This reflective case study report examines the 2012 Olympics Infrastructure project, focusing on its background, budget, stakeholders, aims, and objectives. It critically reviews issues such as strategic alignment, project initiation, lifecycles, and project context, applying theoretical concepts to analyze the successes and challenges encountered. The report emphasizes the importance of strategic alignment for saving time and resources, the role of planning theory in project initiation, and the significance of lifecycles for effective project management. Furthermore, it highlights the need for a proactive and systematic approach to communication and stakeholder engagement to ensure project success. This document is available on Desklib, a platform offering a wide range of study tools and solved assignments for students.
Document Page
Reflective Case Study Report
1
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Contents
1. Introduction..................................................................................................................................3
Background..................................................................................................................................3
Budget and duration.....................................................................................................................3
Relevant stakeholder....................................................................................................................4
Aim..............................................................................................................................................5
Objective......................................................................................................................................5
Purpose........................................................................................................................................5
2. Critically review and reflect on the issues...................................................................................6
Issue-1 Strategic Alignment........................................................................................................6
Issue-2 Project initiation..............................................................................................................7
Issue-3 Lifecycles........................................................................................................................9
Issue-4 Project context...............................................................................................................10
REFERENCES..............................................................................................................................11
2
Document Page
1. Introduction
Background
London’s successful bid for 2012 Olympic Games was created as need for major
construction programme and re-generation to provide excellent venue & infrastructure needed to
different phases of games. Each and every programme of construction was so much expensive,
majorly focus in context of technically & politically challenges. Afterwards, it was fixed the
deadline of opening ceremony of games. Usually, turning the particular vision of Olympic
infrastructure project was attracted people because of their roads, bridges, stadia.
In past decade, it has been concerned about the Olympic Infrastructure which help to
inspire or motivate staff members in the organization. Taking into account in current covid-19
situation, It is evident that rises the remote culture, especially recruitment process. It has become
need of hour. Different organisations are constantly being confronted with major problems at the
time of crisis. Recently, it will focused on the digital conceptual termed to influence 2012
Olympic infrastructure project.
Budget and duration
On the basis of estimation, it was setup the budget of project around 8.1 billion. Before
starting the project, project manager will create suitable documentation that help to record, store
information and identify the scope of project. Afterwards, it will be submitting detailed budget
assessment and take an approval from board of Olympic. The resulting programme baseline
report- 100 page of description and aligned with scope, budget, risk and programmes (Pena,
Mataruna-dos-Santos and PEREIRA, 2019). This can help to the manager where it can easily
identify the items of Olympic infrastructure project, deliver and allocation of risks.
The development of document is consider as crucial step in bottoming out areas of scope
and gave the better footing for delivery of event or programme.
3
Document Page
Challenges
In project of Olympic Infrastructure, It is important to understand the outset that there
would be consider as huge level of public interest in London. Project manager is basically
focused on the recognised the need or requirement for project. Usually, the project can be
achieved the success when it will be delivered in partnership, with a major support of large
coalition of different enterprises. According to theory of infrastructure led development, it is
directly affecting the production of both health services and commodities. As a result, it will be
developed a network and measure degree of efficiency of Olympic infrastructure. This is
completely related to capital and stock of public.
As a result, Olympic Infrastructure project is adopted as high proactive and systematic
approach in context of communication. Therefore, project manager can easily establish a strong
engagement with stakeholders from community or political engagement (Vaccarini and Gulc,
2021). For beginning, it is an essential aspect for project success to implement strategy to
embrace transparency or ensure complete alignment between both external as well as internal
objectives.
The Olympic infrastructure project was designed to maintain and control by project
manager to improve progress of project with intense focus at big moments. Sometimes, it allows
for people as possible to find the positive aspect in the project management and implementation.
Relevant stakeholder
In particular project, it should be included the relevant stakeholders such as staff
members, project manager, executive, investors, supplier etc. These are different stakeholders,
which plays important role in the project development. Stakeholders in the project is to ensure
strategic direction which was clearly represents performance management. This can help to
provide active value for money. On regular basis, project manager will be conducting a meeting
session with stakeholder and give an information of assigned tasks. This is not only acquire
information or data but it also established a strong engaged a project development.
4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
In 2012, Olympic Infrastructure the sponsrs are Acer, Coca-cola, GE, Omega and
Panasonic. These are the biggest companies which has contributed in the development of
Olympic infrastructure.
Aim
ï‚· To design and develop the 2012 Olympics Infrastructure.
Objective
Main objective of 2012 Olympics infrastructure design and development project. The
ODA had five years to staff members, procure, deliver around 5 billion of major construction
works, it is mainly built on the largely derelict or polluted site in London. For purpose of this
project, it is needed to satisfy all stakeholder, consumers which including local residents, public,
medial and government agencies (Silva, Pereira and Magano, 2021). These are focused on the
Olympic infrastructure project, providing the great value for money. Therefore, it also track or
monitor the infrastructure design pattern, required to be understand the different stages of games.
The Olympic Infrastructure project programme of works included an essential
deconstruction and remediation across 400-hecture site, construction take places around 20km of
road, tunnels etc. on the basis of idea, it will be utilised a new infrastructure of Olympic. It also
identified the construction of 14 permanent as well as temporary sporting venue. This kind of
approach will attract more people and inspire with interactive infrastructure of Olympic.
Purpose
The purpose of study is to focus on the advance modern technology, enterprises have
revolutionized their enterprise operations. Under specific revolution, it will be adopted the
modern techniques and method to recruit talented skill people. On the basis of research study, it
intends to identify how different design patterns will support in the Olympic infrastructure
project development (Lalmi, Fernandes and Souad, 2021). Main purpose of 2012 Olympic
infrastructure project is to create an interactive physical space, providing all essential facilities
and services of their guests. Within Olympic Games, there are large number of population
gathered in specific location or areas. That’s why, it is very important to maintain and control all
5
Document Page
facilities. At that time, An interactive infrastructure design and pattern influence different
individual people to give best options.
Success-
The project success is majorly depending on the current states, objective. Project
management documentation was supported to the gathered all essential information or data. The
2012 Olympic infrastructure project has successfully achieved its objectives, both for delivery
the excellent physical infrastructure. It also significant achievements and priority themes, such as
sustainability maintenance. The project is closely related to infrastructure and design pattern
which means that needs a proper planning. Through Olympic Infrastructure project, it is
delivering the successful result or outcome. The project manager will always approach team
members to give their best and improve quality of task execution. Moreover, it is also
concentrated on the establishment of suitable delivery strategy, maintain a high level of
transparency among different stakeholders. This is helping to represent scope and focused on the
project delivery.
2. Critically review and reflect on the issues
Issue-1 Strategic Alignment
It is based on the approach which links an organisations’ vision, mission and strategic
goals or objective. It means that different strategies are executing and enabling a high
performance. A lack of strategic alignment in project which will create a problem in regards of
maintenance. It will be recognised the risk or threat at the time of project objectives, it is not just
for identifying project status (Rustamova, 2021). A strategic alignment is lining up project but it
is not encompasses with both technical and functional activities. But it may arise problem in
project among human resources regarding people motivation, capability and so on.
According to the Strategic based entrenchment theory, this type of approach will
represent the validity of alignment, which has been questioned by participants. On the basis of
evidence, it has been suggested that opposite which may actually hold true aspect. In context of
6
Document Page
project management. Entrenchment theory can support to gain more and more ownership in the
project development.
Project manager will focus on the strategic alignment issue because it is needed to save
time and other resources. It is always keeping the team informed and motivated. A lack of
strategic alignment is one of the primary reason why project fails to achieve their objective. But
in some situation, the strategic alignment cannot be overstated. On the other hand, project
manager will concern about the strategic alignment factors such as capabilities, resources,
processes and systems. These are contribute to align with strategy and able to execute tasks
properly. Within project, it should consider their existing and needed capabilities, resources
during strategic alignment development, implementation.
As per analysis, it has been considered the different factors such as resources, processes,
system and capabilities. These are majorly contribute towards project alignment and provide
brief idea about the entire processes. This is not only providing the better opportunity to gain
more advantage or benefits in project development. The implication of different factors on this
project is to implement long term plan and resources needed to achieve its desirable goal or
objective. It has also been a consistent analysis and uses of strategic technology, change of
innovation over last decades (Holloway, 2021). Project manager will concern about all essential
factors and consider its importance of increasing the role of strategy in managing the project,
improve operational performance. At certain point, it has been examined the inability in project
due to lack of alignment between tasks execution. So as, it is important to align with different
factors and fulfil all essential requirement for project.
Issue-2 Project initiation
The initiation phase is the beginning of project. It is mainly focused on the idea,
assumption for this project to explore, elaborate in proper manner. A poor project initiation issue
will be creating a problem in the project. There is no single list of project or single place. At the
time of initiation, it is very hard for project manager or team members in regards of resources
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
identification. If in case, it cannot be approved the project without any formal process, which
leads to arise issue or problem with resourcing management.
In context of project initiation, planning theory plays important role in term of concepts,
behavioural relationships and assumptions that define body of knowledge. Planning theory can
easily transformed the entire project that is not the best available. It becomes rather clear when
remind or competing theories. Usually, a project manager will focus on the representing the
framework which has provided the entire processing of project according to the Just-in-time. The
primary reason for considerations a planning theory at the time of project initiation. It means that
transformation of view or flow view which include time as attribute. It plays important role and
affected by uncertainty in project initiation. On the other hand, it is always focused on the
direction towards linkages, uncertainty (Rustamova, 2021). It is acknowledged in the
transformation view. In regards of project management, project initiation can view flow of
process and eliminate any kind of unwanted task execution. Such principles as lead reduction of
time, variability which are promoted effectively and efficiently.
During project initiation, Critical factors to ensure that project is successful done. It
including document of business decision, project sponsorship, and on-goi-ng governance. These
are different factors which contribute to project management. Business decision documentation
can be used by project manager to select or choose right approach. This will help to collect,
record all essential information. A project manager issued a proper documentation by project
initiator or sponsor that formally authorizes the existence of a project. Project manager with
authority to apply suitable resources in different activities. According to the PMBOK, it will be
represented the project needs, high level description, product requirements. These are focused on
the particular client and other stakeholder project needs for purpose of executions. On the other
hand, Project governance is also consider the factor in project initiation which means that
identify the project case and prior to establishing project board This type of factor will support in
project management to analyse and authorise, initiate the project.
8
Document Page
Issue-3 Lifecycles
It is a process or method that help for project manager to divide different phases such as
planning, execution and closure. These are different processes which make up the direction and
take places project from starting point. The issue of project lifecycle which poorly define project
in current scenario. During project, it has been developed the excessive re-work, poor
communication and unclear objectives. Team members are finding it tools complex to estimate
price or cost. It is unable to define how much time is needed to completed specific tasks in
proper manner.
According to the project management life cycle, project manager will use theory in order
to broken down into different phases. But it make up the right path or direction which takes
project from starting to the end. The involvement of theory in lifecycle which means that
comprising a set of distinct high level phases required to easily transform an innovative idea into
reality (Rustamova, 2021). That’s why, project manager will consider appropriate theory in
project management to acquire and gain more knowledge.
On the other hand, lifecycles issue may be identified in the project which means that
contribute factors such as testability, inspect-ability, maintainability and reliability. In this way,
Project manager can utilise this factors to improve the overall performance of project at the time
of lifecycle. Technical changes take place in the project at the time of execution. So as, it has
become important to increase the high rate of project effectively and efficiently.
The implication of contributed factors on the project which means ensure a proper
planning and execution of all phases. It allows project manager to check the processing of project
in step by step manner. Through lifecycle, it will be controlled and linked the current progress of
project at every phase, identify the completion of each stages. In most of cases, it would require
to recommend the improve lifecycle process in project. Therefore, it provides the progressive
evolution, review and support governance. Sometimes, it enabled to monitor or track progress by
project manager.
9
Document Page
Issue-4 Project context
Project context is consider the circumstances in which occurs different events or problem.
Usually, it can be represented description of both external as well as internal environment where
project is going to be undertaken. Project context issue is one of the critical components of
enterprise because it would be increased the conflicts among team members. Moreover, it
explores the multi-level influence on the project by contextual factor affect the entire
performance of project.
In project context, theory of constraint is one of the important methodology for
identifying the most important limiting factor. This approach will help to achieve desirable goal
and then systematically improving that constraint until it is no longer limiting factor. Project
manager will use theory of constraints in project context and help to eliminate or remove
challenging issue. On the basis of analysis, Project manager will use different factors such as
repeat the process, exploit the constraint, elevate the performance and subordinate or synchronize
(Silva, Pereira and Magano, 2021). Different factors contribute to the project management and
focus on identifying individual constraints, inhibit the project from achieving its goals. Within
project management, team will use the theory of constraint and its factors which is helping to
project manager to increase throughput of task executions, removing any kind of additional
investment.
The implication for project manager and team members are that implementation as key
phase in identifying the success of project. The indicator of project success are time, cost,
customer satisfaction and technical performance. Project manager will always focused on the
positive relationship to achieve the success criteria, completion and implementation phases in
project lifecycle.
On the basis of factors, it recommends the project manager intended to ensure that there
is accountability for and ownership of accomplishing objectives. It provides the right direction to
strengthen the manager to improve the overall performance of project. Theory of constraints are
10
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
usually involves describing situation, evaluating the possible alternative and proposing a solution
to a problem.
REFERENCES
Book and Journals
Holloway, S., 2021. DATA CENTER PROJECT MANAGEMENT. Data Center Handbook:
Plan, Design, Build, and Operations of a Smart Data Center. pp.611-616.
Lalmi, A., Fernandes, G. and Souad, S.B., 2021. A conceptual hybrid project management model
for construction projects. Procedia Computer Science. 181. pp.921-930.
Pena, B.G., Mataruna-dos-Santos, L.J. and PEREIRA, L., 2019. Proactive Management of
Olympic Legacies: 1972 Munich Games update form the Perspective of the Triple Helix
Model. Journal of Physical Education and Sport. 19(3). pp.1636-1642.
Rustamova, S., 2021. Application of PMI PMBOK standard in the development of the
Construction cost management projects plan. International journal of trends in business
administration, 11(1).
Silva, C.S., Pereira, C. and Magano, J., 2021. The value of project management to
competitiveness: key factors from a holistic and practical perspective. International
Journal of Managing Projects in Business.
Vaccarini, A.I. and Gulc, A., 2021 Megaproject management–case studies of Torino, Vancouver
and Milano Winter Olympic Games.
11
chevron_up_icon
1 out of 11
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]