BCO344 Information Systems Project Plan for Sydney Cycle Business
VerifiedAdded on 2022/12/14
|21
|2550
|211
Project
AI Summary
This project plan outlines the development of a website and mobile application for Sydney Cycle and Bike Selling. The project aims to enhance business operations, reduce manual errors, and expand the company's reach through e-commerce. The plan includes a comprehensive business scenario, identifying the problems with the current retail store operations and proposing online solutions. The project management section details the tasks, timelines, resource allocation, and team roles using a waterfall approach, and the estimated budget and required resources. The deliverables include hardware and software installation, website and application development, testing, and project closing activities. The project is expected to be completed within 138 working days with a budget of $220,000. The team will consist of Amandeep Singh, Lovedeep Singh and Karanvir Singh.

Running Head: INFORMATION SYSTEM PROJECT MANAGEMENT
Information Systems Project BCO344
Name of the Student
Name of the University
Information Systems Project BCO344
Name of the Student
Name of the University
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1INFORMATION SYSTEM PROJECT MANAGEMENT
Table of Contents
1. Project Introduction, Aim and Expectation.................................................................................2
2. Comprehensive Business Scenario and Client Information........................................................2
3. Project Management....................................................................................................................4
A. Tasks.......................................................................................................................................4
B. Timelines, Resources, Teams and Roles.................................................................................6
C. Approaches............................................................................................................................14
D. Deliverables..........................................................................................................................15
Bibliography..................................................................................................................................16
Appendix: MS Project Screenshots...............................................................................................18
Table of Contents
1. Project Introduction, Aim and Expectation.................................................................................2
2. Comprehensive Business Scenario and Client Information........................................................2
3. Project Management....................................................................................................................4
A. Tasks.......................................................................................................................................4
B. Timelines, Resources, Teams and Roles.................................................................................6
C. Approaches............................................................................................................................14
D. Deliverables..........................................................................................................................15
Bibliography..................................................................................................................................16
Appendix: MS Project Screenshots...............................................................................................18

2INFORMATION SYSTEM PROJECT MANAGEMENT
1. Project Introduction, Aim and Expectation
This project is based on the development of a website and mobile application for Sydney
Cycle and Bike Selling that will enable them to enhance the business operations and reduce the
need for error-prone manual work.
The primary aim of the project is to deliver an internet based solution for the company so
that they are able to conduct their business operations online and also be able to reach more
customers without the customers having to visit the store. The website and the application will
also allow the company to enter the ecommerce market and sell products online, which is much
more efficient, effective and less time consuming than the retail sales.
It is expected that the project will be completed within 138 working days and an
estimated budget of $220,000.
2. Comprehensive Business Scenario and Client Information
Sydney Cycle and Bike Selling sells bikes and cycles to the customers through their retail
store. In the store, the customers come and try the bikes, select one for purchase, pay the amount,
receive the handmade bill and the bike and they leave from the store. The main business problem
in this scenario is that often various errors are generated during the making and recording of the
handmade bills. As a result, keeping accurate track of the expenses / income from the sales
becomes very difficult for the company. Another major business problem is that due to the slow
pace of the sales, the store often gets occupied by a number of customers and other potential
customers do not want to enter the shop and choose a different store resulting in loss of a
potential market.
1. Project Introduction, Aim and Expectation
This project is based on the development of a website and mobile application for Sydney
Cycle and Bike Selling that will enable them to enhance the business operations and reduce the
need for error-prone manual work.
The primary aim of the project is to deliver an internet based solution for the company so
that they are able to conduct their business operations online and also be able to reach more
customers without the customers having to visit the store. The website and the application will
also allow the company to enter the ecommerce market and sell products online, which is much
more efficient, effective and less time consuming than the retail sales.
It is expected that the project will be completed within 138 working days and an
estimated budget of $220,000.
2. Comprehensive Business Scenario and Client Information
Sydney Cycle and Bike Selling sells bikes and cycles to the customers through their retail
store. In the store, the customers come and try the bikes, select one for purchase, pay the amount,
receive the handmade bill and the bike and they leave from the store. The main business problem
in this scenario is that often various errors are generated during the making and recording of the
handmade bills. As a result, keeping accurate track of the expenses / income from the sales
becomes very difficult for the company. Another major business problem is that due to the slow
pace of the sales, the store often gets occupied by a number of customers and other potential
customers do not want to enter the shop and choose a different store resulting in loss of a
potential market.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3INFORMATION SYSTEM PROJECT MANAGEMENT
Both these problems can be solved by the proposed website and application if they have
the following functionalities.
Online business portal for the company
Online portal where the customers can open their profile and view the bikes sold
by the company
A suitable interface with specific buttons for home page, products page, purchase
page, online payment page and others
Based on the functionalities, the architecture diagram for the proposed system is as
follows.
Figure 1: System Architecture Diagram
Both these problems can be solved by the proposed website and application if they have
the following functionalities.
Online business portal for the company
Online portal where the customers can open their profile and view the bikes sold
by the company
A suitable interface with specific buttons for home page, products page, purchase
page, online payment page and others
Based on the functionalities, the architecture diagram for the proposed system is as
follows.
Figure 1: System Architecture Diagram
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4INFORMATION SYSTEM PROJECT MANAGEMENT
(Source: Created by Author)
3. Project Management
A. Tasks
The tasks in the project are shown in the following table.
WBS Task Name
0 Development of Website and Application for Sydney Cycle and Bike
1 Project Planning
1.1 Identify Business Problems
1.2 Identify the Impact of the Problems and How They Can be Solved
1.3 Discuss and Determine Website and Application as the Solution
1.4 Discuss About the Functionalities of the Website
1.5 Receive Approval to Proceed with the Project
2 Project Initiation
2.1 Assign Roles to Project Team Members
2.2 Develop Final Project Plan
2.3 Estimate Time Required for the Project
2.4 Estimate Budget Requirements of the Project
2.5 Identify Risks Associated with the Project
2.6 Prepare Management Plan for the Risks
2.7 Budget Allocation to Team
2.8 Recruit Development Team
2.9 Procure Resources
2.10 Discuss the Final Requirements with the Development Team
(Source: Created by Author)
3. Project Management
A. Tasks
The tasks in the project are shown in the following table.
WBS Task Name
0 Development of Website and Application for Sydney Cycle and Bike
1 Project Planning
1.1 Identify Business Problems
1.2 Identify the Impact of the Problems and How They Can be Solved
1.3 Discuss and Determine Website and Application as the Solution
1.4 Discuss About the Functionalities of the Website
1.5 Receive Approval to Proceed with the Project
2 Project Initiation
2.1 Assign Roles to Project Team Members
2.2 Develop Final Project Plan
2.3 Estimate Time Required for the Project
2.4 Estimate Budget Requirements of the Project
2.5 Identify Risks Associated with the Project
2.6 Prepare Management Plan for the Risks
2.7 Budget Allocation to Team
2.8 Recruit Development Team
2.9 Procure Resources
2.10 Discuss the Final Requirements with the Development Team

5INFORMATION SYSTEM PROJECT MANAGEMENT
3 Project Execution
3.1 Hardware Installation
3.1.1 Buy Computer and Other Relevant Hardware
3.1.2 Set Up Server
3.1.3 Install Hardware and Connect with Server
3.1.4 Conduct Testing of the Hardware
3.2 Software Installation
3.2.1 Purchase Software
3.2.2 Install the Software
3.2.3 Test Working of the Software
3.3 Website Development
3.3.1 Develop Website with All Features
3.3.2 Coding
3.3.3 Testing of the Website
3.4 Application Development
3.4.1 Develop Application with All Required Features
3.4.2 Testing of the Application
3.5 Website and Application Testing
3.6 Install Security System and Firewall
3.7 Remove Bugs from the Application
3.8 Go Live
4 Project Closing
4.1 Project Appraisal and Review
4.2 Project Documentation
3 Project Execution
3.1 Hardware Installation
3.1.1 Buy Computer and Other Relevant Hardware
3.1.2 Set Up Server
3.1.3 Install Hardware and Connect with Server
3.1.4 Conduct Testing of the Hardware
3.2 Software Installation
3.2.1 Purchase Software
3.2.2 Install the Software
3.2.3 Test Working of the Software
3.3 Website Development
3.3.1 Develop Website with All Features
3.3.2 Coding
3.3.3 Testing of the Website
3.4 Application Development
3.4.1 Develop Application with All Required Features
3.4.2 Testing of the Application
3.5 Website and Application Testing
3.6 Install Security System and Firewall
3.7 Remove Bugs from the Application
3.8 Go Live
4 Project Closing
4.1 Project Appraisal and Review
4.2 Project Documentation
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6INFORMATION SYSTEM PROJECT MANAGEMENT
4.3 Stakeholder Sign Off
B. Timelines, Resources, Teams and Roles
The timeline for the project is shown in the following table.
WBS Task Name Duration Start Finish Predecessors
0
Development of Website and
Application for Sydney Cycle and
Bike
138 days Tue 5/7/19 Thu
11/14/19
1 Project Planning 12 days Tue 5/7/19 Wed
5/22/19
1.1 Identify Business Problems 2 days Tue 5/7/19 Wed
5/8/19
1.2
Identify the Impact of the
Problems and How They Can be
Solved
3 days Thu 5/9/19 Mon
5/13/19 2
1.3 Discuss and Determine Website
and Application as the Solution 2 days Tue
5/14/19
Wed
5/15/19 3
1.4 Discuss About the
Functionalities of the Website 3 days Thu
5/16/19
Mon
5/20/19 4
1.5 Receive Approval to Proceed
with the Project 2 days Tue
5/21/19
Wed
5/22/19 5
2 Project Initiation 34 days Thu
5/23/19 Tue 7/9/19
2.1 Assign Roles to Project Team
Members 3 days Thu
5/23/19
Mon
5/27/19 6
2.2 Develop Final Project Plan 6 days Tue
5/28/19 Tue 6/4/19 8
2.3 Estimate Time Required for the
Project 2 days Wed
6/5/19 Thu 6/6/19 9
2.4 Estimate Budget Requirements 2 days Fri 6/7/19 Mon 10
4.3 Stakeholder Sign Off
B. Timelines, Resources, Teams and Roles
The timeline for the project is shown in the following table.
WBS Task Name Duration Start Finish Predecessors
0
Development of Website and
Application for Sydney Cycle and
Bike
138 days Tue 5/7/19 Thu
11/14/19
1 Project Planning 12 days Tue 5/7/19 Wed
5/22/19
1.1 Identify Business Problems 2 days Tue 5/7/19 Wed
5/8/19
1.2
Identify the Impact of the
Problems and How They Can be
Solved
3 days Thu 5/9/19 Mon
5/13/19 2
1.3 Discuss and Determine Website
and Application as the Solution 2 days Tue
5/14/19
Wed
5/15/19 3
1.4 Discuss About the
Functionalities of the Website 3 days Thu
5/16/19
Mon
5/20/19 4
1.5 Receive Approval to Proceed
with the Project 2 days Tue
5/21/19
Wed
5/22/19 5
2 Project Initiation 34 days Thu
5/23/19 Tue 7/9/19
2.1 Assign Roles to Project Team
Members 3 days Thu
5/23/19
Mon
5/27/19 6
2.2 Develop Final Project Plan 6 days Tue
5/28/19 Tue 6/4/19 8
2.3 Estimate Time Required for the
Project 2 days Wed
6/5/19 Thu 6/6/19 9
2.4 Estimate Budget Requirements 2 days Fri 6/7/19 Mon 10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7INFORMATION SYSTEM PROJECT MANAGEMENT
of the Project 6/10/19
2.5 Identify Risks Associated with
the Project 3 days Tue
6/11/19
Thu
6/13/19 11
2.6 Prepare Management Plan for
the Risks 4 days Fri 6/14/19 Wed
6/19/19 12
2.7 Budget Allocation to Team 3 days Thu
6/20/19
Mon
6/24/19 13
2.8 Recruit Development Team 4 days Tue
6/25/19 Fri 6/28/19 14
2.9 Procure Resources 3 days Mon
7/1/19
Wed
7/3/19 15
2.10 Discuss the Final Requirements
with the Development Team 4 days Thu 7/4/19 Tue 7/9/19 16
3 Project Execution 81 days Wed
7/10/19
Wed
10/30/19
3.1 Hardware Installation 12 days Wed
7/10/19
Thu
7/25/19
3.1.1 Buy Computer and Other
Relevant Hardware 5 days Wed
7/10/19
Tue
7/16/19 17
3.1.2 Set Up Server 2 days Wed
7/17/19
Thu
7/18/19 20
3.1.3 Install Hardware and Connect
with Server 3 days Fri 7/19/19 Tue
7/23/19 21
3.1.4 Conduct Testing of the
Hardware 2 days Wed
7/24/19
Thu
7/25/19 22
3.2 Software Installation 10 days Wed
7/10/19
Tue
7/23/19
3.2.1 Purchase Software 5 days Wed
7/10/19
Tue
7/16/19 17
3.2.2 Install the Software 2 days Wed
7/17/19
Thu
7/18/19 25
3.2.3 Test Working of the Software 3 days Fri 7/19/19 Tue 26
of the Project 6/10/19
2.5 Identify Risks Associated with
the Project 3 days Tue
6/11/19
Thu
6/13/19 11
2.6 Prepare Management Plan for
the Risks 4 days Fri 6/14/19 Wed
6/19/19 12
2.7 Budget Allocation to Team 3 days Thu
6/20/19
Mon
6/24/19 13
2.8 Recruit Development Team 4 days Tue
6/25/19 Fri 6/28/19 14
2.9 Procure Resources 3 days Mon
7/1/19
Wed
7/3/19 15
2.10 Discuss the Final Requirements
with the Development Team 4 days Thu 7/4/19 Tue 7/9/19 16
3 Project Execution 81 days Wed
7/10/19
Wed
10/30/19
3.1 Hardware Installation 12 days Wed
7/10/19
Thu
7/25/19
3.1.1 Buy Computer and Other
Relevant Hardware 5 days Wed
7/10/19
Tue
7/16/19 17
3.1.2 Set Up Server 2 days Wed
7/17/19
Thu
7/18/19 20
3.1.3 Install Hardware and Connect
with Server 3 days Fri 7/19/19 Tue
7/23/19 21
3.1.4 Conduct Testing of the
Hardware 2 days Wed
7/24/19
Thu
7/25/19 22
3.2 Software Installation 10 days Wed
7/10/19
Tue
7/23/19
3.2.1 Purchase Software 5 days Wed
7/10/19
Tue
7/16/19 17
3.2.2 Install the Software 2 days Wed
7/17/19
Thu
7/18/19 25
3.2.3 Test Working of the Software 3 days Fri 7/19/19 Tue 26

8INFORMATION SYSTEM PROJECT MANAGEMENT
7/23/19
3.3 Website Development 45 days Wed
7/10/19
Tue
9/10/19
3.3.1 Develop Website with All
Features 20 days Wed
7/10/19 Tue 8/6/19 17
3.3.2 Coding 15 days Wed
8/7/19
Tue
8/27/19 29
3.3.3 Testing of the Website 10 days Wed
8/28/19
Tue
9/10/19 30
3.4 Application Development 40 days Wed
7/10/19 Tue 9/3/19
3.4.1 Develop Application with All
Required Features 25 days Wed
7/10/19
Tue
8/13/19 17
3.4.2 Testing of the Application 15 days Wed
8/14/19 Tue 9/3/19 33
3.5 Website and Application Testing 15 days Wed
9/11/19
Tue
10/1/19 23,27,31,34
3.6 Install Security System and
Firewall 10 days Wed
10/2/19
Tue
10/15/19 35
3.7 Remove Bugs from the
Application 10 days Wed
10/16/19
Tue
10/29/19 36
3.8 Go Live 1 day Wed
10/30/19
Wed
10/30/19 37
4 Project Closing 11 days Thu
10/31/19
Thu
11/14/19
4.1 Project Appraisal and Review 4 days Thu
10/31/19
Tue
11/5/19 38
4.2 Project Documentation 6 days Wed
11/6/19
Wed
11/13/19 40
4.3 Stakeholder Sign Off 1 day Thu
11/14/19
Thu
11/14/19 41
The resources required for the project are shown in the following table.
7/23/19
3.3 Website Development 45 days Wed
7/10/19
Tue
9/10/19
3.3.1 Develop Website with All
Features 20 days Wed
7/10/19 Tue 8/6/19 17
3.3.2 Coding 15 days Wed
8/7/19
Tue
8/27/19 29
3.3.3 Testing of the Website 10 days Wed
8/28/19
Tue
9/10/19 30
3.4 Application Development 40 days Wed
7/10/19 Tue 9/3/19
3.4.1 Develop Application with All
Required Features 25 days Wed
7/10/19
Tue
8/13/19 17
3.4.2 Testing of the Application 15 days Wed
8/14/19 Tue 9/3/19 33
3.5 Website and Application Testing 15 days Wed
9/11/19
Tue
10/1/19 23,27,31,34
3.6 Install Security System and
Firewall 10 days Wed
10/2/19
Tue
10/15/19 35
3.7 Remove Bugs from the
Application 10 days Wed
10/16/19
Tue
10/29/19 36
3.8 Go Live 1 day Wed
10/30/19
Wed
10/30/19 37
4 Project Closing 11 days Thu
10/31/19
Thu
11/14/19
4.1 Project Appraisal and Review 4 days Thu
10/31/19
Tue
11/5/19 38
4.2 Project Documentation 6 days Wed
11/6/19
Wed
11/13/19 40
4.3 Stakeholder Sign Off 1 day Thu
11/14/19
Thu
11/14/19 41
The resources required for the project are shown in the following table.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9INFORMATION SYSTEM PROJECT MANAGEMENT
Resource Name Type Max. Units Std. Rate
Project Manager Work 100% $ 175.00/hr
IT Supervisor Work 100% $ 135.00/hr
Hardware Specialist Work 100% $ 75.00/hr
Website Developer Work 100% $ 115.00/hr
Application Developer Work 100% $ 120.00/hr
Hardware Material $ 10,000.00
Software Material $ 5,000.00
Software Subscriptions and
Security Software
Material $ 5,000.00
These resources are then allocated to the activities in the work breakdown structure to
determine the total project costs as follows.
WBS Task Name Duration
Predecessor
s
Resource Names Cost
0
Development of
Website and
Application for Sydney
Cycle and Bike
138 days $ 218,800.00
Resource Name Type Max. Units Std. Rate
Project Manager Work 100% $ 175.00/hr
IT Supervisor Work 100% $ 135.00/hr
Hardware Specialist Work 100% $ 75.00/hr
Website Developer Work 100% $ 115.00/hr
Application Developer Work 100% $ 120.00/hr
Hardware Material $ 10,000.00
Software Material $ 5,000.00
Software Subscriptions and
Security Software
Material $ 5,000.00
These resources are then allocated to the activities in the work breakdown structure to
determine the total project costs as follows.
WBS Task Name Duration
Predecessor
s
Resource Names Cost
0
Development of
Website and
Application for Sydney
Cycle and Bike
138 days $ 218,800.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10INFORMATION SYSTEM PROJECT MANAGEMENT
1 Project Planning 12 days $ 16,800.00
1.1
Identify Business
Problems
2 days Project Manager $ 2,800.00
1.2
Identify the Impact
of the Problems and
How They Can be
Solved
3 days 2 Project Manager $ 4,200.00
1.3
Discuss and
Determine Website and
Application as the
Solution
2 days 3 Project Manager $ 2,800.00
1.4
Discuss About the
Functionalities of the
Website
3 days 4 Project Manager $ 4,200.00
1.5
Receive Approval to
Proceed with the Project
2 days 5 Project Manager $ 2,800.00
2 Project Initiation 34 days $ 36,720.00
2.1
Assign Roles to
Project Team Members
3 days 6 IT Supervisor $ 3,240.00
1 Project Planning 12 days $ 16,800.00
1.1
Identify Business
Problems
2 days Project Manager $ 2,800.00
1.2
Identify the Impact
of the Problems and
How They Can be
Solved
3 days 2 Project Manager $ 4,200.00
1.3
Discuss and
Determine Website and
Application as the
Solution
2 days 3 Project Manager $ 2,800.00
1.4
Discuss About the
Functionalities of the
Website
3 days 4 Project Manager $ 4,200.00
1.5
Receive Approval to
Proceed with the Project
2 days 5 Project Manager $ 2,800.00
2 Project Initiation 34 days $ 36,720.00
2.1
Assign Roles to
Project Team Members
3 days 6 IT Supervisor $ 3,240.00

11INFORMATION SYSTEM PROJECT MANAGEMENT
2.2
Develop Final
Project Plan
6 days 8 IT Supervisor $ 6,480.00
2.3
Estimate Time
Required for the Project
2 days 9 IT Supervisor $ 2,160.00
2.4
Estimate Budget
Requirements of the
Project
2 days 10 IT Supervisor $ 2,160.00
2.5
Identify Risks
Associated with the
Project
3 days 11 IT Supervisor $ 3,240.00
2.6
Prepare
Management Plan for
the Risks
4 days 12 IT Supervisor $ 4,320.00
2.7
Budget Allocation to
Team
3 days 13 IT Supervisor $ 3,240.00
2.8
Recruit
Development Team
4 days 14 IT Supervisor $ 4,320.00
2.9 Procure Resources 3 days 15 IT Supervisor $ 3,240.00
2.10 Discuss the Final
Requirements with the
4 days 16 IT Supervisor $ 4,320.00
2.2
Develop Final
Project Plan
6 days 8 IT Supervisor $ 6,480.00
2.3
Estimate Time
Required for the Project
2 days 9 IT Supervisor $ 2,160.00
2.4
Estimate Budget
Requirements of the
Project
2 days 10 IT Supervisor $ 2,160.00
2.5
Identify Risks
Associated with the
Project
3 days 11 IT Supervisor $ 3,240.00
2.6
Prepare
Management Plan for
the Risks
4 days 12 IT Supervisor $ 4,320.00
2.7
Budget Allocation to
Team
3 days 13 IT Supervisor $ 3,240.00
2.8
Recruit
Development Team
4 days 14 IT Supervisor $ 4,320.00
2.9 Procure Resources 3 days 15 IT Supervisor $ 3,240.00
2.10 Discuss the Final
Requirements with the
4 days 16 IT Supervisor $ 4,320.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 21
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.