Project Plan: HS Buy - Online Shopping Platform Development and Launch
VerifiedAdded on 2022/11/25
|14
|3131
|150
Project
AI Summary
This project management plan outlines the development and launch of an online shopping platform, 'HS Buy'. The plan details the project's purpose, goals, and objectives, which include integrating various trade and commerce activities into a single platform to facilitate online ordering and delivery. The plan covers project scope, including deliverables such as initiating, planning, controlling, and closing phases, along with a detailed budget breakdown. It also addresses risk assessment, identifying potential issues like power outages and slow internet connections, and proposes mitigation strategies. The project timeline is presented through milestones across different phases, from information gathering to testing and maintenance. The plan defines assumptions, constraints, and the project management approach, including roles and responsibilities of the project team. The project aims to improve trade and commerce, save time for both customers and retailers, and successfully develop and implement an online shopping platform, providing a comprehensive overview of the project's lifecycle.

Project Management
1
1
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Contents
Purpose of project plan....................................................................................................................3
Project goal and objective................................................................................................................3
Scope................................................................................................................................................4
Assumptions....................................................................................................................................9
Constraints.......................................................................................................................................9
Project management approach.......................................................................................................10
Conclusion.....................................................................................................................................12
Recommendation...........................................................................................................................12
2
Purpose of project plan....................................................................................................................3
Project goal and objective................................................................................................................3
Scope................................................................................................................................................4
Assumptions....................................................................................................................................9
Constraints.......................................................................................................................................9
Project management approach.......................................................................................................10
Conclusion.....................................................................................................................................12
Recommendation...........................................................................................................................12
2

Title- Project management Plan for “HS Buy”: A proposed online shopping platform and launch
by retailer.
Purpose of project plan
The purpose of project plan overview provide high level description in related to different
activities performance by online shopping platform. Nowadays, many consumers are attracting
towards online platform during covid-19 and consider as successive story of business in world-
wide. In this project management plan, investigator will focus on the developed a proposed
website which aim to integrate with multiple trade and commerce activities through single
platform. it enable consumers place their order online and delivered to them. The name of online
shopping platform is known as HG buy. The proposed website shall be easy to navigate and
integrated with different payment system, delivery options. That’s why, it is always attracting
potential customers who can access online platform and purchase product in proper manner.
Project goal and objective
The project involves developing an online platform and its primary aim to integrate with
different trade and other kind of commerce activities (Antwi, 2020). This kind of project is
always provide great support in term of business growth and development.
Goal- the Goal of project is to provide the facilities and services for potential consumers to place
order online and delivered them via delivery address.
Objective- The objectives of this project shall be divided into different types: business objectives
and technical objectives.
To improve the trade and commerce in markets through innovative ideas. Traditionally,
retailers have already used the old method to sell their product in marketplace. But new
idea will always support for developing an opportunity and increase the revenue of
retailers in marketplace.
To save customers, enterprise time. it is important thing in the business development
because there are different companies pay their workers on the basis of working hours.
3
by retailer.
Purpose of project plan
The purpose of project plan overview provide high level description in related to different
activities performance by online shopping platform. Nowadays, many consumers are attracting
towards online platform during covid-19 and consider as successive story of business in world-
wide. In this project management plan, investigator will focus on the developed a proposed
website which aim to integrate with multiple trade and commerce activities through single
platform. it enable consumers place their order online and delivered to them. The name of online
shopping platform is known as HG buy. The proposed website shall be easy to navigate and
integrated with different payment system, delivery options. That’s why, it is always attracting
potential customers who can access online platform and purchase product in proper manner.
Project goal and objective
The project involves developing an online platform and its primary aim to integrate with
different trade and other kind of commerce activities (Antwi, 2020). This kind of project is
always provide great support in term of business growth and development.
Goal- the Goal of project is to provide the facilities and services for potential consumers to place
order online and delivered them via delivery address.
Objective- The objectives of this project shall be divided into different types: business objectives
and technical objectives.
To improve the trade and commerce in markets through innovative ideas. Traditionally,
retailers have already used the old method to sell their product in marketplace. But new
idea will always support for developing an opportunity and increase the revenue of
retailers in marketplace.
To save customers, enterprise time. it is important thing in the business development
because there are different companies pay their workers on the basis of working hours.
3
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

The proposed project provide the better offers for retailer to increase demand through
online shopping platform.
The technical objective is to successful develop and implement online shopping platform
such as website. In order to integrate with different seller in particular areas or place. This
could help to reduce price or cost in business operational activities. Moreover, it is also
increasing the speed of retailer activities.
Procurement plan-
The nature of project would requires essential resources which needed to be bought online and it
is tangible. Usually, a project manager is mainly focused on the select or chose a particular
domain name for website, hosting, integrated payment processors. In this project, project team
will focus on the intangible resources and relevant as creation of online (Aragonés-Beltrán,
García-Melón and Montesino-Valera, 2017). But the significant role of IT team initiate a request
for manager side and needed to consider technical, quality of resources. Having a finish
development procedure with different processes, request to be approved by project manager.
In recently, it will be increasing demand of successful online platform, project team will
require to follow all resource and its purpose. Afterwards, it is directly integrated with
development procedure to generate accurate result or outcome.
Scope
Project Deliverables – In this project, the deliverables that stakeholder and client expect at the
end of project in website. This will help to achieve desirable goal or objective. The involvement
of project management team has proposed the deliverables and also handle the project life cycle.
Initiating process- in this phase, project manager will focus on the main element which
include in project development (Kerzner, 2017 ). Generally, it should consider necessary
approval, essential resources, equipment’s, authorization of project, commit project
phase. These are essential aspect in which handle by project manager at the time of
initiating process. Therefore, the deliverables of project can be achieved through project
charter, scope, requirements, assumptions as well as constraints.
4
online shopping platform.
The technical objective is to successful develop and implement online shopping platform
such as website. In order to integrate with different seller in particular areas or place. This
could help to reduce price or cost in business operational activities. Moreover, it is also
increasing the speed of retailer activities.
Procurement plan-
The nature of project would requires essential resources which needed to be bought online and it
is tangible. Usually, a project manager is mainly focused on the select or chose a particular
domain name for website, hosting, integrated payment processors. In this project, project team
will focus on the intangible resources and relevant as creation of online (Aragonés-Beltrán,
García-Melón and Montesino-Valera, 2017). But the significant role of IT team initiate a request
for manager side and needed to consider technical, quality of resources. Having a finish
development procedure with different processes, request to be approved by project manager.
In recently, it will be increasing demand of successful online platform, project team will
require to follow all resource and its purpose. Afterwards, it is directly integrated with
development procedure to generate accurate result or outcome.
Scope
Project Deliverables – In this project, the deliverables that stakeholder and client expect at the
end of project in website. This will help to achieve desirable goal or objective. The involvement
of project management team has proposed the deliverables and also handle the project life cycle.
Initiating process- in this phase, project manager will focus on the main element which
include in project development (Kerzner, 2017 ). Generally, it should consider necessary
approval, essential resources, equipment’s, authorization of project, commit project
phase. These are essential aspect in which handle by project manager at the time of
initiating process. Therefore, the deliverables of project can be achieved through project
charter, scope, requirements, assumptions as well as constraints.
4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Planning phase- it is also consider the main element under planning phase in order to
define project scope. Project manager will focus on the gathering or collecting large
amount of data or information related the project. In this phase, project management team
will define the required deliverables, create frame for schedule, record information
(Lima, Tereso and Faria, 2019). In some situation, it is also sharing the data or
information between project team members. In this project, manager will try to find
essential skills, resources, risk analysis. Therefore, it help to estimate the overall price or
cost of project.
Controlling phase- In this process, project management team will focus on the team work
and progress. This is helping to monitor or track performance of team members. All kind
of corrective actions shall be taken, if requires. Project manager will monitor the
performance of development team and analyse that how will resolve any issue or problem
in website project development. The deliverables in this process of project include
performance of website, record status report, measurement metrics, and corrective actions
and resolve error in project management.
Closing Phase- in this stage, project manager will be finalizing the completion of online
shopping platform and then close out including all resolution of open items. Afterwards,
it will be finalizing from manager side. This is key deliverable under this phase in order
to accept and learn new thing.
At the time of project management life cycle, Project team member will select and choose the
best implement process in development life cycle or methodology. So as it become easier to
handle the overall processes in proper manner. Moreover, project management team will be
conducted research and define goals, critical success factor, vendor requirements. It will be
required to deliver the best design documentation (Madauss, 2017). The development of online
shopping platform will be developed based on the particular specification. Furthermore, user will
test entire system in term of performance, functionality, accuracy and response time. Afterwards,
it will be successfully deliver the design document to client.
5
define project scope. Project manager will focus on the gathering or collecting large
amount of data or information related the project. In this phase, project management team
will define the required deliverables, create frame for schedule, record information
(Lima, Tereso and Faria, 2019). In some situation, it is also sharing the data or
information between project team members. In this project, manager will try to find
essential skills, resources, risk analysis. Therefore, it help to estimate the overall price or
cost of project.
Controlling phase- In this process, project management team will focus on the team work
and progress. This is helping to monitor or track performance of team members. All kind
of corrective actions shall be taken, if requires. Project manager will monitor the
performance of development team and analyse that how will resolve any issue or problem
in website project development. The deliverables in this process of project include
performance of website, record status report, measurement metrics, and corrective actions
and resolve error in project management.
Closing Phase- in this stage, project manager will be finalizing the completion of online
shopping platform and then close out including all resolution of open items. Afterwards,
it will be finalizing from manager side. This is key deliverable under this phase in order
to accept and learn new thing.
At the time of project management life cycle, Project team member will select and choose the
best implement process in development life cycle or methodology. So as it become easier to
handle the overall processes in proper manner. Moreover, project management team will be
conducted research and define goals, critical success factor, vendor requirements. It will be
required to deliver the best design documentation (Madauss, 2017). The development of online
shopping platform will be developed based on the particular specification. Furthermore, user will
test entire system in term of performance, functionality, accuracy and response time. Afterwards,
it will be successfully deliver the design document to client.
5

Project Budget
In this project, the cost management plan will provide the comprehensive analysis of
price that is expected to be incurred and project take place. Generally, project manager will
estimate the entire budget of project on the basis of resources, investment. The budget plan of
project has proposed:-
S.No Resources Price or cost
1. manpower 500
2. Hardware and software requirements 10000
3. Funding 12000
4. Reusable components 500
. Total- 230000
Table: 1
In future, any kind of changes to budget must be revised in the document of project plan. It is
important to take approval from project manager and owner.
Risk assessment
In this section, project management team will focus on the proposed project. By
considering a risk or threat, it means any condition of event that might affect the overall
performance of project. Specifically, a potential risk identification and treatment plan for project
were discussed. On the basis of identification, it encountered the common risk or threat during
project development (Sánchez-Morcilio and Aparicio-Carrasco, 2020). It involves power issue,
machine breakdown, slow internet connection, defect in material, delay in resource management,
and bug or error issue in testing.
The project manager is responsible for tracking or monitoring risks and developing
suitable mitigation strategies. This will help to find the risks by project team members. Usually,
different kind of risk will be accessed regularly and ensure protect the system from major faults.
6
In this project, the cost management plan will provide the comprehensive analysis of
price that is expected to be incurred and project take place. Generally, project manager will
estimate the entire budget of project on the basis of resources, investment. The budget plan of
project has proposed:-
S.No Resources Price or cost
1. manpower 500
2. Hardware and software requirements 10000
3. Funding 12000
4. Reusable components 500
. Total- 230000
Table: 1
In future, any kind of changes to budget must be revised in the document of project plan. It is
important to take approval from project manager and owner.
Risk assessment
In this section, project management team will focus on the proposed project. By
considering a risk or threat, it means any condition of event that might affect the overall
performance of project. Specifically, a potential risk identification and treatment plan for project
were discussed. On the basis of identification, it encountered the common risk or threat during
project development (Sánchez-Morcilio and Aparicio-Carrasco, 2020). It involves power issue,
machine breakdown, slow internet connection, defect in material, delay in resource management,
and bug or error issue in testing.
The project manager is responsible for tracking or monitoring risks and developing
suitable mitigation strategies. This will help to find the risks by project team members. Usually,
different kind of risk will be accessed regularly and ensure protect the system from major faults.
6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Risk How will resolve it
Power issue Turn off and unplug as many appliances at the time of
fluctuation. This will help to protect or secure information
which will be accessed at that time.
Slow internet connection In order to resolve slow internet connection while
purchasing a new wireless broad-band network, which
provide the high speed internet connection. This will help
to resolve issue at the time of website accessing.
System failure or error System failure risk may arise in which directly effecting on
the performance of website. So as, it can be resolved
system, failure issue by using update software. It will help
the team to find any kind of defect in the processing.
Table: 2
Milestones
Stages Requirement Time-Frame Estimated time
1 Collecting and
gathering information
One week 19 June
2. Planning Two week 5 July
3. Designing Two week 18 July
4. Coding Two week 24 July
5. Testing, review and
launch
Three week 15 august
6. Maintenance Three week 5 September
Table: 3
7
Power issue Turn off and unplug as many appliances at the time of
fluctuation. This will help to protect or secure information
which will be accessed at that time.
Slow internet connection In order to resolve slow internet connection while
purchasing a new wireless broad-band network, which
provide the high speed internet connection. This will help
to resolve issue at the time of website accessing.
System failure or error System failure risk may arise in which directly effecting on
the performance of website. So as, it can be resolved
system, failure issue by using update software. It will help
the team to find any kind of defect in the processing.
Table: 2
Milestones
Stages Requirement Time-Frame Estimated time
1 Collecting and
gathering information
One week 19 June
2. Planning Two week 5 July
3. Designing Two week 18 July
4. Coding Two week 24 July
5. Testing, review and
launch
Three week 15 august
6. Maintenance Three week 5 September
Table: 3
7
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

In phase-1, the project management team will focus on gather relevant information about the
online platform. This will help to obtain a clear understanding in future scope. Main purpose of
this phase is to target audience and attract potential client towards online platform like website.
In phase-2, planning process can be handled by project team which intend to create a data or
information for client, judge the entire performance of staff members (Satapathy, Sahoo and
Maity, 2021). Sometimes, it will provide the clear visual of website where how will represent or
look at.
In phase-3, it reviews layout, structure and approval from client side. All kind of visual content
include in website which means that attract client by using photos, logos, image. In future, it will
utilise to improve general understanding towards platform.
In phase-4, it involves the testing of website and review the performance. Every single link in the
website will be tested in proper manner. Project management team will check script, run a
spelling check and find possible outcome. Sometimes, it including code validator to check or
follows the web standards.
Assumptions
Project assumptions
it refers to the project factors and consider to be real, true and certain without any
empirical proof. Realistically, it is not possible to make plan a project without consideration of
important assumptions.
Here are considered the assumptions which were made when developing a project by team
members.
This project has been approved from project manager and then start the procedure of
development.
Participating agencies that will continue to support members within present project.
It is focused on the specific commitment of project team members at different level. this
will help to define the entire project plan.
8
online platform. This will help to obtain a clear understanding in future scope. Main purpose of
this phase is to target audience and attract potential client towards online platform like website.
In phase-2, planning process can be handled by project team which intend to create a data or
information for client, judge the entire performance of staff members (Satapathy, Sahoo and
Maity, 2021). Sometimes, it will provide the clear visual of website where how will represent or
look at.
In phase-3, it reviews layout, structure and approval from client side. All kind of visual content
include in website which means that attract client by using photos, logos, image. In future, it will
utilise to improve general understanding towards platform.
In phase-4, it involves the testing of website and review the performance. Every single link in the
website will be tested in proper manner. Project management team will check script, run a
spelling check and find possible outcome. Sometimes, it including code validator to check or
follows the web standards.
Assumptions
Project assumptions
it refers to the project factors and consider to be real, true and certain without any
empirical proof. Realistically, it is not possible to make plan a project without consideration of
important assumptions.
Here are considered the assumptions which were made when developing a project by team
members.
This project has been approved from project manager and then start the procedure of
development.
Participating agencies that will continue to support members within present project.
It is focused on the specific commitment of project team members at different level. this
will help to define the entire project plan.
8

Constraints
Critical project barriers – there are different limitations and constraints identified in the project:-
It relies on the voluntary participation by government, local agencies.
This project has defined the estimated budget.
Project management team will proceed within specific functional requirement but it may
arise a problem during execution.
This project will be started after approval of project manager and then complete all tasks
on the basis of project plan.
Project management approach
Project roles and responsibilities
The project manager is responsible person who acquire a lot of data or information from
different sources. Sometimes, it is also assists other team members in context of project
development. Manager will assign the different tasks of team members on the basis of their
ability and knowledge (Swann, 2018). Similarity, the planning office will be made of people and
divided on the basis of their performance.
Here are discussed the roles and responsibilities of project team members in the project
development:-
Project Manager-
Actively participated into resource planning.
Organising, inspiring and motivating the individual team members.
Analysing and managing the project risk or threat.
Ensuring a proper client satisfaction and meet all expectation level.
Personal Assistant-
Working hand in hand with manage or control the entire project.
Represents the significant role of project manager at the time of meeting, where if
necessary.
Team member is responsible for gathering or collecting large amount of information.
9
Critical project barriers – there are different limitations and constraints identified in the project:-
It relies on the voluntary participation by government, local agencies.
This project has defined the estimated budget.
Project management team will proceed within specific functional requirement but it may
arise a problem during execution.
This project will be started after approval of project manager and then complete all tasks
on the basis of project plan.
Project management approach
Project roles and responsibilities
The project manager is responsible person who acquire a lot of data or information from
different sources. Sometimes, it is also assists other team members in context of project
development. Manager will assign the different tasks of team members on the basis of their
ability and knowledge (Swann, 2018). Similarity, the planning office will be made of people and
divided on the basis of their performance.
Here are discussed the roles and responsibilities of project team members in the project
development:-
Project Manager-
Actively participated into resource planning.
Organising, inspiring and motivating the individual team members.
Analysing and managing the project risk or threat.
Ensuring a proper client satisfaction and meet all expectation level.
Personal Assistant-
Working hand in hand with manage or control the entire project.
Represents the significant role of project manager at the time of meeting, where if
necessary.
Team member is responsible for gathering or collecting large amount of information.
9
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Assist the project manager in order to analyse and measure risk at the time of project
development.
IT team-
Resolving any kind of software errors at the time of task executions.
A major responsibility of IT team to create a proper documentation and include all
necessary software as well as hardware specification.
A responsible for coding.
IT team will support to perform procedure of testing and maintaining the website.
Planning executive-
Assist the project manager at the time of project development. This will help to analyse
and measure any kind of risk in the project.
It is also prepared for planning in context of documentation. Sometimes, It allocate a
proper resources (Satapathy, Sahoo and Maity, 2021).
Communicating with relevant parties in regards of actual status in term of planning
application and also resolve any kind of queries.
It keep record the data or information up to date with proper planning, regulation.
Sometimes, it can easily handle the policy, procedure and legislation.
Maintaining the prioritize workload and always taking a proper flexible approach in
context of change direction.
Project timeline
The project timeline or schedule will be posted online and updated as tasks are completed in
proper manner. If any changes required to schedule which must be documented in the revised
project schedule.
Task Estimated start date End date
Preliminary
functions as defined
and prioritized
19 June 5 July One week
10
development.
IT team-
Resolving any kind of software errors at the time of task executions.
A major responsibility of IT team to create a proper documentation and include all
necessary software as well as hardware specification.
A responsible for coding.
IT team will support to perform procedure of testing and maintaining the website.
Planning executive-
Assist the project manager at the time of project development. This will help to analyse
and measure any kind of risk in the project.
It is also prepared for planning in context of documentation. Sometimes, It allocate a
proper resources (Satapathy, Sahoo and Maity, 2021).
Communicating with relevant parties in regards of actual status in term of planning
application and also resolve any kind of queries.
It keep record the data or information up to date with proper planning, regulation.
Sometimes, it can easily handle the policy, procedure and legislation.
Maintaining the prioritize workload and always taking a proper flexible approach in
context of change direction.
Project timeline
The project timeline or schedule will be posted online and updated as tasks are completed in
proper manner. If any changes required to schedule which must be documented in the revised
project schedule.
Task Estimated start date End date
Preliminary
functions as defined
and prioritized
19 June 5 July One week
10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Implement the
workgroup progress
5 July 18 July Two week
Create a systematic
project plan
18 July 24 July Two week
Report on the survey 24 July 15 august Two week
Develop a test plan 15 august 5 September Three week
Test implemented
functions
5 September 10 September Three week
Table: 4
In this project, a time-line is basically covered a canvas of project in term of deliverables. It
provide the better view in simple manner, but it comprehensive visual overview of project. It will
start from specific end and then finish.
A detailed time-line paints a proper road-map for this project with milestones, dependencies,
tasks and delivery dates. Sometimes, a specific project time-line is also known as visual list of
different tasks or activities. The responsibility of project manager is to view the performance of
entire project in one place. Typically, it takes the different forms of horizontal, where each and
every task is given a name and corresponding.
Conclusion
In above discussion, it has been discussed about the project management plan for new online
shopping platform development. On the basis of analysis, project team is looking forward to
develop a dynamic website for individual’s people who are majorly influenced within online
platform. As team have an expertise and capacity to get better result or outcome. In this report, it
has been summarised about the project goal or objective which may be provided the better
11
workgroup progress
5 July 18 July Two week
Create a systematic
project plan
18 July 24 July Two week
Report on the survey 24 July 15 august Two week
Develop a test plan 15 august 5 September Three week
Test implemented
functions
5 September 10 September Three week
Table: 4
In this project, a time-line is basically covered a canvas of project in term of deliverables. It
provide the better view in simple manner, but it comprehensive visual overview of project. It will
start from specific end and then finish.
A detailed time-line paints a proper road-map for this project with milestones, dependencies,
tasks and delivery dates. Sometimes, a specific project time-line is also known as visual list of
different tasks or activities. The responsibility of project manager is to view the performance of
entire project in one place. Typically, it takes the different forms of horizontal, where each and
every task is given a name and corresponding.
Conclusion
In above discussion, it has been discussed about the project management plan for new online
shopping platform development. On the basis of analysis, project team is looking forward to
develop a dynamic website for individual’s people who are majorly influenced within online
platform. As team have an expertise and capacity to get better result or outcome. In this report, it
has been summarised about the project goal or objective which may be provided the better
11

opportunity for team member to use appropriate resources, equipment’s. Afterwards, it can help
to achieve its desirable objectives.
Recommendation
In this project, the suggestions are intended to ensure that there are increasingly demand of
accountability and ownership of accomplish project management objectives. In the online
platform development, it has suggested the better opportunity to achieve desirable goal or
objective.
1- at the time of project management plan, it is important to find the opinion or view
point of every customers, who have already used the online shopping platform. in this
way, project manager will easily create a clear, consistent, executive communication in
different departments. Afterwards, it can utilise the overall performance and efficiency in
proper manner.
2- Revise the project management procedures, guidelines and manuals which reflects on
the consistency in online shopping platform. Sometimes, it has suggested to add
particular features and influence more consumers towards online platform.
12
to achieve its desirable objectives.
Recommendation
In this project, the suggestions are intended to ensure that there are increasingly demand of
accountability and ownership of accomplish project management objectives. In the online
platform development, it has suggested the better opportunity to achieve desirable goal or
objective.
1- at the time of project management plan, it is important to find the opinion or view
point of every customers, who have already used the online shopping platform. in this
way, project manager will easily create a clear, consistent, executive communication in
different departments. Afterwards, it can utilise the overall performance and efficiency in
proper manner.
2- Revise the project management procedures, guidelines and manuals which reflects on
the consistency in online shopping platform. Sometimes, it has suggested to add
particular features and influence more consumers towards online platform.
12
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 14
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.