This assignment focuses on project management principles, using the redevelopment and construction of the Mooloolaba Holiday Park, including coastal pathway upgrades, as a case study. The solution begins with a high-level project charter, outlining project scope, constraints, deliverables, acceptance criteria, and milestones. Part 2 presents short answers to questions on soft skills crucial for project managers (communication, integrity, trust, relationship development, and leading by example) and the critical path method, including float calculation. It also includes a business case for disaster management for Australian Tree Crop (ATC) and a work breakdown structure. Part 3 provides additional short answer responses, demonstrating a comprehensive understanding of project management concepts and their practical application.

Running head: PROJECT MANAGEMENT AND PRINCIPLES
Project Management and Principles: Full Redevelopment and Construction of Mooloolaba
Holiday Park including Coastal Pathway Upgrades
Name of the Student:
Name of the University:
Project Management and Principles: Full Redevelopment and Construction of Mooloolaba
Holiday Park including Coastal Pathway Upgrades
Name of the Student:
Name of the University:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT AND PRINCIPLES
Table of Contents
Part 1: Project charter..........................................................................................................2
Part 2: Short answer type question......................................................................................4
1. Answer to Question 1..................................................................................................4
2. Answer to Question 2..................................................................................................6
3. Completion of the project business case......................................................................7
4. Work Breakdown Structure for the project.................................................................9
Part 3:.................................................................................................................................11
Answer to Question 1....................................................................................................11
Answer to Question 3:...................................................................................................14
References:........................................................................................................................17
Table of Contents
Part 1: Project charter..........................................................................................................2
Part 2: Short answer type question......................................................................................4
1. Answer to Question 1..................................................................................................4
2. Answer to Question 2..................................................................................................6
3. Completion of the project business case......................................................................7
4. Work Breakdown Structure for the project.................................................................9
Part 3:.................................................................................................................................11
Answer to Question 1....................................................................................................11
Answer to Question 3:...................................................................................................14
References:........................................................................................................................17

2PROJECT MANAGEMENT AND PRINCIPLES
Part 1: Project charter
Project title: Full Redevelopment and Construction of Mooloolaba Holiday Park
including Coastal Pathway Upgrades
Project scope
In order to bid for a project in most cases businesses, organizations and even
government councils also put up tenders and accordingly negotiate those. It is the
responsibility of the project manager and project sub contactors to bid for the project. This
project is about development and construction of Mooloolaba holiday Park including the
coastal pathway upgrades. In order to accomplish this project the project manager needs to
break the complex work into two sub sections or stages. In stage one the coastal pathway will
be upgraded and in the second stage the holiday park will be upgraded as per the consumers
and owner’s expectation. The first stage of the project will be initiated on 1st July, 2019 and
completed within 16th August and the second stage needs to be accomplished within 30th
November. A professional project team is developed and respective resources are also
assigned for each project development activities and stages.
Project constraints
Time: 1st July to 30th November,2019
Budget: $90,000
Project duration
Stage 1: Upgrading the Coastal
pathway (approximately 1 and a half months,
Project budget
From the structure of the entire project
it can be said that the net budget that would
Part 1: Project charter
Project title: Full Redevelopment and Construction of Mooloolaba Holiday Park
including Coastal Pathway Upgrades
Project scope
In order to bid for a project in most cases businesses, organizations and even
government councils also put up tenders and accordingly negotiate those. It is the
responsibility of the project manager and project sub contactors to bid for the project. This
project is about development and construction of Mooloolaba holiday Park including the
coastal pathway upgrades. In order to accomplish this project the project manager needs to
break the complex work into two sub sections or stages. In stage one the coastal pathway will
be upgraded and in the second stage the holiday park will be upgraded as per the consumers
and owner’s expectation. The first stage of the project will be initiated on 1st July, 2019 and
completed within 16th August and the second stage needs to be accomplished within 30th
November. A professional project team is developed and respective resources are also
assigned for each project development activities and stages.
Project constraints
Time: 1st July to 30th November,2019
Budget: $90,000
Project duration
Stage 1: Upgrading the Coastal
pathway (approximately 1 and a half months,
Project budget
From the structure of the entire project
it can be said that the net budget that would
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT AND PRINCIPLES
1st July to 16th August,2019)
Stage 2: Holiday park Upgrading (16th
August to 30th November, 2019)
be needed for the successful accomplishment
of the project is $90,000
Project deliverable
The redevelopment and complete construction project is required to accomplished
within two stages.
Stage 1: Upgrading the Coastal pathway
Stage 2: Holiday park Upgrading
Project acceptance criteria
ï‚· The project should be designed and developed based on the scope statement designed
and approved by the project manager
ï‚· The project must be accomplished within the budget of $90,000
ï‚· The project manager should make sure that it is getting accomplished on or before 30th
November
ï‚· The team member should ensure that, no project development aspects are violated
ï‚· Must be completed followed by respective project development and management
policy and procedures
Milestones
Milestone 1: Project initiation phase
Milestone 2: Project planning phase
Milestone 3: Project design and construction phase
Milestone 4: Project execution phase
Milestone 5: Project completion phase
1st July to 16th August,2019)
Stage 2: Holiday park Upgrading (16th
August to 30th November, 2019)
be needed for the successful accomplishment
of the project is $90,000
Project deliverable
The redevelopment and complete construction project is required to accomplished
within two stages.
Stage 1: Upgrading the Coastal pathway
Stage 2: Holiday park Upgrading
Project acceptance criteria
ï‚· The project should be designed and developed based on the scope statement designed
and approved by the project manager
ï‚· The project must be accomplished within the budget of $90,000
ï‚· The project manager should make sure that it is getting accomplished on or before 30th
November
ï‚· The team member should ensure that, no project development aspects are violated
ï‚· Must be completed followed by respective project development and management
policy and procedures
Milestones
Milestone 1: Project initiation phase
Milestone 2: Project planning phase
Milestone 3: Project design and construction phase
Milestone 4: Project execution phase
Milestone 5: Project completion phase
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT AND PRINCIPLES
Part 2: Short answer type question
1. Answer to Question 1
Soft Skills: The soft skills can be considered as combination of some social skills, people skill,
personality traits, communication skills and career attributes which are important for navigation
of the surrounding environment, achieving the goals and performing well with complementing
hard skills. Thus the soft skills can be described as some desirable qualities in form of employees
which is not depending on the acquired knowledge. Instead of it this are actually depending on
the ability of dealing with the people, common sense and a positive flexible attitude.
Soft skills are extremely important for the project managers to successfully execute a
project. In the following section five essential soft skills will be demonstrated which are
extremely important for project management and for leading the project management team.
ï‚· Communicate and Listen: The soft skill of communicate and listen is very much
important for the project manager for successfully complete a project. From various of
projects it has been assessed that improper type of communication is one of the prior
reason behind the failure of a project (Muller 2017). Thus proper communication and
listening from the end of the project stakeholders is very much important soft skill in this
aspect. This skills can be developed by the project manager by the practice of adapting,
listening, sharing as required. In the project aspects the communication contribute to the
management of the product by sharing the vision of the project with the project team. It
Part 2: Short answer type question
1. Answer to Question 1
Soft Skills: The soft skills can be considered as combination of some social skills, people skill,
personality traits, communication skills and career attributes which are important for navigation
of the surrounding environment, achieving the goals and performing well with complementing
hard skills. Thus the soft skills can be described as some desirable qualities in form of employees
which is not depending on the acquired knowledge. Instead of it this are actually depending on
the ability of dealing with the people, common sense and a positive flexible attitude.
Soft skills are extremely important for the project managers to successfully execute a
project. In the following section five essential soft skills will be demonstrated which are
extremely important for project management and for leading the project management team.
ï‚· Communicate and Listen: The soft skill of communicate and listen is very much
important for the project manager for successfully complete a project. From various of
projects it has been assessed that improper type of communication is one of the prior
reason behind the failure of a project (Muller 2017). Thus proper communication and
listening from the end of the project stakeholders is very much important soft skill in this
aspect. This skills can be developed by the project manager by the practice of adapting,
listening, sharing as required. In the project aspects the communication contribute to the
management of the product by sharing the vision of the project with the project team. It

5PROJECT MANAGEMENT AND PRINCIPLES
also helps to coordinate with the other stakeholder of the project for any type of
requirement changes and potential risks.
ï‚· Integrity and Honesty: Integrity and Honesty is very much important for describing
character of someone. It is very much important for the project manager that the team
will always trust the project manager that the project manager will be able to lead the
project towards a successful completion (Zareei 2018). In this aspect the integrity and the
honesty contributes to the successful leading and managing of the project teams by
building trust among the stakeholders of the project. Building trust among the employees
and the stakeholders is important so that the project always remain in function state and
properly gets to its conclusive state.
ï‚· Trust and Respect: For a successful project management, it is very much important
building trust and respect within the project execution environment. Thus this is an
important skill which must be possessed by the project manager for successful
management of the project. Building trust and respect actively contributes to the leading
and managing the project team as this helps to main and improve the trust with the
stakeholder which are extremely important for the successful project management.
ï‚· Relationship Development: For a successful project management it is very much
important for the project manager to ensure a proper relationship management which will
lead to critical success of the project. Proper development of the relationships with the
project stakeholder is capable of support the project more as critical project success can
achieved through this which is important for management of the project teams.
ï‚· Leading team by examples: Leading the project team is very much important for the
success of the initiated project. Thus in this aspect the project manager can lead the
also helps to coordinate with the other stakeholder of the project for any type of
requirement changes and potential risks.
ï‚· Integrity and Honesty: Integrity and Honesty is very much important for describing
character of someone. It is very much important for the project manager that the team
will always trust the project manager that the project manager will be able to lead the
project towards a successful completion (Zareei 2018). In this aspect the integrity and the
honesty contributes to the successful leading and managing of the project teams by
building trust among the stakeholders of the project. Building trust among the employees
and the stakeholders is important so that the project always remain in function state and
properly gets to its conclusive state.
ï‚· Trust and Respect: For a successful project management, it is very much important
building trust and respect within the project execution environment. Thus this is an
important skill which must be possessed by the project manager for successful
management of the project. Building trust and respect actively contributes to the leading
and managing the project team as this helps to main and improve the trust with the
stakeholder which are extremely important for the successful project management.
ï‚· Relationship Development: For a successful project management it is very much
important for the project manager to ensure a proper relationship management which will
lead to critical success of the project. Proper development of the relationships with the
project stakeholder is capable of support the project more as critical project success can
achieved through this which is important for management of the project teams.
ï‚· Leading team by examples: Leading the project team is very much important for the
success of the initiated project. Thus in this aspect the project manager can lead the
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT AND PRINCIPLES
project by demonstration of various of past examples. By demonstrate the project with
some real-time example the project manager will be able to execute whole project
essentially within the timeframe of the project. Also, by demonstration of the examples
effective relationship can be also build which will contribute to manage the project team.
2. Answer to Question 2
Critical Path: The critical path is considered as a typical type of algorithm which is mainly used
for the scheduling purpose of a set of a whole project activity. In most of the cases this critical
path is used with the conjunction with the PERT or Program Evaluation and Review Technique
(Zareei 2018). The critical path can be determined by the identification of the longest stretch
regarding the dependent activities and the time which is important for the measuring that is
required for completing them from start to the finish.
In the aspects of the project scheduling the critical path is very much important as the
critical path allows the teams to identify the important tasks which need to be performed in the
project with a priority basis. The main benefit due to which the critical path is important are the
improved resource management, shortened timeline and better planning for the project. For these
type of advantages of the critical path it is considered within the aspects of project scheduling.
There are some steps are available which need to be follow sequentially for the
calculation of critical path. In the following section all the steps are described.
1. Finding of all Activities
2. Creation of the Schedule Network Diagram
3. Identification of all the possible paths
4. Calculation duration of each of the path
project by demonstration of various of past examples. By demonstrate the project with
some real-time example the project manager will be able to execute whole project
essentially within the timeframe of the project. Also, by demonstration of the examples
effective relationship can be also build which will contribute to manage the project team.
2. Answer to Question 2
Critical Path: The critical path is considered as a typical type of algorithm which is mainly used
for the scheduling purpose of a set of a whole project activity. In most of the cases this critical
path is used with the conjunction with the PERT or Program Evaluation and Review Technique
(Zareei 2018). The critical path can be determined by the identification of the longest stretch
regarding the dependent activities and the time which is important for the measuring that is
required for completing them from start to the finish.
In the aspects of the project scheduling the critical path is very much important as the
critical path allows the teams to identify the important tasks which need to be performed in the
project with a priority basis. The main benefit due to which the critical path is important are the
improved resource management, shortened timeline and better planning for the project. For these
type of advantages of the critical path it is considered within the aspects of project scheduling.
There are some steps are available which need to be follow sequentially for the
calculation of critical path. In the following section all the steps are described.
1. Finding of all Activities
2. Creation of the Schedule Network Diagram
3. Identification of all the possible paths
4. Calculation duration of each of the path
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT AND PRINCIPLES
Thus by following above four steps the critical path can be determined easily.
Considering an example this the critical path is able impact the life cycle of a project by
shortening the life cycle of the project without decreasing the project efficiency.
Float: In the concept of project scheduling is considered as the total amount time that is which a
particular task in the network of the project can be delayed without any type of delay to the
completion date of the project and the subsequent tasks (Shaw and Sellers 2015).
For the project scheduling purpose the float is very much important as the total float
represents the flexibility of the schedule which can be measured by subtraction of the early start
dates of the path which is needed for the completion of the project (Todorović et al. 2015). Float
is very much important for the critical path as the number of total floats of the noncritical
activities key to computation the critical path drag of a particular type of activity, such that
amount of time directly added to the duration of the project.
The calculation of the float is very much easy. The float can be calculated by difference
between completion date of the project and total duration of the activities of the critical path.
There float can impact the lifecycle of the project by making it more flexible in nature.
3. Completion of the project business case
Overview
These business cases depicts the importance and business value of designin, developing
and implementing a disaster management plan for improving public relationship and integrate
needful company changes. The company that has been nominated for this business case is
Australian Tree Crop (ATC). This company is known for its global business structure of growing
and selling tress (Lock 2017). However, due to serially occurring natural disaster the company is
Thus by following above four steps the critical path can be determined easily.
Considering an example this the critical path is able impact the life cycle of a project by
shortening the life cycle of the project without decreasing the project efficiency.
Float: In the concept of project scheduling is considered as the total amount time that is which a
particular task in the network of the project can be delayed without any type of delay to the
completion date of the project and the subsequent tasks (Shaw and Sellers 2015).
For the project scheduling purpose the float is very much important as the total float
represents the flexibility of the schedule which can be measured by subtraction of the early start
dates of the path which is needed for the completion of the project (Todorović et al. 2015). Float
is very much important for the critical path as the number of total floats of the noncritical
activities key to computation the critical path drag of a particular type of activity, such that
amount of time directly added to the duration of the project.
The calculation of the float is very much easy. The float can be calculated by difference
between completion date of the project and total duration of the activities of the critical path.
There float can impact the lifecycle of the project by making it more flexible in nature.
3. Completion of the project business case
Overview
These business cases depicts the importance and business value of designin, developing
and implementing a disaster management plan for improving public relationship and integrate
needful company changes. The company that has been nominated for this business case is
Australian Tree Crop (ATC). This company is known for its global business structure of growing
and selling tress (Lock 2017). However, due to serially occurring natural disaster the company is

8PROJECT MANAGEMENT AND PRINCIPLES
facing major c=economic loss. In order to get back to the primary high level brand image ACT
has planned to establish an in house team for evaluating natural disaster improve public relations
as well as instigate needful changes.
Problem statement
Due to sequentially occurring natural disaster like- flood, draught, wildfires, cyclone the
revenue of the revenue of the company was affected badly. Apart from that, company fails to
identify and instigate needful changes considering public relations. As a result the entire
company faced major challenges.
Situation analysis
After analyzing the situation, it has been determined that, implementation and
development of proper disaster management plan and natural disaster recovery plan would only
be able to identify the cause of revenue loss (Hornstein 2015). It will also help ACT to get back
on higher economic marginal growth point.
Options available for mitigation
ï‚· Establishment of an in house development team
ï‚· Proper evaluation of the natural disasters serially occurring
ï‚· Instigating company changes
ï‚· Improving proper public relationships
Budget estimated for the business case
The total budget estimated for the business case is: $32,000.
facing major c=economic loss. In order to get back to the primary high level brand image ACT
has planned to establish an in house team for evaluating natural disaster improve public relations
as well as instigate needful changes.
Problem statement
Due to sequentially occurring natural disaster like- flood, draught, wildfires, cyclone the
revenue of the revenue of the company was affected badly. Apart from that, company fails to
identify and instigate needful changes considering public relations. As a result the entire
company faced major challenges.
Situation analysis
After analyzing the situation, it has been determined that, implementation and
development of proper disaster management plan and natural disaster recovery plan would only
be able to identify the cause of revenue loss (Hornstein 2015). It will also help ACT to get back
on higher economic marginal growth point.
Options available for mitigation
ï‚· Establishment of an in house development team
ï‚· Proper evaluation of the natural disasters serially occurring
ï‚· Instigating company changes
ï‚· Improving proper public relationships
Budget estimated for the business case
The total budget estimated for the business case is: $32,000.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT AND PRINCIPLES
4. Work Breakdown Structure for the project
W
BS
Task
Name
Durati
on
Sta
rt
Fini
sh
Resour
ce Names Cost
0
Sched
ule for
Natural
disaster
recovery
plan
100
days
M
on 5/27/19
Fri
10/11/19
$30,032
.00
1
Proj
ect initiation
phase
20
days
M
on 5/27/19
Fri
6/21/19
$6,912.
00
1.1
Un
derstanding
need for
project policy
7 days Mo
n 5/27/19
Tue
6/4/19
Project
manager
$2,016.
00
1.2
An
alysis of
cause for
natural
vulnerabilities
6 days We
d 6/5/19
We
d 6/12/19
Operati
on manager
$1,440.
00
1.3
Re
alizing
changing
weather
forecast
5 days Th
u 6/13/19
We
d 6/19/19
Geogra
phy specialist
$1,600.
00
1.4
Re
ason analysis
causing
natural
disaster
4 days Th
u 6/13/19
Tue
6/18/19
Geogra
phy specialist
$1,280.
00
1.5
Un
derstanding
the disaster
policy
2 days Th
u 6/20/19
Fri
6/21/19
Project
manager $576.00
2 Proj
ect planning
23
days
M
on 6/24/19
We
d 7/24/19
$5,232.
00
2.1
Pr
oject team
development
3 days Mo
n 6/24/19
We
d 6/26/19
Project
manager $864.00
4. Work Breakdown Structure for the project
W
BS
Task
Name
Durati
on
Sta
rt
Fini
sh
Resour
ce Names Cost
0
Sched
ule for
Natural
disaster
recovery
plan
100
days
M
on 5/27/19
Fri
10/11/19
$30,032
.00
1
Proj
ect initiation
phase
20
days
M
on 5/27/19
Fri
6/21/19
$6,912.
00
1.1
Un
derstanding
need for
project policy
7 days Mo
n 5/27/19
Tue
6/4/19
Project
manager
$2,016.
00
1.2
An
alysis of
cause for
natural
vulnerabilities
6 days We
d 6/5/19
We
d 6/12/19
Operati
on manager
$1,440.
00
1.3
Re
alizing
changing
weather
forecast
5 days Th
u 6/13/19
We
d 6/19/19
Geogra
phy specialist
$1,600.
00
1.4
Re
ason analysis
causing
natural
disaster
4 days Th
u 6/13/19
Tue
6/18/19
Geogra
phy specialist
$1,280.
00
1.5
Un
derstanding
the disaster
policy
2 days Th
u 6/20/19
Fri
6/21/19
Project
manager $576.00
2 Proj
ect planning
23
days
M
on 6/24/19
We
d 7/24/19
$5,232.
00
2.1
Pr
oject team
development
3 days Mo
n 6/24/19
We
d 6/26/19
Project
manager $864.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT AND PRINCIPLES
2.2
Ri
sk
management
plan
6 days Th
u 6/27/19
Thu
7/4/19
Project
manager
$1,728.
00
2.3
Co
mmunication
management
planning
5 days Fri
7/5/19
Thu
7/11/19
Operati
on manager
$1,200.
00
2.4
Pr
ocurement
management
acts and law
5 days Fri
7/12/19
Thu
7/18/19
Project
manager
$1,440.
00
2.5
So
cio economic
status analysis
of the state
4 days Fri
7/19/19
We
d 7/24/19 $0.00
3
Dev
elopment of
disaster
management
policy
30
days
Th
u 7/25/19
We
d 9/4/19
$10,464
.00
3.1
Est
ablishment of
necessary
system
8 days Th
u 7/25/19
Mo
n 8/5/19
Natural
disaster analyst
$2,432.
00
3.2
Est
ablishing
proper
structure
6 days Tu
e 8/6/19
Tue
8/13/19
Disaster
recovery
planner,
Natural disaster
analyst
$3,504.
00
3.3
De
sign of proper
disaster
recovery
program
5 days We
d 8/14/19
Tue
8/20/19
Disaster
recovery
planner
$1,400.
00
3.4
Ide
ntification of
resources
5 days We
d 8/21/19
Tue
8/27/19
Disaster
recovery
planner
$1,400.
00
3.5
Co
nducing
capability
analysis plan
6 days We
d 8/28/19
We
d 9/4/19
Project
manager
$1,728.
00
4 Desi
gn of disaster
and threat for
7 days Th
u 9/5/19
Fri
9/13/19
Operati
on manager
$1,680.
00
2.2
Ri
sk
management
plan
6 days Th
u 6/27/19
Thu
7/4/19
Project
manager
$1,728.
00
2.3
Co
mmunication
management
planning
5 days Fri
7/5/19
Thu
7/11/19
Operati
on manager
$1,200.
00
2.4
Pr
ocurement
management
acts and law
5 days Fri
7/12/19
Thu
7/18/19
Project
manager
$1,440.
00
2.5
So
cio economic
status analysis
of the state
4 days Fri
7/19/19
We
d 7/24/19 $0.00
3
Dev
elopment of
disaster
management
policy
30
days
Th
u 7/25/19
We
d 9/4/19
$10,464
.00
3.1
Est
ablishment of
necessary
system
8 days Th
u 7/25/19
Mo
n 8/5/19
Natural
disaster analyst
$2,432.
00
3.2
Est
ablishing
proper
structure
6 days Tu
e 8/6/19
Tue
8/13/19
Disaster
recovery
planner,
Natural disaster
analyst
$3,504.
00
3.3
De
sign of proper
disaster
recovery
program
5 days We
d 8/14/19
Tue
8/20/19
Disaster
recovery
planner
$1,400.
00
3.4
Ide
ntification of
resources
5 days We
d 8/21/19
Tue
8/27/19
Disaster
recovery
planner
$1,400.
00
3.5
Co
nducing
capability
analysis plan
6 days We
d 8/28/19
We
d 9/4/19
Project
manager
$1,728.
00
4 Desi
gn of disaster
and threat for
7 days Th
u 9/5/19
Fri
9/13/19
Operati
on manager
$1,680.
00

11PROJECT MANAGEMENT AND PRINCIPLES
the disaster
5 Exec
ution phase
20
days
M
on 9/16/19
Fri
10/11/19
$5,744.
00
5.1 Re
sponse plan 1 6 days Mo
n 9/16/19
Mo
n 9/23/19
Disaster
recovery
planner
$1,680.
00
5.2 Re
sponse plan 2 6 days Tu
e 9/24/19
Tue
10/1/19
Natural
disaster analyst
$1,824.
00
5.3
Re
sponse option
3
8 days We
d 10/2/19
Fri
10/11/19
Disaster
recovery
planner
$2,240.
00
Part 3:
Answer to Question 1
Strategic project planning is referred to as a process used for managing any project
successfully. If, proper management processes and business strategies are not followed by the
project manager and project team members then, project will fail to meet the expectation, goals
and project objectives (Kerzner and Kerzner 2017). The strategic planning process are comprises
of various steps that the project management team should go throughout the project development
lifecycle phase (Binder 2016). The project strategic plan of the project is comprises of
Analysis of strategic position:
This is the first phase of developing strategic planning for the project. It involves analysis
of the following questions such as what needs to be done, where is to go and how to get there.
Detailed assessment of this aspects are required for developing an effective strategic planning
that ensures success in the project as successful projects are all about effective strategic planning
and execute that according to the project requirements (Davies and Brady 2016). In analyzing
the disaster
5 Exec
ution phase
20
days
M
on 9/16/19
Fri
10/11/19
$5,744.
00
5.1 Re
sponse plan 1 6 days Mo
n 9/16/19
Mo
n 9/23/19
Disaster
recovery
planner
$1,680.
00
5.2 Re
sponse plan 2 6 days Tu
e 9/24/19
Tue
10/1/19
Natural
disaster analyst
$1,824.
00
5.3
Re
sponse option
3
8 days We
d 10/2/19
Fri
10/11/19
Disaster
recovery
planner
$2,240.
00
Part 3:
Answer to Question 1
Strategic project planning is referred to as a process used for managing any project
successfully. If, proper management processes and business strategies are not followed by the
project manager and project team members then, project will fail to meet the expectation, goals
and project objectives (Kerzner and Kerzner 2017). The strategic planning process are comprises
of various steps that the project management team should go throughout the project development
lifecycle phase (Binder 2016). The project strategic plan of the project is comprises of
Analysis of strategic position:
This is the first phase of developing strategic planning for the project. It involves analysis
of the following questions such as what needs to be done, where is to go and how to get there.
Detailed assessment of this aspects are required for developing an effective strategic planning
that ensures success in the project as successful projects are all about effective strategic planning
and execute that according to the project requirements (Davies and Brady 2016). In analyzing
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 19
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.