ITC505 ICT Project Management: A Report on Teamwork and Reflection

Verified

Added on  2024/07/29

|24
|5165
|265
Report
AI Summary
This report delves into teamwork and reflection within the context of ITC505 ICT Project Management, focusing on the development of the i-Crop system for Globex Corp by Virtucon. It includes a project overview, detailing the system's motive to enhance transaction transparency and efficiency. The report outlines a team charter, specifying required skills for roles like analyst, project manager, software designer, and application developer. Meeting scenarios and team rules are described to ensure effective collaboration. A communication plan is presented, and reflections on team experiences are shared, comparing them with leadership qualities. The document emphasizes the importance of teamwork, clear communication, and ethical conduct for successful project completion. Desklib is your go-to for more solved assignments and study resources.
Document Page
ITC505 - ICT Project Management
Assessment item 2: Team work and reflection

1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Contents
Introduction
......................................................................................................................................3
Part One: Project Name / Team / Description
................................................................................. 4
Project Overview
.........................................................................................................................5
Motive of the system
................................................................................................................... 5
Team Charter
............................................................................................................................... 6
Meeting Scenarios
....................................................................................................................... 8
Team rules and expectations
......................................................................................................10
Views from Previous experiences
.........................................................................................10
Team values that are expected from the members of the team
..............................................10
Code of ethics required to be followed in the team
...............................................................11
Rules and expectations from team members
.........................................................................11
Part 2: Learning Cycles
................................................................................................................. 13
Team meetings structure
............................................................................................................13
Assigning roles prior to meeting
................................................................................................13
Part 3: Communication plan of the Project
....................................................................................16
Communication plan for i-Crop
.................................................................................................16
Part 4: Reflection
........................................................................................................................... 19
Experience gained from working in a team
............................................................................... 19
Comparing the experience with leadership quality
...................................................................19
Conclusion
..................................................................................................................................... 21
References
......................................................................................................................................22
2
Document Page
Introduction
Virtucon is one of the leading software and application developers in the Riverine region of

Australia. It has been identified that it is required by the company to develop a new software

system such that it might be able to effectively and efficiently take care of the online payments

and methods. The software would be developed for Globex Corp. Globex is one of the leading

farm and agro-based organization. The system would be developed for online transactions such

that the farmers of the company would be able to sell their crops and the customers would be

able to place their bids as well. The system will introduce transparency in the operations of the

business and the clients would be able to get the best product for the price that is being offered

by them. The system that is being developed is named i-Crop.

Being a long-standing client of Globex, it is important for Virtucon to take into consideration

that the best services should be delivered. In order to ensure the same, Virtucon has made sure

that the current systems of the company are not replaced. For this, the company has developed a

detailed project management plan which will discuss and provide deep insights into the various

essentials of project management and development such as communication plan, stakeholder

management, project description etc. These are the essential constraints and topic which would

be covered in this report.

3
Document Page
Part One: Project Name / Team / Description
Project description is one of the most essential constraints in the project. The project description

is the main document which provides specific and clear details about the project. I-Crop is one of

the most advanced online payment systems that would be implemented by Globex into their

operative systems. The project would not only help the company to manage the transaction but

will also help the clients and customers of the company to transparently conduct a transaction but

will also help the organisation to increase its goodwill in the market by making use of best and

updated systems (C hoi et. al., 2018). The description of the project that would be implemented

by the company in its systems has been provided below as follows:

Title
Description
Project Name
i-Crop
Associated Party 1
Virtucon website
Associated Party 2
Globex Corp.
Project branch
ICT technology
Type of project
Online cash management and payment system
Location
Australia
Description of team:
teamwork in the development of the project is one of the most essential
considerations that helps in ensuring the successful completion of the project. This makes its

primary responsibility of the manager to ensure that the project team is critically evaluated and

selected. Teamwork also helps in creation of human synergy and it helps in amplification of the

individual results to team results (Woodcock, 2017) . This signifies the individual contribution

made by each member of the team. The team description which will help in the development of

i-Crop has been provided below as follows:

List of Team Members

S. no.
Name Contact number
1
Member 1
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
2 Member 2
3
Member 3
4
Member 4
Project Overview

It has been found that there is a need to develop a transparent system such that the clients and

consumers are able to make transaction ins a hassle-free manner. The product offering and its

bids by the traditional method are taking time due to which it is required by the company to

ensure that these operations are conducted in a rapid pace and speed. This makes it important for

the project manager of the company to develop a system for the same (Yang et. al., 2015). in

order to do so, the company has approached its oldest software and computing solutions provider

Virtucon. The project that would be developed by Virtucon is named as i_Crop. I-Crop is an

online payment and sales system which allows the clients and suppliers that are associated with

Globex to make offerings about their products. This also allows the customers to see those offers

and make bids according to their needs and requirements. The transaction and payment would be

done entirely over the gateway of the system and this will also boost up the speed of operations

as well.

Motive of the system

The motive of the system has been provided below as follows:

To remove the interference of middleman from a transaction between consumers and
suppliers;

To ensure that transaction is being done in an efficient and fast;
To introduce transparency into the transactions;
To provide a hassle-free experience to both customers and suppliers
5
Document Page
Team Charter
Team charter can be defined as the document which identifies the roles and responsibilities of

the persons that are associated with the development of the project. It also outlines the skills that

are required in order to signify their role and contribution in the development of the project. The

team charter for the development of i-Crop has been provided below as follows:

S.N

o

Title
Knowledge and skills required
1
Company
analyst

It is important for the analyst of the company to show effective

communication skill such that he might be able to facilitate meetings

with clients and stakeholders of the project. It should be noted that in

the development of project there might be various issues and problems

faced. It is the duty of company analyst to possess problem-solving

skills. In order to do the same, it is also important to possess criteria

thinking and analysing skills (Takey & Carvalho, 2015).

2
Project
manager

The project manager is the person that is responsible for timely and

successful completion of the project. In order to do the same, the

project manager of the company is required to possess the skill of

scheduling and project planning. It is also important that the project

manager is able to determine the risks in project and also makes a

budget for the same. a project manager is also able to have effective

leadership and management skills as well (Takey & Carvalho, 2015).

3
Software
designer

The software designer that would be working to develop the system

should be well equipped with the knowledge regarding Java,

Netbeans, C++, PERL, PHP, CSS etc. He should also possess the

knowled
ge regarding managing and work with SEO (Card, 2017). It is
important for the software designer to possess communication skills

such that he might be able to conduct meetings with consumers and is

also able to understand their requirements regarding the project as

well.

4
Application Application developer for i-Crop is required to have a good sense of
6
Document Page
developer designing and have an effective understanding of the interface as well.
It is important that the application developer should be creative as

well which will enhance the final product. Technical skills that are

required by the application developer include command on HTMS,

CSS and CMS. The application developer should also be able to the

use the master control version as well (Card, 2017).

5
Maintenance
manager

After the system is developed it is essential that the product should be

maintained which will ensure working of the system effectively in the

long run. This calls for appointment of the maintenance manager that

is required to possess administrative and planning skills. The

maintenance manager should be responsible enough which will ensure

that he keeps a constant check on security and safety of the

application.

6
Financial
analyst

The financial analyst is required to have proper knowledge about the

total cost of the project. It is required that the analyst should develop a

constructive breakdown structure for the same

7
Testing
personnel

The testing manager of the project should be able to understand the

working of the software and use QA tools and processes as well. The

manager should also have effective knowledge about the trends

related to technological advancement. He should also be able to test

the code and document the test plans and research new tools for

testing as well. The testing personnel should also be able to identify

various problems as well such that loopholes and bugs can be tested

(Sekaran & Bougie, 2016).

8
Database
manager

The database manager of the company plays a critical part in the

development of the project. This makes it important that he should

have effective database management and modelling skills. He should

be able to ensure metadata management, data security and data

integrity stay to the optimum levels. The database manager should

also possess critical knowledge regarding business management and

ERP as well.

7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
8
Document Page
Meeting Scenarios
Member meets 1

Meeting topic
Timings for meeting Actions required to
be implemented

Viewpoints of the

majority

Planning and

discussing the

design of application

1
st slot: 10 AM to 1
PM

Planning the design

and interface of the i-

Crop application

Majority of the team

members have agreed

upon the design that

has been chosen.

2
nd slot: 3 PM to 6
PM

Discussing the

methods that are

required to be taken

such that best design

and structure of the

application can be

made

Majority of the

members have agreed

to the methods that

have been seeking to

develop the interface

of the application.

Member meets 2

Meeting topic
Timings for meeting Actions required to
be implemented

Viewpoints of the

majority

Discussing the cost

implied in the

development of the

application system

1
st slot: 10 AM to 1
PM

Planning the total

cost that would be

implied in the

development of the

system.

During the discussion

of the total cost that

would be implied in

order to impellent the

system, it has been

identified that the

reactions were mixed

as there were some

members that did not

agree to the current

9
Document Page
pricing scheme of the
project.

2
nd slot: 3 PM to 6
PM

Identifying the

resources that would

be required in order

to develop the

system. It is inclusive

of human as well as

the material resources

that would be

required.

All the members have

agreed to the human

and material resource

requirements that

would help in

successful

completion of the

project.

Meeting 3

Meeting topic
Timings for meeting Actions required to
be implemented

Viewpoints of the

majority

Discussing the

performance of the

system after

conducting tests

1
st slot: 10 AM to 1
PM

Discussing the

performance of the

system after

conducting the

successful tests on

the working of

system

It should be noted

that there were

various issues that

were found in the

working of the

system. Apart from

small bugs, the

software ran

successfully and all

the members of the

team were happy and

satisfied after its

performance

2
nd slot: 3 PM to 6
PM

Implementing

methods to resolve

It should be noted

that there are several

10
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
the issues and
loopholes have been

found in the

development of the

system

methods that can be

effectively taken into

consideration. These

methods were argued

upon by the team

members that are

indulged in the

development of the

project.

Team rules and expectations

Views from Previous experiences

As a senior manager of IT project, it is my duty to effectively manage and coordinate the

working of team such that the team might be able to complete the project in a successful manner

and also in the stipulated time as well. From my previous experiences in the same field, it has

been made sure that it is important for me to ensure that the clients and consumers are respected

and the system developed is effectively able to address their needs and expectations as well. In

order to do the same, it is important that I should also conduct employee meeting and also train

them as well such that they might be able to work in an effective and efficient manner (Cox &

Bobrowski, 2016). Effective decision making is one of the most essential and critical

requirements of the project that might help in ensuring that the project enhances the value of

organisation.

Goal of the team:
To achieve the main motive of successful development of i-Crop system and
enhance the value of consumers of the company.

Team values that are expected from the members of the team

There are some core values that the project manager of the organisation that the project manager

of the company wants to indulge in each and every member of team. These can also be stated as

the DNA that is required in the team. Team values can enhance the working of the team also this

11
Document Page
might also help in making sure that the team is working in a smooth and efficient manner as
well. The core values that are expected in the management and development team of i-Crop are:

Listening to ideas from each team member with an open mind and without any
interruption as well.

Sharing the knowledge and experience in the team meetings such that personal and
professional development of the employees can be enhanced.

The key decisions in the team should be based on the reasoning and practicality and not
on the basis of rank.

The team culture should be based on responsibility and not on blame.
The operations of the team should be targeted to improve the experience of consumers.
Team should also strive for continuous and rapid development as well.
Team members should behave with integrity (McChrystal, 2015).
Team members should positively challenge destructive and dishonest practices in the
development of the team.

Code of ethics required to be followed in the team

The ethical code that is required to be followed during the development of the project have been

stated below as follows:

Consumer satisfaction should be the main focus of the team;
There should be no deviation in the quality of the project that is being completed;
The team members are required to show honest and competent behaviour towards the
development of the project;

All the members of the team are required to show a professional code of conduct until the
project is completed in a successful manner (Brewer, 2015).

Rules and expectations from team members

The rules and expectations from the team have been presented below as follows:

It is required that the team should initiate the project on time such that the completion can
also be ensured on time;