MN601 Network Project Management: Network Infrastructure Project Plan
VerifiedAdded on  2023/06/11
|17
|3010
|336
Report
AI Summary
This report outlines the development of a network infrastructure within an Australian organization, aiming to address challenges and leverage business benefits. The project, estimated to take 15.2 weeks, involves defining functional and non-functional requirements, including network security, hardware, and performance. Key team members and their roles are identified, followed by a detailed project plan encompassing scope, work breakdown structure, timeline, resource needs, cost estimation, quality, stakeholder, communication, and risk management plans. Ethical issues are addressed, and a deployment plan is presented, including project crashing scenarios. The document concludes with project sign-off, review, and recommendations. Desklib provides access to similar project management assignments and resources for students.

Running head: PROJECT MANAGEMENT
Assignment 3: Development of network infrastructure
Name of the Student
Name of the University
Author’s Note
Table of Contents
Assignment 3: Development of network infrastructure
Name of the Student
Name of the University
Author’s Note
Table of Contents
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
1. Clear outline......................................................................................................................................2
2. Project requirements.........................................................................................................................2
3. Project team members.....................................................................................................................3
4. Project plan.......................................................................................................................................5
4.1 Project scope...............................................................................................................................5
4.2 Work breakdown Structure.........................................................................................................5
4.3 Estimated time-line.....................................................................................................................6
4.4 Resource needs...........................................................................................................................8
4.5 Gantt chart and Network Diagram............................................................................................10
4.6 Estimated costs.........................................................................................................................11
4.7 Quality plan...............................................................................................................................14
4.8 Stakeholder analysis..................................................................................................................14
4.9 Communication plan.................................................................................................................15
4.10 Risk management plan............................................................................................................15
4.11 Ethical issue analysis...............................................................................................................17
4.12 Project deployment plan.........................................................................................................17
5. Project crashing by duration of 2 weeks..........................................................................................18
6. Project signoff..................................................................................................................................19
7. Project review and recommendations.............................................................................................19
Bibliography.........................................................................................................................................20
PROJECT MANAGEMENT
1. Clear outline......................................................................................................................................2
2. Project requirements.........................................................................................................................2
3. Project team members.....................................................................................................................3
4. Project plan.......................................................................................................................................5
4.1 Project scope...............................................................................................................................5
4.2 Work breakdown Structure.........................................................................................................5
4.3 Estimated time-line.....................................................................................................................6
4.4 Resource needs...........................................................................................................................8
4.5 Gantt chart and Network Diagram............................................................................................10
4.6 Estimated costs.........................................................................................................................11
4.7 Quality plan...............................................................................................................................14
4.8 Stakeholder analysis..................................................................................................................14
4.9 Communication plan.................................................................................................................15
4.10 Risk management plan............................................................................................................15
4.11 Ethical issue analysis...............................................................................................................17
4.12 Project deployment plan.........................................................................................................17
5. Project crashing by duration of 2 weeks..........................................................................................18
6. Project signoff..................................................................................................................................19
7. Project review and recommendations.............................................................................................19
Bibliography.........................................................................................................................................20

2
PROJECT MANAGEMENT
1. Clear outline
The paper mainly reflects on the network infrastructure development within an organization
in Australia. The main aim of the organization is to mitigate the challenges as well as issues that the
organization faces due to absence of proper network architecture within the organization. The
development of network architecture not only assists in resolving the issues of the organization but
also helps in brining business related benefits. The entire project of network development will be
successfully executed within the time that is around 15.2 weeks by assuming that the project will be
commenced on 31st May 2018. In addition to this, it is analyzed that the entire project will be
completed within the time that is around 13-09-18. The project objectives are listed below:
 To develop network infrastructure within an organization
 To resolve the issues and difficulties that the organization faces
 To finish the project within the timeframe that is around 15.2 weeks.
2. Project requirements
The requirements of the project are mainly categorized into functional and non-functional
requirements are listed below:
Functional requirements: The project functional requirements are listed below:
Network security: proper network security is needed for securing the data as well as
information from third party access. This is because the protection of confidential information is one
of the significant priorities for the organization.
Networking software: The network software that is required mainly includes various types
of network operations, firewall, and operating system as well as different types of other security
related applications in order to enable the entire connectivity as well as operations of the
organization.
Networking hardware: It is found that the organization generally requires various types of
networking hardware including wireless routers, cables as well as switches. All the requirements are
generally required for developing the networking infrastructure quite effectively.
Non-functional requirements: The non-functional requirements for the development of
network infrastructure are listed below:
PROJECT MANAGEMENT
1. Clear outline
The paper mainly reflects on the network infrastructure development within an organization
in Australia. The main aim of the organization is to mitigate the challenges as well as issues that the
organization faces due to absence of proper network architecture within the organization. The
development of network architecture not only assists in resolving the issues of the organization but
also helps in brining business related benefits. The entire project of network development will be
successfully executed within the time that is around 15.2 weeks by assuming that the project will be
commenced on 31st May 2018. In addition to this, it is analyzed that the entire project will be
completed within the time that is around 13-09-18. The project objectives are listed below:
 To develop network infrastructure within an organization
 To resolve the issues and difficulties that the organization faces
 To finish the project within the timeframe that is around 15.2 weeks.
2. Project requirements
The requirements of the project are mainly categorized into functional and non-functional
requirements are listed below:
Functional requirements: The project functional requirements are listed below:
Network security: proper network security is needed for securing the data as well as
information from third party access. This is because the protection of confidential information is one
of the significant priorities for the organization.
Networking software: The network software that is required mainly includes various types
of network operations, firewall, and operating system as well as different types of other security
related applications in order to enable the entire connectivity as well as operations of the
organization.
Networking hardware: It is found that the organization generally requires various types of
networking hardware including wireless routers, cables as well as switches. All the requirements are
generally required for developing the networking infrastructure quite effectively.
Non-functional requirements: The non-functional requirements for the development of
network infrastructure are listed below:
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
Performance: Appropriate speed of network infrastructure must be provided to the
organization for managing the business related operation quite effectively.
Availability: The network infrastructures of the organization need to be available whenever
needed. Appropriate service of network infrastructure generally assists in improving the entire
operations of the business.
3. Project team members
The team members who are involved within the network infrastructure of the organization
are provided in the table below:
Stakeholders Expertise
Project manager The project manager is quite responsible for
managing,, executing as well as monitoring the
project of network infrastructure.
Project planner The project planner works with the project
manager for developing the network
infrastructure of the organization.
Network engineer They are responsible for establishing appropriate
environment off networking by designing system
configuration as well as installing and defining
the entire system..
Network consultant The network consultant provides guidance to
the team members of the project for performing
the work of the project.
Network analyst The network analyst identifies as well as
determines the network related issues that are
associated with the network development.
Hr. manager The Hr. manager takes the responsible for
recruiting as well as providing proper training to
the employees who are hired.
Tester The tester takes the responsibility for testing the
working, usability of the system.
Financial manager The financial manager is responsible for
managing the finance of the entire organization
PROJECT MANAGEMENT
Performance: Appropriate speed of network infrastructure must be provided to the
organization for managing the business related operation quite effectively.
Availability: The network infrastructures of the organization need to be available whenever
needed. Appropriate service of network infrastructure generally assists in improving the entire
operations of the business.
3. Project team members
The team members who are involved within the network infrastructure of the organization
are provided in the table below:
Stakeholders Expertise
Project manager The project manager is quite responsible for
managing,, executing as well as monitoring the
project of network infrastructure.
Project planner The project planner works with the project
manager for developing the network
infrastructure of the organization.
Network engineer They are responsible for establishing appropriate
environment off networking by designing system
configuration as well as installing and defining
the entire system..
Network consultant The network consultant provides guidance to
the team members of the project for performing
the work of the project.
Network analyst The network analyst identifies as well as
determines the network related issues that are
associated with the network development.
Hr. manager The Hr. manager takes the responsible for
recruiting as well as providing proper training to
the employees who are hired.
Tester The tester takes the responsibility for testing the
working, usability of the system.
Financial manager The financial manager is responsible for
managing the finance of the entire organization
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
quite effectively.
4. Project plan
4.1 Project scope
The project scope is provided below:
 Development of proper network infrastructure
 Completion of project within 15.2 weeks
 Designing logical as well as physical network
 Making proper connection with the devices
4.2 Work breakdown Structure
Figure 1: Work Breakdown Structure
(Source: Created by Author)
4.3 Estimated time-line
The time that is needed for the development of the network infrastructure will be around
15.2 weeks. The times that are needed for finishing each of the activities of the project are provided
in the table:
PROJECT MANAGEMENT
quite effectively.
4. Project plan
4.1 Project scope
The project scope is provided below:
 Development of proper network infrastructure
 Completion of project within 15.2 weeks
 Designing logical as well as physical network
 Making proper connection with the devices
4.2 Work breakdown Structure
Figure 1: Work Breakdown Structure
(Source: Created by Author)
4.3 Estimated time-line
The time that is needed for the development of the network infrastructure will be around
15.2 weeks. The times that are needed for finishing each of the activities of the project are provided
in the table:

5
PROJECT MANAGEMENT
WBS Task Name Duration Start Finish
1 Development of network
infrastructure 15.2 wks. Thu 31-05-18 Thu 13-09-18
1.1 Initiation phase 1.6 wks. Thu 31-05-18 Mon 11-06-18
1.1.1 Developing business case 2 days Thu 31-05-18 Fri 01-06-18
1.1.2 Cost-benefit analysis 3 days Mon 04-06-18 Wed 06-06-18
1.1.3 Developing charter 2 days Thu 07-06-18 Fri 08-06-18
1.1.4 Appointing team members 1 day Mon 11-06-18 Mon 11-06-18
1.1.5 Milestone 1: Completion of initiation
phase 0 days Mon 11-06-18 Mon 11-06-18
1.2 Planning phase 3.8 wks. Tue 12-06-18 Fri 06-07-18
1.2.1 Developing project plan 3 days Tue 12-06-18 Thu 14-06-18
1.2.2 Developing resource plan 4 days Fri 15-06-18 Wed 20-06-18
1.2.3 Developing financial plan 3 days Thu 21-06-18 Mon 25-06-18
1.2.4 developing risk management plan 2 days Tue 26-06-18 Wed 27-06-18
1.2.5 developing quality plan 3 days Thu 28-06-18 Mon 02-07-18
1.2.6 Developing procurement plan 2 days Tue 03-07-18 Wed 04-07-18
1.2.7 Developing communication plan 2 days Thu 05-07-18 Fri 06-07-18
1.2.8 Milestone 2: Planning phase
completion 0 days Fri 06-07-18 Fri 06-07-18
1.3 Analysis phase 3 wks. Mon 09-07-18 Fri 27-07-18
1.3.1 Analyzing IP addresses 3 days Mon 09-07-18 Wed 11-07-18
1.3.2 Sub-netting 2 days Thu 12-07-18 Fri 13-07-18
1.3.3 Identifying network device 2 days Mon 16-07-18 Tue 17-07-18
1.3.4 identifying network cables 3 days Wed 18-07-18 Fri 20-07-18
1.3.5 Identifying software 2 days Mon 23-07-18 Tue 24-07-18
1.3.6 Identifying server 3 days Wed 25-07-18 Fri 27-07-18
1.3.7 Completion 3: Completion of
analysis phase 0 days Fri 27-07-18 Fri 27-07-18
1.4 Project designing phase 1.8 wks. Mon 30-07-18 Thu 09-08-18
1.4.1 Design of logical network 5 days Mon 30-07-18 Fri 03-08-18
1.4.2 Design of physical design 4 days Mon 06-08-18 Thu 09-08-18
PROJECT MANAGEMENT
WBS Task Name Duration Start Finish
1 Development of network
infrastructure 15.2 wks. Thu 31-05-18 Thu 13-09-18
1.1 Initiation phase 1.6 wks. Thu 31-05-18 Mon 11-06-18
1.1.1 Developing business case 2 days Thu 31-05-18 Fri 01-06-18
1.1.2 Cost-benefit analysis 3 days Mon 04-06-18 Wed 06-06-18
1.1.3 Developing charter 2 days Thu 07-06-18 Fri 08-06-18
1.1.4 Appointing team members 1 day Mon 11-06-18 Mon 11-06-18
1.1.5 Milestone 1: Completion of initiation
phase 0 days Mon 11-06-18 Mon 11-06-18
1.2 Planning phase 3.8 wks. Tue 12-06-18 Fri 06-07-18
1.2.1 Developing project plan 3 days Tue 12-06-18 Thu 14-06-18
1.2.2 Developing resource plan 4 days Fri 15-06-18 Wed 20-06-18
1.2.3 Developing financial plan 3 days Thu 21-06-18 Mon 25-06-18
1.2.4 developing risk management plan 2 days Tue 26-06-18 Wed 27-06-18
1.2.5 developing quality plan 3 days Thu 28-06-18 Mon 02-07-18
1.2.6 Developing procurement plan 2 days Tue 03-07-18 Wed 04-07-18
1.2.7 Developing communication plan 2 days Thu 05-07-18 Fri 06-07-18
1.2.8 Milestone 2: Planning phase
completion 0 days Fri 06-07-18 Fri 06-07-18
1.3 Analysis phase 3 wks. Mon 09-07-18 Fri 27-07-18
1.3.1 Analyzing IP addresses 3 days Mon 09-07-18 Wed 11-07-18
1.3.2 Sub-netting 2 days Thu 12-07-18 Fri 13-07-18
1.3.3 Identifying network device 2 days Mon 16-07-18 Tue 17-07-18
1.3.4 identifying network cables 3 days Wed 18-07-18 Fri 20-07-18
1.3.5 Identifying software 2 days Mon 23-07-18 Tue 24-07-18
1.3.6 Identifying server 3 days Wed 25-07-18 Fri 27-07-18
1.3.7 Completion 3: Completion of
analysis phase 0 days Fri 27-07-18 Fri 27-07-18
1.4 Project designing phase 1.8 wks. Mon 30-07-18 Thu 09-08-18
1.4.1 Design of logical network 5 days Mon 30-07-18 Fri 03-08-18
1.4.2 Design of physical design 4 days Mon 06-08-18 Thu 09-08-18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
1.4.3 Milestone 4:Completion of designing
phase 0 days Thu 09-08-18 Thu 09-08-18
1.5 Implementation phase 3.2 wks. Fri 10-08-18 Fri 31-08-18
1.5.1 Hardware placement 2 days Fri 10-08-18 Mon 13-08-18
1.5.2 Cable placement 2 days Tue 14-08-18 Wed 15-08-18
1.5.3 Allocation of IP 3 days Thu 16-08-18 Mon 20-08-18
1.5.4 Connecting devices 4 days Tue 21-08-18 Fri 24-08-18
1.5.5 Deploying server 5 days Mon 27-08-18 Fri 31-08-18
1.5.6 Milestone 5: Completion of
implementation phase 0 days Fri 31-08-18 Fri 31-08-18
1.6 Testing phase 0.8 wks. Mon 03-09-18 Thu 06-09-18
1.6.1 Testing of network device 1 day Mon 03-09-18 Mon 03-09-18
1.6.2 Congestion testing 1 day Tue 04-09-18 Tue 04-09-18
1.6.3 Performance testing 1 day Wed 05-09-18 Wed 05-09-18
1.6.4 Milestone 6: Completion of testing
phase 1 day Thu 06-09-18 Thu 06-09-18
1.7 Closure phase 1.2 wks. Thu 06-09-18 Thu 13-09-18
1.7.1 Post-project review 3 days Thu 06-09-18 Mon 10-09-18
1.7.2 Sign off from stakeholders 2 days Tue 11-09-18 Wed 12-09-18
1.7.3 Documentation 1 day Thu 13-09-18 Thu 13-09-18
4.4 Resource needs
The resources that are needed for the development of network infrastructure are provided
below:
Hardware: The hardware that is needed for the development of the network infrastructure is
provided below:
 Routers
 Switches
 Wireless cables
Software: The software that is needed are listed below:
 Operating system
PROJECT MANAGEMENT
1.4.3 Milestone 4:Completion of designing
phase 0 days Thu 09-08-18 Thu 09-08-18
1.5 Implementation phase 3.2 wks. Fri 10-08-18 Fri 31-08-18
1.5.1 Hardware placement 2 days Fri 10-08-18 Mon 13-08-18
1.5.2 Cable placement 2 days Tue 14-08-18 Wed 15-08-18
1.5.3 Allocation of IP 3 days Thu 16-08-18 Mon 20-08-18
1.5.4 Connecting devices 4 days Tue 21-08-18 Fri 24-08-18
1.5.5 Deploying server 5 days Mon 27-08-18 Fri 31-08-18
1.5.6 Milestone 5: Completion of
implementation phase 0 days Fri 31-08-18 Fri 31-08-18
1.6 Testing phase 0.8 wks. Mon 03-09-18 Thu 06-09-18
1.6.1 Testing of network device 1 day Mon 03-09-18 Mon 03-09-18
1.6.2 Congestion testing 1 day Tue 04-09-18 Tue 04-09-18
1.6.3 Performance testing 1 day Wed 05-09-18 Wed 05-09-18
1.6.4 Milestone 6: Completion of testing
phase 1 day Thu 06-09-18 Thu 06-09-18
1.7 Closure phase 1.2 wks. Thu 06-09-18 Thu 13-09-18
1.7.1 Post-project review 3 days Thu 06-09-18 Mon 10-09-18
1.7.2 Sign off from stakeholders 2 days Tue 11-09-18 Wed 12-09-18
1.7.3 Documentation 1 day Thu 13-09-18 Thu 13-09-18
4.4 Resource needs
The resources that are needed for the development of network infrastructure are provided
below:
Hardware: The hardware that is needed for the development of the network infrastructure is
provided below:
 Routers
 Switches
 Wireless cables
Software: The software that is needed are listed below:
 Operating system
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
 Server
 Firewall
Human resources: The human resources who are involved within the project are provided
below:
 Project manager
 Project planner
 Network engineer
 Network consultant
 Network analyst
 Network designer
 System engineer
 Tester
 Financial manager
 Hr. manager
 Project sponsor
PROJECT MANAGEMENT
 Server
 Firewall
Human resources: The human resources who are involved within the project are provided
below:
 Project manager
 Project planner
 Network engineer
 Network consultant
 Network analyst
 Network designer
 System engineer
 Tester
 Financial manager
 Hr. manager
 Project sponsor

8
PROJECT MANAGEMENT
4.5 Gantt chart and Network Diagram
Figure 2: Gantt chart
(Source: Created by Author)
PROJECT MANAGEMENT
4.5 Gantt chart and Network Diagram
Figure 2: Gantt chart
(Source: Created by Author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
Figure 3: Network Diagram
(Source: Created by Author)
4.6 Estimated costs
The budget that is needed for finishing the project of network infrastructure is around
$67,320. The overall budget that is needed is reflected in the table below:
Task Name Duration Resource Names Cost
Development of network
infrastructure 15.2 wks. $ 67,320.00
Initiation phase 1.6 wks. $ 2,480.00
Developing business case 2 days Project manager $ 720.00
Cost-benefit analysis 3 days Financial manager $ 840.00
Developing charter 2 days Project planner $ 640.00
Appointing team members 1 day Hr. manager $ 280.00
Milestone 1: Completion of
initiation phase 0 days $ 0.00
Planning phase 3.8 wks. $ 5,968.00
Developing project plan 3 days Project manager $ 1,080.00
Developing resource plan 4 days Hr. manager $ 1,120.00
Developing financial plan 3 days Financial manager, Project $ 840.00
PROJECT MANAGEMENT
Figure 3: Network Diagram
(Source: Created by Author)
4.6 Estimated costs
The budget that is needed for finishing the project of network infrastructure is around
$67,320. The overall budget that is needed is reflected in the table below:
Task Name Duration Resource Names Cost
Development of network
infrastructure 15.2 wks. $ 67,320.00
Initiation phase 1.6 wks. $ 2,480.00
Developing business case 2 days Project manager $ 720.00
Cost-benefit analysis 3 days Financial manager $ 840.00
Developing charter 2 days Project planner $ 640.00
Appointing team members 1 day Hr. manager $ 280.00
Milestone 1: Completion of
initiation phase 0 days $ 0.00
Planning phase 3.8 wks. $ 5,968.00
Developing project plan 3 days Project manager $ 1,080.00
Developing resource plan 4 days Hr. manager $ 1,120.00
Developing financial plan 3 days Financial manager, Project $ 840.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
sponsor
developing risk management
plan 2 days Tester $ 608.00
developing quality plan 3 days Network analyst $ 960.00
Developing procurement plan 2 days Project manager, Project
sponsor $ 720.00
Developing communication plan 2 days Project planner $ 640.00
Milestone 2: Planning phase
completion 0 days $ 0.00
Analysis phase 3 wks. $ 4,800.00
Analyzing IP addresses 3 days Network consultant $ 960.00
Sub-netting 2 days Network consultant $ 640.00
Identifying network device 2 days Network consultant $ 640.00
identifying network cables 3 days Network consultant $ 960.00
Identifying software 2 days Network consultant $ 640.00
Identifying server 3 days Network consultant $ 960.00
Completion 3: Completion of
analysis phase 0 days $ 0.00
Project designing phase 1.8 wks. $ 5,760.00
Design of logical network 5 days System engineer, Network
designer $ 3,200.00
Design of physical design 4 days System engineer, Network
designer $ 2,560.00
Milestone 4:Completion of
designing phase 0 days $ 0.00
Implementation phase 3.2 wks. $ 35,360.00
Hardware placement 2 days Network analyst, Network
engineer, System engineer $ 1,920.00
Cable placement 2 days
Network analyst, Network
engineer, System engineer,
Hardware[1],Software[1]
$ 21,920.00
Allocation of IP 3 days Network analyst, Network $ 2,880.00
PROJECT MANAGEMENT
sponsor
developing risk management
plan 2 days Tester $ 608.00
developing quality plan 3 days Network analyst $ 960.00
Developing procurement plan 2 days Project manager, Project
sponsor $ 720.00
Developing communication plan 2 days Project planner $ 640.00
Milestone 2: Planning phase
completion 0 days $ 0.00
Analysis phase 3 wks. $ 4,800.00
Analyzing IP addresses 3 days Network consultant $ 960.00
Sub-netting 2 days Network consultant $ 640.00
Identifying network device 2 days Network consultant $ 640.00
identifying network cables 3 days Network consultant $ 960.00
Identifying software 2 days Network consultant $ 640.00
Identifying server 3 days Network consultant $ 960.00
Completion 3: Completion of
analysis phase 0 days $ 0.00
Project designing phase 1.8 wks. $ 5,760.00
Design of logical network 5 days System engineer, Network
designer $ 3,200.00
Design of physical design 4 days System engineer, Network
designer $ 2,560.00
Milestone 4:Completion of
designing phase 0 days $ 0.00
Implementation phase 3.2 wks. $ 35,360.00
Hardware placement 2 days Network analyst, Network
engineer, System engineer $ 1,920.00
Cable placement 2 days
Network analyst, Network
engineer, System engineer,
Hardware[1],Software[1]
$ 21,920.00
Allocation of IP 3 days Network analyst, Network $ 2,880.00

11
PROJECT MANAGEMENT
engineer, System engineer
Connecting devices 4 days Network analyst, Network
engineer, System engineer $ 3,840.00
Deploying server 5 days Network analyst, Network
engineer, System engineer $ 4,800.00
Milestone 5: Completion of
implementation phase 0 days $ 0.00
Testing phase 0.8 wks. $ 10,912.00
Testing of network device 1 day Tester $ 304.00
Congestion testing 1 day Tester, Additional cost[1] $ 10,304.00
Performance testing 1 day Tester $ 304.00
Milestone 6: Completion of
testing phase 1 day $ 0.00
Closure phase 1.2 wks. $ 2,040.00
Post-project review 3 days Project manager $ 1,080.00
Sign off from stakeholders 2 days Project planner $ 640.00
Documentation 1 day Project planner $ 320.00
4.7 Quality plan
Objective Status
Does proper quality metrics are followed? No
Does the project utilize quality plan for the
project?
Yes
Does the project quality plan is accessible by
the stakeholders?
Yes
Does the quality plan is approved? Yes
4.8 Stakeholder analysis
Stakeholder Interest Power
Project manager High High
Project planner High High
Network engineer High High
Network consultant High Low
Network analyst High Low
PROJECT MANAGEMENT
engineer, System engineer
Connecting devices 4 days Network analyst, Network
engineer, System engineer $ 3,840.00
Deploying server 5 days Network analyst, Network
engineer, System engineer $ 4,800.00
Milestone 5: Completion of
implementation phase 0 days $ 0.00
Testing phase 0.8 wks. $ 10,912.00
Testing of network device 1 day Tester $ 304.00
Congestion testing 1 day Tester, Additional cost[1] $ 10,304.00
Performance testing 1 day Tester $ 304.00
Milestone 6: Completion of
testing phase 1 day $ 0.00
Closure phase 1.2 wks. $ 2,040.00
Post-project review 3 days Project manager $ 1,080.00
Sign off from stakeholders 2 days Project planner $ 640.00
Documentation 1 day Project planner $ 320.00
4.7 Quality plan
Objective Status
Does proper quality metrics are followed? No
Does the project utilize quality plan for the
project?
Yes
Does the project quality plan is accessible by
the stakeholders?
Yes
Does the quality plan is approved? Yes
4.8 Stakeholder analysis
Stakeholder Interest Power
Project manager High High
Project planner High High
Network engineer High High
Network consultant High Low
Network analyst High Low
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.