Detailed Analysis of JIT/Lean Production, Procurement & Contracts
VerifiedAdded on 2023/06/04
|21
|3065
|334
Case Study
AI Summary
This case study analyzes a scenario involving a framing contractor and a construction project to build 45 houses over two years, focusing on JIT/Lean production principles, procurement strategies, and contract management. The analysis compares the cost of hiring the framer at a fixed rate of $13,500 per unit versus using the average market rate, which is $15,000 per unit and increases by 10% every three months. The study evaluates whether to proceed with the framer contract, considering the need for a $5,000 equipment purchase and payment terms. It also assesses the impact of increasing production to 45 units per year and the implications of the market rate stabilizing at $13,500 per unit. Additionally, the case study discusses supplier selection based on spend analysis data, cost tolerance between regions, and the impact of PST changes, with reference to legal frameworks and relevant Canadian regulations. The study provides detailed tables and computations to support the analysis and recommendations.

Running head: JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
JIT/Lean Production, Procurement and Contracts
Name of the Student
Name of the University
Authors Note
Course ID
JIT/Lean Production, Procurement and Contracts
Name of the Student
Name of the University
Authors Note
Course ID
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Table of Contents
Answer to Question 1.................................................................................................................2
Answer to Part A........................................................................................................................2
Answer to Part B..................................................................................................................11
Answer to Part C..................................................................................................................14
Answer to Question 2...............................................................................................................14
Answer to Part A..................................................................................................................14
Answer to Part B..................................................................................................................15
Answer to Part C..................................................................................................................15
Answer to Part D..................................................................................................................15
Answer to Part E..................................................................................................................16
Answer to Question 3...............................................................................................................16
Answer to Part A..................................................................................................................17
Answer to Part B..................................................................................................................17
Answer to Part C..................................................................................................................17
Answer to Part D..................................................................................................................17
References................................................................................................................................19
Table of Contents
Answer to Question 1.................................................................................................................2
Answer to Part A........................................................................................................................2
Answer to Part B..................................................................................................................11
Answer to Part C..................................................................................................................14
Answer to Question 2...............................................................................................................14
Answer to Part A..................................................................................................................14
Answer to Part B..................................................................................................................15
Answer to Part C..................................................................................................................15
Answer to Part D..................................................................................................................15
Answer to Part E..................................................................................................................16
Answer to Question 3...............................................................................................................16
Answer to Part A..................................................................................................................17
Answer to Part B..................................................................................................................17
Answer to Part C..................................................................................................................17
Answer to Part D..................................................................................................................17
References................................................................................................................................19

2JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Answer to Question 1
Answer to Part A
As per the present contract the total cost as per the market rate is more expensive. The
total framer price at market rate is depicted to be $ 1482420 over a time period of two years.
On the other hand, the price at framer rate is $ 612500 which is $ 869920 more than the price
at market rate. Therefore, it is advisable to proceed with the contract by making a payment
term of net 30. In addition to this, these are directly relevant to legal framework of
procurement in Canada as per “Tercon Contractors Ltd. v. British Columbia
(Transportation and Highways)”. (Mohammadi, Soleymani and Mozafari 2014).
Average Market Framing Rate 15000 per unit
Framer Rate 13500 per unit
Average market increase rate 10% 90 Days
No. of Units to be built 45 2 Years
Cost of Equipment $5,000
Payment terms 30
Time Required (45 Units) 945 Days
Computation of Price to frame Houses at Market Rate
Particulars Units Amount ($)
Answer to Question 1
Answer to Part A
As per the present contract the total cost as per the market rate is more expensive. The
total framer price at market rate is depicted to be $ 1482420 over a time period of two years.
On the other hand, the price at framer rate is $ 612500 which is $ 869920 more than the price
at market rate. Therefore, it is advisable to proceed with the contract by making a payment
term of net 30. In addition to this, these are directly relevant to legal framework of
procurement in Canada as per “Tercon Contractors Ltd. v. British Columbia
(Transportation and Highways)”. (Mohammadi, Soleymani and Mozafari 2014).
Average Market Framing Rate 15000 per unit
Framer Rate 13500 per unit
Average market increase rate 10% 90 Days
No. of Units to be built 45 2 Years
Cost of Equipment $5,000
Payment terms 30
Time Required (45 Units) 945 Days
Computation of Price to frame Houses at Market Rate
Particulars Units Amount ($)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 1
Week 2
Week 3
Week 4 1 15000
Week 5
Week 6
Week 7
Week 8 1 15000
Week 9
Week 10
Week 11
Week 12 1 16500
Week 13
Week 14
Week 15
Week 16 1 16500
Week 17
Week 18
Week 19
Week 20 1 16500
Week 21
Week 22
Week 23
Week 24 1 18150
Week 25
Week 26
Week 27
Week 28 1 18150
Week 29
Week 30
Week 31
Week 32 1 18150
Week 33
Week 34
Week 35
Week 36 1 19965
Week 37
Week 38
Week 39
Week 40 1 19965
Week 41
Week 42
Week 43
Week 44 1 19965
Week 45
Week 46
Week 1
Week 2
Week 3
Week 4 1 15000
Week 5
Week 6
Week 7
Week 8 1 15000
Week 9
Week 10
Week 11
Week 12 1 16500
Week 13
Week 14
Week 15
Week 16 1 16500
Week 17
Week 18
Week 19
Week 20 1 16500
Week 21
Week 22
Week 23
Week 24 1 18150
Week 25
Week 26
Week 27
Week 28 1 18150
Week 29
Week 30
Week 31
Week 32 1 18150
Week 33
Week 34
Week 35
Week 36 1 19965
Week 37
Week 38
Week 39
Week 40 1 19965
Week 41
Week 42
Week 43
Week 44 1 19965
Week 45
Week 46
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 47
Week 48 1 21961.5
Week 49
Week 50
Week 51
Week 52 1 21961.5
Week 53
Week 54
Week 55
Week 56 1 21961.5
Week 57
Week 58
Week 59
Week 60 1 24157.65
Week 61
Week 62
Week 63
Week 64 1 24157.65
Week 65
Week 66
Week 67
Week 68 1 24157.65
Week 69
Week 70
Week 71
Week 72 1 26573.415
Week 73
Week 74
Week 75
Week 76 1 26573.415
Week 77
Week 78
Week 79
Week 80 1 26573.415
Week 81
Week 82
Week 83
Week 84 1 29230.7565
Week 85
Week 86
Week 87
Week 88 1 29230.7565
Week 89
Week 90
Week 91
Week 92 1 29230.7565
Week 47
Week 48 1 21961.5
Week 49
Week 50
Week 51
Week 52 1 21961.5
Week 53
Week 54
Week 55
Week 56 1 21961.5
Week 57
Week 58
Week 59
Week 60 1 24157.65
Week 61
Week 62
Week 63
Week 64 1 24157.65
Week 65
Week 66
Week 67
Week 68 1 24157.65
Week 69
Week 70
Week 71
Week 72 1 26573.415
Week 73
Week 74
Week 75
Week 76 1 26573.415
Week 77
Week 78
Week 79
Week 80 1 26573.415
Week 81
Week 82
Week 83
Week 84 1 29230.7565
Week 85
Week 86
Week 87
Week 88 1 29230.7565
Week 89
Week 90
Week 91
Week 92 1 29230.7565

5JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 93
Week 94
Week 95
Week 96 1 32153.83215
Week 97
Week 98
Week 99
Week 100 1 32153.83215
Week 101
Week 102
Week 103
Week 104 1 32153.83215
Week 105
Week 106
Week 107
Week 108 1 35369.21537
Week 109
Week 110
Week 111
Week 112 1 35369.21537
Week 113
Week 114
Week 115
Week 116 1 35369.21537
Week 117
Week 118
Week 119
Week 120 1 38906.1369
Week 121
Week 122
Week 123
Week 124 1 38906.1369
Week 125
Week 126
Week 127
Week 128 1 38906.1369
Week 129
Week 130
Week 131
Week 132 1 42796.75059
Week 133
Week 134
Week 135
Week 136 1 42796.75059
Week 137
Week 138
Week 93
Week 94
Week 95
Week 96 1 32153.83215
Week 97
Week 98
Week 99
Week 100 1 32153.83215
Week 101
Week 102
Week 103
Week 104 1 32153.83215
Week 105
Week 106
Week 107
Week 108 1 35369.21537
Week 109
Week 110
Week 111
Week 112 1 35369.21537
Week 113
Week 114
Week 115
Week 116 1 35369.21537
Week 117
Week 118
Week 119
Week 120 1 38906.1369
Week 121
Week 122
Week 123
Week 124 1 38906.1369
Week 125
Week 126
Week 127
Week 128 1 38906.1369
Week 129
Week 130
Week 131
Week 132 1 42796.75059
Week 133
Week 134
Week 135
Week 136 1 42796.75059
Week 137
Week 138
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 139
Week 140 1 42796.75059
Week 141
Week 142
Week 143
Week 144 1 47076.42565
Week 145
Week 146
Week 147
Week 148 1 47076.42565
Week 149
Week 150
Week 151
Week 152 1 47076.42565
Week 153
Week 154
Week 155
Week 156 1 51784.06822
Week 157
Week 158
Week 159
Week 160 1 51784.06822
Week 161
Week 162
Week 163
Week 164 1 51784.06822
Week 165
Week 166
Week 167
Week 168 1 56962.47504
Week 169
Week 170
Week 171
Week 172 1 56962.47504
Week 173
Week 174
Week 175
Week 176 1 56962.47504
Week 177
Week 178
Week 179
Week 180 1 62658.72254
Required Equipment Cost 5000
Total 45 1482420
Week 139
Week 140 1 42796.75059
Week 141
Week 142
Week 143
Week 144 1 47076.42565
Week 145
Week 146
Week 147
Week 148 1 47076.42565
Week 149
Week 150
Week 151
Week 152 1 47076.42565
Week 153
Week 154
Week 155
Week 156 1 51784.06822
Week 157
Week 158
Week 159
Week 160 1 51784.06822
Week 161
Week 162
Week 163
Week 164 1 51784.06822
Week 165
Week 166
Week 167
Week 168 1 56962.47504
Week 169
Week 170
Week 171
Week 172 1 56962.47504
Week 173
Week 174
Week 175
Week 176 1 56962.47504
Week 177
Week 178
Week 179
Week 180 1 62658.72254
Required Equipment Cost 5000
Total 45 1482420
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Framer Rate 13500 per unit
Average framer increase rate 0% 90 Days
No. of Units to be built 45 2 Years
Cost of Equipment $5,000
Payment terms 30
Time Required (45 Units) 945 Days
Computation of Price to frame Houses at Framer Rate
Particulars Units Amount ($)
Week 1
Week 2
Week 3
Week 4 1 13500
Week 5
Week 6
Week 7
Week 8 1 13500
Week 9
Week 10
Week 11
Week 12 1 13500
Week 13
Week 14
Week 15
Week 16 1 13500
Week 17
Week 18
Week 19
Week 20 1 13500
Week 21
Week 22
Week 23
Week 24 1 13500
Week 25
Week 26
Week 27
Week 28 1 13500
Week 29
Week 30
Week 31
Framer Rate 13500 per unit
Average framer increase rate 0% 90 Days
No. of Units to be built 45 2 Years
Cost of Equipment $5,000
Payment terms 30
Time Required (45 Units) 945 Days
Computation of Price to frame Houses at Framer Rate
Particulars Units Amount ($)
Week 1
Week 2
Week 3
Week 4 1 13500
Week 5
Week 6
Week 7
Week 8 1 13500
Week 9
Week 10
Week 11
Week 12 1 13500
Week 13
Week 14
Week 15
Week 16 1 13500
Week 17
Week 18
Week 19
Week 20 1 13500
Week 21
Week 22
Week 23
Week 24 1 13500
Week 25
Week 26
Week 27
Week 28 1 13500
Week 29
Week 30
Week 31

8JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 32 1 13500
Week 33
Week 34
Week 35
Week 36 1 13500
Week 37
Week 38
Week 39
Week 40 1 13500
Week 41
Week 42
Week 43
Week 44 1 13500
Week 45
Week 46
Week 47
Week 48 1 13500
Week 49
Week 50
Week 51
Week 52 1 13500
Week 53
Week 54
Week 55
Week 56 1 13500
Week 57
Week 58
Week 59
Week 60 1 13500
Week 61
Week 62
Week 63
Week 64 1 13500
Week 65
Week 66
Week 67
Week 68 1 13500
Week 69
Week 70
Week 71
Week 72 1 13500
Week 73
Week 74
Week 75
Week 76 1 13500
Week 77
Week 32 1 13500
Week 33
Week 34
Week 35
Week 36 1 13500
Week 37
Week 38
Week 39
Week 40 1 13500
Week 41
Week 42
Week 43
Week 44 1 13500
Week 45
Week 46
Week 47
Week 48 1 13500
Week 49
Week 50
Week 51
Week 52 1 13500
Week 53
Week 54
Week 55
Week 56 1 13500
Week 57
Week 58
Week 59
Week 60 1 13500
Week 61
Week 62
Week 63
Week 64 1 13500
Week 65
Week 66
Week 67
Week 68 1 13500
Week 69
Week 70
Week 71
Week 72 1 13500
Week 73
Week 74
Week 75
Week 76 1 13500
Week 77
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 78
Week 79
Week 80 1 13500
Week 81
Week 82
Week 83
Week 84 1 13500
Week 85
Week 86
Week 87
Week 88 1 13500
Week 89
Week 90
Week 91
Week 92 1 13500
Week 93
Week 94
Week 95
Week 96 1 13500
Week 97
Week 98
Week 99
Week 100 1 13500
Week 101
Week 102
Week 103
Week 104 1 13500
Week 105
Week 106
Week 107
Week 108 1 13500
Week 109
Week 110
Week 111
Week 112 1 13500
Week 113
Week 114
Week 115
Week 116 1 13500
Week 117
Week 118
Week 119
Week 120 1 13500
Week 121
Week 122
Week 123
Week 78
Week 79
Week 80 1 13500
Week 81
Week 82
Week 83
Week 84 1 13500
Week 85
Week 86
Week 87
Week 88 1 13500
Week 89
Week 90
Week 91
Week 92 1 13500
Week 93
Week 94
Week 95
Week 96 1 13500
Week 97
Week 98
Week 99
Week 100 1 13500
Week 101
Week 102
Week 103
Week 104 1 13500
Week 105
Week 106
Week 107
Week 108 1 13500
Week 109
Week 110
Week 111
Week 112 1 13500
Week 113
Week 114
Week 115
Week 116 1 13500
Week 117
Week 118
Week 119
Week 120 1 13500
Week 121
Week 122
Week 123
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 124 1 13500
Week 125
Week 126
Week 127
Week 128 1 13500
Week 129
Week 130
Week 131
Week 132 1 13500
Week 133
Week 134
Week 135
Week 136 1 13500
Week 137
Week 138
Week 139
Week 140 1 13500
Week 141
Week 142
Week 143
Week 144 1 13500
Week 145
Week 146
Week 147
Week 148 1 13500
Week 149
Week 150
Week 151
Week 152 1 13500
Week 153
Week 154
Week 155
Week 156 1 13500
Week 157
Week 158
Week 159
Week 160 1 13500
Week 161
Week 162
Week 163
Week 164 1 13500
Week 165
Week 166
Week 167
Week 168 1 13500
Week 169
Week 124 1 13500
Week 125
Week 126
Week 127
Week 128 1 13500
Week 129
Week 130
Week 131
Week 132 1 13500
Week 133
Week 134
Week 135
Week 136 1 13500
Week 137
Week 138
Week 139
Week 140 1 13500
Week 141
Week 142
Week 143
Week 144 1 13500
Week 145
Week 146
Week 147
Week 148 1 13500
Week 149
Week 150
Week 151
Week 152 1 13500
Week 153
Week 154
Week 155
Week 156 1 13500
Week 157
Week 158
Week 159
Week 160 1 13500
Week 161
Week 162
Week 163
Week 164 1 13500
Week 165
Week 166
Week 167
Week 168 1 13500
Week 169

11JIT/LEAN PRODUCTION, PROCUREMENT AND CONTRACTS
Week 170
Week 171
Week 172 1 13500
Week 173
Week 174
Week 175
Week 176 1 13500
Week 177
Week 178
Week 179
Week 180 1 13500
Required Equipment Cost 5000
Total 45 612500
Answer to Part B
In case the project start is increased to 45 units per year then the production rate from
three weeks per unit should be increased to 2 weeks per unit. In this proposition, the overall
cost reduction will be seen with 50% in compared to producing 45 units in two years.
Framer Rate 13500 per unit
Average framer increase rate 0% 90 Days
No. of Units to be built 45 1 Year
Cost of Equipment $5,000
Payment terms 30
Time Required (45 Units) 945 Days
Computation of Price to frame Houses at Framer Rate
Particulars Units Amount ($)
Week 1
Week 2 1
Week 3
Week 4 1 13500
Week 5
Week 6 1
Week 7
Week 8 1 13500
Week 170
Week 171
Week 172 1 13500
Week 173
Week 174
Week 175
Week 176 1 13500
Week 177
Week 178
Week 179
Week 180 1 13500
Required Equipment Cost 5000
Total 45 612500
Answer to Part B
In case the project start is increased to 45 units per year then the production rate from
three weeks per unit should be increased to 2 weeks per unit. In this proposition, the overall
cost reduction will be seen with 50% in compared to producing 45 units in two years.
Framer Rate 13500 per unit
Average framer increase rate 0% 90 Days
No. of Units to be built 45 1 Year
Cost of Equipment $5,000
Payment terms 30
Time Required (45 Units) 945 Days
Computation of Price to frame Houses at Framer Rate
Particulars Units Amount ($)
Week 1
Week 2 1
Week 3
Week 4 1 13500
Week 5
Week 6 1
Week 7
Week 8 1 13500
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 21
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.




