This project scope statement outlines the construction of the Museo Atlantico, detailing the project's work breakdown structure (WBS) and WBS dictionary. The WBS breaks down the project into five main phases: Preliminary Planning and Discussion, Project Planning, Project Initiation, Project Execution, and Project Closure. Each phase includes specific tasks, resources, and estimated costs. The document provides a comprehensive overview of the project's timeline, budget, and key deliverables, including permits, licenses, blueprints, design reviews, and the procurement of construction materials. The execution phase involves site surveys, excavation, foundation building, framework preparation, structural installations, and finishing works, culminating in the museum's completion and handover. The project closure phase includes reviews, appraisals, payments, and stakeholder sign-offs. The total project cost is estimated at $12,482,000.00, with a completion date of June 23, 2021. The document serves as a detailed guide for managing and executing the underwater museum project.

Running Head: PROJECT SCOPE STATEMENT
Project Scope Statement
Name of the Student
Name of the University
Project Scope Statement
Name of the Student
Name of the University
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT SCOPE STATEMENT
The work breakdown structure (WBS) is developed as follows.
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The work breakdown structure (WBS) is developed as follows.
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)

2PROJECT SCOPE STATEMENT
The WBS dictionary is as follows.
WBS WBS Name Description Resources Finish Cost
1
Construction of
Museo Atlantico
Construction of
Museo Atlantico
Wed 6/23/21
$12,482,000.0
0
1.1
Preliminary
Planning and
Discussion
Preliminary
Planning and
Discussion
Wed 10/31/18 $723, 800.00
1.1.1 Team Meeting
Meeting of
the Project
Management
Team
Mon 8/27/18 $723, 800.00
1.1.2 Decision
Decision on
the Building of
Museo Atlantico
Underwater
Construction
Manager,
Finance
Manager, Project
Manager, Project
Site Supervisor
Mon 9/17/18 $231, 000.00
1.1.3 Business Case Submit
Business Case
for Project
Underwater
Construction
Manager,
Mon 10/1/18 $154, 000.00
The WBS dictionary is as follows.
WBS WBS Name Description Resources Finish Cost
1
Construction of
Museo Atlantico
Construction of
Museo Atlantico
Wed 6/23/21
$12,482,000.0
0
1.1
Preliminary
Planning and
Discussion
Preliminary
Planning and
Discussion
Wed 10/31/18 $723, 800.00
1.1.1 Team Meeting
Meeting of
the Project
Management
Team
Mon 8/27/18 $723, 800.00
1.1.2 Decision
Decision on
the Building of
Museo Atlantico
Underwater
Construction
Manager,
Finance
Manager, Project
Manager, Project
Site Supervisor
Mon 9/17/18 $231, 000.00
1.1.3 Business Case Submit
Business Case
for Project
Underwater
Construction
Manager,
Mon 10/1/18 $154, 000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT SCOPE STATEMENT
Finance
Manager, Project
Manager, Project
Site Supervisor
1.1.4 Presentation
Present
Business Case to
Client
Underwater
Construction
Manager,
Finance
Manager, Project
Manager, Project
Site Supervisor
Wed 10/3/18 $30, 800.00
1.1.5 Proposal
Propose an
Estimated
Overall Budget
Required for the
Project
Underwater
Construction
Manager,
Finance
Manager, Project
Manager, Project
Site Supervisor
Wed 10/10/18 $77, 000.00
1.1.6 Feasibility Test the
Feasibility of the
Underwater
Museum
Underwater
Construction
Manager,
Finance
Wed 10/31/18 $231, 000.00
Finance
Manager, Project
Manager, Project
Site Supervisor
1.1.4 Presentation
Present
Business Case to
Client
Underwater
Construction
Manager,
Finance
Manager, Project
Manager, Project
Site Supervisor
Wed 10/3/18 $30, 800.00
1.1.5 Proposal
Propose an
Estimated
Overall Budget
Required for the
Project
Underwater
Construction
Manager,
Finance
Manager, Project
Manager, Project
Site Supervisor
Wed 10/10/18 $77, 000.00
1.1.6 Feasibility Test the
Feasibility of the
Underwater
Museum
Underwater
Construction
Manager,
Finance
Wed 10/31/18 $231, 000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT SCOPE STATEMENT
Manager, Project
Manager, Project
Site Supervisor
1.1.7 Approval
Receive
Approval to
Proceed with the
Project
Project Manager Wed 10/31/18 $0.00
1.2
Project Planning
Phase
Project
Planning Phase
Fri 2/22/19 $531, 400.00
1.2.1 Team
Develop
Appropriate
Project Team
Project Manager Wed 11/14/18 $44, 000.00
1.2.2 Roadmap
Develop an
Appropriate
Roadmap for the
Project
Underwater
Construction
Manager
Wed 11/28/18 $36, 000.00
1.2.3 Project Charter
Prepare
Project Charter
Thu 11/29/18 $259, 000.00
1.2.4 Scope Determine
Appropriate and
Feasible Scope
Underwater
Construction
Manager, Project
Thu 12/6/18 $37, 000.00
Manager, Project
Manager, Project
Site Supervisor
1.1.7 Approval
Receive
Approval to
Proceed with the
Project
Project Manager Wed 10/31/18 $0.00
1.2
Project Planning
Phase
Project
Planning Phase
Fri 2/22/19 $531, 400.00
1.2.1 Team
Develop
Appropriate
Project Team
Project Manager Wed 11/14/18 $44, 000.00
1.2.2 Roadmap
Develop an
Appropriate
Roadmap for the
Project
Underwater
Construction
Manager
Wed 11/28/18 $36, 000.00
1.2.3 Project Charter
Prepare
Project Charter
Thu 11/29/18 $259, 000.00
1.2.4 Scope Determine
Appropriate and
Feasible Scope
Underwater
Construction
Manager, Project
Thu 12/6/18 $37, 000.00

5PROJECT SCOPE STATEMENT
for the Project Site Supervisor
1.2.5 Schedule
Determine
a Feasible and
Appropriate
Schedule for the
Project
Underwater
Construction
Manager, Project
Site Supervisor
Thu 12/13/18 $37, 000.00
1.2.6 Budget
Estimate an
Overall Budget
for the Project
Underwater
Construction
Manager, Project
Site Supervisor
Thu 12/27/18 $74, 000.00
1.2.7 Feasibility
Determine
the Overall
Feasibility of the
Project
Underwater
Construction
Manager, Project
Site Supervisor
Thu 1/17/19 $111, 000.00
1.2.8 Tender
Release
Tender for
Hiring
Contractor
Underwater
Construction
Manager, Project
Site Supervisor
Thu 1/24/19 $37, 000.00
1.2.9 Contractor Select
Contractor for
the Project
Underwater
Construction
Manager, Project
Tue 1/29/19 $22, 200.00
for the Project Site Supervisor
1.2.5 Schedule
Determine
a Feasible and
Appropriate
Schedule for the
Project
Underwater
Construction
Manager, Project
Site Supervisor
Thu 12/13/18 $37, 000.00
1.2.6 Budget
Estimate an
Overall Budget
for the Project
Underwater
Construction
Manager, Project
Site Supervisor
Thu 12/27/18 $74, 000.00
1.2.7 Feasibility
Determine
the Overall
Feasibility of the
Project
Underwater
Construction
Manager, Project
Site Supervisor
Thu 1/17/19 $111, 000.00
1.2.8 Tender
Release
Tender for
Hiring
Contractor
Underwater
Construction
Manager, Project
Site Supervisor
Thu 1/24/19 $37, 000.00
1.2.9 Contractor Select
Contractor for
the Project
Underwater
Construction
Manager, Project
Tue 1/29/19 $22, 200.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT SCOPE STATEMENT
Site Supervisor
1.2.10 Discussion
Discuss the
Requirements of
the Project
Underwater
Construction
Manager, Project
Site Supervisor
Tue 2/12/19 $74, 000.00
1.2.11 Discussion
Discuss
about the Human
Resources
Required for the
Project
Underwater
Construction
Manager, Project
Site Supervisor
Mon 2/18/19 $29, 600.00
1.2.12 Discussion
Discuss
Suitable Time
Frame and
Budget Spending
Plan
Underwater
Construction
Manager, Project
Site Supervisor
Fri 2/22/19 $29, 600.00
1.2.13 Confirmation
Confirm
Proceeding with
the Project
Underwater
Construction
Manager, Project
Site Supervisor
Fri 2/22/19 $0.00
1.3 Project Initiation Project Fri 7/26/19 $5, 396,
Site Supervisor
1.2.10 Discussion
Discuss the
Requirements of
the Project
Underwater
Construction
Manager, Project
Site Supervisor
Tue 2/12/19 $74, 000.00
1.2.11 Discussion
Discuss
about the Human
Resources
Required for the
Project
Underwater
Construction
Manager, Project
Site Supervisor
Mon 2/18/19 $29, 600.00
1.2.12 Discussion
Discuss
Suitable Time
Frame and
Budget Spending
Plan
Underwater
Construction
Manager, Project
Site Supervisor
Fri 2/22/19 $29, 600.00
1.2.13 Confirmation
Confirm
Proceeding with
the Project
Underwater
Construction
Manager, Project
Site Supervisor
Fri 2/22/19 $0.00
1.3 Project Initiation Project Fri 7/26/19 $5, 396,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT SCOPE STATEMENT
Initiation 000.00
1.3.1 Permit
Receive
Permit for
Underwater
Construction
Underwater
Construction
Manager
Fri 3/15/19 $54, 000.00
1.3.2 License
Receive
License for the
Project
Underwater
Construction
Manager
Fri 4/5/19 $54, 000.00
1.3.3 Blueprint
Develop a
Suitable
Blueprint of the
Museum
Underwater
Construction
Manager
Fri 5/17/19 $108, 000.00
1.3.4 Design
Review the
Museum Design
Underwater
Construction
Manager
Fri 6/7/19 $54, 000.00
1.3.5 Human Resource
Recruit
Human
Resources (Work
Force)
Underwater
Construction
Manager
Fri 6/28/19 $54, 000.00
1.3.6 Materials Procure
Construction
Underwater
Construction
Fri 7/12/19 $5, 036,
Initiation 000.00
1.3.1 Permit
Receive
Permit for
Underwater
Construction
Underwater
Construction
Manager
Fri 3/15/19 $54, 000.00
1.3.2 License
Receive
License for the
Project
Underwater
Construction
Manager
Fri 4/5/19 $54, 000.00
1.3.3 Blueprint
Develop a
Suitable
Blueprint of the
Museum
Underwater
Construction
Manager
Fri 5/17/19 $108, 000.00
1.3.4 Design
Review the
Museum Design
Underwater
Construction
Manager
Fri 6/7/19 $54, 000.00
1.3.5 Human Resource
Recruit
Human
Resources (Work
Force)
Underwater
Construction
Manager
Fri 6/28/19 $54, 000.00
1.3.6 Materials Procure
Construction
Underwater
Construction
Fri 7/12/19 $5, 036,

8PROJECT SCOPE STATEMENT
Materials
Manager,
Construction
Materials and
Other Costs[1]
000.00
1.3.7 Vehicles
Hire
Underwater
Construction
Vehicles
Underwater
Construction
Manager
Fri 7/26/19 $36, 000.00
1.3.8 Initiation
Proceed to
Project Initiation
Underwater
Construction
Manager, Project
Site Supervisor
Fri 7/26/19 $0.00
1.4 Project Execution
Project
Execution
Mon 5/24/21
$5, 712,
000.00
1.4.1 Survey
Underwater
Survey of the
Selected Site
Workers Fri 8/30/19 $300, 000.00
1.4.2 Excavation
Excavate the
Site
Workers Fri 11/1/19 $540, 000.00
1.4.3 Foundation Build
Foundation on
Workers Fri 1/10/20 $600, 000.00
Materials
Manager,
Construction
Materials and
Other Costs[1]
000.00
1.3.7 Vehicles
Hire
Underwater
Construction
Vehicles
Underwater
Construction
Manager
Fri 7/26/19 $36, 000.00
1.3.8 Initiation
Proceed to
Project Initiation
Underwater
Construction
Manager, Project
Site Supervisor
Fri 7/26/19 $0.00
1.4 Project Execution
Project
Execution
Mon 5/24/21
$5, 712,
000.00
1.4.1 Survey
Underwater
Survey of the
Selected Site
Workers Fri 8/30/19 $300, 000.00
1.4.2 Excavation
Excavate the
Site
Workers Fri 11/1/19 $540, 000.00
1.4.3 Foundation Build
Foundation on
Workers Fri 1/10/20 $600, 000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT SCOPE STATEMENT
the Site
1.4.4 Framework
Prepare
Museum
Framework
Workers Fri 6/5/20
$1, 260,
000.00
1.4.5 Structure
Install
Structural
Materials
Workers Fri 7/10/20 $300, 000.00
1.4.6 Zones
Divide Zones
inside the
Underwater
Structure
Workers Fri 8/14/20 $300, 000.00
1.4.7 Structure
Create
Structural
Separations
between the
Zones
Workers Fri 9/18/20 $300, 000.00
1.4.8 Wirings
Install
Electrical
Wirings
Workers Fri 10/23/20 $300, 000.00
1.4.9 Equipments Install Other
Underwater
Workers Fri 11/27/20 $300, 000.00
the Site
1.4.4 Framework
Prepare
Museum
Framework
Workers Fri 6/5/20
$1, 260,
000.00
1.4.5 Structure
Install
Structural
Materials
Workers Fri 7/10/20 $300, 000.00
1.4.6 Zones
Divide Zones
inside the
Underwater
Structure
Workers Fri 8/14/20 $300, 000.00
1.4.7 Structure
Create
Structural
Separations
between the
Zones
Workers Fri 9/18/20 $300, 000.00
1.4.8 Wirings
Install
Electrical
Wirings
Workers Fri 10/23/20 $300, 000.00
1.4.9 Equipments Install Other
Underwater
Workers Fri 11/27/20 $300, 000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT SCOPE STATEMENT
Equipments
1.4.10 Foundations
Place
Underwater
Foundations for
Placing
Specimens
Workers Fri 12/25/20 $240, 000.00
1.4.11 Specimen
Install the
Specimens
Workers Fri 2/5/21 $360, 000.00
1.4.12 Specimen
Install
Various Art
Pieces and
Statues
Workers Fri 2/19/21 $120, 000.00
1.4.13 Electrical Works
Finishing
Electrical and
Other Works
Workers Fri 3/12/21 $180, 000.00
1.4.14 Oxygen Supply
Installation
of Oxygen
Supply System
Workers Fri 3/19/21 $60, 000.00
1.4.15 Safety Installation
of Underwater
Relief and Safety
Workers Fri 4/2/21 $120, 000.00
Equipments
1.4.10 Foundations
Place
Underwater
Foundations for
Placing
Specimens
Workers Fri 12/25/20 $240, 000.00
1.4.11 Specimen
Install the
Specimens
Workers Fri 2/5/21 $360, 000.00
1.4.12 Specimen
Install
Various Art
Pieces and
Statues
Workers Fri 2/19/21 $120, 000.00
1.4.13 Electrical Works
Finishing
Electrical and
Other Works
Workers Fri 3/12/21 $180, 000.00
1.4.14 Oxygen Supply
Installation
of Oxygen
Supply System
Workers Fri 3/19/21 $60, 000.00
1.4.15 Safety Installation
of Underwater
Relief and Safety
Workers Fri 4/2/21 $120, 000.00

11PROJECT SCOPE STATEMENT
Equipments
1.4.16 Additional Works
Additional
Works
Wed 5/19/21 $396, 000.00
1.4.16.
1
Colors
Add Colors
to Museum
Zones
Workers Fri 4/16/21 $120, 000.00
1.4.16.
2
Colors
Add Colors
to Museum
Exterior
Workers Fri 4/30/21 $120, 000.00
1.4.16.
3
Connection Testing
Testing of
the Electrical
Connections
Workers Thu 5/6/21 $48, 000.00
1.4.16.
4
System Testing
Testing of
Emergency
Oxygen Supply
System
Workers Thu 5/13/21 $60, 000.00
1.4.16.
5
Safety Testing
Testing of
the Underwater
Relief and Safety
Equipments
Workers Wed 5/19/21 $48, 000.00
Equipments
1.4.16 Additional Works
Additional
Works
Wed 5/19/21 $396, 000.00
1.4.16.
1
Colors
Add Colors
to Museum
Zones
Workers Fri 4/16/21 $120, 000.00
1.4.16.
2
Colors
Add Colors
to Museum
Exterior
Workers Fri 4/30/21 $120, 000.00
1.4.16.
3
Connection Testing
Testing of
the Electrical
Connections
Workers Thu 5/6/21 $48, 000.00
1.4.16.
4
System Testing
Testing of
Emergency
Oxygen Supply
System
Workers Thu 5/13/21 $60, 000.00
1.4.16.
5
Safety Testing
Testing of
the Underwater
Relief and Safety
Equipments
Workers Wed 5/19/21 $48, 000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 12
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.