IT Centre Development Project: Execution Plan for Canberra, Australia
VerifiedAdded on  2023/06/03
|22
|2561
|478
Project
AI Summary
This document outlines a detailed project plan for the development of an IT centre in Canberra, Australia, with a budget of $40 million. It includes a comprehensive scope covering the development of a new information technology centre to support customer IT needs, adhering to budget and timelines, and resolving customer issues. The plan features a Work Breakdown Structure (WBS) with task scheduling, resource estimation and allocation, and a communication plan. It also includes PDM diagrams, Gantt charts, resource lists with costs, S-curves for budget and cost forecasting, and software reports for project delivery, detailing actual work, remaining work, and baseline work. The project covers initiation, planning, designing, development, testing, and closing phases, with key milestones and resource allocation for hardware, software, and network systems.

Running head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of University
Author’s Note
Project Management
Name of the Student
Name of University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Executive Summary
The paper focuses on the development of IT centre in Australia with the aim of supporting
all the all the IT needs as well as requirements of the customers. It is found that in order to
compete the project total $40 million budget was allocated. Inn this paper, the entire schedule
with cost ad resources for the project is reflected. In addition to this, the report also provides
s-curves as well as other software reports for the delivery of this project.
PROJECT MANAGEMENT
Executive Summary
The paper focuses on the development of IT centre in Australia with the aim of supporting
all the all the IT needs as well as requirements of the customers. It is found that in order to
compete the project total $40 million budget was allocated. Inn this paper, the entire schedule
with cost ad resources for the project is reflected. In addition to this, the report also provides
s-curves as well as other software reports for the delivery of this project.

2
PROJECT MANAGEMENT
Table of Contents
1. Introduction............................................................................................................................3
2. Scope of the project................................................................................................................3
3. Aims and objectives...............................................................................................................3
4. List of tasks and WBS schedule for the project including activity schedule.........................4
5. Project calendar......................................................................................................................6
6. PDM diagram and Gantt chart...............................................................................................8
7. List and cost of resources.....................................................................................................10
8. List and cost of resources schedule in the form of Gantt chart............................................11
9. Budget and cost forecast using s-curves.............................................................................13
10. Software reports for the delivery of this project................................................................18
Bibliography.............................................................................................................................20
PROJECT MANAGEMENT
Table of Contents
1. Introduction............................................................................................................................3
2. Scope of the project................................................................................................................3
3. Aims and objectives...............................................................................................................3
4. List of tasks and WBS schedule for the project including activity schedule.........................4
5. Project calendar......................................................................................................................6
6. PDM diagram and Gantt chart...............................................................................................8
7. List and cost of resources.....................................................................................................10
8. List and cost of resources schedule in the form of Gantt chart............................................11
9. Budget and cost forecast using s-curves.............................................................................13
10. Software reports for the delivery of this project................................................................18
Bibliography.............................................................................................................................20
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
1. Introduction
The paper generally reflects on the development of an IT centre in Australia. The aim
of the project is to develop a new IT centre so that all the IT needs as well as requirements of
the customers can be met quite effectively. It is found that total amount of $25 million was
allocated for the project but further additional $15 million allocated so that the IT centre can
be capable of supporting all the requirements of the customer in the coming five years quite
effectively.
2. Scope of the project
The project scope includes:
ï‚· Development of new information technology entre
ï‚· Supporting IT needs of the customers
ï‚· Finishing the project within total time and budget
ï‚· To resolve the challenges and issues of the customers
3. Aims and objectives
The main aim to develop an information technology centre for supporting all the IT
needs as well as requirements of the customers quite effectively.
The objectives of the project are listed below:
ï‚· To develop new information technology entre
ï‚· To support IT needs of the customers
ï‚· To complete the project within total budget and time
PROJECT MANAGEMENT
1. Introduction
The paper generally reflects on the development of an IT centre in Australia. The aim
of the project is to develop a new IT centre so that all the IT needs as well as requirements of
the customers can be met quite effectively. It is found that total amount of $25 million was
allocated for the project but further additional $15 million allocated so that the IT centre can
be capable of supporting all the requirements of the customer in the coming five years quite
effectively.
2. Scope of the project
The project scope includes:
ï‚· Development of new information technology entre
ï‚· Supporting IT needs of the customers
ï‚· Finishing the project within total time and budget
ï‚· To resolve the challenges and issues of the customers
3. Aims and objectives
The main aim to develop an information technology centre for supporting all the IT
needs as well as requirements of the customers quite effectively.
The objectives of the project are listed below:
ï‚· To develop new information technology entre
ï‚· To support IT needs of the customers
ï‚· To complete the project within total budget and time
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
4. List of tasks and WBS schedule for the project including activity
schedule
The table that s provided below lists project tasks with WBS schedule including the
activity schedule.
WBS Task Name Duration Start Finish
0
Development of new information
technology centre
181 days Fri 05-10-18 Fri 28-06-19
1 Project initiation phase 17 days Fri 05-10-18 Mon 29-10-18
1.1
Identifying project
requirements
8 days Fri 05-10-18 Tue 16-10-18
1.2 Development of project plan 4 days Wed 17-10-18 Mon 22-10-18
1.3 Checking feasibility testing 5 days Tue 23-10-18 Mon 29-10-18
1.4
Milestone 1:Completion of
initiation phase
0 days Mon 29-10-18 Mon 29-10-18
2 Project planning phase 36 days Tue 30-10-18 Wed 19-12-18
2.1 Task scheduling 4 days Tue 30-10-18 Fri 02-11-18
2.2 Estimation of resources 6 days Mon 05-11-18 Mon 12-11-18
2.3 Allocation of resources 9 days Tue 13-11-18 Fri 23-11-18
2.4
Communication plan
development
9 days Mon 26-11-18 Thu 06-12-18
2.5 Task allocation 9 days Fri 07-12-18 Wed 19-12-18
2.6
Milestone 2: Completion of
planning phase
0 days Wed 19-12-18 Wed 19-12-18
3 Project designing phase 36 days Thu 20-12-18 Wed 13-02-19
PROJECT MANAGEMENT
4. List of tasks and WBS schedule for the project including activity
schedule
The table that s provided below lists project tasks with WBS schedule including the
activity schedule.
WBS Task Name Duration Start Finish
0
Development of new information
technology centre
181 days Fri 05-10-18 Fri 28-06-19
1 Project initiation phase 17 days Fri 05-10-18 Mon 29-10-18
1.1
Identifying project
requirements
8 days Fri 05-10-18 Tue 16-10-18
1.2 Development of project plan 4 days Wed 17-10-18 Mon 22-10-18
1.3 Checking feasibility testing 5 days Tue 23-10-18 Mon 29-10-18
1.4
Milestone 1:Completion of
initiation phase
0 days Mon 29-10-18 Mon 29-10-18
2 Project planning phase 36 days Tue 30-10-18 Wed 19-12-18
2.1 Task scheduling 4 days Tue 30-10-18 Fri 02-11-18
2.2 Estimation of resources 6 days Mon 05-11-18 Mon 12-11-18
2.3 Allocation of resources 9 days Tue 13-11-18 Fri 23-11-18
2.4
Communication plan
development
9 days Mon 26-11-18 Thu 06-12-18
2.5 Task allocation 9 days Fri 07-12-18 Wed 19-12-18
2.6
Milestone 2: Completion of
planning phase
0 days Wed 19-12-18 Wed 19-12-18
3 Project designing phase 36 days Thu 20-12-18 Wed 13-02-19

5
PROJECT MANAGEMENT
3.1 Blueprint design 7 days Thu 20-12-18 Fri 28-12-18
3.2 IT needs assigned 6 days Mon 31-12-18 Mon 07-01-19
3.3
Purchasing needed
requirements
7 days Tue 08-01-19 Wed 16-01-19
3.4
Software development
recruitment
20 days Thu 17-01-19 Wed 13-02-19
3.5
Milestone 3: Completion of
project design
0 days Wed 13-02-19 Wed 13-02-19
4 Development phase 61.75 days Thu 14-02-19 Fri 17-05-19
4.1 Assigning new hardware 7 days Thu 14-02-19 Fri 22-02-19
4.2 assigning new software 8 days Mon 25-02-19 Wed 06-03-19
4.3
Development of data
warehouse
20 days Thu 07-03-19 Wed 03-04-19
4.4
Development of network
system
10 days Thu 04-04-19 Wed 17-04-19
4.5 Security System application 10 days Thu 18-04-19 Fri 03-05-19
4.6
Interconnection between
developed overall information
system
9 days Fri 03-05-19 Fri 17-05-19
4.7
Milestone 4: Completion of
execution phase
0 days Fri 17-05-19 Fri 17-05-19
5 Testing Phase 19 days Fri 17-05-19 Thu 13-06-19
5.1 Hardware testing 7 days Fri 17-05-19 Tue 28-05-19
PROJECT MANAGEMENT
3.1 Blueprint design 7 days Thu 20-12-18 Fri 28-12-18
3.2 IT needs assigned 6 days Mon 31-12-18 Mon 07-01-19
3.3
Purchasing needed
requirements
7 days Tue 08-01-19 Wed 16-01-19
3.4
Software development
recruitment
20 days Thu 17-01-19 Wed 13-02-19
3.5
Milestone 3: Completion of
project design
0 days Wed 13-02-19 Wed 13-02-19
4 Development phase 61.75 days Thu 14-02-19 Fri 17-05-19
4.1 Assigning new hardware 7 days Thu 14-02-19 Fri 22-02-19
4.2 assigning new software 8 days Mon 25-02-19 Wed 06-03-19
4.3
Development of data
warehouse
20 days Thu 07-03-19 Wed 03-04-19
4.4
Development of network
system
10 days Thu 04-04-19 Wed 17-04-19
4.5 Security System application 10 days Thu 18-04-19 Fri 03-05-19
4.6
Interconnection between
developed overall information
system
9 days Fri 03-05-19 Fri 17-05-19
4.7
Milestone 4: Completion of
execution phase
0 days Fri 17-05-19 Fri 17-05-19
5 Testing Phase 19 days Fri 17-05-19 Thu 13-06-19
5.1 Hardware testing 7 days Fri 17-05-19 Tue 28-05-19
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
5.2 Software testing 7 days Tue 28-05-19 Thu 06-06-19
5.3 Data Warehouse Testing 5 days Thu 06-06-19 Thu 13-06-19
5.4
Milestone 5:Completion of
testing phase
0 days Thu 13-06-19 Thu 13-06-19
6 Closing Phase 11.25 days Thu 13-06-19 Fri 28-06-19
6.1 Project review 2 days Thu 13-06-19 Mon 17-06-19
6.2 Stakeholder sign off 4 days Mon 17-06-19 Fri 21-06-19
6.3
Maintenance of the Data
Warehouse
5.25 days Fri 21-06-19 Fri 28-06-19
6.4
Milestone 6:Completion of
closure phase'
0 days Fri 28-06-19 Fri 28-06-19
5. Project calendar
Start Date: Fri 05-10-18
Finish Date: Fri 28-06-19
Weekends: Saturday and Sunday (holiday)
Public holidays
Melbourne Cup day 06-11-2018
Christmas day 25-12-18
Boxing day 26-12-18
New year day 01-01-19
Australia day 28-01-19
Labour day 04-03-19
Canberra day 11-03-19
PROJECT MANAGEMENT
5.2 Software testing 7 days Tue 28-05-19 Thu 06-06-19
5.3 Data Warehouse Testing 5 days Thu 06-06-19 Thu 13-06-19
5.4
Milestone 5:Completion of
testing phase
0 days Thu 13-06-19 Thu 13-06-19
6 Closing Phase 11.25 days Thu 13-06-19 Fri 28-06-19
6.1 Project review 2 days Thu 13-06-19 Mon 17-06-19
6.2 Stakeholder sign off 4 days Mon 17-06-19 Fri 21-06-19
6.3
Maintenance of the Data
Warehouse
5.25 days Fri 21-06-19 Fri 28-06-19
6.4
Milestone 6:Completion of
closure phase'
0 days Fri 28-06-19 Fri 28-06-19
5. Project calendar
Start Date: Fri 05-10-18
Finish Date: Fri 28-06-19
Weekends: Saturday and Sunday (holiday)
Public holidays
Melbourne Cup day 06-11-2018
Christmas day 25-12-18
Boxing day 26-12-18
New year day 01-01-19
Australia day 28-01-19
Labour day 04-03-19
Canberra day 11-03-19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
Good Friday 19-04-2019
Easter Saturday 20-04-19
ENZAC day 25-04-19
Labour day 06-05-19
Queen’s birthday 09-06-19
PROJECT MANAGEMENT
Good Friday 19-04-2019
Easter Saturday 20-04-19
ENZAC day 25-04-19
Labour day 06-05-19
Queen’s birthday 09-06-19

8
PROJECT MANAGEMENT
6. PDM diagram and Gantt chart
The PDM diagram is provided below:
Figure 1: PDM diagram
(Source: Created by Author)
PROJECT MANAGEMENT
6. PDM diagram and Gantt chart
The PDM diagram is provided below:
Figure 1: PDM diagram
(Source: Created by Author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
Figure 2: Gantt chart
(Source: Created by Author)
PROJECT MANAGEMENT
Figure 2: Gantt chart
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
7. List and cost of resources
The list and cost of resources are provided in the below table:
Resource
Name
Type
Material
Label
Initials Group
Max.
Units
Std. Rate
Project
Manager
Work P 100% $ 250.00/hr
Project Sponsor Work 100% $ 200.00/hr
Contractor Work C 100% $ 210.00/hr
Risk Manager Work R 100% $ 220.00/hr
Designer Work D 100% $ 200.00/hr
Tester Work T 100% $ 200.00/hr
Business
Consultant
Work B 100% $ 180.00/hr
Financial
Manager
Work F 100% $ 170.00/hr
Team Leaders Work T 100% $ 160.00/hr
Supervisor Work 100% $ 140.00/hr
Hardware Material $ 8,000,000.00
Software Material S $ 7,000,000.00
Additional cost Material A $ 12,000,000.00
Network cost Material N $ 12,000,000.00
PROJECT MANAGEMENT
7. List and cost of resources
The list and cost of resources are provided in the below table:
Resource
Name
Type
Material
Label
Initials Group
Max.
Units
Std. Rate
Project
Manager
Work P 100% $ 250.00/hr
Project Sponsor Work 100% $ 200.00/hr
Contractor Work C 100% $ 210.00/hr
Risk Manager Work R 100% $ 220.00/hr
Designer Work D 100% $ 200.00/hr
Tester Work T 100% $ 200.00/hr
Business
Consultant
Work B 100% $ 180.00/hr
Financial
Manager
Work F 100% $ 170.00/hr
Team Leaders Work T 100% $ 160.00/hr
Supervisor Work 100% $ 140.00/hr
Hardware Material $ 8,000,000.00
Software Material S $ 7,000,000.00
Additional cost Material A $ 12,000,000.00
Network cost Material N $ 12,000,000.00

11
PROJECT MANAGEMENT
8. List and cost of resources schedule in the form of Gantt chart
The list as well as cost of resources in the form of Gantt chart are generally provided
below:
Figure 3: Cost of resources schedule in the form of Gantt chart
(Source: Created by Author)
PROJECT MANAGEMENT
8. List and cost of resources schedule in the form of Gantt chart
The list as well as cost of resources in the form of Gantt chart are generally provided
below:
Figure 3: Cost of resources schedule in the form of Gantt chart
(Source: Created by Author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 22
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.