This report outlines the development of an information system for YouCanFitIn, a fitness organization expanding its operations. The report details the background, organizational structure, and system vision, addressing the need for improved data management and operational efficiency. It includes a problem description, anticipated business benefits, and system capabilities. A work breakdown structure and project management chart provide a timeline and cost analysis. The report further includes data gathering activities, use case descriptions and diagrams, activity diagrams, ER diagrams, and system sequence diagrams. Cost-benefit analysis shows the financial viability of the project, and the report concludes with recommendations for system implementation. Desklib offers similar solved assignments and resources for students.
Document Page
Running head: INFROMATION SYSTEM DEVELOPMENT
Information System Development
You Can Fit In
Name of the Student:
Name of the University:
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
INFROMATION SYSTEM DEVELOPMENT
Table of Contents
Business Information.......................................................................................................................3
Background Information..............................................................................................................3
Organizational Chart....................................................................................................................3
System Vision Document................................................................................................................4
Problem Description....................................................................................................................4
Anticipated Business Benefits.....................................................................................................5
System Capabilities.....................................................................................................................5
Work Breakdown Structure and Project Management Chart..........................................................6
Project Schedule..........................................................................................................................6
Work Breakdown Structure.........................................................................................................8
Project Network Chart.................................................................................................................8
Cost Benefit Analysis......................................................................................................................9
Data Gathering Activities..............................................................................................................12
Questionnaires:..........................................................................................................................13
Use Case Descriptions and Diagram.............................................................................................15
Use Case Descriptions...............................................................................................................15
Use Case Diagram.....................................................................................................................16
Activity Diagram...........................................................................................................................16
ER Diagram...................................................................................................................................18
Document Page
2
INFROMATION SYSTEM DEVELOPMENT
Model Class Diagram....................................................................................................................18
System Sequence Diagram............................................................................................................18
Conclusion.....................................................................................................................................18
Recommendations..........................................................................................................................18
Bibliography..................................................................................................................................19
Document Page
3
INFROMATION SYSTEM DEVELOPMENT
Business Information
Background Information
YouCanFitIn is an organization that is dependent on Victoria and NSW. They have
numerous fitness centres in various cities and want to expand their business by launching there
one new super centre in Queensland. Their operational official found that it could be an
exceedingly advantageous methodology as the gold coast is a well-known zone for the travel
industry. They want to magnetize the visitors mostly in the bad weather when the visitors do not
visit the beaches. According to Mark, hired as the Manager for the super centre, the visitors
would pay for per visits that would be highly beneficial for the organizations growth. Members
would also be avail of premium membership that would include some extra facilities like access
to the swimming pools and children care.
Recently, the organization used All in One system for the management and storing of the
accounts through MS Word and MS Excel. Still the organization wants to enhance their
information system for the super centre that has opened recently in Queensland as it has many
other new facilities, which are not there in the old ones. The CEO of the organization want to
establish a new information system for the centre that must fulfil all their organizations demand
and help to maintain the daily operations.
Organizational Chart
Adam Apple is the CEO and the key decision maker of the organization. There are three
manager under the CEO of the organization who are hired to take the responsibility of
marinating the various activities in all the centres from the headquarter present in Melbourne.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
CEO
Adam Apple
Finance Manager
Donald Dollars
Operational Manager
Chai Chen
Sales and Marketing
Sally Molly
Branch
Managers
Receptionists Instructor
Adam Apple
Cleaning
Department
Adam Apple
Life Gaurd
Adam Apple
INFROMATION SYSTEM DEVELOPMENT
The finance department is taken care by Donald Dollar, the Finance Manager. Sally Molly, the
SM Manager, handles the sales and marketing team. All the operations in the organization is
taken care by the Operational Manager, Chia Chen. All the branch managers answer to the
Operational Manager Chia Chen for all the activities happening in the organization. The
organization has at least 13 centers in various locations. Adam Apple hires Mark Lewis as the
new manager for the new super centre. Mark Lewis has three years of Fitness Experience.
System Vision Document
Problem Description
The organization YouCanFitIn Orgaization would like to develop a system that would be
able to handle the procedures of the business of the organization and provide security to the
Document Page
5
INFROMATION SYSTEM DEVELOPMENT
database of the organization. In addition to this, the organization is looking for a storage system
that would store the details of the employees of the organization. In addition to this, the products,
services, and the payroll details of the trainers of the organization are also required to be
recorded for the organization. The organization also needs a system that would be able to
maneuver the relationship in between the staffs and the members and also they would like to
record the details of the interactions of the staffs and the members in the system. The system
desired by the organization should be able to manage and monitor the business of the
organization efficiently.
Anticipated Business Benefits
The recommended information system will be highly efficient for the organization as the
organization already have 13 centers in various parts and are planning to open a new supercentre
that can compute most of the operations happening inside the organization while maintaining the
staff member associate within the company. The relationship of the members and the staff of the
organization will also become stronger with this approach. The organization will also get the
information about the staffs and employees as desired.
System Capabilities
The system capabilities for the YouCanFitIn organization is described below:
The system will help in storing the data regarding each employee along with the pay rate
provided towards them. Apart from this the system will also store every data regarding to
the working hours and will mark daily attendance.
Document Page
6
INFROMATION SYSTEM DEVELOPMENT
The system developed will be linked with the website that is responsible for publishing
thee features. Apart from this the system will gather the information regarding from the
website regarding the number details, address details and service
The system will help in managing the schedule for each members and will generate
membership information accordingly.
The system are allowed to be accessed by higher ups and will depend entirely on the user
behavior. However certain information regarding the system will remain restricted. Work
Breakdown Structure and Project Management Chart
Project Schedule
The project schedule and the costs associated with the project has been described in the
schedule provided below:
WBS Task Name Duration Start Finish Predecesso
rs
Resource
Names Cost
1
Development of
information system for
You Can Fit In
70 days Mon
12/10/18
Fri
3/15/19 $29,784.00
1.1 Initialization phase 3 days Mon
12/10/18
Wed
12/12/18 $1,080.00
1.1.1 Analysis of the
business function 2 days Mon
12/10/18
Tue
12/11/18
Project
Manager $720.00
1.1.2 Appointment of team
members 1 day Wed
12/12/18
Wed
12/12/18 3 Project
Manager $360.00
1.2 Planning Phase 7 days Thu
12/13/18
Fri
12/21/18 $4,200.00
1.2.1 Requirement analysis
of the project 3 days Thu
12/13/18
Mon
12/17/18 4
Project
Manager,
System
analyst
$1,920.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
INFROMATION SYSTEM DEVELOPMENT
1.2.2 Scheduling the project 4 days Tue
12/18/18
Fri
12/21/18 4 Project
Manager $1,440.00
1.2.3 Information gathering 3 days Tue
12/18/18
Thu
12/20/18 6 System
analyst $840.00
1.3 Development phase 15 days Fri
12/21/18
Thu
1/10/19 $4,200.00
1.3.1 Building the prototype 7 days Wed
1/2/19
Thu
1/10/19 8 Developer $1,960.00
1.3.2 Program and data
modeling 8 days Fri
12/21/18
Tue
1/1/19 8 Developer $2,240.00
1.4 Designing phase 22 days Wed
1/2/19
Thu
1/31/19 $7,560.00
1.4.1 Preparing Context
level DFD 3 days Wed
1/16/19
Fri
1/18/19 11 Designer $840.00
1.4.2 System designing 10 days Wed
1/2/19
Tue
1/15/19 11 Designer $2,800.00
1.4.3 Flow chart of the
system and all level DFDs 4 days Mon
1/21/19
Thu
1/24/19 13,14 Designer $1,120.00
1.4.4 Report and form
designing 5 days Fri
1/25/19
Thu
1/31/19 15 Designer,
Developer $2,800.00
1.5 Coding Phase 9 days Fri
2/1/19
Wed
2/13/19 $2,520.00
1.5.1 Coding of the project 9 days Fri
2/1/19
Wed
2/13/19 16,14,15 Developer $2,520.00
1.6 Testing Phase 17 days Thu
2/14/19
Fri
3/8/19 $7,584.00
1.6.1 Testing of the model
with validation 3 days Thu
2/14/19
Mon
2/18/19 18 Software
tester $696.00
1.6.2 Integration of the
module with the system 5 days Tue
2/19/19
Mon
2/25/19 18,20
Developer,
Software
tester
$2,560.00
1.6.3 Integration with the
system 4 days Tue
2/26/19
Fri
3/1/19 21
Developer,
Software
tester,
Designer
$3,168.00
1.6.4 System testing 5 days Mon
3/4/19
Fri
3/8/19 22 Software
tester $1,160.00
1.7 Documentation Phase 3 days Mon
3/11/19
Wed
3/13/19 $1,920.00
1.7.1 Completion of the
documentation 3 days Mon
3/11/19
Wed
3/13/19 23
Developer,
Project
Manager
$1,920.00
1.8 Release or
implementation of the
2 days Thu
3/14/19
Fri
3/15/19
25 Project
Manager
$720.00
Document Page
8
INFROMATION SYSTEM DEVELOPMENT
product
Work Breakdown Structure
Development of
information system for
international Charity
Foundation
Development of
information system for
You Can Fit In
Initialization phase
Analysis of the
business function
Appointmet of team
members
Planning Phase
Requirement
analysis of the
project
Scheduling the
project
Information
gathering
Devlopment phase
Building the
prototype
Program and data
modeling
Designing phase
Preparing Context
level DFD
System designing
Flow chart of the
system and all level
DFDs
Report and form
designing
Coding Phase
Coding of the
project
Testing Phase
Testing of the model
with validation
Integration of the
module with the
system
Integration with the
system
System testing
Documentation Phase
Completion of the
documentation
Release or
implementation of
the product
Project Network Chart
Project Gantt chart
Document Page
9
INFROMATION SYSTEM DEVELOPMENT
Cost Benefit Analysis
The project has been developed for the YouCanFitIn organization. It has been evaluated
that the development of the project would be beneficial for the project to a great extent. Hence,
the Cost Benefit Analysis has been performed for the evaluation of the finance for the project.
The cost benefit analysis developed for the project has been described below:
Cost/Benefit Analysis for You
Can Fit In
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
INFROMATION SYSTEM DEVELOPMENT
Year of
Project
year 0 year1 year 2 year 3 year 4 year 5
TOTAL
S
Net economic
benefit
$67,600.
00
$67,600.0
0
$67,600.
00
$67,600.
00
$67,600.
00
Discount Rate 6% 1 0.9434 0.8900 0.8396 0.7921 0.7473
PV Of Benefits $0.00
$63,773
.58
$60,163.
76
$56,758
.26
$53,545
.53
$50,514
.65
NPV of all
BENEFITS $0.00
$63,773.
58
$123,937.
34
$180,69
5.61
$234,24
1.14
$284,75
5.79
$284,75
5.79
One Time Costs
$29,784.0
0
Recurring Costs $0.00
($14,400
.00)
($14,400.
00)
($14,400
.00)
($14,400
.00)
($14,400
.00)
Discount Rate 6% 1.0000 0.9434 0.8900 0.8396 0.7921 0.7473
Document Page
11
INFROMATION SYSTEM DEVELOPMENT
PV Of Recurring
Costs $0.00
($13,58
4.91)
($12,815
.95)
($12,09
0.52)
($11,40
6.15)
($10,76
0.52)
NPV Of All Costs
($60,000.0
0)
($73,584
.91)
($86,400.
85)
($98,491
.37)
($109,89
7.52)
($120,65
8.04)
($120,65
8.04)
Overall NPV
$164,09
7.75
ROI 1.36
Breakeven
analysis
Yearly NPV
Cashflow
$29,784.0
0
$50,188
.68
$111,12
1.40
$168,60
5.09
$222,83
4.99
$273,99
5.27
Overall NPV $29,784.0 $79,972. $191,09 $359,69 $582,53 $856,52