Project Management Report: Development of Mobile Application Project
VerifiedAdded on 2020/04/21
|18
|4248
|155
Report
AI Summary
This project management report details the development of a mobile application for a retail organization. The report begins with an introduction to project management principles and then outlines the project's objectives, scope, exclusions, deliverables, and constraints. It includes a Work Breakdown Structure (WBS) and explains the various work packages involved, such as research and business discovery, planning development, prototyping, graphic design, mobile app development, testing, and marketing. The report also covers risk management, including the identification, analysis, and mitigation of potential risks, and presents a risk register. The report provides a comprehensive overview of the project's structure, emphasizing the importance of effective planning and management throughout the mobile application development lifecycle. The report uses methodologies like Prince2 and PMBOK and describes the project in phases from initialization to closure. The report highlights the importance of managing deliverables and mitigating risks to ensure the successful completion of the mobile application development project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

Running head: PROJECT MANAGEMENT REPORT
Project Management Report
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Management Report
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1PROJECT MANAGEMENT REPORT
Table of Contents
1. Introduction..................................................................................................................................2
2. Project Overview.........................................................................................................................2
2.1 Project Objectives..................................................................................................................2
2.2 Project Scope and Exclusions................................................................................................3
2.3 Project Deliverables and Constraints.....................................................................................3
3. Work Breakdown Structure.........................................................................................................4
4. Explanation of a Work Package..................................................................................................5
5. Risk Management and Risk Register...........................................................................................7
5.1 Risk Management Plan..........................................................................................................8
5.2 Risk Register........................................................................................................................10
6. Project Structure........................................................................................................................11
7. Conclusion.................................................................................................................................13
References......................................................................................................................................15
Table of Contents
1. Introduction..................................................................................................................................2
2. Project Overview.........................................................................................................................2
2.1 Project Objectives..................................................................................................................2
2.2 Project Scope and Exclusions................................................................................................3
2.3 Project Deliverables and Constraints.....................................................................................3
3. Work Breakdown Structure.........................................................................................................4
4. Explanation of a Work Package..................................................................................................5
5. Risk Management and Risk Register...........................................................................................7
5.1 Risk Management Plan..........................................................................................................8
5.2 Risk Register........................................................................................................................10
6. Project Structure........................................................................................................................11
7. Conclusion.................................................................................................................................13
References......................................................................................................................................15

2PROJECT MANAGEMENT REPORT
1. Introduction
The development of the various types of project has been eased by the help of effective
project planning and management. According to Svejvig and Andersen (2015), the principles of
project management are implied for developing the increased efficiency and development of the
project integration management. The development of the project operation and the use of
effective project analysis would allow the formation of the system development. The various
types of project like software and application development, construction projects, event
management, and travel planning are being developed by using methodologies like prince2 and
PMBOK (Martinelli and Milosevic 2016). The project lifecycle is formed by selecting the
methodology and aligning activities in that manner.
The following assignment is a project management report that consists of the some initial
information regarding the project. The project selected for the management report is
“Development of the mobile application for the retail organization”. The project would involve
the use of project initialization process, project planning process, mobile application
development techniques, and project closure. The report would involve the overview of the
project by pointing out the objectives, scope, exclusions, constraints, and deliverables of the
project. The work breakdown structure and explanation of the work package have been also
mentioned in the report. The final section of the report would explain the risk management plan
and project structure.
2. Project Overview
2.1 Project Objectives
1. Introduction
The development of the various types of project has been eased by the help of effective
project planning and management. According to Svejvig and Andersen (2015), the principles of
project management are implied for developing the increased efficiency and development of the
project integration management. The development of the project operation and the use of
effective project analysis would allow the formation of the system development. The various
types of project like software and application development, construction projects, event
management, and travel planning are being developed by using methodologies like prince2 and
PMBOK (Martinelli and Milosevic 2016). The project lifecycle is formed by selecting the
methodology and aligning activities in that manner.
The following assignment is a project management report that consists of the some initial
information regarding the project. The project selected for the management report is
“Development of the mobile application for the retail organization”. The project would involve
the use of project initialization process, project planning process, mobile application
development techniques, and project closure. The report would involve the overview of the
project by pointing out the objectives, scope, exclusions, constraints, and deliverables of the
project. The work breakdown structure and explanation of the work package have been also
mentioned in the report. The final section of the report would explain the risk management plan
and project structure.
2. Project Overview
2.1 Project Objectives

3PROJECT MANAGEMENT REPORT
The name of the project is “Development of the mobile application for the retail
organization” and the project is implied for the development of the mobile application for the
retail organization. The objectives of the project are,
To develop the application for the retail organization and imply it effectively
To develop project initial documents and plan for mobile application development
project
To implement the design methodology for designing the mobile application for
the retail organization
To design the graphic for the mobile application and attain expected test results
2.2 Project Scope and Exclusions
The project of “Development of the mobile application for the retail organization” is
developed for ensuring that the mobile application would be developed and launched for the
retail organization. The scope statement of the project is “using effective project management
principles for developing the mobile application for the retail organization”. The in-scope and
out of scope items of the project are,
In-scope: The project of the “Development of the mobile application for the retail
organization” requires the development of the operations and formation of the effective and
improved organization. The project plan, cost estimation, risk management plan, and change
management would be helpful for overcoming the issues in change implementation.
Out of Scope: The out of scope item of the project of the “Development of the mobile
application for the retail organization” are the transport management plan, event management
plan, and communication plan.
2.3 Project Deliverables and Constraints
The name of the project is “Development of the mobile application for the retail
organization” and the project is implied for the development of the mobile application for the
retail organization. The objectives of the project are,
To develop the application for the retail organization and imply it effectively
To develop project initial documents and plan for mobile application development
project
To implement the design methodology for designing the mobile application for
the retail organization
To design the graphic for the mobile application and attain expected test results
2.2 Project Scope and Exclusions
The project of “Development of the mobile application for the retail organization” is
developed for ensuring that the mobile application would be developed and launched for the
retail organization. The scope statement of the project is “using effective project management
principles for developing the mobile application for the retail organization”. The in-scope and
out of scope items of the project are,
In-scope: The project of the “Development of the mobile application for the retail
organization” requires the development of the operations and formation of the effective and
improved organization. The project plan, cost estimation, risk management plan, and change
management would be helpful for overcoming the issues in change implementation.
Out of Scope: The out of scope item of the project of the “Development of the mobile
application for the retail organization” are the transport management plan, event management
plan, and communication plan.
2.3 Project Deliverables and Constraints
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4PROJECT MANAGEMENT REPORT
Deliverables of the project are the final tangible and intangible outcomes of the project
that can be considered as the deliverable of the project (Keatley et al. 2017). The deliverables of
the project of the “Development of the mobile application for the retail organization” are,
Project Plan document that would be required for following during the project
progress
Mobile Application Design that should be realized for developing the application
Mobile Application that would run well for the retail organization
Test Results that would provide the acknowledgement whether the application
would run appropriately
The following table would show the deliverables of the project along with duration and
schedule for the project of the “Development of the mobile application for the retail
organization”,
WB
S Task Name Duration Start Finish
2.5 Complete Plan development 5 days Fri 2/23/18 Thu 3/1/18
4.4 User Interface Design is developed 5 days Tue
3/27/18 Mon 4/2/18
5 Development of Mobile app 29 days Tue
3/27/18 Fri 5/4/18
6 Testing 33 days Tue
3/27/18 Thu 5/10/18
3. Work Breakdown Structure
Work Breakdown Structure is the representation of the various work packages of the
project in a specific manner (Siami-Irdemoosa, Dindarloo and Sharifzadeh 2015). The work
breakdown structure of the project of the “Development of the mobile application for the retail
organization” is given below,
Deliverables of the project are the final tangible and intangible outcomes of the project
that can be considered as the deliverable of the project (Keatley et al. 2017). The deliverables of
the project of the “Development of the mobile application for the retail organization” are,
Project Plan document that would be required for following during the project
progress
Mobile Application Design that should be realized for developing the application
Mobile Application that would run well for the retail organization
Test Results that would provide the acknowledgement whether the application
would run appropriately
The following table would show the deliverables of the project along with duration and
schedule for the project of the “Development of the mobile application for the retail
organization”,
WB
S Task Name Duration Start Finish
2.5 Complete Plan development 5 days Fri 2/23/18 Thu 3/1/18
4.4 User Interface Design is developed 5 days Tue
3/27/18 Mon 4/2/18
5 Development of Mobile app 29 days Tue
3/27/18 Fri 5/4/18
6 Testing 33 days Tue
3/27/18 Thu 5/10/18
3. Work Breakdown Structure
Work Breakdown Structure is the representation of the various work packages of the
project in a specific manner (Siami-Irdemoosa, Dindarloo and Sharifzadeh 2015). The work
breakdown structure of the project of the “Development of the mobile application for the retail
organization” is given below,

5PROJECT MANAGEMENT REPORT
Development of the mobile
application for the Retail
Organization
Research and Business
Discovery
Project Vision
Development
Analyzing the
application
development
requirements
Resource
Accumulation
Project Team Build
up
Project Charter
Documentation
Risk Management
Plan
Planning Development
Making list of
activities required in
mobile app
development
Selecting project
plan methodology
Developing plan
outline
Review of the Plan
Complete Plan
development
Plan Approval
Prototyping the user flow
Analysis of the
guidelines and rules
of app development
Concept
Development
Interactive
visualization of the
application
Wireframes are
developed
Graphic Design
Sending Design
questionnaire to
client for collecting
requirements
Collecting and
analyzing the design
questionnaire
Implying the
wireframes
developed
User Interface Design
is developed
Simulation of design
for testing
Review of the
design
Design is approved
Development of Mobile
app
Listing the program
and functions
Required
Selecting coding
platform for the app
Coding the mobile
app program
Integration of the
application and
database
Testing
Black box testing
White box testing
UX testing
UI testing
Marketing and Launch
Analysis of
application
developed
Review with Client
Development of
Marketing Plan
Marketing via social
media, blogs,
websites, and
advertising
Launch Event
Planning and
Execution
Application is Live
Project is Closed
Figure 1: WBS of the project
4. Explanation of a Work Package
The work package can be defined as the collection of sub-activities and aligning them
under a subproject (Nicholas and Steyn 2017). The complete project is formed for ensuring the
development of the effective and improved project operations for developing the mobile
application for the retail organization. The complete project of the “Development of the mobile
application for the retail organization” is divided into 7 work package namely Research and
Business Discovery, Planning Development, Prototyping the user flow, Graphic Design,
Development of Mobile app, Testing, and Marketing and Launch. These work packages are
formed in an integrated form for the complete project schedule and have been explained below,
Work Package of Research and Business Discovery: The research and business
discovery is the first work package of the complete project plan. It involves activities of project
vision development, analysing the application development requirements, resource
Development of the mobile
application for the Retail
Organization
Research and Business
Discovery
Project Vision
Development
Analyzing the
application
development
requirements
Resource
Accumulation
Project Team Build
up
Project Charter
Documentation
Risk Management
Plan
Planning Development
Making list of
activities required in
mobile app
development
Selecting project
plan methodology
Developing plan
outline
Review of the Plan
Complete Plan
development
Plan Approval
Prototyping the user flow
Analysis of the
guidelines and rules
of app development
Concept
Development
Interactive
visualization of the
application
Wireframes are
developed
Graphic Design
Sending Design
questionnaire to
client for collecting
requirements
Collecting and
analyzing the design
questionnaire
Implying the
wireframes
developed
User Interface Design
is developed
Simulation of design
for testing
Review of the
design
Design is approved
Development of Mobile
app
Listing the program
and functions
Required
Selecting coding
platform for the app
Coding the mobile
app program
Integration of the
application and
database
Testing
Black box testing
White box testing
UX testing
UI testing
Marketing and Launch
Analysis of
application
developed
Review with Client
Development of
Marketing Plan
Marketing via social
media, blogs,
websites, and
advertising
Launch Event
Planning and
Execution
Application is Live
Project is Closed
Figure 1: WBS of the project
4. Explanation of a Work Package
The work package can be defined as the collection of sub-activities and aligning them
under a subproject (Nicholas and Steyn 2017). The complete project is formed for ensuring the
development of the effective and improved project operations for developing the mobile
application for the retail organization. The complete project of the “Development of the mobile
application for the retail organization” is divided into 7 work package namely Research and
Business Discovery, Planning Development, Prototyping the user flow, Graphic Design,
Development of Mobile app, Testing, and Marketing and Launch. These work packages are
formed in an integrated form for the complete project schedule and have been explained below,
Work Package of Research and Business Discovery: The research and business
discovery is the first work package of the complete project plan. It involves activities of project
vision development, analysing the application development requirements, resource

6PROJECT MANAGEMENT REPORT
accumulation, project team build up, project charter documentation, and risk management plan
(Mir and Pinnington 2014). The work package is a sub-project of the main project of the
“Development of the mobile application for the retail organization” and it would help in
initiating the project plan for the development of the improved project development.
Work Package of Planning Development: The planning development is the most
significant alignment of the project planning methodology for ensuring that the project plan for
the project of the “Development of the mobile application for the retail organization” is
developed successfully. The activities include making list of activities required in mobile app
development, selecting project plan methodology, developing plan outline, review of the plan,
complete plan development, and plan approval (Hegazy 2013). These activities would help in
ensuring that the project plan is developed effectively.
Work package of Prototyping the user flow: The prototyping of the user flow is carried
on for the development of an effective prototype of the mobile application and testing it for
getting appropriate test results for the project of the “Development of the mobile application for
the retail organization”. The analysis of the guidelines and rules of app development, concept
development, interactive visualization of the application and wireframes are developed are the
activities of this work package.
Work Package of Graphic Design: The graphic design is implemented in the project for
ensuring that the design for the mobile application is developed successfully. The activities of
this work package are sending design questionnaire to client for collecting requirements,
collecting and analysing the design questionnaire, implying the wireframes developed, user
interface design is developed, simulation of design for testing, review of the design, and design is
accumulation, project team build up, project charter documentation, and risk management plan
(Mir and Pinnington 2014). The work package is a sub-project of the main project of the
“Development of the mobile application for the retail organization” and it would help in
initiating the project plan for the development of the improved project development.
Work Package of Planning Development: The planning development is the most
significant alignment of the project planning methodology for ensuring that the project plan for
the project of the “Development of the mobile application for the retail organization” is
developed successfully. The activities include making list of activities required in mobile app
development, selecting project plan methodology, developing plan outline, review of the plan,
complete plan development, and plan approval (Hegazy 2013). These activities would help in
ensuring that the project plan is developed effectively.
Work package of Prototyping the user flow: The prototyping of the user flow is carried
on for the development of an effective prototype of the mobile application and testing it for
getting appropriate test results for the project of the “Development of the mobile application for
the retail organization”. The analysis of the guidelines and rules of app development, concept
development, interactive visualization of the application and wireframes are developed are the
activities of this work package.
Work Package of Graphic Design: The graphic design is implemented in the project for
ensuring that the design for the mobile application is developed successfully. The activities of
this work package are sending design questionnaire to client for collecting requirements,
collecting and analysing the design questionnaire, implying the wireframes developed, user
interface design is developed, simulation of design for testing, review of the design, and design is
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT REPORT
approved. The development of the project of the “Development of the mobile application for the
retail organization” involves the formation of the specific design of the mobile.
Work package of Development of Mobile app: The mobile app development is the
most crucial operation of the project of the “Development of the mobile application for the retail
organization”. The mobile application development would involve the following activities listing
the program and functions required, selecting coding platform for the app, coding the mobile app
program, and integration of the application and database. The mobile application development
consists of the technical development of the project.
Work Package of Testing: The work package of the testing for the project of the
“Development of the mobile application for the retail organization” is helpful for analysing the
mobile design, prototype, database integration, and coding for the mobile app. The activities of
black box testing, white box testing, UX testing, and UI testing are included in this work package
and the test results are analysed for ensuring the operative functions of the mobile application.
Work package of Marketing and Launch: The work package of marketing and launch
is helpful for promoting the mobile application using various platforms and launch the
application. The analysis of application developed, review with client, development of marketing
plan, marketing via social media, blogs, websites, and advertising, launch event planning and
execution, and application is live are the activities includes in this project work package.
5. Risk Management and Risk Register
Risk Management is an effective and improved process of developing a plan for
managing the probable issues of the project and develop some strategies for the reduction of the
impact on the project (Yildiz et al. 2014). The project of the “Development of the mobile
application for the retail organization” is an application development project and there are
approved. The development of the project of the “Development of the mobile application for the
retail organization” involves the formation of the specific design of the mobile.
Work package of Development of Mobile app: The mobile app development is the
most crucial operation of the project of the “Development of the mobile application for the retail
organization”. The mobile application development would involve the following activities listing
the program and functions required, selecting coding platform for the app, coding the mobile app
program, and integration of the application and database. The mobile application development
consists of the technical development of the project.
Work Package of Testing: The work package of the testing for the project of the
“Development of the mobile application for the retail organization” is helpful for analysing the
mobile design, prototype, database integration, and coding for the mobile app. The activities of
black box testing, white box testing, UX testing, and UI testing are included in this work package
and the test results are analysed for ensuring the operative functions of the mobile application.
Work package of Marketing and Launch: The work package of marketing and launch
is helpful for promoting the mobile application using various platforms and launch the
application. The analysis of application developed, review with client, development of marketing
plan, marketing via social media, blogs, websites, and advertising, launch event planning and
execution, and application is live are the activities includes in this project work package.
5. Risk Management and Risk Register
Risk Management is an effective and improved process of developing a plan for
managing the probable issues of the project and develop some strategies for the reduction of the
impact on the project (Yildiz et al. 2014). The project of the “Development of the mobile
application for the retail organization” is an application development project and there are

8PROJECT MANAGEMENT REPORT
probabilities that the project might face risks. The risks of the project that can have a negative
impact on the project are technical risk, operational risk, and functional risk.
5.1 Risk Management Plan
The risk management plan is a chain mechanism that helps in risk management and
reduction of the issues of the risk by developing some mitigation strategies for the risk faced in
the project (Pritchard and PMP 2014). The risk management plan comprises of identification of
the risk, analysis of the risk, evaluation of the risk, and mitigation of the risk. These processes
have been explained below,
Identification of the Risk: The identification of the risk is the first process of the risk
management plan. The process is marked by the analysis of the processes of the project and
sorting the various risks that can impact the project. The identification of the risk is done by the
help of the past reports, surveys, and discussion with the project team. The project of the
“Development of the mobile application for the retail organization” would face the probability of
issues in designing, cost overrun, conflict among team, system incompatibility, and delay in
operation.
Analysis of the Risk: The analysis of the risk is an improved function for the
development of specific operation. The analysis of the risk is applied for developing the
improved operation and formation of the effective system development. The analysis is based on
the impact and probability of occurrence of the risk (Martinelli and Milosevic 2016). The
analysis would help in developing ratings to the risk factors according to the factor of occurrence
and severity of impact. The risk analysis for the project of the “Development of the mobile
application for the retail organization” is given below,
probabilities that the project might face risks. The risks of the project that can have a negative
impact on the project are technical risk, operational risk, and functional risk.
5.1 Risk Management Plan
The risk management plan is a chain mechanism that helps in risk management and
reduction of the issues of the risk by developing some mitigation strategies for the risk faced in
the project (Pritchard and PMP 2014). The risk management plan comprises of identification of
the risk, analysis of the risk, evaluation of the risk, and mitigation of the risk. These processes
have been explained below,
Identification of the Risk: The identification of the risk is the first process of the risk
management plan. The process is marked by the analysis of the processes of the project and
sorting the various risks that can impact the project. The identification of the risk is done by the
help of the past reports, surveys, and discussion with the project team. The project of the
“Development of the mobile application for the retail organization” would face the probability of
issues in designing, cost overrun, conflict among team, system incompatibility, and delay in
operation.
Analysis of the Risk: The analysis of the risk is an improved function for the
development of specific operation. The analysis of the risk is applied for developing the
improved operation and formation of the effective system development. The analysis is based on
the impact and probability of occurrence of the risk (Martinelli and Milosevic 2016). The
analysis would help in developing ratings to the risk factors according to the factor of occurrence
and severity of impact. The risk analysis for the project of the “Development of the mobile
application for the retail organization” is given below,

9PROJECT MANAGEMENT REPORT
Risk ID Risk Name Risk Description Severity
(1-5)
Occurrence
(1-5)
RF0012001 Issues in
Designing
The issues in designing are resulted
from the minor issues in the operation
of the mobile application. The design
issues would form hindrance in forming
the mobile application for the retail
organization.
3 (Moderate) 4 (Likely)
RF0012002 Cost Overrun The cost overrun is a financial issue that
results in forming the exhaustion of
excess resources for the development of
the project. The limited resources of the
project would have to be managed by
the development of the mobile
application in the project.
4 (Major) 1 (Rare)
RF0012003 Conflict
Among Team
The conflict among the team member is
resulted in forming the issues of
managing work flow. The small-small
issues in the project would form the
major hindrance among the team
members which in turn would cause
issues in completion of the project
2 (Minor) 2 (unlikely)
RF0012004 System
Incompatibility
The incompatible data and system is a
probable issue of the mobile application
development for the organization. The
system incompatibility is resulted due to
the platform dependency in the system
developed.
5
(Catastrophic)
3 (Possible)
RF0012005 Delay in
Operation
The delay in operation of the project is
formed when due to any issue the
activities are not completed in time. The
project of mobile application
development can be delayed due to the
issues in the project operations.
3 (Moderate) 5 (Almost
Certain)
Evaluation of the Risk: The evaluation of the risk is done in order to form the risk
ranking and mitigation strategy. The evaluation phase would consider the risk severity and risk
probability for analysing and developing risk mitigation strategy in the later phase. The risk
evaluation is formed when the implementation of the operation is formed in the improved
operation development. The evaluation of the project management plan is helpful for ensuring
that the analysis of the effective management process would help in enabling the
Risk ID Risk Name Risk Description Severity
(1-5)
Occurrence
(1-5)
RF0012001 Issues in
Designing
The issues in designing are resulted
from the minor issues in the operation
of the mobile application. The design
issues would form hindrance in forming
the mobile application for the retail
organization.
3 (Moderate) 4 (Likely)
RF0012002 Cost Overrun The cost overrun is a financial issue that
results in forming the exhaustion of
excess resources for the development of
the project. The limited resources of the
project would have to be managed by
the development of the mobile
application in the project.
4 (Major) 1 (Rare)
RF0012003 Conflict
Among Team
The conflict among the team member is
resulted in forming the issues of
managing work flow. The small-small
issues in the project would form the
major hindrance among the team
members which in turn would cause
issues in completion of the project
2 (Minor) 2 (unlikely)
RF0012004 System
Incompatibility
The incompatible data and system is a
probable issue of the mobile application
development for the organization. The
system incompatibility is resulted due to
the platform dependency in the system
developed.
5
(Catastrophic)
3 (Possible)
RF0012005 Delay in
Operation
The delay in operation of the project is
formed when due to any issue the
activities are not completed in time. The
project of mobile application
development can be delayed due to the
issues in the project operations.
3 (Moderate) 5 (Almost
Certain)
Evaluation of the Risk: The evaluation of the risk is done in order to form the risk
ranking and mitigation strategy. The evaluation phase would consider the risk severity and risk
probability for analysing and developing risk mitigation strategy in the later phase. The risk
evaluation is formed when the implementation of the operation is formed in the improved
operation development. The evaluation of the project management plan is helpful for ensuring
that the analysis of the effective management process would help in enabling the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10PROJECT MANAGEMENT REPORT
Mitigation of the Risk: The risk mitigation is implied for ensuring that the effect of the
risk on the activities of the project would be related to the development of the activities and
alignment of the operations for the development of the effective and improved analysis. The
integration of the operations would be implied for forming the development of the operation for
forming the analysis of the improved operation. The integration of the operation would be
formed for decreasing the overall impact of the risk.
Figure 2: Risk Management Plan
5.2 Risk Register
Occurrence
Severity
Rare
(1)
Unlikely
(2)
Possible
(3)
Likely
(4)
Almost Certain
(5)
Insignificant
(1)
Minor
(2)
Conflict
Among Team
Moderate
(3)
Issues in
Designing
Delay in
Operation
Mitigation of the Risk: The risk mitigation is implied for ensuring that the effect of the
risk on the activities of the project would be related to the development of the activities and
alignment of the operations for the development of the effective and improved analysis. The
integration of the operations would be implied for forming the development of the operation for
forming the analysis of the improved operation. The integration of the operation would be
formed for decreasing the overall impact of the risk.
Figure 2: Risk Management Plan
5.2 Risk Register
Occurrence
Severity
Rare
(1)
Unlikely
(2)
Possible
(3)
Likely
(4)
Almost Certain
(5)
Insignificant
(1)
Minor
(2)
Conflict
Among Team
Moderate
(3)
Issues in
Designing
Delay in
Operation

11PROJECT MANAGEMENT REPORT
Major
(4)
Cost Overrun
Critical
(5)
System
Incompatibility
6. Project Structure
The project has been structured by following the agile methodology for forming the
development of the improved system development. The analysis of the operations would be
formed for the integration of the operation for development. The structure of the project is
formed by aligning the integration of the improved operations of the organization. The structure
of the project is formed for the deployment of the system integration and development. The
analysis would help in forming the development of the improved integration and management of
system development.
The project structure is shown in the table below,
WBS Task Name Duration Start Finish Predecessors
0 Development of the mobile application
for the retail organization
118
days
Mon
1/1/18
Wed
6/13/18
1 Research and Business Discovery 30 days Mon
1/1/18 Fri 2/9/18
1.1 Project Vision Development 4 days Mon
1/1/18
Thu
1/4/18
1.2 Analyzing the application development
requirements 5 days Fri 1/5/18 Thu
1/11/18 2
1.3 Resource Accumulation 7 days Fri
1/12/18
Mon
1/22/18 3
1.4 Project Team Build up 6 days Tue
1/23/18
Tue
1/30/18 4
1.5 Project Charter Documentation 3 days Wed
1/31/18 Fri 2/2/18 5
1.6 Risk Management Plan 5 days Mon
2/5/18 Fri 2/9/18 6
2 Planning Development 15 days Mon
2/12/18 Fri 3/2/18
Major
(4)
Cost Overrun
Critical
(5)
System
Incompatibility
6. Project Structure
The project has been structured by following the agile methodology for forming the
development of the improved system development. The analysis of the operations would be
formed for the integration of the operation for development. The structure of the project is
formed by aligning the integration of the improved operations of the organization. The structure
of the project is formed for the deployment of the system integration and development. The
analysis would help in forming the development of the improved integration and management of
system development.
The project structure is shown in the table below,
WBS Task Name Duration Start Finish Predecessors
0 Development of the mobile application
for the retail organization
118
days
Mon
1/1/18
Wed
6/13/18
1 Research and Business Discovery 30 days Mon
1/1/18 Fri 2/9/18
1.1 Project Vision Development 4 days Mon
1/1/18
Thu
1/4/18
1.2 Analyzing the application development
requirements 5 days Fri 1/5/18 Thu
1/11/18 2
1.3 Resource Accumulation 7 days Fri
1/12/18
Mon
1/22/18 3
1.4 Project Team Build up 6 days Tue
1/23/18
Tue
1/30/18 4
1.5 Project Charter Documentation 3 days Wed
1/31/18 Fri 2/2/18 5
1.6 Risk Management Plan 5 days Mon
2/5/18 Fri 2/9/18 6
2 Planning Development 15 days Mon
2/12/18 Fri 3/2/18

12PROJECT MANAGEMENT REPORT
2.1 Making list of activities required in
mobile app development 3 days Mon
2/12/18
Wed
2/14/18 7
2.2 Selecting project plan methodology 1 day Thu
2/15/18
Thu
2/15/18 9
2.3 Developing plan outline 3 days Fri
2/16/18
Tue
2/20/18 10
2.4 Review of the Plan 2 days Wed
2/21/18
Thu
2/22/18 11
2.5 Complete Plan development 5 days Fri
2/23/18
Thu
3/1/18 12
2.6 Plan Approval 1 day Fri 3/2/18 Fri 3/2/18 13
3 Prototyping the user flow 14 days Mon
3/5/18
Thu
3/22/18
3.1 Analysis of the guidelines and rules of
app development 3 days Mon
3/5/18
Wed
3/7/18 14
3.2 Concept Development 4 days Thu
3/8/18
Tue
3/13/18 16
3.3 Interactive visualization of the
application 2 days Wed
3/14/18
Thu
3/15/18 17
3.4 Wireframes are developed 5 days Fri
3/16/18
Thu
3/22/18 18
4 Graphic Design 22 days Thu
3/8/18 Fri 4/6/18
4.1 Sending Design questionnaire to client
for collecting requirements 2 days Thu
3/8/18 Fri 3/9/18 16
4.2 Collecting and analyzing the design
questionnaire 3 days Mon
3/12/18
Wed
3/14/18 21
4.3 Implying the wireframes developed 2 days Fri
3/23/18
Mon
3/26/18 19, 22
4.4 User Interface Design is developed 5 days Tue
3/27/18
Mon
4/2/18 23
4.5 Simulation of design for testing 4 days Tue
4/3/18 Fri 4/6/18 24
4.6 Review of the design 3 days Fri
3/30/18
Tue
4/3/18 37, 36
4.7 Design is approved 1 day Wed
4/4/18
Wed
4/4/18 26
5 Development of Mobile app 29 days Tue
3/27/18 Fri 5/4/18
5.1 Listing the program and functions
Required 5 days Tue
3/27/18
Mon
4/2/18 23
5.2 Selecting coding platform for the app 2 days Tue
4/3/18
Wed
4/4/18 29
2.1 Making list of activities required in
mobile app development 3 days Mon
2/12/18
Wed
2/14/18 7
2.2 Selecting project plan methodology 1 day Thu
2/15/18
Thu
2/15/18 9
2.3 Developing plan outline 3 days Fri
2/16/18
Tue
2/20/18 10
2.4 Review of the Plan 2 days Wed
2/21/18
Thu
2/22/18 11
2.5 Complete Plan development 5 days Fri
2/23/18
Thu
3/1/18 12
2.6 Plan Approval 1 day Fri 3/2/18 Fri 3/2/18 13
3 Prototyping the user flow 14 days Mon
3/5/18
Thu
3/22/18
3.1 Analysis of the guidelines and rules of
app development 3 days Mon
3/5/18
Wed
3/7/18 14
3.2 Concept Development 4 days Thu
3/8/18
Tue
3/13/18 16
3.3 Interactive visualization of the
application 2 days Wed
3/14/18
Thu
3/15/18 17
3.4 Wireframes are developed 5 days Fri
3/16/18
Thu
3/22/18 18
4 Graphic Design 22 days Thu
3/8/18 Fri 4/6/18
4.1 Sending Design questionnaire to client
for collecting requirements 2 days Thu
3/8/18 Fri 3/9/18 16
4.2 Collecting and analyzing the design
questionnaire 3 days Mon
3/12/18
Wed
3/14/18 21
4.3 Implying the wireframes developed 2 days Fri
3/23/18
Mon
3/26/18 19, 22
4.4 User Interface Design is developed 5 days Tue
3/27/18
Mon
4/2/18 23
4.5 Simulation of design for testing 4 days Tue
4/3/18 Fri 4/6/18 24
4.6 Review of the design 3 days Fri
3/30/18
Tue
4/3/18 37, 36
4.7 Design is approved 1 day Wed
4/4/18
Wed
4/4/18 26
5 Development of Mobile app 29 days Tue
3/27/18 Fri 5/4/18
5.1 Listing the program and functions
Required 5 days Tue
3/27/18
Mon
4/2/18 23
5.2 Selecting coding platform for the app 2 days Tue
4/3/18
Wed
4/4/18 29
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13PROJECT MANAGEMENT REPORT
5.3 Coding the mobile app program 10 days Thu
4/5/18
Wed
4/18/18 30
5.4 Integration of the application and
database 8 days Wed
4/25/18 Fri 5/4/18 34
6 Testing 33 days Tue
3/27/18
Thu
5/10/18
6.1 Black box testing 4 days Thu
4/19/18
Tue
4/24/18 31
6.2 White box testing 4 days Mon
5/7/18
Thu
5/10/18 32
6.3 UX testing 3 days Tue
3/27/18
Thu
3/29/18 23
6.4 UI testing 3 days Tue
3/27/18
Thu
3/29/18 23
7 Marketing and Launch 23 days Fri
5/11/18
Tue
6/12/18
7.1 Analysis of application developed 3 days Fri
5/11/18
Tue
5/15/18
34, 35, 36, 37,
32
7.2 Review with Client 2 days Wed
5/16/18
Thu
5/17/18 39
7.3 Development of Marketing Plan 5 days Fri
5/18/18
Thu
5/24/18 40
7.4 Marketing via social media, blogs,
websites, and advertising 4 days Fri
5/25/18
Wed
5/30/18 41
7.5 Launch Event Planning and Execution 8 days Thu
5/31/18
Mon
6/11/18 42
7.6 Application is Live 1 day Tue
6/12/18
Tue
6/12/18 43
8 Project is Closed 1 day Wed
6/13/18
Wed
6/13/18 44
7. Conclusion
It can be concluded from the assignment that the alignment of the project management
would form the development of the operations would align the development of operations and
formation of project plan for ensuring the successful completion of the project. The analysis
would allow the integration of the successful project integration and formation of the
development. The scope statement of the project is “using effective project management
5.3 Coding the mobile app program 10 days Thu
4/5/18
Wed
4/18/18 30
5.4 Integration of the application and
database 8 days Wed
4/25/18 Fri 5/4/18 34
6 Testing 33 days Tue
3/27/18
Thu
5/10/18
6.1 Black box testing 4 days Thu
4/19/18
Tue
4/24/18 31
6.2 White box testing 4 days Mon
5/7/18
Thu
5/10/18 32
6.3 UX testing 3 days Tue
3/27/18
Thu
3/29/18 23
6.4 UI testing 3 days Tue
3/27/18
Thu
3/29/18 23
7 Marketing and Launch 23 days Fri
5/11/18
Tue
6/12/18
7.1 Analysis of application developed 3 days Fri
5/11/18
Tue
5/15/18
34, 35, 36, 37,
32
7.2 Review with Client 2 days Wed
5/16/18
Thu
5/17/18 39
7.3 Development of Marketing Plan 5 days Fri
5/18/18
Thu
5/24/18 40
7.4 Marketing via social media, blogs,
websites, and advertising 4 days Fri
5/25/18
Wed
5/30/18 41
7.5 Launch Event Planning and Execution 8 days Thu
5/31/18
Mon
6/11/18 42
7.6 Application is Live 1 day Tue
6/12/18
Tue
6/12/18 43
8 Project is Closed 1 day Wed
6/13/18
Wed
6/13/18 44
7. Conclusion
It can be concluded from the assignment that the alignment of the project management
would form the development of the operations would align the development of operations and
formation of project plan for ensuring the successful completion of the project. The analysis
would allow the integration of the successful project integration and formation of the
development. The scope statement of the project is “using effective project management

14PROJECT MANAGEMENT REPORT
principles for developing the mobile application for the retail organization”. The project plan,
cost estimation, risk management plan, and change management were helpful for overcoming the
issues in change implementation. Deliverables of the project are the final tangible and intangible
outcomes of the project that can be considered as the deliverable of the project. The complete
project of the “Development of the mobile application for the retail organization” was divided
into 7 work package namely Research and Business Discovery, Planning Development,
Prototyping the user flow, Graphic Design, Development of Mobile app, Testing, and Marketing
and Launch. The various risks of the project were issues in designing, cost overrun, conflict
among team, system incompatibility, and delay in operation. The project had been structured by
following the agile methodology for forming the development of the improved system
development.
principles for developing the mobile application for the retail organization”. The project plan,
cost estimation, risk management plan, and change management were helpful for overcoming the
issues in change implementation. Deliverables of the project are the final tangible and intangible
outcomes of the project that can be considered as the deliverable of the project. The complete
project of the “Development of the mobile application for the retail organization” was divided
into 7 work package namely Research and Business Discovery, Planning Development,
Prototyping the user flow, Graphic Design, Development of Mobile app, Testing, and Marketing
and Launch. The various risks of the project were issues in designing, cost overrun, conflict
among team, system incompatibility, and delay in operation. The project had been structured by
following the agile methodology for forming the development of the improved system
development.

15PROJECT MANAGEMENT REPORT
References
Cable, J. and Cheung, C., 2017. Eight Principles of Effective Online Teaching: A Decade-Long
Lessons Learned in Project Management Education.
Cicmil, S., Cooke-Davies, T., Crawford, L. and Richardson, K., 2017, April. Exploring the
complexity of projects: Implications of complexity theory for project management practice.
Project Management Institute.
Devaux, S.A., 2014. Managing Projects as Investments: Earned Value to Business Value. CRC
press.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Flyvbjerg, B., 2013. From Nobel prize to project management: getting risks right. arXiv preprint
arXiv:1302.3642.
Ganesh, M.K.S. and Thanushkodi, K., 2015. An efficient software cost estimation technique
using fuzzy logic with the aid of optimization algorithm. International Journal of Innovative
Computing, Vol11 (2) Pp-587-597.
Hegazy, T., 2013. Computer-Based Construction Project Management: Pearson New
International Edition. Pearson Higher Ed.
Keatley, D.A., Ferguson, E., Lonsdale, A. and Hagger, M.S., 2017. Lay understanding of the
causes of binge drinking in the United Kingdom and Australia: a network diagram
approach. Health education research, 32(1), pp.33-47.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
References
Cable, J. and Cheung, C., 2017. Eight Principles of Effective Online Teaching: A Decade-Long
Lessons Learned in Project Management Education.
Cicmil, S., Cooke-Davies, T., Crawford, L. and Richardson, K., 2017, April. Exploring the
complexity of projects: Implications of complexity theory for project management practice.
Project Management Institute.
Devaux, S.A., 2014. Managing Projects as Investments: Earned Value to Business Value. CRC
press.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Flyvbjerg, B., 2013. From Nobel prize to project management: getting risks right. arXiv preprint
arXiv:1302.3642.
Ganesh, M.K.S. and Thanushkodi, K., 2015. An efficient software cost estimation technique
using fuzzy logic with the aid of optimization algorithm. International Journal of Innovative
Computing, Vol11 (2) Pp-587-597.
Hegazy, T., 2013. Computer-Based Construction Project Management: Pearson New
International Edition. Pearson Higher Ed.
Keatley, D.A., Ferguson, E., Lonsdale, A. and Hagger, M.S., 2017. Lay understanding of the
causes of binge drinking in the United Kingdom and Australia: a network diagram
approach. Health education research, 32(1), pp.33-47.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

16PROJECT MANAGEMENT REPORT
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS
Project. McGraw-Hill.
Martin, B., 2017. The politics of electricity planning in South Africa: A review of dominant
advocacy coalitions seeking to influence the Integrated Resource Plan of 2010 (IRP2010), and
its update in 2013 (Doctoral dissertation, University of Cape Town).
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Martone, R.G., Erickson, A., Mach, M., Hale, T., McGregor, A., Prahler, E.E., Foley, M.,
Caldwell, M. and Hartge, E.H., 2016, February. EcoPrinciples Connect: A Pilot Project
Matching Ecological Principles with Available Data to Promote Ecosystem-Based Management.
In AGU Fall Meeting Abstracts.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Mohammad, I., van den Broek, H., Boots, M.L. and Wong, R., Oracle International Corporation,
2016. Showing relationships between tasks in a Gantt chart. U.S. Patent 9,336,502.
Nakamura, S., Kaneko, K., Okada, Y., Yin, C. and Ogata, H., 2015. Cubic gantt chart as
visualization tool for learning activity data. In 23rd International Conference on Computers in
Education, ICCE 2015. Asia-Pacific Society for Computers in Education.
Nam, S., Lee, D.K., Jeong, Y.K., Lee, P. and Shin, J.G., 2016. Environmental impact assessment
of composite small craft manufacturing using the generic work breakdown
structure. International Journal of Precision Engineering and Manufacturing-Green
Technology, 3(3), pp.261-272.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS
Project. McGraw-Hill.
Martin, B., 2017. The politics of electricity planning in South Africa: A review of dominant
advocacy coalitions seeking to influence the Integrated Resource Plan of 2010 (IRP2010), and
its update in 2013 (Doctoral dissertation, University of Cape Town).
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Martone, R.G., Erickson, A., Mach, M., Hale, T., McGregor, A., Prahler, E.E., Foley, M.,
Caldwell, M. and Hartge, E.H., 2016, February. EcoPrinciples Connect: A Pilot Project
Matching Ecological Principles with Available Data to Promote Ecosystem-Based Management.
In AGU Fall Meeting Abstracts.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Mohammad, I., van den Broek, H., Boots, M.L. and Wong, R., Oracle International Corporation,
2016. Showing relationships between tasks in a Gantt chart. U.S. Patent 9,336,502.
Nakamura, S., Kaneko, K., Okada, Y., Yin, C. and Ogata, H., 2015. Cubic gantt chart as
visualization tool for learning activity data. In 23rd International Conference on Computers in
Education, ICCE 2015. Asia-Pacific Society for Computers in Education.
Nam, S., Lee, D.K., Jeong, Y.K., Lee, P. and Shin, J.G., 2016. Environmental impact assessment
of composite small craft manufacturing using the generic work breakdown
structure. International Journal of Precision Engineering and Manufacturing-Green
Technology, 3(3), pp.261-272.

17PROJECT MANAGEMENT REPORT
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Pritchard, C.L. and PMP, P.R., 2014. Risk management: concepts and guidance. CRC Press.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction
project management. John Wiley & Sons.
Siami-Irdemoosa, E., Dindarloo, S.R. and Sharifzadeh, M., 2015. Work breakdown structure
(WBS) development for underground construction. Automation in Construction, 58, pp.85-94.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Yildiz, A.E., Dikmen, I., Birgonul, M.T., Ercoskun, K. and Alten, S., 2014. A knowledge-based
risk mapping tool for cost estimation of international construction projects. Automation in
Construction, 43, pp.144-155.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Pritchard, C.L. and PMP, P.R., 2014. Risk management: concepts and guidance. CRC Press.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction
project management. John Wiley & Sons.
Siami-Irdemoosa, E., Dindarloo, S.R. and Sharifzadeh, M., 2015. Work breakdown structure
(WBS) development for underground construction. Automation in Construction, 58, pp.85-94.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Yildiz, A.E., Dikmen, I., Birgonul, M.T., Ercoskun, K. and Alten, S., 2014. A knowledge-based
risk mapping tool for cost estimation of international construction projects. Automation in
Construction, 43, pp.144-155.
1 out of 18
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.