International Project Management: Solar Plant Development Project

Verified

Added on  2023/06/14

|10
|1398
|414
Project
AI Summary
This document presents a project management plan for the Alternative Technology Association Company's solar plant development project in East Timor. It includes an executive summary, project description, and detailed plans for risk management, contracting, project control, occupational health and safety, quality assurance, document control, relationship management, knowledge management, project review, organizational structure, and project close-out. The plan identifies potential risks and mitigation strategies, outlines construction and operational activities with timelines, and emphasizes the importance of environmental standards and government policy compliance for successful project deployment. The document also highlights the need for quality equipment, ethical conduct, and effective communication throughout the project lifecycle. Desklib provides access to this and other student-contributed assignments to aid in your studies.
Document Page
International Project Management
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Contents
1. Introduction:..................................................................................................................................2
Executive Summary...........................................................................................................................2
Project Description............................................................................................................................2
2. Project Management plan..............................................................................................................2
Risk Management plan......................................................................................................................2
Contracting plan................................................................................................................................2
Project control Plan...........................................................................................................................3
Occupational, Health, safety, and Environmental Plan......................................................................4
Quality assurance Plan.......................................................................................................................4
Document control and information management plan.......................................................................4
Relationship management plan..........................................................................................................5
Knowledge management plan............................................................................................................5
Project Review Plan...........................................................................................................................5
Organizational Plan...........................................................................................................................7
Project Close out Plan........................................................................................................................7
3. Conclusion.....................................................................................................................................8
4. References.....................................................................................................................................8
Document Page
1. Introduction:
Executive Summary
The purpose of this paper is to develop a project proposal for the ATA Company to develop a
solar plant on the East Timor project location. The case study helps in studying of the
positive and negative side of the proposed project. The analysis of the risks helps in the
development of the project without any distraction from the local people of the community
area and the government agencies.
Project Description
The Alternative Technology Association Company is the small non-government organization
which has started its first solar project in 2000. The project owner wants to develop a project
execution plan framework for improving the business tactics of the plant. The purpose of this
paper is to develop a project execution plan for outlining it to the project owner.
2. Project Management plan
Risk Management plan
Risk Identification Risk Mitigation plan
Limited fund The flow of fund should be managed by
giving emphasis on the sponsorship program
(Chileshe, 2014)
Policies of the government Analysis of the government policies
Internal audit Provide training and development for the
employees
Unethical Behaviour of the employees Distraction and conflicts between the
employees should be handled
Contracting plan
Development Construction Maintenance and Operation
Analysis of the site location
Cooperation and
Development of the detailed
designing of the solar project
Monitoring of the system
Maintenance program
Document Page
coordination among the
project activities
Division of roles and
responsibilities
Development of the internal
engineering program
System Erection Program
with the support of sub-
contractors
Execution of the construction
program
Project control Plan
Activity Project Sub-Activities Start Date Finish Date
Construction
program
Supply and demand of
the water and
resources
5 April, 2018 10 April, 2018
Civil work 11 April, 2018 20 April, 2018
Development of the
control room
21 April, 2018 25 April, 2018
Construction of the
internal road and
bridges
26 April, 2018 2 May, 2018
Deployment of the
water management
system
3 May, 2018 10 May, 2018
Yard Lightening
system
11 May, 2018 21 May, 2018
Fencing program 22 May, 2018 31 May, 2018
Installation of the
generating system
Mounting structure 1 June, 2018 5 June, 2018
Erection equipment
and resources
6 June, 2018 15 June, 2018
Earthing and
Lightening
16 June, 2018 22 June, 2018
Work Load
management
23 June, 2018 30 June, 2018
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Evacuation system Supply of resources
and equipment
1 July, 2018 08 July, 2018
Installation of the
equipment
09 July, 2018 16 July, 2018
Development of the
solar plan
17 July, 2018 22 July, 2018
Testing Development of the
commission plan
23 July, 2018 28 July, 2018
Development of the
site testing plan
29 July, 2018 31 July, 2018
Evaluation of the test
plan
1 August, 2018 6 August, 2018
Project Closure Implementation 07 August, 2018 09 August, 2018
Documentation 10 August, 2018 14 August, 2018
Occupational, Health, safety, and Environmental Plan
ï‚· Good Resources and equipment should be used
ï‚· Renovation of old equipment and technology
ï‚· Training and development program for the staff
ï‚· Proper dumping mechanism for hazardous waste
ï‚· Earthing of the whole system to overcome the problem of electric shock
ï‚· Fire safety mechanism
Quality assurance Plan
The construction of the solar plant should provide the high level of reliability structure of the
plant to generate electricity. The selection of the equipment should be done on the basis of
their quality (Taylor, 2010). The operational capability of the project should be capable of
satisfying the requirement of the project owner. The solar project plan should achieve the
quality of standards in producing electricity (Gomez, 2016).
Document control and information management plan
The document of the project completion report should have the details of project justification,
key features of the proposed project, designing of the construction program, selection of the
technology, standardization of the quality of the resources and equipment, balancing the
Document Page
system, training and development program, designing of the control system, project
standards, specification of the material used, and evaluation of the testing plan (Clean energy
technology centre, 2017).
Relationship management plan
ï‚· Arrangement of meetings with project sponsors and other stakeholders periodically
(Morris, 2013)
ï‚· Review of the action plan
ï‚· Review of government policies
ï‚· Management of communication flow among the team members
Knowledge management plan
Required
knowledge
Priority Potential source Cost Suggestion
Mapping of
organizational
process and
procedures
Very High Functional
module of
quality
management
plan
Minimum Managing link
with quality
control
management
program
Benchmarking
with the process
template
Low Business module High Requirement
specification
plan analysis
Set up of the
organization
High From online and
offline sources
Low Visit to the site
location
Project Review Plan
Activities Review Schedule Status
Supply and demand of the
water and resources
Daily
Civil work Weekly
Development of the control
room
Monthly
Document Page
Construction of the internal
road and bridges
Monthly
Deployment of the water
management system
Daily
Yard Lightening system Daily
Fencing program Weekly
Mounting structure Daily
Erection equipment and
resources
Daily
Earthing and Lightening Weekly
Work Load management Monthly
Supply of resources and
equipment
Weekly
Installation of the equipment Monthly
Development of the solar
plan
Weekly
Development of the
commission plan
Weekly
Development of the site
testing plan
Monthly
Evaluation of the test plan Monthly
Implementation Once
Documentation Once
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Organizational Plan
Project Close out Plan
Category Description Status
Contract close
out
Agreement for the resources and the
equipment required
Yes
Government
close out
Analysis of the government policies (Hasan,
2014)
Yes
Ethical Code of
conduct
Inclusion of ethical code of conduct Yes
Fund approval
close out
Approval of funds from the project sponsor Yes
Construction
program close
out
Completion of the construction work Under process
Project Owner
Project ManagerContracting officer
Quality Manager Superintendent Project Sponsor Purchasing
manager
Testing manager
and inspection
team
Foreman Sub-contractors
Document Page
Testing plan
close out
Development of the testing plan Under process
Maintenance
and operation
close out
After the implementation of the project Throughout the life cycle
of the project.
3. Conclusion
The project plan helps in identifying the risk areas concern with the project deployment plan
and provides successful remedies to establish the solar plant successfully on the site location.
The environmental values and standard should be focused so that the problem of ecological
balance does not occur (Passenheim, 2015). The selection of the equipment should be done
on the basis of their quality. The study of the government policies helps in resolving the legal
and political issues which exist with the implementation schedule of the project.
4. References
Chileshe, N. (2014). Project risks analysis of solar energy project delays. Retrieved from
http://search.ror.unisa.edu.au/record/UNISA_ALMA11143270670001831/media/
digital/open/9915909479901831/12143270660001831/13143298450001831/pdf
Clean energy technology centre. (2017). Health and safety impact of solar photovoltaic.
Retrieved from https://nccleantech.ncsu.edu/wp-content/uploads/Health-and-Safety-
Impacts-of-Solar-Photovoltaics-2017_white-paper.pdf
Gomez, S. (2016). Risk Identification in large photovoltaic plants construction project.
Retrieved from
http://www.aeipro.com/files/congresos/2016cartagena/05015.4665.pdf
Hasan, P. (2014).Solar Construction safety. Retrieved from
http://www.coshnetwork.org/sites/default/files/OSEIA_Solar_Safety_12-06.pdf
Morris, P. (2013). Research and the future of project management. Retrieved from
https://www.emeraldinsight.com/doi/abs/10.1108/17538371011014080
Document Page
Passenheim, O. (2015). Project management. Retrieved from
http://home.hit.no/~hansha/documents/theses/projectmanagement.pdf
Tayor, D. (2010). Occupational health on the job with solar power plant. Retrieved from
https://www.ncbi.nlm.nih.gov/pmc/articles/PMC2831982/