Project Plan: Edith Cowan University Number Plate Recognition System

Verified

Added on  2022/11/26

|14
|2133
|137
Project
AI Summary
This project plan outlines the development of a Number Plate Recognition and Facilities Management System, designed for Edith Cowan University's Mount Lawley campus. The project leverages existing CCTV infrastructure and OpenALPR software on Raspberry Pi devices. The plan details project phases including planning, system design, execution, and closure, with a comprehensive schedule, resource allocation, and Gantt chart. It includes specifications, deliverables, and a breakdown of tasks, dates, and effort. The document also covers resource allocation, project milestones, and a bibliography of relevant project management resources. This project aims to improve facilities management by automating vehicle identification and access control, providing valuable insights into campus traffic and parking utilization.
Document Page
Running head: PROJECT PLAN
Project Plan: Number Plate Recognition and Facilities Management System
Name of the Student:
Name of the University:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT PLAN
3. Project Plan
3.1 Project Schedule
WBS Task Name Duration Start Finish
0 Number Plate Recognition and
Facilities Management System 191 hrs Tue 5/7/19 Fri 6/7/19
1 Project planning phase 53 hrs Tue 5/7/19 Wed 5/15/19
1.1 Identification of the project
requirements 5 hrs Tue 5/7/19 Tue 5/7/19
1.2 Hiring of the project stakeholders 28 hrs Tue 5/7/19 Mon 5/13/19
1.3 Identify the specification of the
system 48 hrs Tue 5/7/19 Wed 5/15/19
1.3.1 Functional specifications 10 hrs Tue 5/7/19 Wed 5/8/19
1.3.2 Non-functional specifications 20 hrs Mon 5/13/19 Wed 5/15/19
1.4 Kick off the project meeting 3 hrs Wed 5/8/19 Thu 5/9/19
1.5 Completion of project planning
phase 0 hrs Thu 5/9/19 Thu 5/9/19
2 Project system design 121 hrs Thu 5/9/19 Thu 5/30/19
2.1 Acquisition of the image 12 hrs Thu 5/9/19 Fri 5/10/19
2.2 Extraction of number plate 15 hrs Fri 5/10/19 Tue 5/14/19
2.3 Character segmentation 60 hrs Wed 5/15/19 Mon 5/27/19
2.3.1 Scaling 18 hrs Wed 5/15/19 Fri 5/17/19
2.3.2 Horizontal projections 20 hrs Fri 5/17/19 Wed 5/22/19
2.3.3 Vertical projections 22 hrs Wed 5/22/19 Mon 5/27/19
2.4 Character recognition 94 hrs Tue 5/14/19 Thu 5/30/19
Document Page
2PROJECT PLAN
2.4.1 Template matching 12 hrs Mon 5/27/19 Tue 5/28/19
2.4.2 Component labeling 14 hrs Tue 5/28/19 Thu 5/30/19
2.4.3 Vertical projections 16 hrs Tue 5/14/19 Thu 5/16/19
2.5 Completion of system design phase 0 hrs Thu 5/16/19 Thu 5/16/19
3 Project execution phase 85 hrs Thu 5/16/19 Fri 5/31/19
3.1 Building of physical project
deliverables 6 hrs Thu 5/16/19 Fri 5/17/19
3.2 Managing of the project
procurement 9 hrs Fri 5/17/19 Mon 5/20/19
3.3 Acceptance of the client 3 hrs Mon 5/27/19 Mon 5/27/19
3.4 Communication plan 5 hrs Tue 5/28/19 Wed 5/29/19
3.5 Risk management plan 7 hrs Wed 5/29/19 Thu 5/30/19
3.6 Sign off the project client 9 hrs Thu 5/30/19 Fri 5/31/19
3.7 Completion of project execution
phase 0 hrs Fri 5/31/19 Fri 5/31/19
4 Project closure phase 45 hrs Fri 5/31/19 Fri 6/7/19
4.1 Release of the project stakeholders 18 hrs Fri 5/31/19 Tue 6/4/19
4.2 Review the project draft 12 hrs Tue 6/4/19 Wed 6/5/19
4.3 Final project sign off 15 hrs Thu 6/6/19 Fri 6/7/19
4.4 Completion of project closure phase 0 hrs Fri 6/7/19 Fri 6/7/19
Document Page
3PROJECT PLAN
3.2 Project Phases
Project
Phases
Original
Planned
Completion
Date
Revised
Planned
Completio
n Date
Actual
Completion
Date
Actual
Finish
Original
Planned
Effort
Revised
Planned
Effort Actual Effort
Project
planning
phase
Wed
5/15/19
Wed
5/15/19 Tue 5/7/19 NA 53 hrs 53 hrs 53 hrs
Project
system design Thu 5/30/19 Thu 5/30/19 Thu 5/9/19 NA 121 hrs 121 hrs 118.8 hrs
Project
execution
phase
Mon 6/3/19 Mon 6/3/19 Thu 5/16/19 NA 92 hrs 92 hrs 54 hrs
Project
closure phase
Mon
6/10/19
Mon
6/10/19 NA NA 45 hrs 45 hrs 0 hrs
3.3 Tasks: Dates and effort
Task Name
Original
Planned
Completion
Date
Revised
Planned
Completion
Date
Actual
Completion
Date
Original
Planned
Effort
Revised
Planned
Effort Actual Effort
Project
planning
phase
Wed 5/15/19 Wed
5/15/19 NA 53 hrs 53 hrs 53 hrs
Identification
of the project
requirements
Wed 5/8/19 Wed 5/8/19 Wed 5/8/19 9 hrs 9 hrs 9 hrs
Hiring of
the project
Mon 5/13/19 Mon Mon 5/13/19 28 hrs 28 hrs 28 hrs
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT PLAN
stakeholders 5/13/19
Identify
the
specification of
the system
Wed 5/15/19 Wed
5/15/19 NA 48 hrs 48 hrs 0 hrs
Functional
specifications
Wed 5/8/19 Wed 5/8/19 NA 10 hrs 10 hrs 0 hrs
Non-
functional
specifications
Wed 5/15/19 Wed
5/15/19 NA 20 hrs 20 hrs 0 hrs
Kick off the
project meeting Thu 5/9/19 Thu 5/9/19 Thu 5/9/19 8 hrs 8 hrs 8 hrs
Completion
of project
planning phase
Fri 5/10/19 Fri 5/10/19 Fri 5/10/19 8 hrs 8 hrs 8 hrs
Project
system design Thu 5/30/19 Thu 5/30/19 NA 121 hrs 121 hrs 118.8 hrs
Acquisition
of the image Fri 5/10/19 Fri 5/10/19 Fri 5/10/19 12 hrs 12 hrs 12 hrs
Extraction
of number plate Tue 5/14/19 Tue 5/14/19 Tue 5/14/19 15 hrs 15 hrs 15 hrs
Character
segmentation Mon 5/27/19 Mon
5/27/19 Mon 5/27/19 60 hrs 60 hrs 60 hrs
Scaling Fri 5/17/19 Fri 5/17/19 Fri 5/17/19 18 hrs 18 hrs 18 hrs
Horizontal
projections
Wed 5/22/19 Wed
5/22/19 Wed 5/22/19 20 hrs 20 hrs 20 hrs
Vertical
projections Mon 5/27/19 Mon
5/27/19 Mon 5/27/19 22 hrs 22 hrs 22 hrs
Character Thu 5/30/19 Thu 5/30/19 NA 94 hrs 94 hrs 25.8 hrs
Document Page
5PROJECT PLAN
recognition
Template
matching Tue 5/28/19 Tue 5/28/19 NA 12 hrs 12 hrs 10.8 hrs
Component
labeling
Thu 5/30/19 Thu 5/30/19 NA 14 hrs 14 hrs 7 hrs
Vertical
projections Thu 5/16/19 Thu 5/16/19 NA 16 hrs 16 hrs 8 hrs
Completion
of system
design phase
Fri 5/17/19 Fri 5/17/19 Fri 5/17/19 6 hrs 6 hrs 6 hrs
Project
execution
phase
Mon 6/3/19 Mon 6/3/19 NA 92 hrs 92 hrs 54 hrs
Building of
physical project
deliverables
Fri 5/17/19 Fri 5/17/19 Fri 5/17/19 7 hrs 7 hrs 7 hrs
Managing
of the project
procurement
Mon 5/20/19 Mon
5/20/19 NA 9 hrs 9 hrs 8 hrs
Acceptance
of the client Tue 5/28/19 Tue 5/28/19 Tue 5/28/19 8 hrs 8 hrs 8 hrs
Communicatio
n plan
Wed 5/29/19 Wed
5/29/19 Wed 5/29/19 8 hrs 8 hrs 8 hrs
Risk
management
plan
Thu 5/30/19 Thu 5/30/19 Thu 5/30/19 7 hrs 7 hrs 8 hrs
Sign off the
project client Fri 5/31/19 Fri 5/31/19 NA 9 hrs 9 hrs 8 hrs
Completion Mon 6/3/19 Mon 6/3/19 Mon 6/3/19 7 hrs 7 hrs 7 hrs
Document Page
6PROJECT PLAN
of project
execution phase
Project
closure phase Mon 6/10/19 Mon
6/10/19 NA 45 hrs 45 hrs 0 hrs
Release of
the project
stakeholders
Wed 6/5/19 Wed 6/5/19 NA 18 hrs 18 hrs 0 hrs
Review the
project draft Thu 6/6/19 Thu 6/6/19 NA 12 hrs 12 hrs 0 hrs
Final
project sign off Mon 6/10/19 Mon
6/10/19 NA 15 hrs 15 hrs 0 hrs
Completion
of project
closure phase
Mon 6/10/19 Mon
6/10/19 NA 0 hrs 0 hrs 0 hrs
3.4 Task Deliverables: Original, revised and actual dates
Task Name
Original
Planned
Completion
Date
Revised
Planned
Completion
Date
Actual
Completion
Date
Original
Planned
Effort
Revised
Planned
Effort Actual Effort
Project
planning
phase
Wed 5/15/19 Wed
5/15/19 NA 53 hrs 53 hrs 53 hrs
Identification
of the project
requirements
Wed 5/8/19 Wed 5/8/19 Wed 5/8/19 9 hrs 9 hrs 9 hrs
Hiring of
the project
stakeholders
Mon 5/13/19 Mon
5/13/19 Mon 5/13/19 28 hrs 28 hrs 28 hrs
Identify
the
Wed 5/15/19 Wed NA 48 hrs 48 hrs 0 hrs
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT PLAN
specification of
the system 5/15/19
Functional
specifications
Wed 5/8/19 Wed 5/8/19 NA 10 hrs 10 hrs 0 hrs
Non-
functional
specifications
Wed 5/15/19 Wed
5/15/19 NA 20 hrs 20 hrs 0 hrs
Kick off the
project meeting Thu 5/9/19 Thu 5/9/19 Thu 5/9/19 8 hrs 8 hrs 8 hrs
Completion
of project
planning phase
Fri 5/10/19 Fri 5/10/19 Fri 5/10/19 8 hrs 8 hrs 8 hrs
Project
system design Thu 5/30/19 Thu 5/30/19 NA 121 hrs 121 hrs 118.8 hrs
Acquisition
of the image Fri 5/10/19 Fri 5/10/19 Fri 5/10/19 12 hrs 12 hrs 12 hrs
Extraction
of number plate Tue 5/14/19 Tue 5/14/19 Tue 5/14/19 15 hrs 15 hrs 15 hrs
Character
segmentation Mon 5/27/19 Mon
5/27/19 Mon 5/27/19 60 hrs 60 hrs 60 hrs
Scaling Fri 5/17/19 Fri 5/17/19 Fri 5/17/19 18 hrs 18 hrs 18 hrs
Horizontal
projections
Wed 5/22/19 Wed
5/22/19 Wed 5/22/19 20 hrs 20 hrs 20 hrs
Vertical
projections Mon 5/27/19 Mon
5/27/19 Mon 5/27/19 22 hrs 22 hrs 22 hrs
Character
recognition Thu 5/30/19 Thu 5/30/19 NA 94 hrs 94 hrs 25.8 hrs
Document Page
8PROJECT PLAN
Template
matching Tue 5/28/19 Tue 5/28/19 NA 12 hrs 12 hrs 10.8 hrs
Component
labeling
Thu 5/30/19 Thu 5/30/19 NA 14 hrs 14 hrs 7 hrs
Vertical
projections Thu 5/16/19 Thu 5/16/19 NA 16 hrs 16 hrs 8 hrs
Completion
of system
design phase
Fri 5/17/19 Fri 5/17/19 Fri 5/17/19 6 hrs 6 hrs 6 hrs
Project
execution
phase
Mon 6/3/19 Mon 6/3/19 NA 92 hrs 92 hrs 54 hrs
Building of
physical project
deliverables
Fri 5/17/19 Fri 5/17/19 Fri 5/17/19 7 hrs 7 hrs 7 hrs
Managing
of the project
procurement
Mon 5/20/19 Mon
5/20/19 NA 9 hrs 9 hrs 8 hrs
Acceptance
of the client Tue 5/28/19 Tue 5/28/19 Tue 5/28/19 8 hrs 8 hrs 8 hrs
Communicatio
n plan
Wed 5/29/19 Wed
5/29/19 Wed 5/29/19 8 hrs 8 hrs 8 hrs
Risk
management
plan
Thu 5/30/19 Thu 5/30/19 Thu 5/30/19 7 hrs 7 hrs 8 hrs
Sign off the
project client Fri 5/31/19 Fri 5/31/19 NA 9 hrs 9 hrs 8 hrs
Completion
of project
Mon 6/3/19 Mon 6/3/19 Mon 6/3/19 7 hrs 7 hrs 7 hrs
Document Page
9PROJECT PLAN
execution phase
Project
closure phase Mon 6/10/19 Mon
6/10/19 NA 45 hrs 45 hrs 0 hrs
Release of
the project
stakeholders
Wed 6/5/19 Wed 6/5/19 NA 18 hrs 18 hrs 0 hrs
Review the
project draft Thu 6/6/19 Thu 6/6/19 NA 12 hrs 12 hrs 0 hrs
Final
project sign off Mon 6/10/19 Mon
6/10/19 NA 15 hrs 15 hrs 0 hrs
Completion
of project
closure phase
Mon 6/10/19 Mon
6/10/19 NA 0 hrs 0 hrs 0 hrs
3.5 Resource Allocation
WBS Task Name Duration Resource Names
0 Number Plate Recognition and
Facilities Management System 198 hrs
1 Project planning phase 53 hrs
1.1 Identification of the project
requirements 9 hrs Project Coordinator, Project Team
Member
1.2 Hiring of the project
stakeholders 28 hrs Project Team Member
1.3 Identify the specification of
the system 48 hrs
1.3.1 Functional specifications 10 hrs Developer, Supervisor
1.3.2 Non-functional
specifications 20 hrs Developer
1.4 Kick off the project meeting 8 hrs Project Manager
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT PLAN
1.5 Completion of project
planning phase 8 hrs Project Manager
2 Project system design 121 hrs
2.1 Acquisition of the image 12 hrs Project Coordinator, Project Manager
2.2 Extraction of number plate 15 hrs Stationary [1],Supervisor
2.3 Character segmentation 60 hrs
2.3.1 Scaling 18 hrs Developer, Project Manager
2.3.2 Horizontal projections 20 hrs
4 Channel 4MP Hikvision CCTV
Camera System Installed [1],Open
ALPR software [1]
2.3.3 Vertical projections 22 hrs
4 Channel 4MP Hikvision CCTV
Camera System Installed [1],Open
ALPR software [1]
2.4 Character recognition 94 hrs
2.4.1 Template matching 12 hrs Developer, Open ALPR software [1]
2.4.2 Component labeling 14 hrs Open ALPR software [1],Project
Coordinator
2.4.3 Vertical projections 16 hrs
4 Channel 4MP Hikvision CCTV
Camera System Installed [1],Open
ALPR software [1]
2.5 Completion of system design
phase 6 hrs Developer
3 Project execution phase 92 hrs
3.1 Building of physical project
deliverables 7 hrs Supervisor, Ubuntu desktop [1]
3.2 Managing of the project 9 hrs Stationary [1]
Document Page
11PROJECT PLAN
procurement
3.3 Acceptance of the client 8 hrs Stationary [1],Supervisor
3.4 Communication plan 8 hrs Supervisor
3.5 Risk management plan 7 hrs Project Manager[243%],Project Team
Member[243%]
3.6 Sign off the project client 9 hrs Project Manager
3.7 Completion of project
execution phase 7 hrs Project Manager
4 Project closure phase 45 hrs
4.1 Release of the project
stakeholders 18 hrs Project Manager
4.2 Review the project draft 12 hrs Project Manager
4.3 Final project sign off 15 hrs Project Manager
4.4 Completion of project closure
phase 0 hrs Project Manager
3.6 Project Milestones and Gantt chart
Project Milestones
WBS Task Name Expected Completion
Date
1.5 Completion of project planning phase Fri 5/10/19
2.5 Completion of system design phase Fri 5/17/19
3.7 Completion of project execution phase Mon 6/3/19
4.4 Completion of project closure phase Mon 6/10/19