This project report details the development of an IoT-based healthcare application for a healthcare center in Brisbane, Australia. The report outlines the project's benefits, including improved patient satisfaction and increased revenue, along with its objectives, which are to implement a quality-compliant application and meet project timelines and costs. The report provides a Work Breakdown Structure (WBS), a comprehensive project plan using the PMBoK and Agile methodologies, and a detailed project schedule with a Gantt chart. It covers project costs, resource allocation, and risk management strategies. The project aims to provide remote health monitoring and assistance, reducing the burden on medical professionals and enhancing the quality of patient care. The report also includes sections on change control processes and references, providing a complete overview of the project's lifecycle from initiation to closure, including user feedback and training processes.
Document Page
IoT-based Healthcare Application
Project Report
11/28/2018
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
IoT-based Healthcare Application
Table of Contents
Organization Overview..........................................................................................................................2
Project Description................................................................................................................................2
Project Benefits.................................................................................................................................2
Project Objectives..................................................................................................................................2
Project Priorities....................................................................................................................................3
Work Breakdown Structure (WBS).......................................................................................................3
Project Plan...........................................................................................................................................5
Project Approach...............................................................................................................................5
Project Scope.....................................................................................................................................5
Project Scheduling.............................................................................................................................5
Gantt chart...................................................................................................................................10
Project Costs....................................................................................................................................11
Project Resources............................................................................................................................17
Monitoring Project Performance......................................................................................................20
Project Risk Management................................................................................................................20
Change Control Process...................................................................................................................21
References...........................................................................................................................................22
1
Document Page
IoT-based Healthcare Application
Organization Overview
XYZ is a healthcare centre that is based out of Brisbane, Australia. The healthcare centre was
established in 2004 and has been able to capture excellent market share since then. The
healthcare centre comprises of 75 medical staff that comprises of doctors, nursing staff, and
assistants. The organization recently had set-up a specialized facility for the patients for
quicker treatment and diagnosis. However, there is a lot of burden on the medical
professionals associated with the medical centre with the increase in the number of patients.
The patients also experience longer waiting hours due to the same reason.
Project Description
The project that is proposed to the healthcare centre is IoT-based Healthcare Application.
Internet of Things (IoT) is a technology that inter-connects varied set of components with
each other to carry out a common goal. The application will be developed for the patients to
allow them to carry out tele-health monitoring of their health conditions. Diagnosis and
assistance will also be provided to them remotely eliminating the need to visit the healthcare
centre (Harsh, 2017). The application will allow the patients to record their health signs
which will be transferred to their respective medical professionals. The medical reports and
comments will be shared over the web platform.
Project Benefits
The project will provide following benefits to the organizations and its associated
stakeholders.
ï‚· Patient engagement and satisfaction levels will improve with the reduction in the
waiting hours.
ï‚· Medical professionals will be able to perform better with the reduction of the burden.
ï‚· Revenues will improve by 35% in the first quarter after the implementation of the
application (Dziak, Jachimczyk & Kulesza, 2017).
ï‚· The organization will be able to gain competitive edge in the market.
Project Objectives
ï‚· To implement an IoT-based healthcare application for patients and medical
professionals as per the quality and healthcare standards.
2
Document Page
IoT-based Healthcare Application
ï‚· To meet the project schedule and costs estimated for the project.
Project Priorities
ï‚· Healthcare standards as Health Insurance Portability & Accountability Act (HIPAA)
and others will be kept at the top priority to maintain the adherence levels.
ï‚· The project requirements will be kept at the top priority at the time of the execution of
project tasks.
ï‚· The customer feedback and analysis will be kept at the next priority level and the
changes will be made accordingly.
Work Breakdown Structure (WBS)
WBS Task Name
1 IoT-based Healthcare Application
1.1 Initiation & Proposal
1.1.1 Healthcare Data Collection
1.1.2 Analysis of the Data and Services
1.1.3 Highlighting of the Major Flaws and Loopholes
1.1.4 Needs Assessment
1.1.5 Project Proposal
1.1.6 Milestone 1: Project Proposal
1.2 Planning & Analysis
1.2.1 Approval on the Project
1.2.2 Planning on the Approach & Scope
1.2.3 Project Requirements Analysis - Functional, Non-
Functional, User
1.2.4 Project Areas Planning - Risks, Resources,
Stakeholders, Quality
1.2.5 Project Estimates
1.2.6 Resource Identification & Allocation
1.2.7 Milestone 2: Project Plan
1.3 Project Design & Development
1.3.1 Procurement of Gadgets & Healthcare Equipment
3
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
IoT-based Healthcare Application
1.3.2 Network Design & Architecture
1.3.3 Application Design
1.3.4 Development of the application code
1.3.5 Integration of the elements
1.3.6 Unit testing
1.3.7 Milestone 3: Integration of Elements
1.4 Implementation & Control
1.4.1 Test creation and conduction of test activities
1.4.2 Implementation at the client side
1.4.3 User Acceptance Testing
1.4.4 Audits and Change Management
1.4.5 Milestone 4: Audit Report
1.5 Closure Phase
1.5.1 User Feedback and its Analysis
1.5.2 Training Processes
1.5.3 Reflection and Lessons Acquired
1.5.4 IoT Application Documentation
1.5.5 Closure Report
1.5.6 Milestone 5: Closure Report
4
IoT-based
Healthcare
Application
Initiation &
Proposal
Healthcare Data
Collection
Analysis of the
Data and Services
Highlighting of the
Major Flaws and
Loopholes
Needs Assessment
Project Proposal
Milestone 1:
Project Proposal
Planning &
Analysis
Approval on the
Project
Planning on the
Approach & Scope
Project
Requirements
Analysis -
Functional, Non-
Functional, User
Project Areas
Planning - Risks,
Resources,
Stakeholders,
Quality
Project Estimates
Resource
Identification &
Allocation
Milestone 2:
Project Plan
Project Design &
Development
Procurement of
Gadgets &
Healthcare
Equipment
Network Design &
Architecture
Application Design
Development of
the application
code
Integration of the
elements
Unit testing
Milestone 3:
Integration of
Elements
Implementation &
Control
Test creation and
conduction of test
activities
Implementation at
the client side
User Acceptance
Testing
Audits and Change
Management
Milestone 4: Audit
Report
Closure Phase
User Feedback and
its Analysis
Training Processes
Reflection and
Lessons Acquired
IoT Application
Documentation
Closure Report
Milestone 5:
Closure Report
Document Page
IoT-based Healthcare Application
Project Plan
Project Approach
The approach that will be used to manage the project will be Project Management Body of
Knowledge (PMBoK). According to this approach, the management of the project activities
will be done in five process groups as initiation, planning, execution, control, and closure
(Cuevas, Gil, Sanchez & Hernandez, 2018). These five phases will then be applied to the
development methodology as Agile Methodology for Software Development. The
development of a web interface and the design activities will be handled using the agile
methodology. The management and the development methodologies will be integrated and
kept in sync with each other to carry out the project tasks and activities (Altameem, 2015).
Project Scope
There will be a lot of activities that will be carried out by the project resources as a part of the
project. The initiation phase shall include the healthcare data collection and its analysis to
determine the major flaws and loopholes in the existing process. Needs assessment shall be
done to identify and propose the project. The project shall be approved by the Project
Sponsor and the planning activities shall include the finalization of project approach and
scope. The requirements analysis and definition shall be done as Functional, Non-Functional,
User. The other project areas that shall be planned out shall be risks, resources, stakeholder,
quality, schedule, and budget. The resources for the project shall be tagged and shall be
allocated with their respective duties and responsibilities. Procurement of gadgets &
healthcare equipment shall be done along with network design and architecture. Application
design and the development of its code along with the integration of the elements and unit
testing shall be done (Zwikael, 2009). Test creation and conduction of test activities will be
included in the scope along with the implementation at the client side. User acceptance
testing, audits and management of the changes will be done. The final phase will be the
closure phase in which user feedback and analysis will be done followed by conduction of
training processes. Reflection and lessons acquired along with IoT application documentation
shall be done with submission of the closure report as the final activity.
Project Scheduling
The technique that is used to estimate the project schedule is Bottom-Up estimation in which
the project activities at the lowermost level in the hierarchy are estimated first followed by
the ones above.
5
Document Page
IoT-based Healthcare Application
WBS Task Name Duration Start Finish Predecessor
s
Resource
Names
1 IoT-based Healthcare
Application 188 days
Wed
28-11-
18
Fri 16-
08-19
1.1 Initiation & Proposal 31 days
Wed
28-11-
18
Wed 09-
01-19
1.1.1 Healthcare Data
Collection 8 days
Wed
28-11-
18
Fri 07-
12-18
Data Analyst ,
Healthcare
Analyst
1.1.2 Analysis of the Data
and Services 7 days
Mon
10-12-
18
Fri 28-
12-18 3
Data Analyst ,
Business
Analyst ,
Healthcare
Analyst
1.1.3
Highlighting of the
Major Flaws and
Loopholes
5 days Thu 03-
01-19
Wed 09-
01-19 3, 4 Business
Analyst
1.1.4 Needs Assessment 3 days
Mon
31-12-
18
Wed 02-
01-19 3, 4
Healthcare
Analyst ,
Business
Analyst ,
Project
Manager
1.1.5 Project Proposal 4 days Thu 03-
01-19
Tue 08-
01-19 6 Project
Manager
1.1.6 Milestone 1: Project
Proposal 0 days Tue 08-
01-19
Tue 08-
01-19 7
1.2 Planning & Analysis 60 days
Wed
09-01-
19
Tue 02-
04-19
1.2.1 Approval on the 2 days Wed Thu 10- 8 Project Sponsor
6
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
IoT-based Healthcare Application
Project 09-01-
19 01-19
1.2.2 Planning on the
Approach & Scope 4 days Fri 11-
01-19
Wed 16-
01-19 10 Project
Manager
1.2.3
Project Requirements
Analysis - Functional,
Non-Functional, User
12 days Fri 08-
02-19
Thu 07-
03-19 11
Project
Manager ,
Business
Analyst ,
Healthcare
Analyst
1.2.4
Project Areas Planning
- Risks, Resources,
Stakeholders, Quality
12 days Fri 08-
03-19
Mon 25-
03-19 12 Project
Manager
1.2.5 Project Estimates 7 days Thu 17-
01-19
Fri 25-
01-19 11 Project
Manager
1.2.6 Resource Identification
& Allocation 6 days Tue 26-
03-19
Tue 02-
04-19 14, 13 Project
Manager
1.2.7 Milestone 2: Project
Plan 0 days Tue 02-
04-19
Tue 02-
04-19 15
1.3 Project Design &
Development 81 days Thu 17-
01-19
Thu 09-
05-19
1.3.1
Procurement of
Gadgets & Healthcare
Equipment
10 days
Wed
03-04-
19
Tue 16-
04-19 16
Business
Analyst ,
Healthcare
Analyst ,
Medical Coder ,
Project
Manager
1.3.2 Network Design &
Architecture 15 days Thu 17-
01-19
Wed 06-
02-19 11 Network
Specialist
1.3.3 Application Design 15 days Thu 07-
02-19
Wed 27-
02-19 19 UI Expert
1.3.4 Development of the 25 days Thu 28- Wed 03- 20 Application
7
Document Page
IoT-based Healthcare Application
application code 02-19 04-19 Developer,
Medical Coder
1.3.5 Integration of the
elements 12 days
Wed
17-04-
19
Thu 02-
05-19 20, 18, 19
Application
Developer,
Medical Coder ,
Network
Specialist , UI
Expert
1.3.6 Unit testing 5 days Fri 03-
05-19
Thu 09-
05-19 22
Application
Developer,
Medical Coder ,
Network
Specialist , UI
Expert
1.3.7 Milestone 3:
Integration of Elements 0 days Thu 09-
05-19
Thu 09-
05-19 23
1.4 Implementation &
Control 52 days Fri 10-
05-19
Mon 22-
07-19
1.4.1 Test creation and
conduction of test activities 14 days Fri 10-
05-19
Wed 29-
05-19 24 Tester
1.4.2 Implementation at the
client side 12 days Thu 30-
05-19
Fri 14-
06-19 26
Medical Coder ,
Application
Developer
1.4.3 User Acceptance
Testing 8 days
Mon
01-07-
19
Wed 10-
07-19 27 Project Sponsor
1.4.4 Audits and Change
Management
8 days Thu 11-
07-19
Mon 22-
07-19
28 Application
Developer,
Business
Analyst , Data
Analyst ,
Healthcare
Analyst ,
8
Document Page
IoT-based Healthcare Application
Medical Coder ,
Network
Specialist ,
Project
Manager , UI
Expert
1.4.5 Milestone 4: Audit
Report 0 days
Mon
22-07-
19
Mon 22-
07-19 29
1.5 Closure Phase 45 days
Mon
17-06-
19
Fri 16-
08-19
1.5.1 User Feedback and its
Analysis 6 days
Mon
17-06-
19
Mon 24-
06-19 27
Project
Manager ,
Project Sponsor
1.5.2 Training Processes 8 days Tue 23-
07-19
Thu 01-
08-19 29 Trainer
1.5.3 Reflection and Lessons
Acquired 5 days Tue 23-
07-19
Mon 29-
07-19 30
Medical Coder ,
Application
Developer,
Business
Analyst , Data
Analyst ,
Healthcare
Analyst ,
Network
Specialist ,
Project
Manager ,
Technical
Writer , Tester,
UI Expert
1.5.4 IoT Application 7 days Tue 30- Fri 09- 34 Technical
9
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
IoT-based Healthcare Application
Documentation 07-19 08-19 Writer
1.5.5 Closure Report 5 days
Mon
12-08-
19
Fri 16-
08-19 35 Technical
Writer
1.5.6 Milestone 5: Closure
Report 0 days Fri 16-
08-19
Fri 16-
08-19 36
Gantt chart
The images below show the Gantt chart for the project.
10
Document Page
IoT-based Healthcare Application
Project Costs
Resource Name Type Initials Max.