INFO843: Individual Project Schedule and Resources for a Project

Verified

Added on  2023/01/05

|5
|457
|30
Project
AI Summary
This assignment is a project schedule and resource management plan for INFO843 at Macquarie University. The project involves creating a detailed schedule with task dependencies, start and finish dates, durations, and assigned resources (designers and programmers) for various project activities. The schedule spans from April 2019 to October 2019 and includes milestones. It also provides a critical summary of the project, highlighting important aspects. The student utilized Microsoft Project to create the schedule. This project aims to demonstrate the ability to plan, schedule, and manage resources effectively in a project environment. The assignment also includes a brief overview of the project, the software used and the importance of individual effort.
Document Page
2
Start: 18-04-19 ID: 2
Finish: 01-05-19 Dur: 2 wks
Res: Designer 4, Programmer 4
3
Start: 18-04-19 ID: 3
Finish: 24-04-19 Dur: 1 wk
Res: Programmer 5
4
Start: 18-04-19 ID: 4
Finish: 01-05-19 Dur: 2 wks
Res: Designer 5
5
Start: 18-04-19 ID: 5
Finish: 01-05-19 Dur: 2 wks
Res: Programmer 6, Programmer 7, Designer 6
1
Start: 11-04-19 ID: 1
Finish: 17-04-19 Dur: 1 wk
Res: Designer 1, Designer 2, Designer 3, Programmer 1, Programmer 2, Programmer 3
Page 1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
6
Start: 02-05-19 ID: 6
Finish: 22-05-19 Dur: 3 wks
Res: Designer 7, Programmer 8
7
Start: 23-05-19 ID: 7
Finish: 10-07-19 Dur: 7 wks
Res: Designer 1, Designer 2
8
Start: 02-05-19 ID: 8
Finish: 15-05-19 Dur: 2 wks
Res: Programmer 1
9
Start: 02-05-19 ID: 9
Finish: 29-05-19 Dur: 4 wks
Res: Programmer 2
10
Start: 02-05-19 ID: 10
Finish: 12-06-19 Dur: 6 wks
Res: Designer 3
13
Start: 13-06-19 ID: 13
Finish: 03-07-19 Dur: 3 wks
Res: Programmer 6, Designer 4, Designer 5
12
Start: 30-05-19 ID: 12
Finish: 05-06-19 Dur: 1 wk
Res: Designer 4, Programmer 5
Page 2
Document Page
11
Start: 11-07-19 ID: 11
Finish: 17-07-19 Dur: 1 wk
Res: Programmer 3, Programmer 4
14
Start: 18-07-19 ID: 14
Finish: 31-07-19 Dur: 2 wks
Res: Programmer 7, Programmer 8
15
Start: 06-06-19 ID: 15
Finish: 26-06-19 Dur: 3 wks
Res: Designer 6
16
Start: 04-07-19 ID: 16
Finish: 31-07-19 Dur: 4 wks
Res: Designer 7, Programmer 1
18
Start: 01-08-19 ID: 18
Finish: 04-09-19 Dur: 5 wks
Res: Programmer 2
Page 3
Document Page
17
Start: 01-08-19 ID: 17
Finish: 21-08-19 Dur: 3 wks
Res: Designer 1, Designer 2
19
Start: 05-09-19 ID: 19
Finish: 02-10-19 Dur: 4 wks
Res: Designer 3, Programmer 3
20
Start: 03-10-19 ID: 20
Finish: 16-10-19 Dur: 2 wks
Res: Designer 4, Programmer 4
Page 4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 5
Project: 1061716
Date: Tue 27-08-19