This report details the project management plan for the construction of a new manufacturing site for JKB Bloggins Ltd. It encompasses various aspects of project management, including the type of project, scope management utilizing tools like Work Breakdown Structure (WBS), and a comparison between Gantt charts and critical paths. The report also covers project success evaluation, change management plans, and methods for ensuring project success. Furthermore, it provides an introduction to the project, outlining its purpose, background, and approach, which follows an Agile lifecycle. It defines the required skills and competencies of the project manager, establishes goals and objectives, and details the scope statement, project deliverables, and milestones. Technical requirements, limits, and exclusions are also identified. The report includes a Work Breakdown Structure, stakeholder analysis, project team structure, project scheduling (Gantt chart and network diagram), resource plan, risk plan, communication plan, monitoring process, and evaluation and closure strategies. Finally, it offers a conclusion and references to support the findings.

Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
Task 1...............................................................................................................................................3
1. Type of project for JKB Bloggins Ltd.....................................................................................3
2. Scope Management and tools useful for the scope subdivision..............................................3
3. Difference between Gantt chart and critical path....................................................................4
4. Project Success Evaluation......................................................................................................4
5. Change Management Plan.......................................................................................................4
6. Methods of Project Success.....................................................................................................5
Task 2...............................................................................................................................................6
Introduction..................................................................................................................................6
Purpose of the Plan..................................................................................................................6
Project Background.................................................................................................................6
Project Approach (Project Lifecycle Description)..................................................................6
Skills and Competencies required by Project Manager...........................................................7
Goals and Objectives...................................................................................................................8
Scope (Scope Statement).............................................................................................................8
Project Deliverables.................................................................................................................8
Project Milestone.....................................................................................................................9
Technical Requirements........................................................................................................10
Limits and Exclusions............................................................................................................10
Table of Contents
Task 1...............................................................................................................................................3
1. Type of project for JKB Bloggins Ltd.....................................................................................3
2. Scope Management and tools useful for the scope subdivision..............................................3
3. Difference between Gantt chart and critical path....................................................................4
4. Project Success Evaluation......................................................................................................4
5. Change Management Plan.......................................................................................................4
6. Methods of Project Success.....................................................................................................5
Task 2...............................................................................................................................................6
Introduction..................................................................................................................................6
Purpose of the Plan..................................................................................................................6
Project Background.................................................................................................................6
Project Approach (Project Lifecycle Description)..................................................................6
Skills and Competencies required by Project Manager...........................................................7
Goals and Objectives...................................................................................................................8
Scope (Scope Statement).............................................................................................................8
Project Deliverables.................................................................................................................8
Project Milestone.....................................................................................................................9
Technical Requirements........................................................................................................10
Limits and Exclusions............................................................................................................10

2PROJECT MANAGEMENT
Work Breakdown Structure...................................................................................................10
Stakeholder Analysis.................................................................................................................11
Project Team Structure..............................................................................................................12
Project Scheduling.....................................................................................................................12
Project Gantt chart.................................................................................................................16
Network Diagram..................................................................................................................17
Resource Plan............................................................................................................................17
Risk Plan....................................................................................................................................18
Communication Plan.................................................................................................................19
Monitoring Process....................................................................................................................20
Evaluation and Closure..............................................................................................................20
Conclusion.................................................................................................................................20
Bibliography..............................................................................................................................22
Appendices................................................................................................................................27
Appendix A: Work Breakdown Structure.............................................................................27
Appendix B: Gantt chart........................................................................................................28
Appendix C: Critical Path......................................................................................................29
Appendix D: Network Diagram.............................................................................................30
Appendix E: Time Phased Budget.........................................................................................31
Work Breakdown Structure...................................................................................................10
Stakeholder Analysis.................................................................................................................11
Project Team Structure..............................................................................................................12
Project Scheduling.....................................................................................................................12
Project Gantt chart.................................................................................................................16
Network Diagram..................................................................................................................17
Resource Plan............................................................................................................................17
Risk Plan....................................................................................................................................18
Communication Plan.................................................................................................................19
Monitoring Process....................................................................................................................20
Evaluation and Closure..............................................................................................................20
Conclusion.................................................................................................................................20
Bibliography..............................................................................................................................22
Appendices................................................................................................................................27
Appendix A: Work Breakdown Structure.............................................................................27
Appendix B: Gantt chart........................................................................................................28
Appendix C: Critical Path......................................................................................................29
Appendix D: Network Diagram.............................................................................................30
Appendix E: Time Phased Budget.........................................................................................31
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
Task 1
1. Type of project for JKB Bloggins Ltd
The project for the JKB Bloggins Ltd would include the development of a specific site
building along with the required equipments. The type of the project is Market Driven as the
construction of the building for JKB Bloggins Ltd. is inspired from the needs of the customer
and to some extent the trend of the market.
The JKB Bloggins Ltd is employed for the development of their operations with the
manufacturing of the new building for the construction and installing new equipments. The
market driven project is implied for the formation of the effective employment (Fleming and
Koppelman 2016). The integration of the deployed methods would be formed for the
development of the operations of JKB Bloggins Ltd and it would form the management of the
operations.
2. Scope Management and tools useful for the scope subdivision
According to Devaux (2014), the scope management is a process of ensuring that all the
required works in the project is include so that the project can be completed successfully along
with controlling the project. The alignment of the project in scope items is formed for ensuring
that the project is aligned successfully.
The scope management is deployed for ensuring that all crucial works of the projects is
implied for the development of the improved functional analysis along with the integration of the
operations (Schwalbe 2015). The management of the operations would be formed for the
alignment of the project management principles for JKB Bloggins Ltd. The use of the WBS
Task 1
1. Type of project for JKB Bloggins Ltd
The project for the JKB Bloggins Ltd would include the development of a specific site
building along with the required equipments. The type of the project is Market Driven as the
construction of the building for JKB Bloggins Ltd. is inspired from the needs of the customer
and to some extent the trend of the market.
The JKB Bloggins Ltd is employed for the development of their operations with the
manufacturing of the new building for the construction and installing new equipments. The
market driven project is implied for the formation of the effective employment (Fleming and
Koppelman 2016). The integration of the deployed methods would be formed for the
development of the operations of JKB Bloggins Ltd and it would form the management of the
operations.
2. Scope Management and tools useful for the scope subdivision
According to Devaux (2014), the scope management is a process of ensuring that all the
required works in the project is include so that the project can be completed successfully along
with controlling the project. The alignment of the project in scope items is formed for ensuring
that the project is aligned successfully.
The scope management is deployed for ensuring that all crucial works of the projects is
implied for the development of the improved functional analysis along with the integration of the
operations (Schwalbe 2015). The management of the operations would be formed for the
alignment of the project management principles for JKB Bloggins Ltd. The use of the WBS
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
would be helpful for showing the sub divisions of the scope by the help of the work packages as
the work packages are aligned with the scope of the project.
3. Difference between Gantt chart and critical path
The full project Gantt chart is deployed for the development of the detailed project
schedule development (Walker 2015). The use of the specific Gantt chart would be helpful for
ensuring that the project schedule is developed successfully. The Gantt chart represents the
complete list of the activities of the project and it would form the development of the complete
analysis of the processes. However, the critical path helps in analysing the crucial and important
activities of the project. A critical path may omit the activities that can run along a critical project
activity or activities.
4. Project Success Evaluation
The project success evaluation can be done by analysing the activities of the project in
terms of the success factors (Larson and Gray 2013). The deployment of the success criteria
evaluation would be helpful for realizing the development of the project and evaluate the
progress. The project must be completed in the expected cost and time for ensuring the success
of the project.
5. Change Management Plan
The changes in the project can be managed by the help of the change management plan
and implying it for the successful change implication (Devaux 2014). A project might require the
modification of the operations, scope or activities and the change management plan helps in
ensuring that the changes of the project are implied successfully. The change management plan
would be helpful for showing the sub divisions of the scope by the help of the work packages as
the work packages are aligned with the scope of the project.
3. Difference between Gantt chart and critical path
The full project Gantt chart is deployed for the development of the detailed project
schedule development (Walker 2015). The use of the specific Gantt chart would be helpful for
ensuring that the project schedule is developed successfully. The Gantt chart represents the
complete list of the activities of the project and it would form the development of the complete
analysis of the processes. However, the critical path helps in analysing the crucial and important
activities of the project. A critical path may omit the activities that can run along a critical project
activity or activities.
4. Project Success Evaluation
The project success evaluation can be done by analysing the activities of the project in
terms of the success factors (Larson and Gray 2013). The deployment of the success criteria
evaluation would be helpful for realizing the development of the project and evaluate the
progress. The project must be completed in the expected cost and time for ensuring the success
of the project.
5. Change Management Plan
The changes in the project can be managed by the help of the change management plan
and implying it for the successful change implication (Devaux 2014). A project might require the
modification of the operations, scope or activities and the change management plan helps in
ensuring that the changes of the project are implied successfully. The change management plan

5PROJECT MANAGEMENT
is helpful for managing both internal and external changes. The activities of the change
management are,
1) Introduction of the process for submission, evaluation, and approval of the
changes
2) Definition of the guidelines for the team members
3) Review of the changes with the project team
4) Approval of the changes and communication of the changes concerned
5) Documentation and tracking of the changes for the project
Some changes that would be included in the project of constructing the new
manufacturing site for the JKB Blogging Ltd along with improved equipments and technology
are relocation, data migration, handling of new equipments, and alignment of the operations at
the new manufacturing site. The development of the change management plan would be helpful
for overcoming the issues of the changes and implement it successfully.
6. Methods of Project Success
The project evaluation, monitoring, and control are implied for ensuring that the project
is completed in the estimated time duration (Kerzner 2013). The development of the project
evaluation is done by evaluating the project in terms of cost and time. The Monitoring of the
project is done with the help of the development of the project progress report for ensuring that
the project is progressing as expected. The use of the project schedule and cost estimation plan
would be helpful in ensuring that the project is completed in the estimated time and budget. The
project progress report would help the operations of the project.
is helpful for managing both internal and external changes. The activities of the change
management are,
1) Introduction of the process for submission, evaluation, and approval of the
changes
2) Definition of the guidelines for the team members
3) Review of the changes with the project team
4) Approval of the changes and communication of the changes concerned
5) Documentation and tracking of the changes for the project
Some changes that would be included in the project of constructing the new
manufacturing site for the JKB Blogging Ltd along with improved equipments and technology
are relocation, data migration, handling of new equipments, and alignment of the operations at
the new manufacturing site. The development of the change management plan would be helpful
for overcoming the issues of the changes and implement it successfully.
6. Methods of Project Success
The project evaluation, monitoring, and control are implied for ensuring that the project
is completed in the estimated time duration (Kerzner 2013). The development of the project
evaluation is done by evaluating the project in terms of cost and time. The Monitoring of the
project is done with the help of the development of the project progress report for ensuring that
the project is progressing as expected. The use of the project schedule and cost estimation plan
would be helpful in ensuring that the project is completed in the estimated time and budget. The
project progress report would help the operations of the project.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
Task 2
Introduction
The project management unit has been playing a significant role in the development of
the improved processes. The alignment of the profound development would be helpful for
carrying out the development of the operations and forming the consideration of the operations.
The following assignment is formed for the development of a report for the project of
Construction of Manufacturing Site at JKB Bloggins Ltd. The report had covered the scope,
objectives, deliverables, milestone, project schedule, network diagram, work breakdown
structure, risk matrix, communication plan, and quality management. The alignment of the
project would help the analysis of the project formation.
Purpose of the Plan
The project had been formed for constructing a new site for the JKB Bloggins Ltd for
implementing their operations. The alignment of the project plan would help in forming the
development of the improved operations for the construction activities.
Project Background
The project is held responsible for the alignment of the operations and development of
the effective management process. The formation of the activities would be helpful for forming
the deployment of the effective project operations. The Construction of Manufacturing Site at
JKB Bloggins Ltd is helpful for integrating the formation of the manufacturing of the site for the
organization.
Project Approach (Project Lifecycle Description)
Task 2
Introduction
The project management unit has been playing a significant role in the development of
the improved processes. The alignment of the profound development would be helpful for
carrying out the development of the operations and forming the consideration of the operations.
The following assignment is formed for the development of a report for the project of
Construction of Manufacturing Site at JKB Bloggins Ltd. The report had covered the scope,
objectives, deliverables, milestone, project schedule, network diagram, work breakdown
structure, risk matrix, communication plan, and quality management. The alignment of the
project would help the analysis of the project formation.
Purpose of the Plan
The project had been formed for constructing a new site for the JKB Bloggins Ltd for
implementing their operations. The alignment of the project plan would help in forming the
development of the improved operations for the construction activities.
Project Background
The project is held responsible for the alignment of the operations and development of
the effective management process. The formation of the activities would be helpful for forming
the deployment of the effective project operations. The Construction of Manufacturing Site at
JKB Bloggins Ltd is helpful for integrating the formation of the manufacturing of the site for the
organization.
Project Approach (Project Lifecycle Description)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
The task of Development of New Manufacturing Site for JKB Bloggins Ltd. takes after
Agile (Adaptive) Lifecycle. The Agile undertaking lifecycle can be ordered into introductory
stage, arranging stage, outlining stage, execution stage, testing stage, and conclusion stage
(Martone et al. 2016). The underlying stage incorporates the improvement of the underlying
documentation and asset advancement. The arranging stage would include choosing an
undertaking design technique and building up the calendar for the task. The planning stage
would include influencing the outline for the working of the assembling to site. The execution
stage would contain the usage of the exercises for the undertaking. The testing stage would
include the examination of the results of the execution stage and alter the exercises if required.
The venture conclusion stage would contain the advancement of the exercises for definite
shutting of the undertaking.
Skills and Competencies required by Project Manager
The project manager plays a significant role in the development of the project and
completion of the project successfully. The complete management and alignment of the project
activities fall under the responsibility of the project manager. The skills and competencies
required by the project manager for this large project are listed in the table below,
Skills Competencies
Communication
Leadership
Team Management
Negotiation
Personal Organization
Execution
Decision Making
Strategy Development
Technical Competence
Critical Thinking
The task of Development of New Manufacturing Site for JKB Bloggins Ltd. takes after
Agile (Adaptive) Lifecycle. The Agile undertaking lifecycle can be ordered into introductory
stage, arranging stage, outlining stage, execution stage, testing stage, and conclusion stage
(Martone et al. 2016). The underlying stage incorporates the improvement of the underlying
documentation and asset advancement. The arranging stage would include choosing an
undertaking design technique and building up the calendar for the task. The planning stage
would include influencing the outline for the working of the assembling to site. The execution
stage would contain the usage of the exercises for the undertaking. The testing stage would
include the examination of the results of the execution stage and alter the exercises if required.
The venture conclusion stage would contain the advancement of the exercises for definite
shutting of the undertaking.
Skills and Competencies required by Project Manager
The project manager plays a significant role in the development of the project and
completion of the project successfully. The complete management and alignment of the project
activities fall under the responsibility of the project manager. The skills and competencies
required by the project manager for this large project are listed in the table below,
Skills Competencies
Communication
Leadership
Team Management
Negotiation
Personal Organization
Execution
Decision Making
Strategy Development
Technical Competence
Critical Thinking

8PROJECT MANAGEMENT
Risk Management Business Expert
Goals and Objectives
The objectives of the project of Construction of Manufacturing Site at JKB Bloggins Ltd
are given below,
To form the development of the project plan that would help in constructing the
manufacturing site for JKB Bloggins Ltd.
To complete the project in the estimated time and budget so that JKB Bloggins Ltd can
get the benefit
To successfully form the project of implementing the construction activities for aligning
the development of the new manufacturing site of JKB Bloggins Ltd
To recruit and train some candidates for working at the new manufacturing site of JKB
Bloggins Ltd.
Scope (Scope Statement)
The project of Construction of Manufacturing Site at JKB Bloggins Ltd consists of both
in scope and out of scope items. The project plan, documents, risk management plan, and
manufacturing site are the in scope items of the project. These should be included in the project
for the development of proper documents and alignment of the operations.
Project Deliverables
The deliverables for the project of Construction of Manufacturing Site at JKB Bloggins
Ltd are given below,
Risk Management Business Expert
Goals and Objectives
The objectives of the project of Construction of Manufacturing Site at JKB Bloggins Ltd
are given below,
To form the development of the project plan that would help in constructing the
manufacturing site for JKB Bloggins Ltd.
To complete the project in the estimated time and budget so that JKB Bloggins Ltd can
get the benefit
To successfully form the project of implementing the construction activities for aligning
the development of the new manufacturing site of JKB Bloggins Ltd
To recruit and train some candidates for working at the new manufacturing site of JKB
Bloggins Ltd.
Scope (Scope Statement)
The project of Construction of Manufacturing Site at JKB Bloggins Ltd consists of both
in scope and out of scope items. The project plan, documents, risk management plan, and
manufacturing site are the in scope items of the project. These should be included in the project
for the development of proper documents and alignment of the operations.
Project Deliverables
The deliverables for the project of Construction of Manufacturing Site at JKB Bloggins
Ltd are given below,
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
Documents: The Project Initiation and Charter Documents are made for the project in 7
days by Tue 10/4/16. The final documents of the project are made in 5 days by Tue 3/6/18.
Plan and Design: The complete reviewed plan is developed in 23 days by Thu 12/1/16
and the design is developed in 45 days by Thu 3/2/17.
Site and Structure: The site of the new manufacturing unit of JKB Bloggins Ltd is
bought for HK$ 6,000,000.00 on Mon 3/20/17. The structure of the building is built in 171 days
by Tue 12/19/17
Equipments and Materials: The materials are bought at a price of HK$ 2,789,200.00 on
Wed 5/10/17 and the equipments are bought at a price of HK$ 668,800.00 on Tue 11/21/17.
Final Documentation and Manufacturing Site: The final documentation is formed in 5
days by Tue 3/6/18. The manufacturing site will be in work by Thu 3/29/18.
Recruiting and Training of staff: The training and recruiting of staffs is another major
factor that would be required in the project. The training session would last of 12 months and it
would be helpful for the staff recruited for working at the new manufacturing site of JKB
Bloggins Ltd.
Project Milestone
The project plan consists of 6 phase namely initial phase, plan phase, design phase,
execution phase, documentation and approval phase, and closure phase and they act as
milestones of the project (Keatley et al. 2017). The milestone of the project of Construction of
Manufacturing Site at JKB Bloggins Ltd along with the time schedule is given in the table
below,
Documents: The Project Initiation and Charter Documents are made for the project in 7
days by Tue 10/4/16. The final documents of the project are made in 5 days by Tue 3/6/18.
Plan and Design: The complete reviewed plan is developed in 23 days by Thu 12/1/16
and the design is developed in 45 days by Thu 3/2/17.
Site and Structure: The site of the new manufacturing unit of JKB Bloggins Ltd is
bought for HK$ 6,000,000.00 on Mon 3/20/17. The structure of the building is built in 171 days
by Tue 12/19/17
Equipments and Materials: The materials are bought at a price of HK$ 2,789,200.00 on
Wed 5/10/17 and the equipments are bought at a price of HK$ 668,800.00 on Tue 11/21/17.
Final Documentation and Manufacturing Site: The final documentation is formed in 5
days by Tue 3/6/18. The manufacturing site will be in work by Thu 3/29/18.
Recruiting and Training of staff: The training and recruiting of staffs is another major
factor that would be required in the project. The training session would last of 12 months and it
would be helpful for the staff recruited for working at the new manufacturing site of JKB
Bloggins Ltd.
Project Milestone
The project plan consists of 6 phase namely initial phase, plan phase, design phase,
execution phase, documentation and approval phase, and closure phase and they act as
milestones of the project (Keatley et al. 2017). The milestone of the project of Construction of
Manufacturing Site at JKB Bloggins Ltd along with the time schedule is given in the table
below,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
WBS Task Name Duratio
n Start Finish
M1 Initial Phase 24 days Mon 9/19/16 Thu 10/20/16
M2 Plan Phase 23 days Tue 11/1/16 Thu 12/1/16
M3 Design Phase 45 days Fri 12/30/16 Thu 3/2/17
M4 Execution Phase 251 days Fri 3/3/17 Fri 2/16/18
M5 Documentation and Approval 22 days Wed 2/28/18 Thu 3/29/18
M6 Project is closed 1 day Fri 3/30/18 Fri 3/30/18
Table 1: Project Milestones with Schedule Duration
(Source: Created by the author)
Technical Requirements
The technical requirements of the project are Analyst, Documenter, Project Manager,
Planner, Designer, Client, Contractor, Workers, Engineer, Government Officer, Site,
Equipments, Iron Pillars, Cement, Brick, Sand, Clay, and Transportation Cost.
Limits and Exclusions
The transportation of the materials is aligned for the construction of the building site
where the manufacturing of the materials would take place. The out of scope of the project are
change management, transportation of the materials, and marketing of the event for the project.
Work Breakdown Structure
The work breakdown structure is developed for forming the specific work packages and
aligning the operations of the project for ensuring that the project is completed in specific time.
WBS Task Name Duratio
n Start Finish
M1 Initial Phase 24 days Mon 9/19/16 Thu 10/20/16
M2 Plan Phase 23 days Tue 11/1/16 Thu 12/1/16
M3 Design Phase 45 days Fri 12/30/16 Thu 3/2/17
M4 Execution Phase 251 days Fri 3/3/17 Fri 2/16/18
M5 Documentation and Approval 22 days Wed 2/28/18 Thu 3/29/18
M6 Project is closed 1 day Fri 3/30/18 Fri 3/30/18
Table 1: Project Milestones with Schedule Duration
(Source: Created by the author)
Technical Requirements
The technical requirements of the project are Analyst, Documenter, Project Manager,
Planner, Designer, Client, Contractor, Workers, Engineer, Government Officer, Site,
Equipments, Iron Pillars, Cement, Brick, Sand, Clay, and Transportation Cost.
Limits and Exclusions
The transportation of the materials is aligned for the construction of the building site
where the manufacturing of the materials would take place. The out of scope of the project are
change management, transportation of the materials, and marketing of the event for the project.
Work Breakdown Structure
The work breakdown structure is developed for forming the specific work packages and
aligning the operations of the project for ensuring that the project is completed in specific time.

11PROJECT MANAGEMENT
The work breakdown structure for the project of Construction of Manufacturing Site at JKB
Bloggins Ltd is in the appendix section of the report below.
Stakeholder Analysis
Resource Name
Analyst Analyzing the requirements
Documenter
Developing PID document, Charter
Documentation, Submission of the documents,
and Making final documents
Project Manager
Review and Sign off, Plan Approval, Design
review and approval, Review and Sign off the
final documents, Project is closed, and Final
Inspection of the completed building structure
Planner
Selecting Plan Strategy, Developing plan
outline, Plan review, and Plan Completion
Designer
Selecting Building Design Platform,
Developing design of the new building,
Reviewing the design, and Simulation of the
design
Client Site Approval, Work Started at New
Manufacturing Site, Selection of the site for
The work breakdown structure for the project of Construction of Manufacturing Site at JKB
Bloggins Ltd is in the appendix section of the report below.
Stakeholder Analysis
Resource Name
Analyst Analyzing the requirements
Documenter
Developing PID document, Charter
Documentation, Submission of the documents,
and Making final documents
Project Manager
Review and Sign off, Plan Approval, Design
review and approval, Review and Sign off the
final documents, Project is closed, and Final
Inspection of the completed building structure
Planner
Selecting Plan Strategy, Developing plan
outline, Plan review, and Plan Completion
Designer
Selecting Building Design Platform,
Developing design of the new building,
Reviewing the design, and Simulation of the
design
Client Site Approval, Work Started at New
Manufacturing Site, Selection of the site for
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 31
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.