost required
for business operations within the organization.
2 months
2 Strategy This project will help to keep track of the client details
and requirements thus decrease of money.
1 month
3 Customer This project will help in reducing the response time thus
decrease of money.
1 month
4 Social This project will help to develop proper communications
between the client and organization thus there will be
decrease of money.
2 months
5. Financial This project will help to achieve high return on
investment and thus there will be increase of money.
6 months
3. Part Two: Define Scope and produce a Scope Management Plan
3.1 Scope definition and scope management
The scope of this project is development of a new online cash marketplace platform
“i-Crop” to support the business operations of Globex. The new system will help to bring the
buyers and growers together in a single platform.
In scope: The system will help to keep track and record details of the clients such as
Name, Contact and other relevant information so that the response time could be easily
reduced and business efficiency can be increased.

5PROJECT MANAGEMENT
Out scope: Proper training have to be provided to the staffs for operating the new
system such that business processes can be carried out effectively and as per requirement.
Procedure for scope management: The project deliverables will be approved at
every stage of the project as per requirements of the stakeholders. The stakeholders will be
associated at every stage of the project through proper communication procedures such that
they are aware of the project deliverables.
3.2 List of Resources
People: Project Manager, Business Analyst, Website Designer, Application Designer,
Website Developer, Application Developer, Tester, Quality Analyst, Technical Writer
Technology: Mobile application platform, Web designing tools, Website
Development platform, Website Domain
Facilities: Testing Facility, Research and Development Facility, Design Facility
4. Part Three: Schedule for the project
4.1 Milestones for each phase and Deliverable
WBS Task Name Duration Start Finish
1 Phase 1 - Initiation 10 days Mon
10/8/18 Fri 10/19/18
M1 Project charter sign-off 0 days Fri 10/19/18 Fri 10/19/18
2 Phase 2 - Planning 11 days Mon
10/22/18
Mon
11/5/18
M2 Approval of plan 0 days Mon 11/5/18 Mon 11/5/18
3 Phase 3 - Design 39 days Tue 11/6/18 Fri 12/28/18
3.1 Designing the Website 17 days Tue 11/6/18 Wed
11/28/18
M3 Approval of website design 0 days Wed
11/28/18
Wed
11/28/18
3.2 Designing the Application 22 days Thu
11/29/18 Fri 12/28/18
M4 Approval of application design 0 days Fri 12/28/18 Fri 12/28/18
Out scope: Proper training have to be provided to the staffs for operating the new
system such that business processes can be carried out effectively and as per requirement.
Procedure for scope management: The project deliverables will be approved at
every stage of the project as per requirements of the stakeholders. The stakeholders will be
associated at every stage of the project through proper communication procedures such that
they are aware of the project deliverables.
3.2 List of Resources
People: Project Manager, Business Analyst, Website Designer, Application Designer,
Website Developer, Application Developer, Tester, Quality Analyst, Technical Writer
Technology: Mobile application platform, Web designing tools, Website
Development platform, Website Domain
Facilities: Testing Facility, Research and Development Facility, Design Facility
4. Part Three: Schedule for the project
4.1 Milestones for each phase and Deliverable
WBS Task Name Duration Start Finish
1 Phase 1 - Initiation 10 days Mon
10/8/18 Fri 10/19/18
M1 Project charter sign-off 0 days Fri 10/19/18 Fri 10/19/18
2 Phase 2 - Planning 11 days Mon
10/22/18
Mon
11/5/18
M2 Approval of plan 0 days Mon 11/5/18 Mon 11/5/18
3 Phase 3 - Design 39 days Tue 11/6/18 Fri 12/28/18
3.1 Designing the Website 17 days Tue 11/6/18 Wed
11/28/18
M3 Approval of website design 0 days Wed
11/28/18
Wed
11/28/18
3.2 Designing the Application 22 days Thu
11/29/18 Fri 12/28/18
M4 Approval of application design 0 days Fri 12/28/18 Fri 12/28/18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
4 Phase 4 - Development 35 days Mon
12/31/18 Fri 2/15/19
4.1 Development of website 19 days Mon
12/31/18 Thu 1/24/19
M5 Completion of website development 0 days Thu 1/24/19 Thu 1/24/19
4.2 Development of Mobile Application 17 days Thu 1/24/19 Fri 2/15/19
M6 Completion of Application Development 0 days Fri 2/15/19 Fri 2/15/19
5 Phase 5 - Closure 5 days Mon
2/18/19 Fri 2/22/19
M7 Closure of project 0 days Fri 2/22/19 Fri 2/22/19
4.2 Activities / Tasks for the project
WBS Task Name
0 Website and Application Development project for i-Crop
1 Phase 1 - Initiation
1.1 Requirements gathering and analysis
1.2 Development of project charter
1.3 Documentation of the initial project plan
M1 Project charter sign-off
2 Phase 2 - Planning
2.1 Selection of suitable project management methodology
2.2 Outlining the plan for project
2.3 Review of designed plan
2.4 Completion of project plan
M2 Approval of plan
3 Phase 3 - Design
3.1 Designing the Website
3.1.1 Selecting the platform for website development
3.1.2 Designing outline for the website
3.1.3 Reviewing the website design
3.1.4 Completing the design of website
M3 Approval of website design
3.2 Designing the Application
3.2.1 Selecting the platform for application development
3.2.2 Designing outline for the application
3.2.3 Review of the application design
3.2.4 Completing the design of application
M4 Approval of application design
4 Phase 4 - Development
4.1 Development of website
4.1.1 Acquiring domain for website
4.1.2 Developing the interface for website
4.1.3 Alignment of the functions as per requirement
4 Phase 4 - Development 35 days Mon
12/31/18 Fri 2/15/19
4.1 Development of website 19 days Mon
12/31/18 Thu 1/24/19
M5 Completion of website development 0 days Thu 1/24/19 Thu 1/24/19
4.2 Development of Mobile Application 17 days Thu 1/24/19 Fri 2/15/19
M6 Completion of Application Development 0 days Fri 2/15/19 Fri 2/15/19
5 Phase 5 - Closure 5 days Mon
2/18/19 Fri 2/22/19
M7 Closure of project 0 days Fri 2/22/19 Fri 2/22/19
4.2 Activities / Tasks for the project
WBS Task Name
0 Website and Application Development project for i-Crop
1 Phase 1 - Initiation
1.1 Requirements gathering and analysis
1.2 Development of project charter
1.3 Documentation of the initial project plan
M1 Project charter sign-off
2 Phase 2 - Planning
2.1 Selection of suitable project management methodology
2.2 Outlining the plan for project
2.3 Review of designed plan
2.4 Completion of project plan
M2 Approval of plan
3 Phase 3 - Design
3.1 Designing the Website
3.1.1 Selecting the platform for website development
3.1.2 Designing outline for the website
3.1.3 Reviewing the website design
3.1.4 Completing the design of website
M3 Approval of website design
3.2 Designing the Application
3.2.1 Selecting the platform for application development
3.2.2 Designing outline for the application
3.2.3 Review of the application design
3.2.4 Completing the design of application
M4 Approval of application design
4 Phase 4 - Development
4.1 Development of website
4.1.1 Acquiring domain for website
4.1.2 Developing the interface for website
4.1.3 Alignment of the functions as per requirement
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
4.1.4 Developing the website functionalities
4.1.5 Checking compatibility of website
M5 Completion of website development
4.2 Development of Mobile Application
4.2.1 Developing the interface for mobile application
4.2.2 Developing the application modules
4.2.3 Testing of the modules
4.2.4 Integrating the application
M6 Completion of Application Development
5 Phase 5 - Closure
5.1 Review of post project implementation
5.2 Documenting Lessons Learned
5.3 Development of closure checklist
5.4 Project evaluation
M7 Closure of project
4.3 Resource Assignments
4.1.4 Developing the website functionalities
4.1.5 Checking compatibility of website
M5 Completion of website development
4.2 Development of Mobile Application
4.2.1 Developing the interface for mobile application
4.2.2 Developing the application modules
4.2.3 Testing of the modules
4.2.4 Integrating the application
M6 Completion of Application Development
5 Phase 5 - Closure
5.1 Review of post project implementation
5.2 Documenting Lessons Learned
5.3 Development of closure checklist
5.4 Project evaluation
M7 Closure of project
4.3 Resource Assignments

8PROJECT MANAGEMENT
4.4 Estimates for Each Activity / Task
4.5 Project Budget
The budget that has been estimated for the project is $68,074.00 and an overview of
the cash flow for this project is presented as below:
WBS Task Name Cost
0 Website and Application Development
project for i-Crop $68,074.00
1 Phase 1 - Initiation $6,080.00
1.1 Requirements gathering and analysis $1,680.00
1.2 Development of project charter $3,200.00
1.3 Documentation of the initial project plan $1,200.00
M1 Project charter sign-off $0.00
2 Phase 2 - Planning $6,080.00
4.4 Estimates for Each Activity / Task
4.5 Project Budget
The budget that has been estimated for the project is $68,074.00 and an overview of
the cash flow for this project is presented as below:
WBS Task Name Cost
0 Website and Application Development
project for i-Crop $68,074.00
1 Phase 1 - Initiation $6,080.00
1.1 Requirements gathering and analysis $1,680.00
1.2 Development of project charter $3,200.00
1.3 Documentation of the initial project plan $1,200.00
M1 Project charter sign-off $0.00
2 Phase 2 - Planning $6,080.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
2.1 Selection of suitable project management
methodology $800.00
2.2 Outlining the plan for project $2,560.00
2.3 Review of designed plan $1,520.00
2.4 Completion of project plan $1,200.00
M2 Approval of plan $0.00
3 Phase 3 - Design $21,080.00
3.1 Designing the Website $9,740.00
3.1.1 Selecting the platform for website
development $1,360.00
3.1.2 Designing outline for the website $1,600.00
3.1.3 Reviewing the website design $2,040.00
3.1.4 Completing the design of website $4,740.00
M3 Approval of website design $0.00
3.2 Designing the Application $11,340.00
3.2.1 Selecting the platform for application
development $1,360.00
3.2.2 Designing outline for the application $2,240.00
3.2.3 Review of the application design $2,040.00
3.2.4 Completing the design of application $5,700.00
M4 Approval of application design $0.00
4 Phase 4 - Development $31,874.00
4.1 Development of website $19,706.00
4.1.1 Acquiring domain for website $10,970.00
4.1.2 Developing the interface for website $1,440.00
4.1.3 Alignment of the functions as per
requirement $4,760.00
4.1.4 Developing the website functionalities $1,800.00
4.1.5 Checking compatibility of website $736.00
M5 Completion of website development $0.00
4.2 Development of Mobile Application $12,168.00
4.2.1 Developing the interface for mobile
application $4,300.00
4.2.2 Developing the application modules $5,020.00
4.2.3 Testing of the modules $2,208.00
4.2.4 Integrating the application $640.00
M6 Completion of Application Development $0.00
5 Phase 5 - Closure $2,960.00
5.1 Review of post project implementation $1,680.00
5.2 Documenting Lessons Learned $240.00
5.3 Development of closure checklist $640.00
5.4 Project evaluation $400.00
M7 Closure of project $0.00
5. Part Four: Project Risk Analysis and Plan
2.1 Selection of suitable project management
methodology $800.00
2.2 Outlining the plan for project $2,560.00
2.3 Review of designed plan $1,520.00
2.4 Completion of project plan $1,200.00
M2 Approval of plan $0.00
3 Phase 3 - Design $21,080.00
3.1 Designing the Website $9,740.00
3.1.1 Selecting the platform for website
development $1,360.00
3.1.2 Designing outline for the website $1,600.00
3.1.3 Reviewing the website design $2,040.00
3.1.4 Completing the design of website $4,740.00
M3 Approval of website design $0.00
3.2 Designing the Application $11,340.00
3.2.1 Selecting the platform for application
development $1,360.00
3.2.2 Designing outline for the application $2,240.00
3.2.3 Review of the application design $2,040.00
3.2.4 Completing the design of application $5,700.00
M4 Approval of application design $0.00
4 Phase 4 - Development $31,874.00
4.1 Development of website $19,706.00
4.1.1 Acquiring domain for website $10,970.00
4.1.2 Developing the interface for website $1,440.00
4.1.3 Alignment of the functions as per
requirement $4,760.00
4.1.4 Developing the website functionalities $1,800.00
4.1.5 Checking compatibility of website $736.00
M5 Completion of website development $0.00
4.2 Development of Mobile Application $12,168.00
4.2.1 Developing the interface for mobile
application $4,300.00
4.2.2 Developing the application modules $5,020.00
4.2.3 Testing of the modules $2,208.00
4.2.4 Integrating the application $640.00
M6 Completion of Application Development $0.00
5 Phase 5 - Closure $2,960.00
5.1 Review of post project implementation $1,680.00
5.2 Documenting Lessons Learned $240.00
5.3 Development of closure checklist $640.00
5.4 Project evaluation $400.00
M7 Closure of project $0.00
5. Part Four: Project Risk Analysis and Plan
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
5.1 Assumptions
Budget: The budget of the project has been prepared considering the costs associated
with resources including people as well as material after analysis of the requirements.
Time: The time for completing the project has been estimated properly through proper
discussions in project team meeting.
Schedule: The timeline for project has been developed by the Project Manager after
determining the required activities.
Resources: The resource allocation has been done as expected and there is no issues
of resource over allocation in the project plan.
5.2 Risk Assessment
No. Ran
k
Risk Description Categor
y
Risk
Owner
Probabilit
y
Impact Mitigation
Strategy
R1
2
1 Over
budgeting
Improper
allocation
and
determinatio
n of budget
for the
project.
Financia
l risk
Project
manager
Medium High Effective
planning
and proper
budget
developmen
t.
R0
8
2 Requiremen
ts analysis
Improper
requirement
s gathering
People
risk
Project
Manager
Medium High Proper
requirement
s gathering
5.1 Assumptions
Budget: The budget of the project has been prepared considering the costs associated
with resources including people as well as material after analysis of the requirements.
Time: The time for completing the project has been estimated properly through proper
discussions in project team meeting.
Schedule: The timeline for project has been developed by the Project Manager after
determining the required activities.
Resources: The resource allocation has been done as expected and there is no issues
of resource over allocation in the project plan.
5.2 Risk Assessment
No. Ran
k
Risk Description Categor
y
Risk
Owner
Probabilit
y
Impact Mitigation
Strategy
R1
2
1 Over
budgeting
Improper
allocation
and
determinatio
n of budget
for the
project.
Financia
l risk
Project
manager
Medium High Effective
planning
and proper
budget
developmen
t.
R0
8
2 Requiremen
ts analysis
Improper
requirement
s gathering
People
risk
Project
Manager
Medium High Proper
requirement
s gathering

11PROJECT MANAGEMENT
and
difficulty in
identificatio
n of client
requirement
s.
and
identificatio
n have to be
carried out.
R0
6
3 Technical
issues or
System
Failure
Improper
system
maintenance
may lead to
errors or
fault in the
system
Technic
al risk
Develope
r
High High Proper
maintenanc
e
procedures
have to be
followed
and carried
out on a
regular
basis.
R1
8
4 Delay in
project
Progress of
project is
not
according to
the
developed
schedule.
Schedul
e risk
Project
manager
Medium Mediu
m
The project
progress
should be
evaluated
and
monitored
continuousl
y.
and
difficulty in
identificatio
n of client
requirement
s.
and
identificatio
n have to be
carried out.
R0
6
3 Technical
issues or
System
Failure
Improper
system
maintenance
may lead to
errors or
fault in the
system
Technic
al risk
Develope
r
High High Proper
maintenanc
e
procedures
have to be
followed
and carried
out on a
regular
basis.
R1
8
4 Delay in
project
Progress of
project is
not
according to
the
developed
schedule.
Schedul
e risk
Project
manager
Medium Mediu
m
The project
progress
should be
evaluated
and
monitored
continuousl
y.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 21
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.