This assignment presents a comprehensive ICT project management plan for the development of the iCrop application, designed to facilitate direct communication between crop growers and buyers. The project aims to enhance transparency in warehouse grain management and sales, focusing on financial and customer impact. Key elements include a detailed scope management plan, resource allocation, milestone definitions, activity scheduling, and budget estimation. The plan also addresses potential risks and assumptions, incorporating a quality management plan to ensure project success. The project's progress is tracked using a Gantt chart and a Work Breakdown Structure (WBS), with clearly defined tasks, resource assignments, and estimated durations. The assignment concludes with an annotated bibliography, a project closure checklist, and a project evaluation, providing a thorough overview of the project's lifecycle from initiation to completion.
Document Page
Running head: ICT PROJECT MANAGEMENT
ICT Project Management
Name of the Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
ICT PROJECT MANAGEMENT
Table of Contents
1. Part One...........................................................................................................................3
2. Part Two...........................................................................................................................4
2.1. Scope and Scope management..................................................................................4
2.2. List of Resources......................................................................................................4
3. Part Three.........................................................................................................................5
3.1. Milestone..................................................................................................................5
3.2. Activities/tasks..........................................................................................................6
3.3. Resource Assignments..............................................................................................9
3.4. Estimates for Each Activity....................................................................................10
3.5. Project Budget........................................................................................................12
4. Part Four........................................................................................................................13
4.1. Assumptions...........................................................................................................13
4.2. Risks.......................................................................................................................13
4.3. Risk Analysis..........................................................................................................14
5. Part Five: Quality Management Plan.............................................................................15
6. Part Six...........................................................................................................................16
6.1. Annotated Bibliography..........................................................................................16
6.2. Closure Checklist....................................................................................................18
6.3. Project Evaluation...................................................................................................18
Document Page
2
ICT PROJECT MANAGEMENT
Bibliography......................................................................................................................20
Document Page
3
ICT PROJECT MANAGEMENT
1. Part One
The aim of the project is to develop and online website and an application called iCrop
that will help the crop growers and buyers to directly communicate with each other regarding
business. The desired area of impact for the project is to bring in transparency in the process of
managing and selling of the warehouse grains. The project is expected to have a large impact on
strategy, financial, operational and social groups. The ranking of these areas in terms of
importance is represented in the following table-
Rank 1 is of highest importance while rank 5 is the smallest
Area of Impact Rank
Financial 1- Since it will improve the financial condition of
the crop growers
Customer 2- It will increase the transparency in the process of
dealing with the warehoused grains
Strategy 3- This strategy will help in business improvements
Operational 4- It aims in eliminating the operational issues
Social 5- No such impact in social sector.
The values the project will enforce are as follows-
Faster Dealing with the crops will be faster mainly
because the bidding will be done in an online
platform
Better The process of dealing with the warehoused grains
will be better by this project as it will increase the
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
ICT PROJECT MANAGEMENT
transparency.
The metric developed for this project associated with the expectations of the stakeholders are-
1. Completion of project within the schedule time
2. Completion of the project in as much less cost as possible
3. Increase in the business value
The target metrics are needed to be achieved by the end of project closure phase.
2. Part Two
2.1. Scope and Scope management
The project scope incorporates implementation of i-Crop Website and application by
Virtucon in as much less cost as possible. A scope management plan is generally developed in
order to define and manage the processes of the project. As a part of the scope management plan,
the resources and the activities of the project, is identified. The scope of the project will be
managed by developing a scope management plan and by ensuring that the resources of the
project are properly allocation. The following section gives an idea of the major resources
associated with this project.
2.2. List of Resources
The list of resources associated with this project and their standard rates is represented in
the following table-
Document Page
5
ICT PROJECT MANAGEMENT
Resource Name Type Max. Units Std. Rate Cost/Use
Project Manager Work 100% $70.00/hr $0.00
Resource Manager Work 200% $50.00/hr $0.00
Project Supervisor Work 100% $40.00/hr $0.00
Coders Work 500% $35.00/hr $0.00
Testers Work 500% $38.00/hr $0.00
Database Administrator Work 200% $30.00/hr $0.00
Software licensing cost Material $0.00 $75,000.00
Website Upload Cost Material $0.00 $50,000.00
Trainers Work 200% $25.00/hr $0.00
Archieve Material $0.00 $5,000.00
Content writer Work 200% $20.00/hr $0.00
3. Part Three
3.1. Milestone
The major milestones of the project are as follows-
M1: Completion of Requirements Gathering
Document Page
6
ICT PROJECT MANAGEMENT
M2: Development and Approval of Project Plan
M3: Completion of Development of application and website
M4: Completion of Testing
M5: Completion of Users' Training
M6: Successful Project Closure
3.2. Activities/tasks
The activities that will be followed while implementation of the i-Crop software and
website is represented in the following table-
WBS Task Name
0 Development of i-Crop Application
1 Project Starts
2 Project Initiation
2.1 Understanding the Requirements of the Project
2.2 Understanding the specifications of the Website and the
Application to be developed
2.3 Documenting the Requirements
2.4 Sharing it with the Clients
2.5 M1: Completion of Requirements Gathering
3 Project Planning
3.1 Planning the Implementation
3.2 Scheduling
3.3 Budget estimation
3.4 Resource Requirement
3.5 Resource Allocation
3.6 M2: Development and Approval of Project Plan
4 Project Execution
4.1 Coding the Website
4.2 Coding the iCrop Application
4.3 Linking the i-Crop Application to Database
4.4 Documenting the activities
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
ICT PROJECT MANAGEMENT
4.5 M3: Completion of Development of application and website
5 Testing
5.1 Unit Testing
5.2 System testing
5.3 User acceptance testing
5.4 Bug Fixing (if any)
5.5 M4: Completion of Testing
6 Training
6.1 Developing training manuals
6.2 Imparting training
6.3 M5: Completion of Users' Training
7 Project Closure
7.1 Completion of documenting
7.2 Record Archival
7.3 Resource Release
7.4 Client Sign off
7.5 M6: Successful Project Closure
8 Project ends
Successful completion of each of these tasks will ensure success of the project. The
projects are needed to be completed within the estimated schedule and budget.
The Gantt chart and the WBS of the project in represented in the following pictures-
Document Page
8
ICT PROJECT MANAGEMENT
Document Page
9
ICT PROJECT MANAGEMENT
Figure 1: Representing the Gantt Chart of the project
(Source: Generated by Author using MS project)
The work activities marked in red in the Gantt chart above depict the critical path of the project
The work breakdown structure of the project is represented in the following picture-
Development of i-Crop
Application
Project Starts Project Initiation
Understanding the
Requirements of the
Project
Understanding the
specifications of the
Website and the
Applictaion to be
developed
Documenting the
Requirements
Sharing it with the Clients
M1: Completion of
Requirements Gathering
Project Planning
Planning the
Implementation
Scheduling
Budget estimation
Resource Requirement
Resource Allocation
M2: Development and
Approval of Project Plan
Project Execution
Coding the Website
Coding the iCrop
Application
Linking the i-Crop
Application to Database
Documenting the
activitiesM3: Completion of
Development of
application and website
Testing
Unit Testing
System testing
User acceptance testing
Bug Fixing (if
any)M4: Completion of
Testing
Training
Developing training
manuals
Imparting training
M5: Completion of Users'
Training
Project Closure
Completion of
documenting
Record Archival
Resource Release
Client Sign off
M6: Successful Project
Closure
Project ends
Figure 2: Representing the Work Breakdown Structure of the Project
(Source: Generated by Author using MS Schedule Pro)
3.3. Resource Assignments
The resource estimated and the allocated resources of each of the tasks is represented in
the following table-
Task Name Resource Names
Development of i-Crop Application
Project Starts Project Manager
Project Initiation
Understanding the Requirements of the Project Project Manager, Resource Manager
Understanding the specifications of the Website
and the Application to be developed Project Manager
Documenting the Requirements Archieve [1],Content writer
Sharing it with the Clients Project Manager
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
ICT PROJECT MANAGEMENT
M1: Completion of Requirements Gathering
Project Planning
Planning the Implementation Project Manager, Project Supervisor
Scheduling Project Manager, Project Supervisor
Budget estimation Project Manager, Resource Manager
Resource Requirement Resource Manager
Resource Allocation Resource Manager
M2: Development and Approval of Project Plan
Project Execution
Coding the Website Coders, Website Upload Cost[1]
Coding the iCrop Application Coders, Software licensing cost[1]
Linking the i-Crop Application to Database Coders, Database Administrator
Documenting the activities Archieve [1],Content writer
M3: Completion of Development of application
and website
Testing
Unit Testing Testers
System testing Testers
User acceptance testing Testers
Bug Fixing (if any) Testers
M4: Completion of Testing
Training
Developing training manuals Trainers
Imparting training Trainers
M5: Completion of Users' Training
Project Closure
Completion of documenting Archieve [1],Content writer
Record Archival Archieve [1]
Resource Release Project Manager
Client Sign off Project Manager
M6: Successful Project Closure
Project ends Project Manager
3.4. Estimates for Each Activity
The estimated duration for each of the activities of the project is represented in the
following table-
Document Page
11
ICT PROJECT MANAGEMENT
Task Name Duration Start Finish