ITC505 Project Management: Final Report on I-Crop Web & App Project
VerifiedAdded on 2023/06/04
|23
|3388
|70
Report
AI Summary
This document presents the final report for the I-Crop website and mobile application development project, undertaken as part of the ITC505 Project Management course. It covers various aspects of the project, including the Measurable Organizational Value (MOV), scope definition and management plan, Work Breakdown Structure (WBS), risk analysis and plan, quality management plan, and project closure and evaluation. The report details resource allocation, budget, and timelines, alongside identifying potential risks and mitigation strategies. The project aimed to develop an innovative website and mobile application for I-Crop to improve operational efficiency and customer engagement. Desklib provides access to this and many other solved assignments.

[Type here]
ITC505-Project Management
Project Final Report
Website and Application Development for I-Crop
Name of the Student: Wasif Numan
Student ID: 11640426
ITC505-Project Management
Project Final Report
Website and Application Development for I-Crop
Name of the Student: Wasif Numan
Student ID: 11640426
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

ITC505-Assignment 3
Table of Contents
1. Part One: MOV - Measurable Organisational Value...................................................................2
2. Part Two: Define Scope and produce a Scope Management Plan...............................................4
3. Part Three: WBS..........................................................................................................................6
4. Part Four: Project Risk Analysis and Plan.................................................................................15
5. Part Five: Quality Management Plan.........................................................................................16
6. Part Six: Closure and Evaluation...............................................................................................17
MS PROJECT FILE......................................................................................................................20
Bibliography..................................................................................................................................21
1 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Table of Contents
1. Part One: MOV - Measurable Organisational Value...................................................................2
2. Part Two: Define Scope and produce a Scope Management Plan...............................................4
3. Part Three: WBS..........................................................................................................................6
4. Part Four: Project Risk Analysis and Plan.................................................................................15
5. Part Five: Quality Management Plan.........................................................................................16
6. Part Six: Closure and Evaluation...............................................................................................17
MS PROJECT FILE......................................................................................................................20
Bibliography..................................................................................................................................21
1 | W a s i f N u m a n - 1 1 6 4 0 4 2 6

ITC505-Assignment 3
1. Part One: MOV - Measurable Organisational Value
Financial Area: Financial area of the project of website and mobile application
development of I-Crop Project is the most crucial aspect of delivering the effective
project execution as the economic value of the projects.
Customer Area: Customer area of the project of website and mobile application
development of I-Crop Project is the second most aspect of delivering the effective
project outcome as the alignment of the client’s requirement is a major factor for the
project execution.
Operational Area: Operational area of the project of website and mobile application
development of I-Crop Project is third most aspect of delivering the finite project
execution and alignment.
Strategy Area: Strategically alignment of the successful project execution has been
helpful for achieving the deployment of the effective implication model for the project of
website and mobile application development of I-Crop Project.
Social Area: The social area is responsible for the inclusion of the operations and aligning
the utilization of the social platform for the effective process modification.
Better- The implication of the website and mobile application for I-Crop would be
helpful for improving the operations aligned with the development.
2 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
1. Part One: MOV - Measurable Organisational Value
Financial Area: Financial area of the project of website and mobile application
development of I-Crop Project is the most crucial aspect of delivering the effective
project execution as the economic value of the projects.
Customer Area: Customer area of the project of website and mobile application
development of I-Crop Project is the second most aspect of delivering the effective
project outcome as the alignment of the client’s requirement is a major factor for the
project execution.
Operational Area: Operational area of the project of website and mobile application
development of I-Crop Project is third most aspect of delivering the finite project
execution and alignment.
Strategy Area: Strategically alignment of the successful project execution has been
helpful for achieving the deployment of the effective implication model for the project of
website and mobile application development of I-Crop Project.
Social Area: The social area is responsible for the inclusion of the operations and aligning
the utilization of the social platform for the effective process modification.
Better- The implication of the website and mobile application for I-Crop would be
helpful for improving the operations aligned with the development.
2 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

ITC505-Assignment 3
Faster- The faster operation development can be achieved with the improvement of the
effective website and mobile application
Cheaper- The overall cost of the operations of I-Crop would be decreased with the
inclusion of the website and mobile application.
Do more- The installation of website and mobile application would help in easing the
communication management for the operations for I-Crop.
Rank Impact Metrics Timeframe (in months)
1 Financial Profit Margin 3
2 Customer Feedbacks and Orders 4
3 Operational Processing Time 2
4 Strategy Effective Implication 1
5 Social Feedbacks on social media web 5
3 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Faster- The faster operation development can be achieved with the improvement of the
effective website and mobile application
Cheaper- The overall cost of the operations of I-Crop would be decreased with the
inclusion of the website and mobile application.
Do more- The installation of website and mobile application would help in easing the
communication management for the operations for I-Crop.
Rank Impact Metrics Timeframe (in months)
1 Financial Profit Margin 3
2 Customer Feedbacks and Orders 4
3 Operational Processing Time 2
4 Strategy Effective Implication 1
5 Social Feedbacks on social media web 5
3 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

ITC505-Assignment 3
2. Part Two: Define Scope and produce a Scope Management Plan
Define the scope: The project scope involves the simplification management and integration of
the successive and improved operations for I-Crop. The project scope definition would be
implied for identifying the alignment of the operations and execution. The scope definition
would be implied for easing the significant formation and development. The alignment would be
helpful for integrating the successful formation of the improved website and mobile
development. The information development would support the formation of the improved
functional development and improvements. The project scope would include the functions of
developing the website and mobile design, developing the website and mobile, implementation
plan, and closure documents.
Provide a list of Resources:
People: Analyst, Documenter, Planner, Project Manager, Website Designer, Application
Designer, Engineer, Website Developer, Programmer, and Application Developer.
Technology: Website Development, Mobile Application Development, Design Development,
Mobile Application UI Development, and Testing technology.
Facilities: Testing and UI simulation environment facility would be required for the completion
of the project.
4 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
2. Part Two: Define Scope and produce a Scope Management Plan
Define the scope: The project scope involves the simplification management and integration of
the successive and improved operations for I-Crop. The project scope definition would be
implied for identifying the alignment of the operations and execution. The scope definition
would be implied for easing the significant formation and development. The alignment would be
helpful for integrating the successful formation of the improved website and mobile
development. The information development would support the formation of the improved
functional development and improvements. The project scope would include the functions of
developing the website and mobile design, developing the website and mobile, implementation
plan, and closure documents.
Provide a list of Resources:
People: Analyst, Documenter, Planner, Project Manager, Website Designer, Application
Designer, Engineer, Website Developer, Programmer, and Application Developer.
Technology: Website Development, Mobile Application Development, Design Development,
Mobile Application UI Development, and Testing technology.
Facilities: Testing and UI simulation environment facility would be required for the completion
of the project.
4 | W a s i f N u m a n - 1 1 6 4 0 4 2 6

ITC505-Assignment 3
Screenshot of Project Resource List:
ID Resource Name Type Max. Units Std. Rate Ovt. Rate
1 Analyst Work 100% $50.00/hr $0.00/hr
2 Documenter Work 100% $55.00/hr $0.00/hr
3 Planner Work 100% $60.00/hr $0.00/hr
4 Project Manager Work 100% $125.00/hr $0.00/hr
5 Website Designer Work 100% $90.00/hr $0.00/hr
6 Application Designer Work 100% $90.00/hr $0.00/hr
7 Engineer Work 100% $120.00/hr $0.00/hr
8 Website Developer Work 100% $100.00/hr $0.00/hr
9 Programmer Work 100% $110.00/hr $0.00/hr
10 Application Developer Work 100% $100.00/hr $0.00/hr
11 Documents Material $150.00
12 Design Tools Material $1,200.00
13 Domain Cost Material $750.00
Scope Management Plan: The project of website and mobile application development of I-Crop
Project would be executed for developing the innovative technology for mobile and website
development in integrating the alignment of the innovative operation development.
5 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Screenshot of Project Resource List:
ID Resource Name Type Max. Units Std. Rate Ovt. Rate
1 Analyst Work 100% $50.00/hr $0.00/hr
2 Documenter Work 100% $55.00/hr $0.00/hr
3 Planner Work 100% $60.00/hr $0.00/hr
4 Project Manager Work 100% $125.00/hr $0.00/hr
5 Website Designer Work 100% $90.00/hr $0.00/hr
6 Application Designer Work 100% $90.00/hr $0.00/hr
7 Engineer Work 100% $120.00/hr $0.00/hr
8 Website Developer Work 100% $100.00/hr $0.00/hr
9 Programmer Work 100% $110.00/hr $0.00/hr
10 Application Developer Work 100% $100.00/hr $0.00/hr
11 Documents Material $150.00
12 Design Tools Material $1,200.00
13 Domain Cost Material $750.00
Scope Management Plan: The project of website and mobile application development of I-Crop
Project would be executed for developing the innovative technology for mobile and website
development in integrating the alignment of the innovative operation development.
5 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

ITC505-Assignment 3
Requirements: The analysis of the factors of development can be implied for easing the design
and development of the website and mobile application. The integration management would be
helpful for ensuring the completion of the project.
In scope-out scope items: The project plan, developing the website and mobile design,
developing the website and mobile, implementation plan, and closure documents are the in scope
items where as the transportation requirements, communication, and change management are the
out of scope items of the project.
Deliverables: The deliverables for the website and mobile application development of I-Crop
Project would include project plan, design, development, testing results, and closure
documentation.
Acceptance Criteria:
Feasible Project Plan is made
Simulation of the design provides positive outcomes
Developed website and mobile application meets the requirement criteria
Testing results are as per the expectation
3. Part Three: WBS
6 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Requirements: The analysis of the factors of development can be implied for easing the design
and development of the website and mobile application. The integration management would be
helpful for ensuring the completion of the project.
In scope-out scope items: The project plan, developing the website and mobile design,
developing the website and mobile, implementation plan, and closure documents are the in scope
items where as the transportation requirements, communication, and change management are the
out of scope items of the project.
Deliverables: The deliverables for the website and mobile application development of I-Crop
Project would include project plan, design, development, testing results, and closure
documentation.
Acceptance Criteria:
Feasible Project Plan is made
Simulation of the design provides positive outcomes
Developed website and mobile application meets the requirement criteria
Testing results are as per the expectation
3. Part Three: WBS
6 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

ITC505-Assignment 3
Milestones
WBS Milestone Name Duration Start Finish
1.5 Signing off 0 days Mon 11/12/18 Mon 11/12/18
2.5 Approving Complete Plan 0 days Wed 11/21/18 Wed 11/21/18
3.1.5 Approving Website 0 days Fri 11/30/18 Fri 11/30/18
3.2.5 Approving Mobile Application 0 days Tue 12/11/18 Tue 12/11/18
5.5 Closure 0 days Fri 1/25/19 Fri 1/25/19
Activities / Tasks
WBS Task Name
0 I-Crop Website and Mobile Application Development Project
1 Initialization Phase
1.1 Analyzing requirements
1.2 Making Project Charter Documents
1.3 Making Project Initiation Documents
1.4 Submitting documents
1.5 Signing off
2 Plan Development Phase
2.1 Selecting Plan Methodology
2.2 Making Plan Outline
2.3 Reviewing Plan Outline
7 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Milestones
WBS Milestone Name Duration Start Finish
1.5 Signing off 0 days Mon 11/12/18 Mon 11/12/18
2.5 Approving Complete Plan 0 days Wed 11/21/18 Wed 11/21/18
3.1.5 Approving Website 0 days Fri 11/30/18 Fri 11/30/18
3.2.5 Approving Mobile Application 0 days Tue 12/11/18 Tue 12/11/18
5.5 Closure 0 days Fri 1/25/19 Fri 1/25/19
Activities / Tasks
WBS Task Name
0 I-Crop Website and Mobile Application Development Project
1 Initialization Phase
1.1 Analyzing requirements
1.2 Making Project Charter Documents
1.3 Making Project Initiation Documents
1.4 Submitting documents
1.5 Signing off
2 Plan Development Phase
2.1 Selecting Plan Methodology
2.2 Making Plan Outline
2.3 Reviewing Plan Outline
7 | W a s i f N u m a n - 1 1 6 4 0 4 2 6

ITC505-Assignment 3
2.4 Making Complete Plan
2.5 Approving Complete Plan
3 Design Development Phase
3.1 Design of Website
3.1.1 Selecting Design Platform
3.1.2 Making Website Outline
3.1.3 Reviewing Website Outline
3.1.4 Making Complete Website
3.1.5 Approving Website
3.2 Design of Mobile Application
3.2.1 Selecting Design Platform
3.2.2 Making Mobile Application Outline
3.2.3 Reviewing Mobile Application Outline
3.2.4 Making Complete Mobile Application
3.2.5 Approving Mobile Application
4 Development Phase
4.1 Development of Website
4.1.1 Buying Website Domain
4.1.2 Developing Website Interface
4.1.3 Aligning Functions of Website
4.1.4 Making Programs for Website
4.1.5 Checking Mobile Compatibility
8 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
2.4 Making Complete Plan
2.5 Approving Complete Plan
3 Design Development Phase
3.1 Design of Website
3.1.1 Selecting Design Platform
3.1.2 Making Website Outline
3.1.3 Reviewing Website Outline
3.1.4 Making Complete Website
3.1.5 Approving Website
3.2 Design of Mobile Application
3.2.1 Selecting Design Platform
3.2.2 Making Mobile Application Outline
3.2.3 Reviewing Mobile Application Outline
3.2.4 Making Complete Mobile Application
3.2.5 Approving Mobile Application
4 Development Phase
4.1 Development of Website
4.1.1 Buying Website Domain
4.1.2 Developing Website Interface
4.1.3 Aligning Functions of Website
4.1.4 Making Programs for Website
4.1.5 Checking Mobile Compatibility
8 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

ITC505-Assignment 3
4.1.6 Completion of Website Development
4.2 Development of Mobile Application
4.2.1 Developing Application Interface
4.2.2 Making Programs for Mobile Application
4.2.3 Integrating Mobile Applications
4.2.4 Completion of Mobile Application Development
5 Closing Phase
5.1 Making Closure Reports
5.2 Making Evaluation Checklist
5.3 Submitting Report Documents
5.4 Signing off
5.5 Closure
9 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
4.1.6 Completion of Website Development
4.2 Development of Mobile Application
4.2.1 Developing Application Interface
4.2.2 Making Programs for Mobile Application
4.2.3 Integrating Mobile Applications
4.2.4 Completion of Mobile Application Development
5 Closing Phase
5.1 Making Closure Reports
5.2 Making Evaluation Checklist
5.3 Submitting Report Documents
5.4 Signing off
5.5 Closure
9 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

ITC505-Assignment 3
Resource Assignments
ID Resource Name Work
1 Analyst 8 hrs
2 Documenter 64 hrs
3 Planner 48 hrs
4 Project Manager 32 hrs
5 Website Designer 48 hrs
6 Application Designer 48 hrs
7 Engineer 40 hrs
8 Website Developer 72 hrs
9 Programmer 56 hrs
10 Application Developer 64 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
M S S F T W T M
Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
8h
40h 16h 8h
24h 24h
8h 24h
48h
48h
8h 16h 8h 8h
8h 56h 8h
16h 40h
16h 48h
2 1
2 2
1
10 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
Resource Assignments
ID Resource Name Work
1 Analyst 8 hrs
2 Documenter 64 hrs
3 Planner 48 hrs
4 Project Manager 32 hrs
5 Website Designer 48 hrs
6 Application Designer 48 hrs
7 Engineer 40 hrs
8 Website Developer 72 hrs
9 Programmer 56 hrs
10 Application Developer 64 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
M S S F T W T M
Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
8h
40h 16h 8h
24h 24h
8h 24h
48h
48h
8h 16h 8h 8h
8h 56h 8h
16h 40h
16h 48h
2 1
2 2
1
10 | W a s i f N u m a n - 1 1 6 4 0 4 2 6

ITC505-Assignment 3
11 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
11 | W a s i f N u m a n - 1 1 6 4 0 4 2 6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.