This report offers a comprehensive analysis of ICT project management within Globex Corporation. It begins with an executive summary and table of contents, followed by an introduction to the project. The report delves into the Measurable Organizational Value (MOV), explaining its significance and illustrating it with a Gantt chart and work breakdown structure. It then examines scope and scope management, presenting a Gantt chart for the scope management plan. The schedule is analyzed using a high-level Work Breakdown Structure (WBS) and Gantt chart. Project risk analysis and quality management plans are also included. The report concludes with project closure and evaluation, featuring an annotated bibliography, closure checklist, and project evaluation. The report emphasizes the importance of quality management, risk analysis, and effective planning for successful project outcomes, using Gantt charts and WBS to visualize project timelines and structures. The document also provides a detailed cost analysis and a discussion on the project's strategic importance to Globex Corporation.

Running head: ICT PROJECT MANAGEMENT
ICT Project Management
(Globex Corporation)
Name of the student:
Name of the university:
Author Note
ICT Project Management
(Globex Corporation)
Name of the student:
Name of the university:
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1ICT PROJECT MANAGEMENT
Executive summary
Globex Corporation, a leading consulting business has been conducting its ICT project management.
In this study, the scope management planning and MOV or Measurable Organizational values are
investigated for the project. Moreover, it has demonstrated quality management and risk analysis
planning.
Executive summary
Globex Corporation, a leading consulting business has been conducting its ICT project management.
In this study, the scope management planning and MOV or Measurable Organizational values are
investigated for the project. Moreover, it has demonstrated quality management and risk analysis
planning.

2ICT PROJECT MANAGEMENT
Table of Contents
1. Introduction:......................................................................................................................................3
2. Measurable Organizational Value (MOV):.......................................................................................3
3. Scope and Scope Management Plan:.................................................................................................3
4. Schedule using Schedule using a high level Work Breakdown Structure (WBS):...........................5
5. Project Risk Analysis and Plan:.........................................................................................................8
6. Quality management plan:.................................................................................................................9
7. Project closure and evaluation:........................................................................................................10
7.a. Annotated bibliography:...............................................................................................10
7. b. Closure checklist:.........................................................................................................13
7. c. Project evaluation:.......................................................................................................14
8. Conclusion:......................................................................................................................................15
9. References:......................................................................................................................................16
Table of Contents
1. Introduction:......................................................................................................................................3
2. Measurable Organizational Value (MOV):.......................................................................................3
3. Scope and Scope Management Plan:.................................................................................................3
4. Schedule using Schedule using a high level Work Breakdown Structure (WBS):...........................5
5. Project Risk Analysis and Plan:.........................................................................................................8
6. Quality management plan:.................................................................................................................9
7. Project closure and evaluation:........................................................................................................10
7.a. Annotated bibliography:...............................................................................................10
7. b. Closure checklist:.........................................................................................................13
7. c. Project evaluation:.......................................................................................................14
8. Conclusion:......................................................................................................................................15
9. References:......................................................................................................................................16
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3ICT PROJECT MANAGEMENT
1. Introduction:
Globex Corporation is a successful multi-discipline, international consulting agency. It has
been providing farming equipment and the turning key for structural, mechanical and electrical
engineering solutions.
The organisation has undergone through ICT project management. The following report has
analysed the Measurable Organizational Values and scope management plans. Further, it has
included the risk analysis plans and quality management plans.
2. Measurable Organizational Value (MOV):
Globex’s project decision must be made after making consultation with the effects on various
measurable and verifiable values of an organisation. For example, they must consider the addition of
various features of new websites, and this must be incorporated as the feature rises MOV. Further,
the decision maker has been asking that the feature has been increasing the user experiences.
Further, Globex must consider whether the feature has been developing the effective usage of sires
and decrease of cost of up gradation. Here, the project decision must make the end product
functional cheaper, faster and better (Nicholas & Steyn, 2017). It is illustrated through the following
task schedule.
Task Mode WBS Task Name Duration Start Finish
Auto
Schedule
d
0 Research on energy initiatives
implemented by Tesla 282 days Tue 7/4/17 Wed 8/1/18
Auto
Scheduled 1 Project Initiation 255 days Tue 7/4/17 Mon 6/25/18
Auto
Scheduled 1.1 Formation of project team 9 days Mon 6/4/18 Thu 6/14/18
Auto
Scheduled 1.2 Defining Project Charter 3 days Thu 6/21/18 Mon 6/25/18
1. Introduction:
Globex Corporation is a successful multi-discipline, international consulting agency. It has
been providing farming equipment and the turning key for structural, mechanical and electrical
engineering solutions.
The organisation has undergone through ICT project management. The following report has
analysed the Measurable Organizational Values and scope management plans. Further, it has
included the risk analysis plans and quality management plans.
2. Measurable Organizational Value (MOV):
Globex’s project decision must be made after making consultation with the effects on various
measurable and verifiable values of an organisation. For example, they must consider the addition of
various features of new websites, and this must be incorporated as the feature rises MOV. Further,
the decision maker has been asking that the feature has been increasing the user experiences.
Further, Globex must consider whether the feature has been developing the effective usage of sires
and decrease of cost of up gradation. Here, the project decision must make the end product
functional cheaper, faster and better (Nicholas & Steyn, 2017). It is illustrated through the following
task schedule.
Task Mode WBS Task Name Duration Start Finish
Auto
Schedule
d
0 Research on energy initiatives
implemented by Tesla 282 days Tue 7/4/17 Wed 8/1/18
Auto
Scheduled 1 Project Initiation 255 days Tue 7/4/17 Mon 6/25/18
Auto
Scheduled 1.1 Formation of project team 9 days Mon 6/4/18 Thu 6/14/18
Auto
Scheduled 1.2 Defining Project Charter 3 days Thu 6/21/18 Mon 6/25/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4ICT PROJECT MANAGEMENT
Auto
Scheduled 1.3 Submiting Project Charter 7 days Tue 7/18/17 Wed 7/26/17
Auto
Scheduled 1.4 Milestone 1: Approval on
Project Charter 5 days Tue 7/4/17 Mon 7/10/17
Auto
Scheduled 2 Project Planning 9 days Tue 6/26/18 Fri 7/6/18
Auto
Scheduled 2.1 Estimating Project Scope 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.1.1 Building Scope document 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.1.2 Approval of Scope document 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.2 Creating Work Breakdown
Structure (WBS) 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.2.1 Building WBS 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.2.2 Submitting WBS 3 days Tue 6/26/18 Thu 6/28/18
Auto
Scheduled 2.2.3 Approving WBS 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.3 Creating Gantt Chart 9 days Tue 6/26/18 Fri 7/6/18
Auto
Scheduled 2.3.1 Designing Gantt Chart 3 days Tue 6/26/18 Thu 6/28/18
Auto
Scheduled 2.3.2 Submitting Gantt Chart 6 days Tue 6/26/18 Tue 7/3/18
Auto
Scheduled 2.3.3 Approval of Gantt Chart 9 days Tue 6/26/18 Fri 7/6/18
Auto
Scheduled 2.4 Creating Risk Register 8 days Tue 6/26/18 Thu 7/5/18
Auto
Scheduled 2.4.1 Finding Risks 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.4.2 Submitting Risk Register 7 days Tue 6/26/18 Wed 7/4/18
Auto
Scheduled 2.4.3 Approving Risk Register 8 days Tue 6/26/18 Thu 7/5/18
Auto
Scheduled 2.5 Initiating project environment 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.6 Organizing meetings 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.7 Preparing project plan 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.8 Identification of dependencies
and estimate duration 6 days Tue 6/26/18 Tue 7/3/18
Auto
Scheduled 2.9 Estimating human resource
management 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 1.3 Submiting Project Charter 7 days Tue 7/18/17 Wed 7/26/17
Auto
Scheduled 1.4 Milestone 1: Approval on
Project Charter 5 days Tue 7/4/17 Mon 7/10/17
Auto
Scheduled 2 Project Planning 9 days Tue 6/26/18 Fri 7/6/18
Auto
Scheduled 2.1 Estimating Project Scope 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.1.1 Building Scope document 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.1.2 Approval of Scope document 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.2 Creating Work Breakdown
Structure (WBS) 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.2.1 Building WBS 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.2.2 Submitting WBS 3 days Tue 6/26/18 Thu 6/28/18
Auto
Scheduled 2.2.3 Approving WBS 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.3 Creating Gantt Chart 9 days Tue 6/26/18 Fri 7/6/18
Auto
Scheduled 2.3.1 Designing Gantt Chart 3 days Tue 6/26/18 Thu 6/28/18
Auto
Scheduled 2.3.2 Submitting Gantt Chart 6 days Tue 6/26/18 Tue 7/3/18
Auto
Scheduled 2.3.3 Approval of Gantt Chart 9 days Tue 6/26/18 Fri 7/6/18
Auto
Scheduled 2.4 Creating Risk Register 8 days Tue 6/26/18 Thu 7/5/18
Auto
Scheduled 2.4.1 Finding Risks 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.4.2 Submitting Risk Register 7 days Tue 6/26/18 Wed 7/4/18
Auto
Scheduled 2.4.3 Approving Risk Register 8 days Tue 6/26/18 Thu 7/5/18
Auto
Scheduled 2.5 Initiating project environment 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.6 Organizing meetings 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.7 Preparing project plan 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.8 Identification of dependencies
and estimate duration 6 days Tue 6/26/18 Tue 7/3/18
Auto
Scheduled 2.9 Estimating human resource
management 4 days Tue 6/26/18 Fri 6/29/18

5ICT PROJECT MANAGEMENT
Auto
Scheduled 2.10 Estimating software
requirement 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.11 Preparing schedule 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.12 Assigning tasks to members 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.13 Estimating budget 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.14 Submission of project plan 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.15 Milestone 2: Approval on plan 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 3 Project Execution 14 days Mon 7/9/18 Thu 7/26/18
Auto
Scheduled 3.1
Researching and finalizing best
method to develop web
application
2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.2 Project designing 4 days Mon 7/9/18 Thu 7/12/18
Auto
Scheduled 3.2.1 Back end designing
(database) 2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.2.2 Front end designing 4 days Mon 7/9/18 Thu 7/12/18
Auto
Scheduled 3.3 Project development 5 days Mon 7/9/18 Fri 7/13/18
Auto
Scheduled 3.3.1 Developing database 3 days Mon 7/9/18 Wed 7/11/18
Auto
Scheduled 3.3.2 Developing website 5 days Mon 7/9/18 Fri 7/13/18
Auto
Scheduled 3.4 Website installation 2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.5 Webserver installation 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.6 Intranet Installation 2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.7 Testing (front end and back
end) 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.8 Intranet testing 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.9 Bug fixing and testing 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.10 Milestone 3: Implementation 14 days Mon 7/9/18 Thu 7/26/18
Auto
Scheduled 3.11
Updating every information
regarding research through
intranet login
4 days Mon 7/9/18 Thu 7/12/18
Auto
Scheduled 2.10 Estimating software
requirement 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.11 Preparing schedule 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.12 Assigning tasks to members 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 2.13 Estimating budget 5 days Tue 6/26/18 Mon 7/2/18
Auto
Scheduled 2.14 Submission of project plan 4 days Tue 6/26/18 Fri 6/29/18
Auto
Scheduled 2.15 Milestone 2: Approval on plan 2 days Tue 6/26/18 Wed 6/27/18
Auto
Scheduled 3 Project Execution 14 days Mon 7/9/18 Thu 7/26/18
Auto
Scheduled 3.1
Researching and finalizing best
method to develop web
application
2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.2 Project designing 4 days Mon 7/9/18 Thu 7/12/18
Auto
Scheduled 3.2.1 Back end designing
(database) 2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.2.2 Front end designing 4 days Mon 7/9/18 Thu 7/12/18
Auto
Scheduled 3.3 Project development 5 days Mon 7/9/18 Fri 7/13/18
Auto
Scheduled 3.3.1 Developing database 3 days Mon 7/9/18 Wed 7/11/18
Auto
Scheduled 3.3.2 Developing website 5 days Mon 7/9/18 Fri 7/13/18
Auto
Scheduled 3.4 Website installation 2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.5 Webserver installation 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.6 Intranet Installation 2 days Mon 7/9/18 Tue 7/10/18
Auto
Scheduled 3.7 Testing (front end and back
end) 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.8 Intranet testing 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.9 Bug fixing and testing 1 day Mon 7/9/18 Mon 7/9/18
Auto
Scheduled 3.10 Milestone 3: Implementation 14 days Mon 7/9/18 Thu 7/26/18
Auto
Scheduled 3.11
Updating every information
regarding research through
intranet login
4 days Mon 7/9/18 Thu 7/12/18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6ICT PROJECT MANAGEMENT
Auto
Scheduled 3.12 Training researchers 5 days Mon 7/9/18 Fri 7/13/18
Auto
Scheduled 3.13 Upgrading information about
events within websites 3 days Mon 7/9/18 Wed 7/11/18
Auto
Scheduled 4 Project Closing 4 days Fri 7/27/18 Wed 8/1/18
Auto
Scheduled 4.1 Summary on result of project 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.2 Presentation 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.3 Documentation 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.4 User manual 4 days Fri 7/27/18 Wed 8/1/18
Auto
Scheduled 4.5 Preparing final project report 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.6 Report development on
lessons learned 4 days Fri 7/27/18 Wed 8/1/18
Auto
Scheduled 4.7 Conducting closure meeting 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.8 Milestone 4: Project
completion 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 3.12 Training researchers 5 days Mon 7/9/18 Fri 7/13/18
Auto
Scheduled 3.13 Upgrading information about
events within websites 3 days Mon 7/9/18 Wed 7/11/18
Auto
Scheduled 4 Project Closing 4 days Fri 7/27/18 Wed 8/1/18
Auto
Scheduled 4.1 Summary on result of project 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.2 Presentation 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.3 Documentation 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.4 User manual 4 days Fri 7/27/18 Wed 8/1/18
Auto
Scheduled 4.5 Preparing final project report 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.6 Report development on
lessons learned 4 days Fri 7/27/18 Wed 8/1/18
Auto
Scheduled 4.7 Conducting closure meeting 2 days Fri 7/27/18 Mon 7/30/18
Auto
Scheduled 4.8 Milestone 4: Project
completion 2 days Fri 7/27/18 Mon 7/30/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7ICT PROJECT MANAGEMENT
Figure 1: “Gantt Chart as per the Measurable Organizational Value of Globex”
(Source: Created by Author)
Figure 1: “Gantt Chart as per the Measurable Organizational Value of Globex”
(Source: Created by Author)

8ICT PROJECT MANAGEMENT
Figure 2: “Work breakdown structure as per the Measurable Organizational Value of Globex”
(Source: Created by Author)
It must be noted that the working days us 5 days per week
The working hours are 8 hours per day.
Therefore, total hours of works done per month= (5*8)*4= 160 hours
Total hours of work per year= (160*365) = 58400$
Total cost every year= (650*58400)$ = 37960000$
3. Scope and Scope Management Plan:
The scope of the project is the part of planning that incorporates documenting and
determining particular costs, deadlines, tasks, functions, features, deliverable and goals. The scope
management is developed to include separate scopes to answer various queries. This includes the
way in which the scope of achieved, tools needed to accomplish the scope, enterprise environmental
factors needed to accomplish the scope and needed organisational resources. Lastly, it must
Figure 2: “Work breakdown structure as per the Measurable Organizational Value of Globex”
(Source: Created by Author)
It must be noted that the working days us 5 days per week
The working hours are 8 hours per day.
Therefore, total hours of works done per month= (5*8)*4= 160 hours
Total hours of work per year= (160*365) = 58400$
Total cost every year= (650*58400)$ = 37960000$
3. Scope and Scope Management Plan:
The scope of the project is the part of planning that incorporates documenting and
determining particular costs, deadlines, tasks, functions, features, deliverable and goals. The scope
management is developed to include separate scopes to answer various queries. This includes the
way in which the scope of achieved, tools needed to accomplish the scope, enterprise environmental
factors needed to accomplish the scope and needed organisational resources. Lastly, it must
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9ICT PROJECT MANAGEMENT
determine who the scope gets controlled and manages the project. As Globex’s project gets
completed, the project manager can get enough time to decide how the scope is controlled and
executed. At this place, the decisions become the part of scope management plan.
Task
Mode
WBS Task Name Duration Start Finish Predecessors
Auto
Schedule
d
0
Scope Management Plan
for agricultural solutions
for Globex Corporation
44 days Mon 9/3/18 Thu 11/1/18
Auto
Schedule
d
1
Finding people and
personnel needed for this
project
2 days Mon 9/3/18 Tue 9/4/18
Auto
Schedule
d
2
Determining software,
network and hardware
needs supporting clients
and Globex’s project team
12 days Wed 9/5/18 Thu 9/20/18 1
Auto
Schedule
d
3
Finding facilities and
places where most of the
teamwork is to be done
5 days Fri 9/21/18 Thu 9/27/18 2
Auto
Schedule
d
4
Travelling for product
promotion
10 days Fri 9/28/18 Thu 10/11/18 3
determine who the scope gets controlled and manages the project. As Globex’s project gets
completed, the project manager can get enough time to decide how the scope is controlled and
executed. At this place, the decisions become the part of scope management plan.
Task
Mode
WBS Task Name Duration Start Finish Predecessors
Auto
Schedule
d
0
Scope Management Plan
for agricultural solutions
for Globex Corporation
44 days Mon 9/3/18 Thu 11/1/18
Auto
Schedule
d
1
Finding people and
personnel needed for this
project
2 days Mon 9/3/18 Tue 9/4/18
Auto
Schedule
d
2
Determining software,
network and hardware
needs supporting clients
and Globex’s project team
12 days Wed 9/5/18 Thu 9/20/18 1
Auto
Schedule
d
3
Finding facilities and
places where most of the
teamwork is to be done
5 days Fri 9/21/18 Thu 9/27/18 2
Auto
Schedule
d
4
Travelling for product
promotion
10 days Fri 9/28/18 Thu 10/11/18 3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10ICT PROJECT MANAGEMENT
Auto
Schedule
d
5 Training to employees 15 days Fri 10/12/18 Thu 11/1/18 4
Figure 3: “Gantt Chart for Scope Management Plan of the current Case study”
(Source: Created by Author)
4. Schedule using Schedule using a high level Work Breakdown Structure
(WBS):
Task
Mode
WBS Task Name Duration Start Finish Predecessors
Auto
Scheduled
0 Research on achieving
agricultural solutions for
85 days Fri 6/1/18 Thu 9/27/18
Auto
Schedule
d
5 Training to employees 15 days Fri 10/12/18 Thu 11/1/18 4
Figure 3: “Gantt Chart for Scope Management Plan of the current Case study”
(Source: Created by Author)
4. Schedule using Schedule using a high level Work Breakdown Structure
(WBS):
Task
Mode
WBS Task Name Duration Start Finish Predecessors
Auto
Scheduled
0 Research on achieving
agricultural solutions for
85 days Fri 6/1/18 Thu 9/27/18

11ICT PROJECT MANAGEMENT
Globex Corporation
Auto
Scheduled
1
Conducting project
meetings
3 days Fri 6/1/18 Tue 6/5/18
Auto
Scheduled
2 Workshop with clients 9 days Wed 6/6/18 Mon 6/18/18 1
Auto
Scheduled
3 Reporting to community 3 days Thu 6/21/18 Mon 6/25/18 2
Auto
Scheduled
4 Quality checks 7 days Tue 6/26/18 Wed 7/4/18 3
Auto
Scheduled
5 Research Planning 5 days Thu 7/5/18 Wed 7/11/18 4
Auto
Scheduled
6 Survey preparation 4 days Thu 7/12/18 Tue 7/17/18 5
Auto
Scheduled
7 Data analysis 5 days
Wed
7/18/18
Tue 7/24/18 6
Auto
Scheduled
8
Targeting user
segmentation
4 days
Wed
7/25/18
Mon 7/30/18 7
Auto
Scheduled
9 Re-segmentation 2 days Tue 7/31/18 Wed 8/1/18 8
Auto 10 Prototype development 6 days Thu 8/2/18 Thu 8/9/18 9
Globex Corporation
Auto
Scheduled
1
Conducting project
meetings
3 days Fri 6/1/18 Tue 6/5/18
Auto
Scheduled
2 Workshop with clients 9 days Wed 6/6/18 Mon 6/18/18 1
Auto
Scheduled
3 Reporting to community 3 days Thu 6/21/18 Mon 6/25/18 2
Auto
Scheduled
4 Quality checks 7 days Tue 6/26/18 Wed 7/4/18 3
Auto
Scheduled
5 Research Planning 5 days Thu 7/5/18 Wed 7/11/18 4
Auto
Scheduled
6 Survey preparation 4 days Thu 7/12/18 Tue 7/17/18 5
Auto
Scheduled
7 Data analysis 5 days
Wed
7/18/18
Tue 7/24/18 6
Auto
Scheduled
8
Targeting user
segmentation
4 days
Wed
7/25/18
Mon 7/30/18 7
Auto
Scheduled
9 Re-segmentation 2 days Tue 7/31/18 Wed 8/1/18 8
Auto 10 Prototype development 6 days Thu 8/2/18 Thu 8/9/18 9
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.