ISYS302 Project: Cloud Based SAP Instance Project Management Plan

Verified

Added on  2023/06/14

|20
|2404
|326
Project
AI Summary
This project management assignment outlines a comprehensive plan for deploying a cloud-based SAP instance for Dai-Ichi Corporation. It details the project objectives, deliverables (including high-level requirements like database and application servers), and project management controls such as regular meetings, earned value analysis, and critical path analysis. The plan includes resource allocation, a detailed budget of $864,668.75, a Work Breakdown Structure (WBS) diagram, a schedule with Gantt chart and critical path analysis, a communication management plan, and a risk management plan addressing schedule slippage, budget shortfalls, and security issues. The project spans from the initiation phase to closure, with key milestones and activities defined for each phase. The document includes supporting diagrams and tables to clearly illustrate the project's timeline, resource allocation, and risk mitigation strategies.
Document Page
Running head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Project objectives........................................................................................................................2
2. Deliverables................................................................................................................................2
2.1 High-level requirements........................................................................................................2
2.2 Project management controls.................................................................................................2
3. Resources.....................................................................................................................................3
4. Budget..........................................................................................................................................4
5. WBS diagram...............................................................................................................................7
5.1 Schedule.................................................................................................................................7
5.1.1 Gantt chart....................................................................................................................10
5.1.2 Critical path..................................................................................................................12
5.1.3 Network Diagram.........................................................................................................13
6. Communication management plan...........................................................................................14
7. Risk management plan...............................................................................................................15
Bibliography..................................................................................................................................18
Document Page
2
PROJECT MANAGEMENT
1. Project objectives
The objectives of the project are as follows:
To deploy the same platform into the Oceania operations
To deploy the SAP instance on the cloud
To facilitate SAP instance to be managed out of Europe
2. Deliverables
2.1 High-level requirements
The high-level requirements for the project include:
2X Database servers
2X Application servers
3X Web Services Layer servers
X86 Image- per instance
SAP Cloud instance
JIRA
2.2 Project management controls
The project can be controlled by utilizing methods that are as follows:
Conducting regular meetings: It is very much necessary to conduct regular meetings in
so that the project team members can able to discuss about the project hurdles as well as can
update the tasks of the project effectively. Team meetings involves identification of
dependencies as well as risks that are assigned to the tasks.
Document Page
3
PROJECT MANAGEMENT
Using earned value analysis: Earned value analysis is one of the project control
technique that mainly helps in measuring the performance of the project. It is one of the
technique, which not only assists in quantifying project progress but also helps in controlling
project. It is very much necessary to keep an eye on the CPI as well as SPI, which are related
with earned value analysis in order to ensure that the entire project will be completed within the
estimated budget and time.
Using critical path analysis: If the activities that are related with critical path is delayed
then the project completion date gets impacted and therefore inn order to monitor as well as
control the project it is necessary to keep proper track on the critical path of the project.
3. Resources
The resources that are required in the project are listed in the table below:
Resource Name Type Initials
Max.
Units
Std. Rate Accrue At
Base
Calendar
Project manager Work P 100% $2,000.00/day Prorated Standard
Paulo-SAP Expert Work P 100% $2,000.00/day Prorated Standard
Sanjay-Cloud
architect
Work S 100% $7,500.00/month Prorated Standard
June-SAP expert Work J 100% $7,500.00/ month Prorated Standard
Larry jones-LAMP
stack specialist
Work L 100% $3,500.00/ month Prorated Standard
Jenny Harvey-Linux
Administrator+
Work J 100% $3,250.00/ month Prorated Standard
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
LAMP
Amazon cloud
infrastructure( X 86
image-Per instance)
Work 100% $2,750.00/ month Prorated Standard
SAP Cloud
instance-Site
License for
Australia
Material $200,000.00 Prorated
JIRA Material J $50.00 Prorated
Travel and
accommodation
expenses for Paolo
Work 100% $10,000.00/month Prorated Standard
4. Budget
It is estimated that the cloud based SAP instance for Dai-Ichi Corporation will be
completed successfully within the budget that is around $864,668.75. The table below helps in
reflecting the cost that is needed to complete each of the activities of the project.
Task Name Duration Cost
Creating cloud based SAP instance
for Dai-Ichi Corporation Australia
60 days $864,668.75
Initiation Phase 4 days $9,387.50
Defining scope of the project 0.5 days $1,000.00
Defining project time 1 day $2,375.00
Document Page
5
PROJECT MANAGEMENT
Defining cost constraints of the
project
1 day $550.00
Defining high level requirements 0.5 days $1,462.50
Forming project team 1 day $4,000.00
Milestone 1: Completion of project
initiation phase
0 days $0.00
Planning phase 6 days $211,650.00
Developing project plan 1 day $2,550.00
Creating schedule of the project 1 day $375.00
Creating detailed budget for the
project
2 days $4,750.00
Obtaining sign off on plan 0.5 days $1,437.50
Getting approval for the project 0.5 days $2,000.00
Signals approval by steering
committee
1 day $200,537.50
Milestone 2: Completion of
planning phase
0 days $0.00
Design/build phase 36 days $220,818.75
Detailed requirement gathering 1 day $202,375.00
Security requirements 1 day $162.50
Infrastructure planning 1.5 days $206.25
Document Page
6
PROJECT MANAGEMENT
System operation strategy 1.5 days $825.00
Training preparation 2 days $4,000.00
Configuration and development 2 days $5,100.00
Unit/Process business acceptance
testing
3 days $525.00
Infrastructure implementation 5 days $500.00
Implement AWS Cloud
Infrastructure
5 days $0.00
Develop SAP on the System 4 days $0.00
Test the SAP on the AWS Cloud
Infrastructure
3 days $0.00
Find Bugs and Glitches 2 days $0.00
Troubleshoot Issues 2 days $0.00
Make Some Modifications in
System Function
3 days $7,125.00
Milestone 3: Completion of
design/Build phase
0 days $0.00
Go live phase 10 days $414,437.50
End user training 3 days $7,500.00
Business simulation 2 days $0.00
End user practice in the system 1 day $200,375.00
Infrastructure finalization 1 day $200,137.50
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
Data migration to production 2 days $4,050.00
Pre-go live operations 1 day $2,375.00
Milestone 4: Completion of go live
phase
0 days $0.00
Closure phase 4 days $8,375.00
Post-project review 1 day $2,000.00
Stakeholder sign off 1 day $2,375.00
Documentation 2 days $4,000.00
Milestone 5: Completion of project
closure phase
0 days $0.00
5. WBS diagram
5.1 Schedule
Task Name Duration Start Finish
Creating cloud based SAP instance
for Dai-Ichi Corporation Australia
60 days Mon 4/9/18 Fri 6/29/18
Initiation Phase 4 days Mon 4/9/18 Thu 4/12/18
Defining scope of the project 0.5 days Mon 4/9/18 Mon 4/9/18
Defining project time 1 day Mon 4/9/18 Tue 4/10/18
Defining cost constraints of the
project
1 day Tue 4/10/18 Wed 4/11/18
Defining high level requirements 0.5 days Wed 4/11/18 Wed 4/11/18
Document Page
8
PROJECT MANAGEMENT
Forming project team 1 day Thu 4/12/18 Thu 4/12/18
Milestone 1: Completion of project
initiation phase
0 days Thu 4/12/18 Thu 4/12/18
Planning phase 6 days Fri 4/13/18 Fri 4/20/18
Developing project plan 1 day Fri 4/13/18 Fri 4/13/18
Creating schedule of the project 1 day Mon 4/16/18 Mon 4/16/18
Creating detailed budget for the
project
2 days Tue 4/17/18 Wed 4/18/18
Obtaining sign off on plan 0.5 days Thu 4/19/18 Thu 4/19/18
Getting approval for the project 0.5 days Thu 4/19/18 Thu 4/19/18
Signals approval by steering
committee
1 day Fri 4/20/18 Fri 4/20/18
Milestone 2: Completion of
planning phase
0 days Fri 4/20/18 Fri 4/20/18
Design/build phase 36 days Mon 4/23/18 Mon 6/11/18
Detailed requirement gathering 1 day Mon 4/23/18 Mon 4/23/18
Security requirements 1 day Tue 4/24/18 Tue 4/24/18
Infrastructure planning 1.5 days Wed 4/25/18 Thu 4/26/18
System operation strategy 1.5 days Thu 4/26/18 Fri 4/27/18
Training preparation 2 days Mon 4/30/18 Tue 5/1/18
Configuration and development 2 days Wed 5/2/18 Thu 5/3/18
Document Page
9
PROJECT MANAGEMENT
Unit/Process business acceptance
testing
3 days Fri 5/4/18 Tue 5/8/18
Infrastructure implementation 5 days Wed 5/9/18 Tue 5/15/18
Implement AWS Cloud
Infrastructure
5 days Wed 5/16/18 Tue 5/22/18
Develop SAP on the System 4 days Wed 5/23/18 Mon 5/28/18
Test the SAP on the AWS Cloud
Infrastructure
3 days Tue 5/29/18 Thu 5/31/18
Find Bugs and Glitches 2 days Fri 6/1/18 Mon 6/4/18
Troubleshoot Issues 2 days Tue 6/5/18 Wed 6/6/18
Make Some Modifications in
System Function
3 days Thu 6/7/18 Mon 6/11/18
Milestone 3: Completion of
design/Build phase
0 days Mon 6/11/18 Mon 6/11/18
Go live phase 10 days Tue 6/12/18 Mon 6/25/18
End user training 3 days Tue 6/12/18 Thu 6/14/18
Business simulation 2 days Fri 6/15/18 Mon 6/18/18
End user practice in the system 1 day Tue 6/19/18 Tue 6/19/18
Infrastructure finalization 1 day Wed 6/20/18 Wed 6/20/18
Data migration to production 2 days Thu 6/21/18 Fri 6/22/18
Pre-go live operations 1 day Mon 6/25/18 Mon 6/25/18
Milestone 4: Completion of go live 0 days Mon 6/25/18 Mon 6/25/18
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
phase
Closure phase 4 days Tue 6/26/18 Fri 6/29/18
Post-project review 1 day Tue 6/26/18 Tue 6/26/18
Stakeholder sign off 1 day Wed 6/27/18 Wed 6/27/18
Documentation 2 days Thu 6/28/18 Fri 6/29/18
Milestone 5: Completion of project
closure phase
0 days Fri 6/29/18 Fri 6/29/18
5.1.1 Gantt chart
The figure that is provided below is the Gantt chart, which is one of the graphical tool
that helps in reflecting activities as well as tasks that are needed to be performed against time. In
this project, the Gantt chart reflects the activities that are needed to be completed in order to
execute the project of SAP within organization “Dai-Ichi Corporation” in 12 weeks.
Document Page
11
PROJECT MANAGEMENT
Figure 1: Gantt chart
(Source: Created by Author)