This report outlines the implementation of an Information System (IS) for Highland Explore Tours, detailing the project's initiation, planning, execution, controlling, and closure phases. The project aims to develop strategies to support the implementation of activities that align information and simplify processes, utilizing a website and a mobile app as key subsystems. The report includes a project schedule, budget, and work breakdown structure (WBS), highlighting tasks, durations, and dependencies. It also addresses risk management, stakeholder analysis, and the roles and responsibilities of project team members. The controlling phase emphasizes monitoring and managing project changes to optimize outcomes and ensure successful implementation. This document is available on Desklib, where students can find similar solved assignments and past papers.

Running head: IMPLEMENTATION OF INFORMATION SYSTEM
Assessment Component 2
Implementation of Information System for Highland Explore Tours
Student name:
ID number:
Name of the University:
Assessment Component 2
Implementation of Information System for Highland Explore Tours
Student name:
ID number:
Name of the University:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1IMPLEMENTATION OF INFORMATION SYSTEM
Assignment 2
Part 1: Initiation
The following is considered as project management for Implementation of Highland
Explore Tour.
Project description: The project has been developed in order to develop strategies to
support the process of implementing the activities that can align the information of the factors to
support the process of designing the simplification of the activities. In addition, implementing
project management plan would be established successfully to ease the flow of information. The
project objectives can be described as followed. The subsystem of the Information System (IS)
that has been designed specifically for the Highland Explore Tours are a website and a Mobile
App. Both of these subsystems are expected to be completed by the system designers within
estimated time a budget. The objectives for the development of the Information System in terms
of the website and the Mobile App are developed in this assignment.
To develop new strategies supporting the process of implementing highland
explore tour project plan and activities
To deploy the project tour of highland explore tour supporting development of the
factors and enhanced communication
To analyze the factors related to development of the activities and implement
them properly
Deliverable of the projects is as followed.
Assignment 2
Part 1: Initiation
The following is considered as project management for Implementation of Highland
Explore Tour.
Project description: The project has been developed in order to develop strategies to
support the process of implementing the activities that can align the information of the factors to
support the process of designing the simplification of the activities. In addition, implementing
project management plan would be established successfully to ease the flow of information. The
project objectives can be described as followed. The subsystem of the Information System (IS)
that has been designed specifically for the Highland Explore Tours are a website and a Mobile
App. Both of these subsystems are expected to be completed by the system designers within
estimated time a budget. The objectives for the development of the Information System in terms
of the website and the Mobile App are developed in this assignment.
To develop new strategies supporting the process of implementing highland
explore tour project plan and activities
To deploy the project tour of highland explore tour supporting development of the
factors and enhanced communication
To analyze the factors related to development of the activities and implement
them properly
Deliverable of the projects is as followed.

2IMPLEMENTATION OF INFORMATION SYSTEM
Strategy for making integration of the aligning the activities
Deploying the factors that are able to define the enhanced activities
Implementation of highland explore tour would be achieved for completion of the project
Project Schedule
WBS Task Name Duration Start Finish
0 Implementation of highland explore 34 days Mon 5/28/18 Thu 7/12/18
1 Initiation 6 days Mon 5/28/18 Mon 6/4/18
1.1 Analysis of the requirements 3 days Mon 5/28/18 Wed 5/30/18
1.2 Charter Documentation 2 days Thu 5/31/18 Fri 6/1/18
1.3 Risk Management 1 day Mon 6/4/18 Mon 6/4/18
2 Planning 11 days Thu 5/31/18 Thu 6/14/18
2.1 Outline of Plan 2 days Thu 5/31/18 Fri 6/1/18
2.2 Review of Plan 3 days Tue 6/5/18 Thu 6/7/18
2.3 Complete Plan Development 5 days Fri 6/8/18 Thu 6/14/18
3 Execution 14 days Thu 5/31/18 Tue 6/19/18
3.1 The place is selected 1 day Thu 5/31/18 Thu 5/31/18
3.2 The process is Migrated 5 days Fri 6/1/18 Thu 6/7/18
3.3 Operation Alignment 8 days Fri 6/8/18 Tue 6/19/18
4 Controlling 11 days Wed 6/20/18 Wed 7/4/18
4.1 Processes Monitoring 4 days Wed 6/20/18 Mon 6/25/18
4.2 Problem Detection 2 days Tue 6/26/18 Wed 6/27/18
4.3 Modification of the processes 5 days Thu 6/28/18 Wed 7/4/18
5 Closing 6 days Thu 7/5/18 Thu 7/12/18
5.1 Final Documentation 3 days Thu 7/5/18 Mon 7/9/18
Strategy for making integration of the aligning the activities
Deploying the factors that are able to define the enhanced activities
Implementation of highland explore tour would be achieved for completion of the project
Project Schedule
WBS Task Name Duration Start Finish
0 Implementation of highland explore 34 days Mon 5/28/18 Thu 7/12/18
1 Initiation 6 days Mon 5/28/18 Mon 6/4/18
1.1 Analysis of the requirements 3 days Mon 5/28/18 Wed 5/30/18
1.2 Charter Documentation 2 days Thu 5/31/18 Fri 6/1/18
1.3 Risk Management 1 day Mon 6/4/18 Mon 6/4/18
2 Planning 11 days Thu 5/31/18 Thu 6/14/18
2.1 Outline of Plan 2 days Thu 5/31/18 Fri 6/1/18
2.2 Review of Plan 3 days Tue 6/5/18 Thu 6/7/18
2.3 Complete Plan Development 5 days Fri 6/8/18 Thu 6/14/18
3 Execution 14 days Thu 5/31/18 Tue 6/19/18
3.1 The place is selected 1 day Thu 5/31/18 Thu 5/31/18
3.2 The process is Migrated 5 days Fri 6/1/18 Thu 6/7/18
3.3 Operation Alignment 8 days Fri 6/8/18 Tue 6/19/18
4 Controlling 11 days Wed 6/20/18 Wed 7/4/18
4.1 Processes Monitoring 4 days Wed 6/20/18 Mon 6/25/18
4.2 Problem Detection 2 days Tue 6/26/18 Wed 6/27/18
4.3 Modification of the processes 5 days Thu 6/28/18 Wed 7/4/18
5 Closing 6 days Thu 7/5/18 Thu 7/12/18
5.1 Final Documentation 3 days Thu 7/5/18 Mon 7/9/18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3IMPLEMENTATION OF INFORMATION SYSTEM
5.2 Submission of Reports 2 days Tue 7/10/18 Wed 7/11/18
5.3 Sign off 1 day Thu 7/12/18 Thu 7/12/18
The project plan would comprise the following activities in order to align the activities
successfully. The project plan execution would be based on aligning the information as well as
developed successfully that help to develop the factors and use of the specific factors. The
project plan of Implementation of highland would be based on the activities and easing the
process of completing the enhanced activity development. On the other hand, aligning the
activities would be implemented the process and manage the factors.
Project budget: The budget for the project is Implementation of highland explore is
shown below.
Resource Name Type Work Standard Rate Cost
Project Manager Work 144 hrs RM100.00/hr RM14,400.00
Vendor Work 40 hrs RM90.00/hr RM3,600.00
Risk Manager Work 32 hrs RM50.00/hr RM1,600.00
Sponsor Work 8 hrs RM0.00/hr RM0.00
VP of Operations Work 40 hrs RM110.00/hr RM4,400.00
VP of Marketing Work 112 hrs RM80.00/hr RM8,960.00
5.2 Submission of Reports 2 days Tue 7/10/18 Wed 7/11/18
5.3 Sign off 1 day Thu 7/12/18 Thu 7/12/18
The project plan would comprise the following activities in order to align the activities
successfully. The project plan execution would be based on aligning the information as well as
developed successfully that help to develop the factors and use of the specific factors. The
project plan of Implementation of highland would be based on the activities and easing the
process of completing the enhanced activity development. On the other hand, aligning the
activities would be implemented the process and manage the factors.
Project budget: The budget for the project is Implementation of highland explore is
shown below.
Resource Name Type Work Standard Rate Cost
Project Manager Work 144 hrs RM100.00/hr RM14,400.00
Vendor Work 40 hrs RM90.00/hr RM3,600.00
Risk Manager Work 32 hrs RM50.00/hr RM1,600.00
Sponsor Work 8 hrs RM0.00/hr RM0.00
VP of Operations Work 40 hrs RM110.00/hr RM4,400.00
VP of Marketing Work 112 hrs RM80.00/hr RM8,960.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4IMPLEMENTATION OF INFORMATION SYSTEM
Monitor Tools Material 2 RM700.00 RM700.00
System Material 3 RM1,000.00 RM3,000.00
Database Material 1 RM300.00 RM300.00
Documents Material 5 RM20.00 RM40.00
Total Budget RM 38,000.00
Part 2: Planning
The work breakdown structure for Implementation of highland explore can be shown as below.
WBS Task Name Duration Start Finish Predecessors
0 Implementation of highland
explore 34 days Mon 5/28/18 Thu 7/12/18
1 Analysis Phase 6 days Mon 5/28/18 Mon 6/4/18
1.1 Requirements analysis 3 days Mon 5/28/18 Wed 5/30/18
1.1.1 Project Requirements 1.5 days Mon 5/28/18 Tue 5/29/18
1.1.2 System Requirements 1.5 days Tue 5/29/18 Wed 5/30/18 3
1.2 Risk Management 1 day Mon 6/4/18 Mon 6/4/18
1.2.1 Risk Analysis 0.5 days Mon 6/4/18 Mon 6/4/18 11
1.2.2 Risk Mitigation 0.5 days Mon 6/4/18 Mon 6/4/18 6
2 Documentation Phase 28 days Thu 5/31/18 Mon 7/9/18
2.1 Charter Documentation 2 days Thu 5/31/18 Fri 6/1/18
2.1.1 Initiation document 1 day Thu 5/31/18 Thu 5/31/18 4
2.1.2 Charter Plan document 1 day Fri 6/1/18 Fri 6/1/18 10
Monitor Tools Material 2 RM700.00 RM700.00
System Material 3 RM1,000.00 RM3,000.00
Database Material 1 RM300.00 RM300.00
Documents Material 5 RM20.00 RM40.00
Total Budget RM 38,000.00
Part 2: Planning
The work breakdown structure for Implementation of highland explore can be shown as below.
WBS Task Name Duration Start Finish Predecessors
0 Implementation of highland
explore 34 days Mon 5/28/18 Thu 7/12/18
1 Analysis Phase 6 days Mon 5/28/18 Mon 6/4/18
1.1 Requirements analysis 3 days Mon 5/28/18 Wed 5/30/18
1.1.1 Project Requirements 1.5 days Mon 5/28/18 Tue 5/29/18
1.1.2 System Requirements 1.5 days Tue 5/29/18 Wed 5/30/18 3
1.2 Risk Management 1 day Mon 6/4/18 Mon 6/4/18
1.2.1 Risk Analysis 0.5 days Mon 6/4/18 Mon 6/4/18 11
1.2.2 Risk Mitigation 0.5 days Mon 6/4/18 Mon 6/4/18 6
2 Documentation Phase 28 days Thu 5/31/18 Mon 7/9/18
2.1 Charter Documentation 2 days Thu 5/31/18 Fri 6/1/18
2.1.1 Initiation document 1 day Thu 5/31/18 Thu 5/31/18 4
2.1.2 Charter Plan document 1 day Fri 6/1/18 Fri 6/1/18 10

5IMPLEMENTATION OF INFORMATION SYSTEM
2.2 Final Documentation 3 days Thu 7/5/18 Mon 7/9/18
2.2.1 Test Results are identified 2 days Thu 7/5/18 Fri 7/6/18 28
2.2.2 Documented in report 1 day Mon 7/9/18 Mon 7/9/18 13
3 Planning Phase 11 days Thu 5/31/18 Thu 6/14/18
3.1 Outline of Plan 2 days Thu 5/31/18 Fri 6/1/18 4
3.2 Review of Plan 3 days Tue 6/5/18 Thu 6/7/18 7
3.3 Complete Plan Development 5 days Fri 6/8/18 Thu 6/14/18 17
4 Technology Development Phase 14 days Thu 5/31/18 Tue 6/19/18
4.1 Big Data Platform is selected 1 day Thu 5/31/18 Thu 5/31/18 4
4.2 Data is Migrated 5 days Fri 6/1/18 Thu 6/7/18 20
4.3 Operation Alignment 8 days Fri 6/8/18 Tue 6/19/18 21
5 Monitoring Phase 6 days Wed 6/20/18 Wed 6/27/18
5.1 Processes Monitoring 4 days Wed 6/20/18 Mon 6/25/18 22
5.2 Problem Detection 2 days Tue 6/26/18 Wed 6/27/18 24
6 Modification Phase 5 days Thu 6/28/18 Wed 7/4/18
6.1 Processes Change Implementation 1 day Thu 6/28/18 Thu 6/28/18 25
6.2 Modification of the processes 4 days Fri 6/29/18 Wed 7/4/18 27
7 Closure Phase 3 days Tue 7/10/18 Thu 7/12/18
7.1 Submission of Reports 2 days Tue 7/10/18 Wed 7/11/18 14
7.2 Sign off 1 day Thu 7/12/18 Thu 7/12/18 30
The work packages of the project consist of the requirements, risk management, charter
documentation and technology formation. The completion of work packages is based on the
simplifying the activities regarding the development of the activities regarding the alignment of
2.2 Final Documentation 3 days Thu 7/5/18 Mon 7/9/18
2.2.1 Test Results are identified 2 days Thu 7/5/18 Fri 7/6/18 28
2.2.2 Documented in report 1 day Mon 7/9/18 Mon 7/9/18 13
3 Planning Phase 11 days Thu 5/31/18 Thu 6/14/18
3.1 Outline of Plan 2 days Thu 5/31/18 Fri 6/1/18 4
3.2 Review of Plan 3 days Tue 6/5/18 Thu 6/7/18 7
3.3 Complete Plan Development 5 days Fri 6/8/18 Thu 6/14/18 17
4 Technology Development Phase 14 days Thu 5/31/18 Tue 6/19/18
4.1 Big Data Platform is selected 1 day Thu 5/31/18 Thu 5/31/18 4
4.2 Data is Migrated 5 days Fri 6/1/18 Thu 6/7/18 20
4.3 Operation Alignment 8 days Fri 6/8/18 Tue 6/19/18 21
5 Monitoring Phase 6 days Wed 6/20/18 Wed 6/27/18
5.1 Processes Monitoring 4 days Wed 6/20/18 Mon 6/25/18 22
5.2 Problem Detection 2 days Tue 6/26/18 Wed 6/27/18 24
6 Modification Phase 5 days Thu 6/28/18 Wed 7/4/18
6.1 Processes Change Implementation 1 day Thu 6/28/18 Thu 6/28/18 25
6.2 Modification of the processes 4 days Fri 6/29/18 Wed 7/4/18 27
7 Closure Phase 3 days Tue 7/10/18 Thu 7/12/18
7.1 Submission of Reports 2 days Tue 7/10/18 Wed 7/11/18 14
7.2 Sign off 1 day Thu 7/12/18 Thu 7/12/18 30
The work packages of the project consist of the requirements, risk management, charter
documentation and technology formation. The completion of work packages is based on the
simplifying the activities regarding the development of the activities regarding the alignment of
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6IMPLEMENTATION OF INFORMATION SYSTEM
the activities implementing Implementation of highland explore. The duration for the successful
implementation of the project including work type and working hours are also illustrated in this
section. In addition to this, the power functions, roles, power influence and responsibilities of the
project team members are also elaborated in this section.
The following table is considered as the usage plan for the project:
Resource Name Activity Listed Type Work
VP of Operations
Total Work 124 hrs
Complete Plan Development Work 30 hrs
Processes Monitoring Work 12 hrs
Problem Detection Work 18 hrs
Modification of the processes Work 50 hrs
Outline of Plan Work 26 hrs
VP of Marketing
Total Work 30 hrs
Final Documentation Work 14 hrs
Submission of Reports Work 16 hrs
Risk Manager Work 24hrs
Risk Management Work 9hrs
Plan Reviewer Work 16 hrs
Sponsor Work 18 hrs
Sign off Work 8 hrs
Project Manager
Total Work 30 hrs
Requirements analysis Work 24 hrs
Charter Documentation Work 26 hrs
Vendor Total Work 112 hrs
the activities implementing Implementation of highland explore. The duration for the successful
implementation of the project including work type and working hours are also illustrated in this
section. In addition to this, the power functions, roles, power influence and responsibilities of the
project team members are also elaborated in this section.
The following table is considered as the usage plan for the project:
Resource Name Activity Listed Type Work
VP of Operations
Total Work 124 hrs
Complete Plan Development Work 30 hrs
Processes Monitoring Work 12 hrs
Problem Detection Work 18 hrs
Modification of the processes Work 50 hrs
Outline of Plan Work 26 hrs
VP of Marketing
Total Work 30 hrs
Final Documentation Work 14 hrs
Submission of Reports Work 16 hrs
Risk Manager Work 24hrs
Risk Management Work 9hrs
Plan Reviewer Work 16 hrs
Sponsor Work 18 hrs
Sign off Work 8 hrs
Project Manager
Total Work 30 hrs
Requirements analysis Work 24 hrs
Charter Documentation Work 26 hrs
Vendor Total Work 112 hrs
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7IMPLEMENTATION OF INFORMATION SYSTEM
The place is selected Work 18 hrs
process is Migrated Work 30 hrs
Operation Alignment Work 54 hrs
Project 3: Execution
The stakeholder register for Implementation of highland explore can be represented in the
following table.
Name Role Type Power Influence
John Smith VP of Operations Internal High High
Roy
Manson
VP of Marketing Internal Low Low
Rick toy Risk Manager Internal Low High
Smith
Prone(CFO)
Project Sponsor Internal Low High
Jack Susan (CIO) Member of Steering Committee Internal Low High
<<please fill>> Project Manager Internal Low High
Name Role Type Power Influence Function
Roy
Manson
VP of
marketing
Interna
l High High
Managing the activities as well as
ensuring the project is completed
successfully
Rick toy Risk manager Interna
l
High Low Making sure the management of
the activities as well as
promoting the establishment to a
The place is selected Work 18 hrs
process is Migrated Work 30 hrs
Operation Alignment Work 54 hrs
Project 3: Execution
The stakeholder register for Implementation of highland explore can be represented in the
following table.
Name Role Type Power Influence
John Smith VP of Operations Internal High High
Roy
Manson
VP of Marketing Internal Low Low
Rick toy Risk Manager Internal Low High
Smith
Prone(CFO)
Project Sponsor Internal Low High
Jack Susan (CIO) Member of Steering Committee Internal Low High
<<please fill>> Project Manager Internal Low High
Name Role Type Power Influence Function
Roy
Manson
VP of
marketing
Interna
l High High
Managing the activities as well as
ensuring the project is completed
successfully
Rick toy Risk manager Interna
l
High Low Making sure the management of
the activities as well as
promoting the establishment to a

8IMPLEMENTATION OF INFORMATION SYSTEM
wider scale
Smith
Prone(CFO)
Project
sponsor
Interna
l Low Low
Managing the risk management
procedure as well as ensuring the
alignment of effective alignment
of the operations for reducing the
factors of risk
Jack Susan
(CIO)
Member of
Steering
Committee
Interna
l High High
Managing the activities for
aligning the process of
implication of the resources to
establish the effective integration
of the factors
<<please
fill>>
Project
Manager
Interna
l Low High
In charge of the management of
the activities, it is aligning
synthetic development of
development
The above mentioned two tables clearly depict the stakeholder register to implement of
highland explore. In the first table, 6 persons are involved in the project. All of them are of
internal type. Only John Smith has a high power and the rest all have low power. The influences
of these people are however different. Only Roy Manson has a low influence and all rest of the
people have higher influences. This demonstrates that Roy Manson has a lesser impact on this
particular project.
The second table depicts that 5 persons are involved in this particular project. In this
table, Roy Manson has a higher impact on the project with high power and high influence. Only
Smith Prone, the Chief Financial Officer, has a lower impact on the project with low power and
lower influence. Jack Susan, who is the Chief Information Officer in this project, has similar
influence like Ray Manson with higher power and higher influence. He is responsible for
managing the several activities for aligning the process of implication of the resources to
establish the effective integration of the factors. The project manager of the project has low
power and high influence in this project. He is in charge of the activity management.
wider scale
Smith
Prone(CFO)
Project
sponsor
Interna
l Low Low
Managing the risk management
procedure as well as ensuring the
alignment of effective alignment
of the operations for reducing the
factors of risk
Jack Susan
(CIO)
Member of
Steering
Committee
Interna
l High High
Managing the activities for
aligning the process of
implication of the resources to
establish the effective integration
of the factors
<<please
fill>>
Project
Manager
Interna
l Low High
In charge of the management of
the activities, it is aligning
synthetic development of
development
The above mentioned two tables clearly depict the stakeholder register to implement of
highland explore. In the first table, 6 persons are involved in the project. All of them are of
internal type. Only John Smith has a high power and the rest all have low power. The influences
of these people are however different. Only Roy Manson has a low influence and all rest of the
people have higher influences. This demonstrates that Roy Manson has a lesser impact on this
particular project.
The second table depicts that 5 persons are involved in this particular project. In this
table, Roy Manson has a higher impact on the project with high power and high influence. Only
Smith Prone, the Chief Financial Officer, has a lower impact on the project with low power and
lower influence. Jack Susan, who is the Chief Information Officer in this project, has similar
influence like Ray Manson with higher power and higher influence. He is responsible for
managing the several activities for aligning the process of implication of the resources to
establish the effective integration of the factors. The project manager of the project has low
power and high influence in this project. He is in charge of the activity management.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9IMPLEMENTATION OF INFORMATION SYSTEM
Part 4: Controlling
The project has activities that need controlling and monitoring in order to develop the
ease of implication for the factors helpful in providing the definition of formation of successful
activities of implementation of Information System (IS). The project controlling is dependent
mostly on the factors that are specific for the successful implications were the activities have
eased the implication process. The factors that have successful alignment would control the
project and achieve success in the implication of defining the factors that are aligning by the ease
of those factors that are utilized. Project control is the gathering, managing as well as analysis of
data that is utilized for the prediction, understanding as well as constructively influencing the
cost and time results of any specific project and program. This type of project control is done by
the information communication to obtain effective management and proper decision making.
The factors for controlling would depend successfully on the process as well as effective
communication. The significant implication of controlling and monitoring would be formed by
the implication management that is effective to form. Project controlling is done to know about
the recent changes in a project. The proper strategy or the undertaking planning methods
eventually help the project manager to optimize all the future outcomes. Moreover, this is even
helpful in estimating the costs and cost engineering or control. The proper management of risks
like the maintenance of risk register or risk analysis and assessment are done by the project
control in any typical project. The overall schedule and cost is also checked with the help of this
particular project phase. The factors would be simplified that are ease for utilizing the definition
of implication that has formation being done successfully. The work packages that each
individual have need to be completed and would be assisted for aligning the activities with
successive implication. The dependency of the project is completely based on the alignment of
Part 4: Controlling
The project has activities that need controlling and monitoring in order to develop the
ease of implication for the factors helpful in providing the definition of formation of successful
activities of implementation of Information System (IS). The project controlling is dependent
mostly on the factors that are specific for the successful implications were the activities have
eased the implication process. The factors that have successful alignment would control the
project and achieve success in the implication of defining the factors that are aligning by the ease
of those factors that are utilized. Project control is the gathering, managing as well as analysis of
data that is utilized for the prediction, understanding as well as constructively influencing the
cost and time results of any specific project and program. This type of project control is done by
the information communication to obtain effective management and proper decision making.
The factors for controlling would depend successfully on the process as well as effective
communication. The significant implication of controlling and monitoring would be formed by
the implication management that is effective to form. Project controlling is done to know about
the recent changes in a project. The proper strategy or the undertaking planning methods
eventually help the project manager to optimize all the future outcomes. Moreover, this is even
helpful in estimating the costs and cost engineering or control. The proper management of risks
like the maintenance of risk register or risk analysis and assessment are done by the project
control in any typical project. The overall schedule and cost is also checked with the help of this
particular project phase. The factors would be simplified that are ease for utilizing the definition
of implication that has formation being done successfully. The work packages that each
individual have need to be completed and would be assisted for aligning the activities with
successive implication. The dependency of the project is completely based on the alignment of
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10IMPLEMENTATION OF INFORMATION SYSTEM
the activities. The project is completely dependent on the activities having alignment with
successive inclusion which defines the formation of the activities to be improved. Due to this
dependency, it is not possible to execute a project without project control.
On the other hand, there is a formation of successful implication of the ease that has the
model of formation. The project completion would be effectively utilized which could help in
formation of activities with ease. The result of project usage could make the modification in the
formation of the information. The execution of the project plan is actually based on the
alignment which has the development of forming successfully about the factors that are inclusion
with the development of utilizing factors. The planning of the project is completely based on the
project of Implementation of Highland explore tour which is the actual implementation process.
The completion ease would be successfully deployed by the activities that would improve the
formation of activities. The deployment of alignment activities would ease the factors that are
aligning for the process of formation to be developed.
Part 5: Closing
The functional alignment is ease which would implied successfully by improving the
functional formation. The process of effective management in being utilize with the process of
effective implementation. The completion of the project helps the alignment factors that are to be
ease. Thus, the project has some lesson to be learnt that are discussed below:
Prepared by: <Please fill> Date: <5/28/2018-7/12/2018>
Project Name: Implementation of information system (subsystem websites
the activities. The project is completely dependent on the activities having alignment with
successive inclusion which defines the formation of the activities to be improved. Due to this
dependency, it is not possible to execute a project without project control.
On the other hand, there is a formation of successful implication of the ease that has the
model of formation. The project completion would be effectively utilized which could help in
formation of activities with ease. The result of project usage could make the modification in the
formation of the information. The execution of the project plan is actually based on the
alignment which has the development of forming successfully about the factors that are inclusion
with the development of utilizing factors. The planning of the project is completely based on the
project of Implementation of Highland explore tour which is the actual implementation process.
The completion ease would be successfully deployed by the activities that would improve the
formation of activities. The deployment of alignment activities would ease the factors that are
aligning for the process of formation to be developed.
Part 5: Closing
The functional alignment is ease which would implied successfully by improving the
functional formation. The process of effective management in being utilize with the process of
effective implementation. The completion of the project helps the alignment factors that are to be
ease. Thus, the project has some lesson to be learnt that are discussed below:
Prepared by: <Please fill> Date: <5/28/2018-7/12/2018>
Project Name: Implementation of information system (subsystem websites

11IMPLEMENTATION OF INFORMATION SYSTEM
and mobile app) for Highland Explore Tours
Project Sponsor: <Please fill>
Project Manager: <Please fill>
Project Dates: <8/13/2018-4/19/2019>
Final Budget: Total budget for the project is $51,000
1. Did the project meet scope, time, and cost goals?
From the detail learning of the case project of development of Information System
in terms of website and mobile app I have realized that, scope time and goals the most
important project constraints to be considered for the successful implementation of the
project. At the early project development phase components are required to be estimated
by the system designer and project manager.
2. What was the success criteria listed in the project scope statement?
Proper decision making to implement required changes in the project
An achievable date of project delivery with the design of project schedule
Less scope creep
Internal coordination between the contractor and the suppliers
Less range of project scope creep
Availability for the project resources
3. Reflect on whether or not you met the project success criteria.
I think that the project success criterion for the information system development
project has been met within estimated time and budget. This is the role of the project
manager to complete the project within estimated time and budget. Proper Key
and mobile app) for Highland Explore Tours
Project Sponsor: <Please fill>
Project Manager: <Please fill>
Project Dates: <8/13/2018-4/19/2019>
Final Budget: Total budget for the project is $51,000
1. Did the project meet scope, time, and cost goals?
From the detail learning of the case project of development of Information System
in terms of website and mobile app I have realized that, scope time and goals the most
important project constraints to be considered for the successful implementation of the
project. At the early project development phase components are required to be estimated
by the system designer and project manager.
2. What was the success criteria listed in the project scope statement?
Proper decision making to implement required changes in the project
An achievable date of project delivery with the design of project schedule
Less scope creep
Internal coordination between the contractor and the suppliers
Less range of project scope creep
Availability for the project resources
3. Reflect on whether or not you met the project success criteria.
I think that the project success criterion for the information system development
project has been met within estimated time and budget. This is the role of the project
manager to complete the project within estimated time and budget. Proper Key
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.