BSBMGT608 Project Plan: BizOps Online Shopping App Implementation

Verified

Added on  2023/04/21

|15
|2456
|490
Project
AI Summary
This project plan details the implementation of a mobile app for BizOps, aimed at enhancing business efficiency and increasing revenue. It includes sections on project identification, objectives, and key deliverables, such as a user-friendly mobile app designed to improve retail operations. The plan outlines assigned responsibilities for key activities, a schedule for app development and testing, and a resource and cost plan totaling $28,552. A risk assessment identifies potential challenges like technical skill gaps and security vulnerabilities, along with corresponding control measures. The plan also covers quality measurement, focusing on operational abilities and user experience, and communication strategies for reporting project progress. Key personnel involved include Sean Bamford and Nancy Tooket. The project aims to improve intranet sustainability and manage risks effectively, adhering to legal and regulatory requirements for green solutions.
Document Page
Running head: PROJECT MANAGEMENT
Project Management: BizOps online shopping app implementation plan
Name of the student:
Name of the university:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
2PROJECT MANAGEMENT
Document Page
3PROJECT MANAGEMENT
Table of Contents
1. Identification and description......................................................................................................3
1.1 The purpose of the innovation...............................................................................................3
1.3 The background context for the project.................................................................................3
1.4 Project objectives...................................................................................................................3
1.5 Key deliverables....................................................................................................................4
2. Plan and assign responsibilities for key activities.......................................................................4
3. Prepare a schedule for the development and trial of the app.......................................................5
4. Prepare a resource and cost plan..................................................................................................7
5. Identify and assess risk to the project..........................................................................................8
5.1 Risk categorization table........................................................................................................8
5.2 Risk control/treatment...........................................................................................................9
5.3 Implementation plan............................................................................................................10
6. Determine quality measurement plan for the project................................................................10
7. Develop a communications and reporting plan.........................................................................11
8. Project progress report presentation..........................................................................................11
References......................................................................................................................................12
Document Page
4PROJECT MANAGEMENT
1. Identification and description
Project title: Implementation of Mobile app to increase business efficiency
1.1 The purpose of the innovation
BizOps is focuses on providing very high quality, innovative service outcomes
considering their frequently changing requirements also. The purpose of BizOps is to offer
innovative green product solution adopting suitable work practices as well.
1.3 The background context for the project
Using combines business experiences of Simmon, Devon and Ntushka BizOps has
become a very popular retail company in these days. However, due to their product affordability
and service efficacy the numbers of consumers of the company is growing rapidly. Staring from
a single store front currently the numbers of outlets operating the owners are near about more
than 150. In order to obtain structured and measurable revenue from the competitive market and
to gain competitive advantages in the market the marketing manager of the company has planned
to implement a mobile application for their consumers.
1.4 Project objectives
To enhance the revenue of the company by around 15% within the financial year
ending
To maintain the rate of annual profit by 15% for each and every offered services
and products
To reinvest a profit rate by75% by the end of the financial year
To maintain the marketing position by launching high quality and user friendly
products
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
5PROJECT MANAGEMENT
To offer timey training to the employees by using needful resources (human,
financial etc)
1.5 Key deliverables
BizOps is focused to deliver a user friendly mobile app to their consumers to increase the
business efficacy and gain a profit margin up to 75% by the end of the financial year. The issues
associated to physical stores and organizational operations will be completely resolved with the
design and implementation of the mobile app. The aim of BizOps is to deliver a mobile app
which will provide a new direction to the retail operations.
2. Plan and assign responsibilities for key activities
Task Name Duration Resource Names
Project schedule for BizOps mobile app
development 111 days
Project initiation phase 16 days
Developing scope statement for
BizOps 5 days Retail operation managing
director
Assigning project team 5 days HR manager
Resource identification 3 days Resource manager
Gathering requirements 4 days Resource manager
Requirement analysis 4 days Resource manager
Milestone 1: Submitting project
outline draft 0 days Chief Executive officer
Project planning phase 16 days
Risk management plan 5 days managing director: Business
operation
Quality management plan 2 days Retail operation managing
director
Stakeholder management plan 3 days HR manager
Identification of functional and non-
functional requirements 4 days Managing director: Finance
operation
Feasibility study and budget plan 2 days Managing director: Finance
operation
Milestone 2: Completion of project 0 days Chief Executive officer
Document Page
6PROJECT MANAGEMENT
planning phase
Design and development of the Mobile
app 50 days
Operating tool and platform selection 10 days system designer
Designing prototype 10 days system developer
UML diagram presentation 10 days system designer, Application
programmer
Simulation 10 days Application programmer
Server/database connectivity 10 days Retail operation managing
director
Milestone 4: Completion of project
design and development phase 0 days Chief Executive officer
Project testing phase 14 days
Unit testing 5 days tester
Integrated testing 3 days tester
Acceptance testing 6 days tester
Milestone 5: Final Prototype testing 0 days Managing director: Finance
operation
Closure phase 15 days
Change management (if required) 6 days managing director: Business
operation
Post maintenance plan 2 days Chief Executive officer
Promoting the mobile app 2 days managing director: Business
operation
Future business success strategies
development 3 days Retail operation managing
director
Stakeholders signoff 2 days HR manager
Milestone 6: Completion of project
closure phase 0 days Chief Executive officer
3. Prepare a schedule for the development and trial of the app
Task Name Duratio
n Start Finish
Project schedule for BizOps mobile app development 111 days Thu 1/3/19 Thu 6/6/19
Project initiation phase 16 days Thu 1/3/19 Thu
1/24/19
Developing scope statement for BizOps 5 days Thu 1/3/19 Wed 1/9/19
Assigning project team 5 days Thu 1/10/19 Wed
1/16/19
Resource identification 3 days Thu 1/10/19 Mon
1/14/19
Document Page
7PROJECT MANAGEMENT
Gathering requirements 4 days Mon
1/21/19
Thu
1/24/19
Requirement analysis 4 days Tue 1/15/19 Fri 1/18/19
Milestone 1: Submitting project outline draft 0 days Thu 1/24/19 Thu
1/24/19
Project planning phase 16 days Fri 1/25/19 Fri 2/15/19
Risk management plan 5 days Fri 1/25/19 Thu
1/31/19
Quality management plan 2 days Fri 2/1/19 Mon 2/4/19
Stakeholder management plan 3 days Tue 2/5/19 Thu 2/7/19
Identification of functional and non-functional
requirements 4 days Fri 2/8/19 Wed
2/13/19
Feasibility study and budget plan 2 days Thu 2/14/19 Fri 2/15/19
Milestone 2: Completion of project planning phase 0 days Fri 2/15/19 Fri 2/15/19
Design and development of the Mobile app 50 days Mon
2/18/19 Fri 4/26/19
Operating tool and platform selection 10 days Mon
2/18/19 Fri 3/1/19
Designing prototype 10 days Mon 3/4/19 Fri 3/15/19
UML diagram presentation 10 days Mon
3/18/19 Fri 3/29/19
Simulation 10 days Mon 4/1/19 Fri 4/12/19
Server/database connectivity 10 days Mon
4/15/19 Fri 4/26/19
Milestone 4: Completion of project design and
development phase 0 days Fri 4/26/19 Fri 4/26/19
Project testing phase 14 days Mon
4/29/19
Thu
5/16/19
Unit testing 5 days Mon
4/29/19 Fri 5/3/19
Integrated testing 3 days Mon 5/6/19 Wed 5/8/19
Acceptance testing 6 days Thu 5/9/19 Thu
5/16/19
Milestone 5: Final Prototype testing 0 days Thu 5/16/19 Thu
5/16/19
Closure phase 15 days Fri 5/17/19 Thu 6/6/19
Change management (if required) 6 days Fri 5/17/19 Fri 5/24/19
Post maintenance plan 2 days Mon
5/27/19 Tue 5/28/19
Promoting the mobile app 2 days Wed
5/29/19
Thu
5/30/19
Future business success strategies development 3 days Fri 5/31/19 Tue 6/4/19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
8PROJECT MANAGEMENT
Stakeholders signoff 2 days Wed 6/5/19 Thu 6/6/19
Milestone 6: Completion of project closure phase 0 days Thu 6/6/19 Thu 6/6/19
4. Prepare a resource and cost plan
The net cost assigned for the project is $28,552 and the lists of resources and respective
cost assigned for the project are elaborated in the below section:
Deliverable/ milestones/phases Resource Cost
Project schedule for BizOps mobile
app development $28,552.00
Project initiation phase $4,592.00
Developing scope statement for
BizOps
Retail operation managing
director $1,360.00
Assigning project team HR manager $1,120.00
Resource identification Resource manager $576.00
Gathering requirements Resource manager $768.00
Requirement analysis Resource manager $768.00
Milestone 1: Submitting project
outline draft Chief Executive officer $0.00
Project planning phase $4,056.00
Risk management plan managing director: Business
operation $1,400.00
Quality management plan Retail operation managing
director $544.00
Stakeholder management plan HR manager $672.00
Identification of functional and
non-functional requirements
Managing director: Finance
operation $960.00
Feasibility study and budget plan Managing director: Finance
operation $480.00
Milestone 2: Completion of project
planning phase Chief Executive officer $0.00
Design and development of the
Mobile app $12,800.00
Operating tool and platform
selection system designer $2,240.00
Designing prototype system developer $2,080.00
UML diagram presentation system designer, Application
programmer $4,000.00
Simulation Application programmer $1,760.00
Document Page
9PROJECT MANAGEMENT
Server/database connectivity Retail operation managing
director $2,720.00
Milestone 4: Completion of project
design and development phase Chief Executive officer $0.00
Project testing phase $2,800.00
Unit testing tester $1,000.00
Integrated testing tester $600.00
Acceptance testing tester $1,200.00
Milestone 5: Final Prototype testing Managing director: Finance
operation $0.00
Closure phase $4,304.00
Change management (if required) managing director: Business
operation $1,680.00
Post maintenance plan Chief Executive officer $800.00
Promoting the mobile app managing director: Business
operation $560.00
Future business success strategies
development
Retail operation managing
director $816.00
Stakeholders signoff HR manager $448.00
Milestone 6: Completion of project
closure phase Chief Executive officer $0.00
5. Identify and assess risk to the project
5.1 Risk categorization table
Priority Risk Likelihood Impact Level of
risk
R1 Lack of technical skills among the project
team members
Likely Major High
R2 Lack of security measures in the Mobile
app
Rare Catastrophic Extreme
R3 Lack of operational abilities in the newly
developed system
Unlikely Moderate Medium
Document Page
10PROJECT MANAGEMENT
R4 Overrunning cost Likely Minor Low
5.2 Risk control/treatment
Risks:
1. Lack of technical skills among the project team members
2. Lack of security measures in the Mobile app
3. Lack of operational abilities in the newly developed system
4. Overrunning cost
Control measure Strength Weakness
Control
measures/treatment
Arrangement of on
job technical training
Skill of the team
members will increase
Additional cost is
needed
Incorporating
encryption
mechanism
Security of the system
will become stronger
Extra cost is needed
Feasibility study Proper budget plan
will be implemented
If accurate budget is n
not planned then it
will exceed the budget
ratio
Impact of risk The identified risks can negatively impact the regular success and operational
abilities of the mobile app that is going to be implemented for
Personnel involved Sean Bamford
Nancy Tooket
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
11PROJECT MANAGEMENT
Mike Booth
Expected outcomes of
the risk treatment
It will be able to improve the current intranet sustainability
It helps to hold the recent workers compensation as well as
product liability and business assets
5.3 Implementation plan
In order to implement the risk management plan different legal acts, law, policy and
regulations must be considered. The supply chain, logistics and elements for green solutions are
all considered.
6. Determine quality measurement plan for the project
In order to check that whether quality of the mobile application is running according to
the company need and consumers demand or not the measurement plan that are developed
include the below:
Checking operational abilities, user friendliness and functionalities of the newly
developed mobile app
Providing an accurate user experience
Checking performance of the mobile app
Document Page
12PROJECT MANAGEMENT
7. Develop a communications and reporting plan
People involved Purpose When Frequency
Project manager and
project team members
To prepare the project
scope statement
At the project
initiation phase
Monthly
Project sponsor and
finance manager
To develop budget of
the project
At the project
planning phase
Monthly
Project manager,
developer and
designer
Project prototype
design details
Project planning and
implementation phase
Weekly
8. Project progress report presentation
Name of the project Implementation of mobile app for BizOps
Project manager Please Fill
Report provided to The project sponsor
Current progress achievement Recently the project is running across the
design and development phase
Issues experienced Technical flaw is the only flaw that has been
experienced by this phase
Recommended records and reports Project status report
Ongoing management plan Project promotional activities
Innovation of technical product solutions
Undertaking continuous project