MGT5IPM: MAC Case Study Analysis of Airbus and Boeing Projects
VerifiedAdded on 2023/06/04
|10
|2912
|281
Case Study
AI Summary
This case study analyzes the Murasaki Aircraft Corporation (MAC), examining the Airbus A380 and Boeing 787 projects to derive lessons learned and provide recommendations. The analysis covers project backgrounds, stakeholder information, and reasons for failures, including poor risk management, unrealistic expectations, project conflicts, communication gaps, design complexities, supply chain issues, and outsourcing complexities. The study highlights key lessons such as the importance of integrated project handling, employee-friendly work environments, realistic project expectations, and in-house capabilities. Recommendations for MAC include integrated project handling, stakeholder buy-in, employee training, iterative methods, careful supplier selection, in-depth information gathering, and a robust risk management strategy. The report concludes with a summary of the failures and the measures MAC should take to avoid similar problems, emphasizing the need for effective project management practices, risk mitigation, and stakeholder engagement to ensure project success. This document is a student's response to an assignment brief, to be published on Desklib.

Murasaki Aircraft Corporation (MAC) Case Study
Lessons Learned & Applications
10/11/2018
Lessons Learned & Applications
10/11/2018
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Murasaki Aircraft Corporation (MAC)
TABLE OF CONTENTS
Introduction......................................................................................................................................................................... 2
Project Background...................................................................................................................................................... 2
Stakeholder Information............................................................................................................................................. 2
Airbus A380 Project......................................................................................................................................................... 2
Overviee of the Project................................................................................................................................................ 2
Reasons for failure........................................................................................................................................................ 3
Lesson Learned.............................................................................................................................................................. 3
Boeing 787 Dreamliner Project..................................................................................................................................... 4
Project Background...................................................................................................................................................... 4
reasons for failure......................................................................................................................................................... 4
Lesson Learned.............................................................................................................................................................. 5
Recommendations for MAC.......................................................................................................................................... 5
Conclusions......................................................................................................................................................................... 6
References............................................................................................................................................................................ 8
1
TABLE OF CONTENTS
Introduction......................................................................................................................................................................... 2
Project Background...................................................................................................................................................... 2
Stakeholder Information............................................................................................................................................. 2
Airbus A380 Project......................................................................................................................................................... 2
Overviee of the Project................................................................................................................................................ 2
Reasons for failure........................................................................................................................................................ 3
Lesson Learned.............................................................................................................................................................. 3
Boeing 787 Dreamliner Project..................................................................................................................................... 4
Project Background...................................................................................................................................................... 4
reasons for failure......................................................................................................................................................... 4
Lesson Learned.............................................................................................................................................................. 5
Recommendations for MAC.......................................................................................................................................... 5
Conclusions......................................................................................................................................................................... 6
References............................................................................................................................................................................ 8
1

Murasaki Aircraft Corporation (MAC)
INTRODUCTION
PROJECT BACKGROUND
Murasaki Aircraft Corporation (MAC) is an organization that is based out of Japan. The company is
majorly involved in the production of regional jets and is a prime supplier of aircraft wings for Boeing 787.
The aim of the company is to launch lightweight aircrafts and has analyzed the functions and business
operations of Airbus A380 and Boeing 787 Dreamliner. The analysis is done to have an understanding of
the major issues and risks that shall be identified in advance. The analysis is done on the two case studies
and the procedures followed in each. The primary cases behind failures, understanding of the major risk
areas, lessons acquired, and recommendations have been provided.
STAKEHOLDER INFORMATION
Murasaki Heavy Industries (MHI), Toyota Motor Corporation, Mitsubishi Corporation are the
primary shareholders of the company with 64%, 10%, and 10% shares respectively. The other
shareholders include Mitsui & Co. and Sumitomo Corporation.
During the project lifecycle, MAC will be the primary decision-maker. MHI will be major supplier of
aircraft wings and necessary equipment. MHI will be actively involved in the process of defining the
policies and strategies. Mitsubishi Corporation and Sumitomo Corporation will provide regional
support and technical assistance respectively.
AIRBUS A380 PROJECT
OVERVIEE OF THE PROJECT
Airbus A380 was started in 2007 and the first take off were from Singapore to Sydney. One year later,
there was an additional route added that covered Melbourne to Los Angeles. There are several
leading market players associated with the company as its clients, such as Emirates, Air France,
Lufthansa, and many more. There were certain issues that the company experienced in the areas of
production and delivery.
The company worked on the idea of launching a triple decker aircraft, first of its kind. The overall
capacity would have been 1405 comprising of 850 economy and 555 separate seating spacing. The
project aimed to include several advanced facilities covering beauty salons, bars, and many more. The
cost of the project was determined as $347m covering all the costs (Bbc, 2012).
2
INTRODUCTION
PROJECT BACKGROUND
Murasaki Aircraft Corporation (MAC) is an organization that is based out of Japan. The company is
majorly involved in the production of regional jets and is a prime supplier of aircraft wings for Boeing 787.
The aim of the company is to launch lightweight aircrafts and has analyzed the functions and business
operations of Airbus A380 and Boeing 787 Dreamliner. The analysis is done to have an understanding of
the major issues and risks that shall be identified in advance. The analysis is done on the two case studies
and the procedures followed in each. The primary cases behind failures, understanding of the major risk
areas, lessons acquired, and recommendations have been provided.
STAKEHOLDER INFORMATION
Murasaki Heavy Industries (MHI), Toyota Motor Corporation, Mitsubishi Corporation are the
primary shareholders of the company with 64%, 10%, and 10% shares respectively. The other
shareholders include Mitsui & Co. and Sumitomo Corporation.
During the project lifecycle, MAC will be the primary decision-maker. MHI will be major supplier of
aircraft wings and necessary equipment. MHI will be actively involved in the process of defining the
policies and strategies. Mitsubishi Corporation and Sumitomo Corporation will provide regional
support and technical assistance respectively.
AIRBUS A380 PROJECT
OVERVIEE OF THE PROJECT
Airbus A380 was started in 2007 and the first take off were from Singapore to Sydney. One year later,
there was an additional route added that covered Melbourne to Los Angeles. There are several
leading market players associated with the company as its clients, such as Emirates, Air France,
Lufthansa, and many more. There were certain issues that the company experienced in the areas of
production and delivery.
The company worked on the idea of launching a triple decker aircraft, first of its kind. The overall
capacity would have been 1405 comprising of 850 economy and 555 separate seating spacing. The
project aimed to include several advanced facilities covering beauty salons, bars, and many more. The
cost of the project was determined as $347m covering all the costs (Bbc, 2012).
2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Murasaki Aircraft Corporation (MAC)
REASONS FOR FAILURE
Poor Risk & Issues Management: The risk and issue avoidance approach followed and
applied in the project was not up to the mark.
Non-Realistic Expectations: The initial launch date of the project was set up as 2006 with
initiation in 2000. It takes at least 5 years for a normal aircraft to be launched. In this case,
there were new and unexplored functionalities and services involved that demanded increased
timeframe. The expectations that were set were not relevant (Freimuth, 2016).
Project Conflicts: There were conflicts among the engineers and the project management
team. The management was willing to adopt and implement 3D models while the engineers
supported the use of 2D models. Due to these conflicts, the engineers showed resistance
which negatively impacted their productivity levels. The company management made use of
Catia and Circe software packages that were not supported by the operational staff and
engineers.
Errors in calculations: Wire installation process witnessed several errors which contributed
in the overrun of schedule and also added to the project complexities.
Communication Gaps: The Company has 16 operational units in different geographical
locations. Integration and active communication of all the units and their respective staff
members was necessary and the strategy of re-structuring and re-location was adopted. It
further impacted the project team which led to the emergence of ownership disputes.
Design complexities: Consistency issues and design complexities were associated with the
project. For instance, Hamburg plant made use of outdated Catia version whereas Toulouse
plant incorporated updated version. As a result, incompatibility of the results came up.
LESSON LEARNED
• The nature of issues involved in the failure of a project may be technical issues or
others. It is not certain that the projects always fail because of technical complexities
and errors. It needs to be ensured that integrated handling of the project is done and
the role of management is active to avoid issues under any category (Dorfler &
Baumann, 2014).
• The work culture and organization structure has a direct implication on the levels of
employee productivity and performance. It must be ensured that the work
environment is employee-friendly.
• There are specific requirements of the project in terms of the material and tools that
are needed. The requirements shall be handled in advance and the environments
3
REASONS FOR FAILURE
Poor Risk & Issues Management: The risk and issue avoidance approach followed and
applied in the project was not up to the mark.
Non-Realistic Expectations: The initial launch date of the project was set up as 2006 with
initiation in 2000. It takes at least 5 years for a normal aircraft to be launched. In this case,
there were new and unexplored functionalities and services involved that demanded increased
timeframe. The expectations that were set were not relevant (Freimuth, 2016).
Project Conflicts: There were conflicts among the engineers and the project management
team. The management was willing to adopt and implement 3D models while the engineers
supported the use of 2D models. Due to these conflicts, the engineers showed resistance
which negatively impacted their productivity levels. The company management made use of
Catia and Circe software packages that were not supported by the operational staff and
engineers.
Errors in calculations: Wire installation process witnessed several errors which contributed
in the overrun of schedule and also added to the project complexities.
Communication Gaps: The Company has 16 operational units in different geographical
locations. Integration and active communication of all the units and their respective staff
members was necessary and the strategy of re-structuring and re-location was adopted. It
further impacted the project team which led to the emergence of ownership disputes.
Design complexities: Consistency issues and design complexities were associated with the
project. For instance, Hamburg plant made use of outdated Catia version whereas Toulouse
plant incorporated updated version. As a result, incompatibility of the results came up.
LESSON LEARNED
• The nature of issues involved in the failure of a project may be technical issues or
others. It is not certain that the projects always fail because of technical complexities
and errors. It needs to be ensured that integrated handling of the project is done and
the role of management is active to avoid issues under any category (Dorfler &
Baumann, 2014).
• The work culture and organization structure has a direct implication on the levels of
employee productivity and performance. It must be ensured that the work
environment is employee-friendly.
• There are specific requirements of the project in terms of the material and tools that
are needed. The requirements shall be handled in advance and the environments
3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Murasaki Aircraft Corporation (MAC)
needed for executing the project activities must be ready for the employees prior to
the initiation of the project (Shore, 2009).
• The project expectations must be set as per the project attributes and properties. For
this purpose, enhanced level of planning shall be carried out and all the team members
must be involved in the process. The project planning must be done for all the project
areas well in advance (Rochfort, 2006).
BOEING 787 DREAMLINER PROJECT
PROJECT BACKGROUND
Boeing came up with the Dreamliner in 2003. The design and technique associated with the project was
advanced and the use of composite material was done in the same. The project was a success and achieved
to enhance the fuel efficiency by 20%. Maintenance costs also decreased with the release of the aircraft
and the organization received the order of 500 aircrafts soon after the launch.
In spite of the successful results and outcomes, the project was a failure from the aspect of project
management. It is because there was overrun of schedule and budget along with decrease in revenues and
customer base that was experienced. The delay in the launch was 3 years which had an impact on the
project costs.
REASONS FOR FAILURE
The problems were detected in early 2007 which resulted in an initial overrun of the schedule by six
months. In order to tackle the issue, the company incorporated additional number of resources to
manage the problems and issues. However, the issue could be resolved in 3 years and the launch took
place in 2009. The initial sets of problems were witnessed in the year 2007 that led to a delay of six
months. Following are some of the reasons that led to the emergence of the issue.
Supply chain issues: There were less number of fasteners required by the engineers and
members of the project team. The suppliers were wishing to target the larger orders and did
not show high levels of interest in the deliveries. It led to the delay in delivery of the fasteners
which impacted the project schedule. There were also poor training mechanisms involved and
the resources were not adequately trained. It resulted in the increased amount of re-work
which had a negative impact on the cost and time (Tang & Zimmerman, 2009).
Outsourcing Complexities: There was a lot of outsourcing involved in the execution of
manufacturing tasks and only a handful of activities were executed in-house. Boeing gave
4
needed for executing the project activities must be ready for the employees prior to
the initiation of the project (Shore, 2009).
• The project expectations must be set as per the project attributes and properties. For
this purpose, enhanced level of planning shall be carried out and all the team members
must be involved in the process. The project planning must be done for all the project
areas well in advance (Rochfort, 2006).
BOEING 787 DREAMLINER PROJECT
PROJECT BACKGROUND
Boeing came up with the Dreamliner in 2003. The design and technique associated with the project was
advanced and the use of composite material was done in the same. The project was a success and achieved
to enhance the fuel efficiency by 20%. Maintenance costs also decreased with the release of the aircraft
and the organization received the order of 500 aircrafts soon after the launch.
In spite of the successful results and outcomes, the project was a failure from the aspect of project
management. It is because there was overrun of schedule and budget along with decrease in revenues and
customer base that was experienced. The delay in the launch was 3 years which had an impact on the
project costs.
REASONS FOR FAILURE
The problems were detected in early 2007 which resulted in an initial overrun of the schedule by six
months. In order to tackle the issue, the company incorporated additional number of resources to
manage the problems and issues. However, the issue could be resolved in 3 years and the launch took
place in 2009. The initial sets of problems were witnessed in the year 2007 that led to a delay of six
months. Following are some of the reasons that led to the emergence of the issue.
Supply chain issues: There were less number of fasteners required by the engineers and
members of the project team. The suppliers were wishing to target the larger orders and did
not show high levels of interest in the deliveries. It led to the delay in delivery of the fasteners
which impacted the project schedule. There were also poor training mechanisms involved and
the resources were not adequately trained. It resulted in the increased amount of re-work
which had a negative impact on the cost and time (Tang & Zimmerman, 2009).
Outsourcing Complexities: There was a lot of outsourcing involved in the execution of
manufacturing tasks and only a handful of activities were executed in-house. Boeing gave
4

Murasaki Aircraft Corporation (MAC)
shape to the activities that were specific to general designs and assemblies. However a major
portion of the activities were outsourced to the vendors as Alenia Aeronautica, Spirit
AeroSystems, and many others. These vendors also outsourced the tasks to their supplier
groups and the cycle went on. It led to difficulties in tracking the supplies and only 16% of
the overall delivery could be made by the end of first supply of the aircraft (Baker, 2013).
Many of the technical errors and design issues were reported which led to the loss of effort,
time, and costs. For example, Crane delivered a brake controlling system that was not in
adherence to the defined standards and a loss of $18.9 million was witnessed (Elahi,
Sheikhzadeh & Lamba, 2012).
High Development Costs: There were high development costs associated with the project
that resulted in the inability to control the costs in the advanced lifecycle.
Lack of competency: Boeing decided to play the role of the system integrator and it was not
the strongest area of expertise. The Dreamliner project was also new and there were areas that
were not previously explored. The multi-layered outsourcing model was associated that
further enhanced the number of complexities. The absence of required skills and experience
levels led to the compromise of the performance and outcomes (Mseitif, 2014).
LESSON LEARNED
• It is necessary for the organization to define and work upon their core skill sets. The
roles and responsibilities shall be allotted as per the matching skill sets. The failure to
do so may result in the compromise of the productivity levels which may enhance the
likelihood of the risks (Denning, 2013).
• It is best to utilize in-house capabilities to a larger share of business operations. The
use of such an approach eliminates the complexities that may be involved (Amalraj,
2007).
• It is necessary for the management to remain involved in the monitoring and control
phases so that the audits and inspections can be given shape accordingly.
• There shall be a tracking system involved in the process of outsourcing to avoid the
performance and execution issues.
RECOMMENDATIONS FOR MAC
• MAC shall ensure that integrated handling of the project is done and the role of management
is active to avoid issues under any category. The management must carry out reviews, audits,
5
shape to the activities that were specific to general designs and assemblies. However a major
portion of the activities were outsourced to the vendors as Alenia Aeronautica, Spirit
AeroSystems, and many others. These vendors also outsourced the tasks to their supplier
groups and the cycle went on. It led to difficulties in tracking the supplies and only 16% of
the overall delivery could be made by the end of first supply of the aircraft (Baker, 2013).
Many of the technical errors and design issues were reported which led to the loss of effort,
time, and costs. For example, Crane delivered a brake controlling system that was not in
adherence to the defined standards and a loss of $18.9 million was witnessed (Elahi,
Sheikhzadeh & Lamba, 2012).
High Development Costs: There were high development costs associated with the project
that resulted in the inability to control the costs in the advanced lifecycle.
Lack of competency: Boeing decided to play the role of the system integrator and it was not
the strongest area of expertise. The Dreamliner project was also new and there were areas that
were not previously explored. The multi-layered outsourcing model was associated that
further enhanced the number of complexities. The absence of required skills and experience
levels led to the compromise of the performance and outcomes (Mseitif, 2014).
LESSON LEARNED
• It is necessary for the organization to define and work upon their core skill sets. The
roles and responsibilities shall be allotted as per the matching skill sets. The failure to
do so may result in the compromise of the productivity levels which may enhance the
likelihood of the risks (Denning, 2013).
• It is best to utilize in-house capabilities to a larger share of business operations. The
use of such an approach eliminates the complexities that may be involved (Amalraj,
2007).
• It is necessary for the management to remain involved in the monitoring and control
phases so that the audits and inspections can be given shape accordingly.
• There shall be a tracking system involved in the process of outsourcing to avoid the
performance and execution issues.
RECOMMENDATIONS FOR MAC
• MAC shall ensure that integrated handling of the project is done and the role of management
is active to avoid issues under any category. The management must carry out reviews, audits,
5
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Murasaki Aircraft Corporation (MAC)
and inspections at the regular intervals to tackle any issues on a real-time basis (Shariff,
2013).
• Gaining of buy-in will prove to be beneficial for the project and the organization as a whole.
The internal and external stakeholders shall be made aware about additional responsibilities to
handle the process. Also, they must be explained the benefits associated with the decision to
maintain the motivation and engagement.
• Training is one of the most significant activities that MAC shall include in its architecture.
The training activities shall be given shape to enhance the skill sets and competencies of the
employees (Newton, 2015).
• There shall be use and implementation of iterative & adaptive methods so that the outcomes
are in accordance with the project requirements. The use of iterations will ensure that short-
term goals are defined that are easy to carry out. There will also be customer interactions
involved which would enhance the overall quality and will make it easier to improve upon the
results. The scalability and flexibility will also improve (Csbdu, 2004).
• The selection of the supplier groups shall be done as per the needs assessment and the results
on the market analysis. The suppliers shall be made aware of the contractual norms and
agreements along with the terms of services in the legal document. The legal contract must be
signed by both the parties.
• There must be in-depth information collection processes executed so that the requirements
that are collected are real and in accordance with the defined standards. Also, the data sources
must be explored to make sure that the relevant data sets are collected for the project (Bilkent,
2010).
• The risk and issue avoidance approach followed and applied in the project was not up to the
mark in Airbus and Boeing that led to negative implication (Crane, 2013). MAC shall adopt a
risk management strategy in accordance with the management methodologies.
CONCLUSIONS
The report covered the reasons of failure for Airbus and Boeing projects and included the measures to
be taken by MAC to avoid the same set of problems. In case of Airbus, there were new and
unexplored functionalities and services involved that demanded increased timeframe. Wire
installation process witnessed several errors which contributed in the overrun of schedule and also
added to the project complexities. Communication gaps, design complexities, and non-realistic
expectations were also involved. In the case of Boeing, there were also poor training mechanisms
involved and the resources were not adequately trained. The vendors outsourced the tasks to their
supplier groups and the cycle went on. It led to difficulties in tracking the supplies and the
6
and inspections at the regular intervals to tackle any issues on a real-time basis (Shariff,
2013).
• Gaining of buy-in will prove to be beneficial for the project and the organization as a whole.
The internal and external stakeholders shall be made aware about additional responsibilities to
handle the process. Also, they must be explained the benefits associated with the decision to
maintain the motivation and engagement.
• Training is one of the most significant activities that MAC shall include in its architecture.
The training activities shall be given shape to enhance the skill sets and competencies of the
employees (Newton, 2015).
• There shall be use and implementation of iterative & adaptive methods so that the outcomes
are in accordance with the project requirements. The use of iterations will ensure that short-
term goals are defined that are easy to carry out. There will also be customer interactions
involved which would enhance the overall quality and will make it easier to improve upon the
results. The scalability and flexibility will also improve (Csbdu, 2004).
• The selection of the supplier groups shall be done as per the needs assessment and the results
on the market analysis. The suppliers shall be made aware of the contractual norms and
agreements along with the terms of services in the legal document. The legal contract must be
signed by both the parties.
• There must be in-depth information collection processes executed so that the requirements
that are collected are real and in accordance with the defined standards. Also, the data sources
must be explored to make sure that the relevant data sets are collected for the project (Bilkent,
2010).
• The risk and issue avoidance approach followed and applied in the project was not up to the
mark in Airbus and Boeing that led to negative implication (Crane, 2013). MAC shall adopt a
risk management strategy in accordance with the management methodologies.
CONCLUSIONS
The report covered the reasons of failure for Airbus and Boeing projects and included the measures to
be taken by MAC to avoid the same set of problems. In case of Airbus, there were new and
unexplored functionalities and services involved that demanded increased timeframe. Wire
installation process witnessed several errors which contributed in the overrun of schedule and also
added to the project complexities. Communication gaps, design complexities, and non-realistic
expectations were also involved. In the case of Boeing, there were also poor training mechanisms
involved and the resources were not adequately trained. The vendors outsourced the tasks to their
supplier groups and the cycle went on. It led to difficulties in tracking the supplies and the
6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Murasaki Aircraft Corporation (MAC)
complexities also increased. The multi-layered outsourcing model was associated that further
enhanced the number of complexities. MAC shall ensure that integrated handling of the project is
done and the role of management is active to avoid issues under any category. The management must
carry out reviews, audits, and inspections at the regular intervals to tackle any issues on a real-time
basis. There must also be enhanced planning and analysis involved to make sure that the successful
results are achieved.
7
complexities also increased. The multi-layered outsourcing model was associated that further
enhanced the number of complexities. MAC shall ensure that integrated handling of the project is
done and the role of management is active to avoid issues under any category. The management must
carry out reviews, audits, and inspections at the regular intervals to tackle any issues on a real-time
basis. There must also be enhanced planning and analysis involved to make sure that the successful
results are achieved.
7

Murasaki Aircraft Corporation (MAC)
REFERENCES
Amalraj, J. (2007). Project Management: Challenges & Lessons Learned. Retrieved 11 October 2018,
from http://www.beg.utexas.edu/energyecon/ua_2007/AB_Project_Mgt_challenges.pdf
Baker, M. (2013). Boeing 787-8 Design, Certification, And Manufacturing Systems Review. Faa.gov.
Retrieved 11 October 2018, from
https://www.faa.gov/about/plans_reports/media/787_Report_Final.pdf
Bbc. (2012). Factfile: Airbus A380. BBC News. Retrieved 11 October 2018, from
http://www.bbc.com/news/uk-11693164
Bilkent. (2010). A Guide to the Project Management Body of Knowledge. Cs.bilkent.edu.tr. Retrieved
11 October 2018, from http://www.cs.bilkent.edu.tr/~cagatay/cs413/PMBOK.pdf
Crane, L. (2013). Introduction to Risk Management. Extensionrme.org. Retrieved 11 October 2018,
from http://extensionrme.org/pubs/IntroductionToRiskManagement.pdf
Csbdu. (2004). A Guide to the Project Management Body of Knowledge. Retrieved 11 October 2018,
from http://www.csbdu.in/csbdu-old/pdf/A%20Guide%20to%20the%20Project
%20Management%20Body%20of%20Knowledge.pdf
Denning, S. (2013). The Boeing Debacle: Seven Lessons Every CEO Must Learn. Comlabgames.com.
Retrieved 11 October 2018, from http://comlabgames.com/45-971/instructor/boeing/Boeing
%20Debacle_Seven%20Lessons%20Every%20CEO%20Must%20Learn
%20%20Forbes_01_17_13.pdf
Dorfler, I., & Baumann, O. (2014). Learning from a Drastic Failure: The Case of the Airbus A380
Program. Taylor & Francis. Retrieved 11 October 2018, from
http://www.tandfonline.com/doi/abs/10.1080/13662716.2014.910891
Elahi, E., Sheikhzadeh, M., & Lamba, N. (2012). "An Integrated Outsourcing Framework: Analyzing
Boeing’s Outsourcing Program for Dreamliner (B787). Scholarworks.umb.edu. Retrieved
11 October 2018, from http://scholarworks.umb.edu/msis_faculty_pubs/26/
Freimuth, D. (2016). Financial evaluation of the Airbus A380 Neo program. Brage.bibsys.no.
Retrieved 11 October 2018, from
https://brage.bibsys.no/xmlui/bitstream/handle/11250/2442498/MSc0152016.pdf?sequence=1
Mseitif, J. (2014). Boeing’s Behavior in a Liberalized Marketplace: The 787 Dreamliner Project
and Impact on Puget Sound Workers. Digital.lib.washington.edu. Retrieved 11 October 2018,
8
REFERENCES
Amalraj, J. (2007). Project Management: Challenges & Lessons Learned. Retrieved 11 October 2018,
from http://www.beg.utexas.edu/energyecon/ua_2007/AB_Project_Mgt_challenges.pdf
Baker, M. (2013). Boeing 787-8 Design, Certification, And Manufacturing Systems Review. Faa.gov.
Retrieved 11 October 2018, from
https://www.faa.gov/about/plans_reports/media/787_Report_Final.pdf
Bbc. (2012). Factfile: Airbus A380. BBC News. Retrieved 11 October 2018, from
http://www.bbc.com/news/uk-11693164
Bilkent. (2010). A Guide to the Project Management Body of Knowledge. Cs.bilkent.edu.tr. Retrieved
11 October 2018, from http://www.cs.bilkent.edu.tr/~cagatay/cs413/PMBOK.pdf
Crane, L. (2013). Introduction to Risk Management. Extensionrme.org. Retrieved 11 October 2018,
from http://extensionrme.org/pubs/IntroductionToRiskManagement.pdf
Csbdu. (2004). A Guide to the Project Management Body of Knowledge. Retrieved 11 October 2018,
from http://www.csbdu.in/csbdu-old/pdf/A%20Guide%20to%20the%20Project
%20Management%20Body%20of%20Knowledge.pdf
Denning, S. (2013). The Boeing Debacle: Seven Lessons Every CEO Must Learn. Comlabgames.com.
Retrieved 11 October 2018, from http://comlabgames.com/45-971/instructor/boeing/Boeing
%20Debacle_Seven%20Lessons%20Every%20CEO%20Must%20Learn
%20%20Forbes_01_17_13.pdf
Dorfler, I., & Baumann, O. (2014). Learning from a Drastic Failure: The Case of the Airbus A380
Program. Taylor & Francis. Retrieved 11 October 2018, from
http://www.tandfonline.com/doi/abs/10.1080/13662716.2014.910891
Elahi, E., Sheikhzadeh, M., & Lamba, N. (2012). "An Integrated Outsourcing Framework: Analyzing
Boeing’s Outsourcing Program for Dreamliner (B787). Scholarworks.umb.edu. Retrieved
11 October 2018, from http://scholarworks.umb.edu/msis_faculty_pubs/26/
Freimuth, D. (2016). Financial evaluation of the Airbus A380 Neo program. Brage.bibsys.no.
Retrieved 11 October 2018, from
https://brage.bibsys.no/xmlui/bitstream/handle/11250/2442498/MSc0152016.pdf?sequence=1
Mseitif, J. (2014). Boeing’s Behavior in a Liberalized Marketplace: The 787 Dreamliner Project
and Impact on Puget Sound Workers. Digital.lib.washington.edu. Retrieved 11 October 2018,
8
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Murasaki Aircraft Corporation (MAC)
from https://digital.lib.washington.edu/researchworks/bitstream/handle/1773/26912/
Mseitif_washington_0250O_13381.pdf;sequence=1
Newton, P. (2015). Principles of Project Management. Retrieved 11 October 2018, from
http://www.free-management-ebooks.com/dldebk-pdf/fme-project-principles.pdf
Rochfort, S. (2006). Delay issues cloud A380 visit - Business - Business - smh.com.au. Smh.com.au.
Retrieved 11 October 2018, from http://www.smh.com.au/news/business/delay-issues-cloud-
a380-visit/2006/11/28/1164476179330.html
Shariff, S. (2013). Assessment of Project Management Skills and Learning Outcomes in Students’
Projects. Retrieved 11 October 2018, from
http://www.sciencedirect.com/science/article/pii/S1877042813020363/pdf?
md5=16f498b0203d44eb0bb95f5b83d90b6f&pid=1-s2.0-S1877042813020363-main.pdf
Shore, B. (2009). Airbus A380 - Project Failure Lessons Learned. Globalprojectstrategy.com.
Retrieved 11 October 2018, from http://globalprojectstrategy.com/lessons/case.php?id=23
Tang, C., & Zimmerman, J. (2009). Managing New Product Development and Supply Chain Risks:
The Boeing 787 Case. Retrieved 11 October 2018, from
https://eng.umd.edu/~austin/ense622.d/lecture-resources/Boeing787-Outsourcing2009.pdf
9
from https://digital.lib.washington.edu/researchworks/bitstream/handle/1773/26912/
Mseitif_washington_0250O_13381.pdf;sequence=1
Newton, P. (2015). Principles of Project Management. Retrieved 11 October 2018, from
http://www.free-management-ebooks.com/dldebk-pdf/fme-project-principles.pdf
Rochfort, S. (2006). Delay issues cloud A380 visit - Business - Business - smh.com.au. Smh.com.au.
Retrieved 11 October 2018, from http://www.smh.com.au/news/business/delay-issues-cloud-
a380-visit/2006/11/28/1164476179330.html
Shariff, S. (2013). Assessment of Project Management Skills and Learning Outcomes in Students’
Projects. Retrieved 11 October 2018, from
http://www.sciencedirect.com/science/article/pii/S1877042813020363/pdf?
md5=16f498b0203d44eb0bb95f5b83d90b6f&pid=1-s2.0-S1877042813020363-main.pdf
Shore, B. (2009). Airbus A380 - Project Failure Lessons Learned. Globalprojectstrategy.com.
Retrieved 11 October 2018, from http://globalprojectstrategy.com/lessons/case.php?id=23
Tang, C., & Zimmerman, J. (2009). Managing New Product Development and Supply Chain Risks:
The Boeing 787 Case. Retrieved 11 October 2018, from
https://eng.umd.edu/~austin/ense622.d/lecture-resources/Boeing787-Outsourcing2009.pdf
9
1 out of 10
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.