CIS 5800: Developing a WBS in Microsoft Project - Individual Exercise

Verified

Added on  2019/09/26

|2
|330
|62
Project
AI Summary
This assignment requires students to utilize Microsoft Project to develop a Work Breakdown Structure (WBS) for a selected project, such as replacing computer lab desktops or setting up a wireless network. The assignment involves creating summary tasks and subtasks, defining task durations, setting up dependencies, and managing resources. Students must create a project plan that includes cost estimates for staff, hardware, and software, and submit the project plan with specific columns such as Duration, Start and Finish Dates, Predecessors, Successors, Resource Names, and Cost. The assignment assesses the student's ability to create a WBS, manage project schedules and resources, and estimate project costs. The solution is available on Desklib, a platform providing AI-based study tools and resources for students.
Document Page
Individual Exercise 2: Using Microsoft Project – Appendix A of the Textbook
Objective:
Develop hands-on experience using MS Project to create a Work Breakdown Structure (WBS)
Assignment Guidelines:
Using the textbook, Appendix A, with the following sections, as a guide,
o Creating a New File and Entering Tasks in a Work Breakdown Structure
o Developing the Schedule
o Project Cost and Resource Management
Select from one of the following projects, and identify the summary and subtasks for the project:
o Replacing 15 desktops in the school’s Computer Lab
o Setting up a wireless network in a Coffee Shop
o Developing a stand-alone business software
Create a Work Breakdown Structure in Microsoft Project with:
o Summary Tasks (Level 2 items), organized by one of the following:
SDLC
Project Management Process Groups
Project Products (Deliverables)
o Subtasks (Level 3 items)
o Numbered Tasks
Develop a Schedule
o Enter Task Durations with Start and Finish Dates
o Dependencies (Predecessors and Successors), if any
o A new Calendar with four human resources
o Assign a Resource to the summary tasks or subtasks
Project Cost and Resource Management for each human resource
Enter cost estimates for staff, and any hardware and software in the WBS
Submit the MS Project Plan in Blackboard, with the following columns:
o Duration, Start and Finish Dates, Predecessors, and Successors
o Include the Resource Names and Cost columns
o You are not required to print/hand-in the Gantt Chart for this assignment
General Guidelines:
This is an individual exercise
Each student is to do and submit your own work
Submissions after due date/time are considered late
CIS 5800 – Prof. Brown 1
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Grading Considerations:
The Individual Assignment will be reviewed based on, but not limited to the following:
The MS Project Plan
o Meets or exceeds the Assignment Guidelines
o Is correct, and relevant
The completed assignment is submitted within the due date/time
CIS 5800 – Prof. Brown 2
chevron_up_icon
1 out of 2
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]