ISY2004: ERP Implementation Project Plan & Management Report
VerifiedAdded on  2023/04/23
|17
|3012
|251
Report
AI Summary
This report provides a detailed project plan for implementing an ERP system in the XYZ organization. It includes a background and rationale for ERP implementation, a project charter outlining key milestones and budget information, a Gantt chart detailing project phases and activities, a network diagram illustrating task dependencies, and a milestone table defining key project events. The report also covers human resource management with a resource table, cost and budget management with a project budget breakdown, and communication management with a RACI table. The project plan encompasses initialization, analysis, design, coding, testing, implementation, documentation, and closure phases, providing a comprehensive roadmap for successful ERP system deployment. Desklib provides access to this document along with numerous study tools for students.

Running head: INFORMATION SYSTEM AND PROJECT MANAGEMENT
ISY2004 Information System and Project Management
Name of Student-
Name of University-
Author’s Note-
ISY2004 Information System and Project Management
Name of Student-
Name of University-
Author’s Note-
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1INFORMATION SYSTEM AND PROJECT MANAGEMENT
Introduction
1. Background and Rationale
The background of the case study explains implementation of ERP in the XYZ
organization. ERP is considered as an integrated system which allows an organization to keep
record of all its resources in its organization. The ERP in the organization is a software that helps
to customize as well as analyze all data and helps to handle the data and deploy the data as
needed. The ERP software is an application process which is a lightweight software and can
customize the business industry. The ERP system in the organization will help the replace the
legacy of software or the incorporate the application of ERP as because there is no system that
exists in the organization. The ERP module in an organization helps to focus on a particular
business process that includes the products of the organization, development as well as
marketing. The ERP modules in the XYZ organization includes product planning, finance
planning, material purchasing, distribution planning as well as inventory control in the
organization.
This report will details all the details of implementing the ERP system in XYZ
organization. This report explains the implementation process through Gantt chart. The critical
path of the Gantt chart is shown by a network diagram and all the milestones are explained
briefly in this report. There are resources included in the project implementation and all those
resources are explained in this report. This report states the total budget of carrying out this
project and a RACI table that shows the responsibility, accountability, consulted as well as
person who is to keep informed.
Introduction
1. Background and Rationale
The background of the case study explains implementation of ERP in the XYZ
organization. ERP is considered as an integrated system which allows an organization to keep
record of all its resources in its organization. The ERP in the organization is a software that helps
to customize as well as analyze all data and helps to handle the data and deploy the data as
needed. The ERP software is an application process which is a lightweight software and can
customize the business industry. The ERP system in the organization will help the replace the
legacy of software or the incorporate the application of ERP as because there is no system that
exists in the organization. The ERP module in an organization helps to focus on a particular
business process that includes the products of the organization, development as well as
marketing. The ERP modules in the XYZ organization includes product planning, finance
planning, material purchasing, distribution planning as well as inventory control in the
organization.
This report will details all the details of implementing the ERP system in XYZ
organization. This report explains the implementation process through Gantt chart. The critical
path of the Gantt chart is shown by a network diagram and all the milestones are explained
briefly in this report. There are resources included in the project implementation and all those
resources are explained in this report. This report states the total budget of carrying out this
project and a RACI table that shows the responsibility, accountability, consulted as well as
person who is to keep informed.

2INFORMATION SYSTEM AND PROJECT MANAGEMENT
2. Project Charter
Project Title: Implementation of ERP system in XYZ organization
Date of Authorization: [Please Fill]
Project Start Date: 25 – 05 - 2019
Project Finish Date: 10 – 09 - 2019
Key schedule milestones:
ï‚· The first milestone of completing the project feasibility test is completed within 4
– 06 – 2019.
 The milestone of testing checking is completed within 02 – 08 – 2019.
 The milestone of project sign off is completed within 10 – 09 – 2019.
 The milestone of system documentation is completed within 30 – 08 – 2019.
Budget Information: The total budget for completing the project is $131,320.00
Project Manager: [Please Fill]
Scheduling/Time Management
3. Gantt Chart
The figure 1 shows the details of the project implementation. The figure shows the phases
of implementing ERP in the organization and their related activities that are to be carried out in
implementing the project. The initialization phase is completed within 6 days, the analyzing
phase is completed within 10 days, the designing phase will be completed in 18 days, the coding
phase will be completed within 15 days, the testing phase will be completed within 12 days and
implementation phase will be completed within 12 days as well. There is a documentation phase
2. Project Charter
Project Title: Implementation of ERP system in XYZ organization
Date of Authorization: [Please Fill]
Project Start Date: 25 – 05 - 2019
Project Finish Date: 10 – 09 - 2019
Key schedule milestones:
ï‚· The first milestone of completing the project feasibility test is completed within 4
– 06 – 2019.
 The milestone of testing checking is completed within 02 – 08 – 2019.
 The milestone of project sign off is completed within 10 – 09 – 2019.
 The milestone of system documentation is completed within 30 – 08 – 2019.
Budget Information: The total budget for completing the project is $131,320.00
Project Manager: [Please Fill]
Scheduling/Time Management
3. Gantt Chart
The figure 1 shows the details of the project implementation. The figure shows the phases
of implementing ERP in the organization and their related activities that are to be carried out in
implementing the project. The initialization phase is completed within 6 days, the analyzing
phase is completed within 10 days, the designing phase will be completed in 18 days, the coding
phase will be completed within 15 days, the testing phase will be completed within 12 days and
implementation phase will be completed within 12 days as well. There is a documentation phase
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3INFORMATION SYSTEM AND PROJECT MANAGEMENT
shown in the chart below that shows the completion of phase in 14 days and the project closure is
completed within 1 day. The below table shows duration each phase for implementing ERP.
Task Name Duration Start Finish Predecessors Resource Names
Development of ERP
System 76 days Tue
28/05/19
Tue
10/09/19
Initialization Phase 6 days Tue
28/05/19 Tue 4/06/19
Making Project
Charter 2 days Tue
28/05/19
Wed
29/05/19
Financial manager,
Project Manager
Making project risk
plan 2 days Thu
30/05/19 Fri 31/05/19 2 Project Manager, Risk
assessment manager
Making feasibility
Test 2 days Mon 3/06/19 Tue 4/06/19 3 Project Manager,
Quality Manager
Analyzing Phase 10 days Wed
5/06/19 Tue 18/06/19
SWOT Analysis 3 days Wed 5/06/19 Fri 7/06/19 4 Financial manager,
Procurement manager
Determining Risks 2 days Mon
10/06/19 Tue 11/06/19 6 Financial manager,
Procurement manager
Business
Requirements 5 days Wed
12/06/19 Tue 18/06/19 7
Project Manager,
Quality Manager,
Software engineer
Designing Phase 18 days Wed
19/06/19 Fri 12/07/19
Creating User
Interface 8 days Wed
19/06/19 Fri 28/06/19 8
Software engineer,
Software
Requirements[1]
Creating Database
Design 10 days Mon 1/07/19 Fri 12/07/19 10
Software engineer, Risk
assessment manager,
Project Manager
Program Designing 10 days Mon 1/07/19 Fri 12/07/19 10
Hardware
requirements[1],Quality
Manager
Coding Phase 15 days Mon
15/07/19 Fri 2/08/19
Coding Programs 15 days Mon
15/07/19 Fri 2/08/19 12 Project Manager
Integrating the
programs 8 days Mon
15/07/19
Wed
24/07/19 12 Quality Manager, Risk
assessment manager
Testing Phase 12 days Thu
25/07/19 Fri 9/08/19
Implementing Black
Box testing 5 days Mon 5/08/19 Fri 9/08/19 15,14 Quality Manager
Implementing White 5 days Thu Wed 15 Financial manager,
shown in the chart below that shows the completion of phase in 14 days and the project closure is
completed within 1 day. The below table shows duration each phase for implementing ERP.
Task Name Duration Start Finish Predecessors Resource Names
Development of ERP
System 76 days Tue
28/05/19
Tue
10/09/19
Initialization Phase 6 days Tue
28/05/19 Tue 4/06/19
Making Project
Charter 2 days Tue
28/05/19
Wed
29/05/19
Financial manager,
Project Manager
Making project risk
plan 2 days Thu
30/05/19 Fri 31/05/19 2 Project Manager, Risk
assessment manager
Making feasibility
Test 2 days Mon 3/06/19 Tue 4/06/19 3 Project Manager,
Quality Manager
Analyzing Phase 10 days Wed
5/06/19 Tue 18/06/19
SWOT Analysis 3 days Wed 5/06/19 Fri 7/06/19 4 Financial manager,
Procurement manager
Determining Risks 2 days Mon
10/06/19 Tue 11/06/19 6 Financial manager,
Procurement manager
Business
Requirements 5 days Wed
12/06/19 Tue 18/06/19 7
Project Manager,
Quality Manager,
Software engineer
Designing Phase 18 days Wed
19/06/19 Fri 12/07/19
Creating User
Interface 8 days Wed
19/06/19 Fri 28/06/19 8
Software engineer,
Software
Requirements[1]
Creating Database
Design 10 days Mon 1/07/19 Fri 12/07/19 10
Software engineer, Risk
assessment manager,
Project Manager
Program Designing 10 days Mon 1/07/19 Fri 12/07/19 10
Hardware
requirements[1],Quality
Manager
Coding Phase 15 days Mon
15/07/19 Fri 2/08/19
Coding Programs 15 days Mon
15/07/19 Fri 2/08/19 12 Project Manager
Integrating the
programs 8 days Mon
15/07/19
Wed
24/07/19 12 Quality Manager, Risk
assessment manager
Testing Phase 12 days Thu
25/07/19 Fri 9/08/19
Implementing Black
Box testing 5 days Mon 5/08/19 Fri 9/08/19 15,14 Quality Manager
Implementing White 5 days Thu Wed 15 Financial manager,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4INFORMATION SYSTEM AND PROJECT MANAGEMENT
Box testing 25/07/19 31/07/19 Procurement manager
Carry out performance
testing 5 days Thu
25/07/19
Wed
31/07/19 15 Cloud vendor
Integrating testing 5 days Thu
25/07/19
Wed
31/07/19 15 Software engineer
Quality Testing 5 days Thu
25/07/19
Wed
31/07/19 15 Quality Manager
Testing Checklist 2 days Thu 1/08/19 Fri 2/08/19 21 Procurement manager,
Project Manager
Implementation Phase 12 days Mon
5/08/19 Tue 20/08/19
Deployment of Phase 5 days Mon 5/08/19 Fri 9/08/19 22,15,11 Cloud vendor, Financial
manager
Installation of Phase 5 days Mon
12/08/19 Fri 16/08/19 24,17 Cloud vendor, Project
Manager
Providing User
Training 2 days Mon
19/08/19 Tue 20/08/19 25,18 Cloud vendor
Providing Training
Materials 0 days Tue
20/08/19 Tue 20/08/19 26,19 Cloud vendor, Project
Manager
Documentation phase 14 days Wed
21/08/19 Mon 9/09/19
User Documentation 7 days Wed
21/08/19 Thu 29/08/19 27,20 Project Manager
System
Documentation 7 days Fri 30/08/19 Mon 9/09/19 29,21,22 Project Manager,
Quality Manager
Project Closure 1 day Mon
9/09/19 Tue 10/09/19
Checking checklist 0 days Mon 9/09/19 Mon 9/09/19 30 Financial manager,
Project Manager
Handing over the
project 1 day Tue
10/09/19 Tue 10/09/19 32 Project Manager
Project sign off 0 days Tue
10/09/19 Tue 10/09/19 33 Project Manager
Table 1: Gantt chart Table
Box testing 25/07/19 31/07/19 Procurement manager
Carry out performance
testing 5 days Thu
25/07/19
Wed
31/07/19 15 Cloud vendor
Integrating testing 5 days Thu
25/07/19
Wed
31/07/19 15 Software engineer
Quality Testing 5 days Thu
25/07/19
Wed
31/07/19 15 Quality Manager
Testing Checklist 2 days Thu 1/08/19 Fri 2/08/19 21 Procurement manager,
Project Manager
Implementation Phase 12 days Mon
5/08/19 Tue 20/08/19
Deployment of Phase 5 days Mon 5/08/19 Fri 9/08/19 22,15,11 Cloud vendor, Financial
manager
Installation of Phase 5 days Mon
12/08/19 Fri 16/08/19 24,17 Cloud vendor, Project
Manager
Providing User
Training 2 days Mon
19/08/19 Tue 20/08/19 25,18 Cloud vendor
Providing Training
Materials 0 days Tue
20/08/19 Tue 20/08/19 26,19 Cloud vendor, Project
Manager
Documentation phase 14 days Wed
21/08/19 Mon 9/09/19
User Documentation 7 days Wed
21/08/19 Thu 29/08/19 27,20 Project Manager
System
Documentation 7 days Fri 30/08/19 Mon 9/09/19 29,21,22 Project Manager,
Quality Manager
Project Closure 1 day Mon
9/09/19 Tue 10/09/19
Checking checklist 0 days Mon 9/09/19 Mon 9/09/19 30 Financial manager,
Project Manager
Handing over the
project 1 day Tue
10/09/19 Tue 10/09/19 32 Project Manager
Project sign off 0 days Tue
10/09/19 Tue 10/09/19 33 Project Manager
Table 1: Gantt chart Table

5INFORMATION SYSTEM AND PROJECT MANAGEMENT
Figure 1: Screenshot of Gantt chart
(Source: Created by author using MS Project)
The above figure shows the Gantt chart that shows the tasks that are carried out for
implementing the ERP system in the organization.
Figure 1: Screenshot of Gantt chart
(Source: Created by author using MS Project)
The above figure shows the Gantt chart that shows the tasks that are carried out for
implementing the ERP system in the organization.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6INFORMATION SYSTEM AND PROJECT MANAGEMENT
4. Network Diagram
The network diagram shown below shows the relationship between the activities included in ERP implementation. The tasks
that are in red shows the critical path of carrying out the activities. Project activities that are in red has to be completed in the given
time so that the project get completed in specified time.
Figure 2: Screenshot of Network Diagram
(Source: Created by Author)
4. Network Diagram
The network diagram shown below shows the relationship between the activities included in ERP implementation. The tasks
that are in red shows the critical path of carrying out the activities. Project activities that are in red has to be completed in the given
time so that the project get completed in specified time.
Figure 2: Screenshot of Network Diagram
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7INFORMATION SYSTEM AND PROJECT MANAGEMENT
5. Milestones
Milestone shows the important event that are to be carried out in completing the project.
The milestones included in this implementation project are listed in the table below. The
milestones are selected as per the SMART criteria of completing the project. The milestone of
making feasibility test is specific as because the specific tasks are carried out in completing the
feasibility test. The business requirement task is measurable as because completing this
milestone helps to state the amount of work that is being completed.
Task Name Start Date Status Responsible
Stakeholder Comment
Making feasibility Test Mon 3/06/19 Completed Project Manager,
Quality Manager
All Task
Completed
Business Requirements Wed
12/06/19 Completed
Project Manager,
Quality Manager,
Software engineer
Adding
requirements
Testing Checklist Thu 1/08/19 Completed Procurement manager,
Project Manager
Adding extra
feature
Providing Training
Materials
Tue
20/08/19 Completed Cloud vendor, Project
Manager
All training
materials
provided
System Documentation Fri 30/08/19 Completed Project Manager,
Quality Manager
Updating the
stakeholders
table, RACI
table
Checking checklist Mon 9/09/19 Completed Financial manager,
Project Manager
All tasks
completed
Project Sign off Tue
10/09/19 Completed Project Manager
Table 2: Milestone Table
Human Resource Management
6. Resource Table
The resource table below shows the resources that are needed for carrying out this
project. There are human resource and materials resources that are needed to complete this
5. Milestones
Milestone shows the important event that are to be carried out in completing the project.
The milestones included in this implementation project are listed in the table below. The
milestones are selected as per the SMART criteria of completing the project. The milestone of
making feasibility test is specific as because the specific tasks are carried out in completing the
feasibility test. The business requirement task is measurable as because completing this
milestone helps to state the amount of work that is being completed.
Task Name Start Date Status Responsible
Stakeholder Comment
Making feasibility Test Mon 3/06/19 Completed Project Manager,
Quality Manager
All Task
Completed
Business Requirements Wed
12/06/19 Completed
Project Manager,
Quality Manager,
Software engineer
Adding
requirements
Testing Checklist Thu 1/08/19 Completed Procurement manager,
Project Manager
Adding extra
feature
Providing Training
Materials
Tue
20/08/19 Completed Cloud vendor, Project
Manager
All training
materials
provided
System Documentation Fri 30/08/19 Completed Project Manager,
Quality Manager
Updating the
stakeholders
table, RACI
table
Checking checklist Mon 9/09/19 Completed Financial manager,
Project Manager
All tasks
completed
Project Sign off Tue
10/09/19 Completed Project Manager
Table 2: Milestone Table
Human Resource Management
6. Resource Table
The resource table below shows the resources that are needed for carrying out this
project. There are human resource and materials resources that are needed to complete this

8INFORMATION SYSTEM AND PROJECT MANAGEMENT
project successfully. The resource sheet also show the standard rate of the human resources and
the onetime cost of the materials that are included in the project.
Resource Name Type Material Label Initials Group Max.
Units Std. Rate
Project Manager Work P 100% $100.00/hr
Procurement manager Work P 100% $90.00/hr
Financial manager Work F 100% $90.00/hr
Quality Manager Work Q 100% $90.00/hr
Risk assessment
manager Work R 100% $80.00/hr
Cloud vendor Work C 100% $50.00/hr
Software engineer Work S 100% $50.00/hr
Hardware requirements Material H $1,500.00
Software Requirements Material S $1,500.00
Table 3: Milestone Table
Cost/Budget Management
7. Project Budget
The project budget shows the total budget of the project that sis used for carrying out the
activities in implementing the ERP system. The total cost of the project is shown as $131,320
and each phases has different cost structure for completing the project.
WBS Task Name Resource Names Cost
0 Development of ERP
System $131,320.00
1 Initialization Phase $8,960.00
1.1 Making Project Charter Financial manager, Project Manager $3,040.00
1.2 Making project risk plan Project Manager, Risk assessment
manager $2,880.00
1.3 Making feasibility Test Project Manager, Quality Manager $3,040.00
2 Analyzing Phase $16,800.00
2.1 SWOT Analysis Financial manager, Procurement
manager $4,320.00
2.2 Determining Risks Financial manager, Procurement
manager $2,880.00
2.3 Business Requirements Project Manager, Quality Manager,
Software engineer $9,600.00
3 Designing Phase $31,800.00
project successfully. The resource sheet also show the standard rate of the human resources and
the onetime cost of the materials that are included in the project.
Resource Name Type Material Label Initials Group Max.
Units Std. Rate
Project Manager Work P 100% $100.00/hr
Procurement manager Work P 100% $90.00/hr
Financial manager Work F 100% $90.00/hr
Quality Manager Work Q 100% $90.00/hr
Risk assessment
manager Work R 100% $80.00/hr
Cloud vendor Work C 100% $50.00/hr
Software engineer Work S 100% $50.00/hr
Hardware requirements Material H $1,500.00
Software Requirements Material S $1,500.00
Table 3: Milestone Table
Cost/Budget Management
7. Project Budget
The project budget shows the total budget of the project that sis used for carrying out the
activities in implementing the ERP system. The total cost of the project is shown as $131,320
and each phases has different cost structure for completing the project.
WBS Task Name Resource Names Cost
0 Development of ERP
System $131,320.00
1 Initialization Phase $8,960.00
1.1 Making Project Charter Financial manager, Project Manager $3,040.00
1.2 Making project risk plan Project Manager, Risk assessment
manager $2,880.00
1.3 Making feasibility Test Project Manager, Quality Manager $3,040.00
2 Analyzing Phase $16,800.00
2.1 SWOT Analysis Financial manager, Procurement
manager $4,320.00
2.2 Determining Risks Financial manager, Procurement
manager $2,880.00
2.3 Business Requirements Project Manager, Quality Manager,
Software engineer $9,600.00
3 Designing Phase $31,800.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9INFORMATION SYSTEM AND PROJECT MANAGEMENT
3.1 Creating User Interface Software engineer, Software
Requirements[1] $4,700.00
3.2 Creating Database
Design
Software engineer, Risk assessment
manager, Project Manager $18,400.00
3.3 Program Designing Hardware requirements[1],Quality
Manager $8,700.00
4 Coding Phase $22,880.00
4.1 Coding Programs Project Manager $12,000.00
4.2 Integrating the programs Quality Manager, Risk assessment
manager $10,880.00
5 Testing Phase $21,440.00
5.1 Implementing Black Box
testing Quality Manager $3,600.00
5.2 Implementing White Box
testing
Financial manager, Procurement
manager $7,200.00
5.3 Carry out performance
testing Cloud vendor $2,000.00
5.4 Integrating testing Software engineer $2,000.00
5.5 Quality Testing Quality Manager $3,600.00
5.6 Testing Checklist Procurement manager, Project Manager $3,040.00
6 Implementation Phase $12,400.00
6.1 Deployment of Phase Cloud vendor, Financial manager $5,600.00
6.2 Installation of Phase Cloud vendor, Project Manager $6,000.00
6.3 Providing User Training Cloud vendor $800.00
6.4 Providing Training
Materials Cloud vendor, Project Manager $0.00
7 Documentation phase $16,240.00
7.1 User Documentation Project Manager $5,600.00
7.2 System Documentation Project Manager, Quality Manager $10,640.00
8 Project Closure $800.00
8.1 Checking checklist Financial manager, Project Manager $0.00
8.2 Handing over the project Project Manager $800.00
8.3 Project sign off Project Manager $0.00
Table 4: Project Budget
3.1 Creating User Interface Software engineer, Software
Requirements[1] $4,700.00
3.2 Creating Database
Design
Software engineer, Risk assessment
manager, Project Manager $18,400.00
3.3 Program Designing Hardware requirements[1],Quality
Manager $8,700.00
4 Coding Phase $22,880.00
4.1 Coding Programs Project Manager $12,000.00
4.2 Integrating the programs Quality Manager, Risk assessment
manager $10,880.00
5 Testing Phase $21,440.00
5.1 Implementing Black Box
testing Quality Manager $3,600.00
5.2 Implementing White Box
testing
Financial manager, Procurement
manager $7,200.00
5.3 Carry out performance
testing Cloud vendor $2,000.00
5.4 Integrating testing Software engineer $2,000.00
5.5 Quality Testing Quality Manager $3,600.00
5.6 Testing Checklist Procurement manager, Project Manager $3,040.00
6 Implementation Phase $12,400.00
6.1 Deployment of Phase Cloud vendor, Financial manager $5,600.00
6.2 Installation of Phase Cloud vendor, Project Manager $6,000.00
6.3 Providing User Training Cloud vendor $800.00
6.4 Providing Training
Materials Cloud vendor, Project Manager $0.00
7 Documentation phase $16,240.00
7.1 User Documentation Project Manager $5,600.00
7.2 System Documentation Project Manager, Quality Manager $10,640.00
8 Project Closure $800.00
8.1 Checking checklist Financial manager, Project Manager $0.00
8.2 Handing over the project Project Manager $800.00
8.3 Project sign off Project Manager $0.00
Table 4: Project Budget
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10INFORMATION SYSTEM AND PROJECT MANAGEMENT
Communication Management
8. RACI Table
Task Name Project
Manager
Procurement
Manager
Financial
Manager
Quality
Manager
Risk
Assessment
Manager
Cloud
Vendor
Software
Engineer
Making
Project
Charter
R C A I A I I
Making
project risk
plan
R R R I I C A
Making
feasibility Test
A I A C I A R
SWOT
Analysis
R R A A C I C
Determining
Risks
A A R R C A I
Business
Requirements
I I R R C I A
Creating User
Interface
C C A R I A R
Creating
Database
Design
R R R I I C A
Program
Designing
R R R I I C A
Coding
Programs
R A C A I R R
Integrating the
programs
R R R I I C A
Implementing
Black Box
testing
A A I R R C I
Implementing
White Box
testing
A A I R R C I
Carry out
performance
testing
A C I R R C I
Integrating
testing
A A I R R C I
Quality
Testing
A I I R R C I
Testing
Checklist
R A I R R C I
Deployment of
Phase
A A I A R C C
Communication Management
8. RACI Table
Task Name Project
Manager
Procurement
Manager
Financial
Manager
Quality
Manager
Risk
Assessment
Manager
Cloud
Vendor
Software
Engineer
Making
Project
Charter
R C A I A I I
Making
project risk
plan
R R R I I C A
Making
feasibility Test
A I A C I A R
SWOT
Analysis
R R A A C I C
Determining
Risks
A A R R C A I
Business
Requirements
I I R R C I A
Creating User
Interface
C C A R I A R
Creating
Database
Design
R R R I I C A
Program
Designing
R R R I I C A
Coding
Programs
R A C A I R R
Integrating the
programs
R R R I I C A
Implementing
Black Box
testing
A A I R R C I
Implementing
White Box
testing
A A I R R C I
Carry out
performance
testing
A C I R R C I
Integrating
testing
A A I R R C I
Quality
Testing
A I I R R C I
Testing
Checklist
R A I R R C I
Deployment of
Phase
A A I A R C C

11INFORMATION SYSTEM AND PROJECT MANAGEMENT
Installation of
Phase
R I C R A A C
Providing User
Training
A A I A R R I
Providing
Training
Materials
R I I R R R C
User
Documentation
A R I R A C I
System
Documentation
C I I A A C C
Checking
checklist
R R R C R C A
Handing over
the project
R R R R C A I
Project sign off R R R C R C A
Table 5: RACI Matrix
Installation of
Phase
R I C R A A C
Providing User
Training
A A I A R R I
Providing
Training
Materials
R I I R R R C
User
Documentation
A R I R A C I
System
Documentation
C I I A A C C
Checking
checklist
R R R C R C A
Handing over
the project
R R R R C A I
Project sign off R R R C R C A
Table 5: RACI Matrix
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.