MAN 5401: Managing Project Scope - St. Helena Marina Development

Verified

Added on  2023/06/11

|29
|5521
|145
Case Study
AI Summary
This case study solution analyzes the proposed St. Helena Marina development project, focusing on project management approaches, stakeholder identification and management, communication strategies, and potential political issues. It outlines a business case for the project, including an executive summary, background information, financial considerations, objectives, scope, benefits, stakeholder issues, a stakeholder management plan, key milestones, a high-level schedule, a project budget, risk assessment, assumptions, project communications, and recommendations. The report emphasizes the importance of considering logistical and engineering work, and the role of project management frameworks in ensuring the project's success. The constraints and information provided can be utilized by the government for the development of the environment that can result in better profits for the UK government.
Document Page
Running head: PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Project Management
St. Helena Marina Development Project
Name of the Student
Name of the University
Author note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Table of Contents
Introduction......................................................................................................................................2
Task 1: Stakeholders........................................................................................................................2
Task 2: Stakeholder, Communications, & Political Issues..............................................................6
Task 3: Outline of Business Case..................................................................................................13
Executive Summary...................................................................................................................13
Background................................................................................................................................13
Finance: Source of funds...........................................................................................................13
Objectives and scope.................................................................................................................14
Benefits......................................................................................................................................14
Summary of stakeholder issues.................................................................................................15
Stakeholder management plan...................................................................................................16
Key milestones...........................................................................................................................16
High-Level Schedule.................................................................................................................16
Project Budget...........................................................................................................................18
Risks..........................................................................................................................................20
Assumptions..............................................................................................................................21
Project communications.............................................................................................................21
Recommendation.......................................................................................................................21
Task 4.............................................................................................................................................21
Bibliography..................................................................................................................................23
Appendix........................................................................................................................................24
Figure 1: Gantt chart......................................................................................................................24
Document Page
2
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Introduction
A volcanic tropical island, Saint Helena in the South Atlantic Ocean having dimensions
of 4000 x 1950 kilometers marking the border between Angola and Namibia in the Southwestern
Africa. It has a population of 4,534 individuals and measures about sixteen by eight kilometers.
A project is being considered for the development of the island through transforming the existing
operations and operational structures and providing the tourists and individuals looking forward
to visit the island. The project is about to establish a marina near Jamestown Wharf in manner to
complement the recently build airport and allowing better services to the tourists and others who
are willing to take a tour to the island. The project will lead to shaping the surroundings those are
around the hills in manner to release more flat building and lands within the existing
environment of the island and creating more new and attractive facilities.
This report presents the project management approaches those are necessary for the
development of this transformation within the existing environment of the island regarding the
logistical and engineering work. Consideration of the project management approaches and
frameworks will be playing crucial role in the development of this project and leading towards
the success. The constraints and information provided in this report can be utilized by the
government for the development of the environment that can result in better profits for the UK
government. Following report presents all the constraints those are necessary for the
identification of a sophisticated scope for delivering the entire project.
Document Page
3
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Task 1: Stakeholders
The information gather techniques those could be utilized for the collection of the
information related to the stakeholder perspective are interviews, face to face meetings, surveys,
conference, telephonic interview and many more. The collection of the data through
questionnaire distribution can be represented as the appropriate approach towards the successful
and efficient delivery of the project. Following are some of the important concerns related to the
identified stakeholders, their roles, and responsibilities throughout the project lifecycle.
Name Stakeho
lder
Roles Responsibilities Impa
ct
Inter
est
Aimee
Curtis
Project
Manager
Mange the roles and
responsibilities of other
stakeholders including all
the responsible activities
those are necessary for the
successful development of
the project
Identify the needs and
requirements of the project
and involved stakeholders
and manage all the
constraints of the project in
an efficient and effective
manner.
Very
High
Very
High
Louie
Phillip
s
Head of
the
Project
Take the hard decisions
those are related to the
overall growth and
development of the
organization and approved
all the necessary approvals
for the project execution
Decisions should be taken
considering the
consequences of the
decisions on every
stakeholder and managing
their roles and
responsibilities in an
Very
High
High
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
efficient and effective
manner.
Morga
n
Norris
Architec
t
Prepare the design for the
execution of the project
and develop a
sophisticated and precise
model for the new
development. He will be
playing the very crucial
role in the development of
the project and
establishing the new
transformation.
Develop the design
considering each and every
corner of the design
considering the future
impacts and long run of the
project ad use the latest
technologies that ca
contribute in the engineering
works.
High Medi
um
Emily
Hough
ton
Business
Analyst
Analyze the business
environment of the island
considering the tourism,
costs, and profits those
could be made through
new development
Thoroughly research the
business environment and
propose sophisticated model
on the costs and competitors
strategies those can
contribute in the successful
growth and development of
this project
High High
Erin
Newto
Resourc
e
Take care of the resources
those are necessary for the
He or she should assure that
the resources will not lag
High Medi
um
Document Page
5
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
n
Manager
project execution and
manage them throughout
the project lifecycle
including the logistics and
transporting
throughout the project
lifecycle and all the
resources will be managed
in an efficient and effective
manner
Charli
e
Nixon
Market
Analyst
Analyze the external and
internal environment of the
tourism for the island and
identify the necessary
steps those should be
carried out by the UK
government for the
development of a better
revenue through executing
this project
Thorough research the
market strategies being
adopted by the competitors
and utilize them for
proposing the strategies
those could alternatively
result in the development of
a project that can result in
the effective and efficient
output
Medi
um
Medi
um
Georgi
na
Dohert
y
Promoti
onal
Manager
Promote the new
development and growth
of the project and attract
more tourists those can
alternatively result in the
enhancement of the
revenue being invested for
the growth and
Make sure that every
eligible individual is well
introduced with the project
development and all the
tourists who are looking
forward for an Island tour
consider once for arriving at
the island.
Medi
um
High
Document Page
6
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
development of the
organization.
-
Local
commun
ity
Promote the growth and
development of the project
through supporting the
new development and
assuring that the project
delivery has not any
obstacle in the successful
development
They should assure that the
project is being delivered
has not been restricted by
any of the individual and the
project is being delivered in
an efficient and effective
manner
High Low
Louie
Arnol
d
Civil
Enginee
rs
The civil engineers will be
executing the design
developed by the architect
for the construction and
destruction those are
necessary for this
transformation
Make sure that the
construction will proceed
exactly as per the design
developed by the architect
and assure that the
objectives and engineering
works of the project is being
achieved
High Very
High
-
UK
Govern
ment
Support the project
through providing
necessary funds and legal
approvals without resisting
the transformation.
Provide enough funds and
all the necessary legal
allowance
High High
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Task 2: Stakeholder, Communications, & Political Issues
Name Role Communica
tion type
Objective Medium Frequen
cy
Owner Deliverab
le
Aimee
Curtis
Project
Manager
Project team
meetings
Develop
an
effective
and
efficient
project
managem
ent
strategies
Face to
face
Weekly Project
manage
r
Agenda,
and
Meeting
Minutes
Louie
Phillips
Head of
the
Project
Kickoff
meeting
Get
approval
for the
growth
and
developm
ent of the
project
Conferen
ce call,
face to
face
meeting
Monthly Project
manage
r
Agenda,
Meeting
Minutes,
schedule
Morgan
Norris
Architect Designing
and
development
Discuss
the
technical
Face to
face
Weekly Techni
cal lead
Design,
developm
ent,
Document Page
8
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
of the project design
and
developm
ent of the
project
changes
Emily
Hought
on Business
Analyst
Business
constraints
Needs and
requireme
nt analysis
related to
the
business
Telephon
ic, face
to face,
Twice a
month
Project
manage
r
Agenda,
and
Meeting
Minutes
Erin
Newton
Resource
Manager
Resource
analysis and
management
Identificat
ion of the
resources
necessary
for the
developm
ent and
growth of
the project
Face to
face
Monthly Project
manage
r
Agenda,
and
Meeting
Minutes
Charlie
Nixon
Market
Analyst
Effective
solutions
related to
Coping up
with the
tourism
Face to
face
Weekly Project
manage
r
Agenda,
and
Meeting
Document Page
9
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
market
growth
competitiv
e market
Minutes
Georgi
na
Dohert
y
Promotio
nal
Manager
Identification
of the
promotional
strategies and
campaign
Popularity
and
promotion
s of the
changes
being
proposed
for the
project
developm
ent
Conferen
ce call
face to
face
Twice a
Month
Project
manage
r
Agenda,
and
Meeting
Minutes
-
Local
communi
ty
Review the
benefits of
the project
Needs,
requireme
nts of the
communit
y and
possible
benefits
those
could be
adhered
Face to
face,
conferen
ce
Monthly Project
manage
r
Agenda,
and
Meeting
Minutes
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Louie
Arnold
Civil
Engineer
s
Construction
and
engineering
perspectives
Project
execution
related
matter and
managem
ent of the
stakeholde
rs under
civil
engineer
Face to
face
meeting,
conferen
ce call
Weekly Project
manage
r
Agenda,
and
Meeting
Minutes
-
UK
Governm
ent
Loans related
conversation
Loan
perspectiv
e
questions
and
answers
and
approval
discussion
Email Twice a
Month
Agenda,
and
Meeting
Minutes
Political issues
Local community needs to be agreed upon the changes and transformation being
implemented within the environment that could lead to the political issues as the local
Document Page
11
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
community might resist the change and not willing to hand over their properties to the
government.
Loan needs to be approved that means political aspects are necessary and it becomes
crucial part to agree the government for paying the expenses needed for the delivery of the
project. The political aspects are considerable factor as all the stakeholders need to be agreed on
the same concept.
The project will include the transport and logistics for connecting the island with the
cities and thus, political agreement on this topic is crucial for the successful development and
execution of the project.
The tourism is the major sector of concern for the development and execution of this
project and hence, the tourists need to have proper passports and political approval for moving
into the island ad availing the services being offered to them.
Following are the issues those might affect the overall growth and development of the project
from the perspective of then different stakeholders:
Communication gap: The communication should be executed in an efficient and effective
manner as the project will run for long time and the stakeholders need to be well informed and
updates should be provided on regular basis. Regular meeting in every month can be
recommended as the best approach towards connecting with the stakeholders and analyzing the
different perspectives related to the project execution.
Schedule escalation: there are the possibilities that uncertainties could lead to the
enhancement in the schedule of the project and that can be eliminated through single action that
include proper and effective project planning considering every sector of the project.
chevron_up_icon