Online Stud Farm Management Project: Part One, Two, and Three Analysis

Verified

Added on  2021/06/18

|17
|4085
|225
Project
AI Summary
This project analyzes the development of an online stud farm management system for Globex, focusing on customer impact. It identifies key areas like strategy, customer service, financial investment, operational efficiency, and social support, ranking customer service as the most crucial. The project aims to provide faster and cheaper services to attract more customers. The scope includes requirements gathering, system design and development, testing, implementation, and support, with a budget of $40,000 and a timeframe of six months. The project utilizes MS Project to develop a detailed schedule with a Work Breakdown Structure (WBS), including milestones, tasks, resource allocation, and cost estimates for each phase. The document also addresses assumptions, constraints, and a scope management plan, ensuring the project's successful implementation and alignment with stakeholder expectations. The project outlines hardware, software, and network requirements, emphasizing the need for technical and cultural training for employees.
Document Page
Student Name
ID Assignment: 3 Title:
Online Stud Farm
Management
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1. Part One:
1.1 MOV - Measurable Organisational Value
Identify the desired area of impact - Rank the following areas in terms of importance: Strategy /
Customer / Financial / Operational / Social (5 Marks)
Rank the area of impact (add in any more area you can think of)
Area of Impact Rank (1 to 5)
Strategy: Proper business strategies will
help the online stud farm to gain
competitive advantages and commercial
profit.
3
Customer: Customers are referred to as
one of the most valuable asset for any
business. Similarly, before developing
the management system stud farm the
Globex should focus on building a
customer focused system. With the
successful implementation of the
system, the breeder’s details, stud
details and secured level payment can
also be processed accordingly.
1
Financial: Capital investment is another
important thing on which the developers
should concentrate as well. The project
sponsors are responsible to deliver
required amount of capital so that the
system can be implemented securely.
2
Operational: Besides proper investment
over capital for the development of the
online stud farm management system
another thing on which the developers
should concentrate is proper
maintenance of operation. This is the
responsibility of the project manager
and the operation manager to make sure
that all the system operations are
running accurately.
4
Social: The breeding farm should have
proper social support during operation
period. It is expected that, with social
support the administrative errors will be
significantly reduced.
5
Document Page
• SUMMARISE THE MOV IN A CLEAR CONCISE STATEMENT OR TABLE
(Note: the MOV should inform everyone what the project will achieve, not how it will be achieved. It
should also focus on the organisation, not on the technology that will be used to build or support the
information system).
Choose the area of impact you have ranked as no 1.
For that area of impact
With reference to your project, identify one or two of the following types of value:
Better
Faster
Cheaper
Do more
For the online stud farm management project the chosen area that have been ranked as number
1 is the consumer. With reference to the project the values those are specified include: faster
and cheaper
Faster: The purpose of the project is to make sure that all true percentage of through breeding is
maintained and breeding services are offered. There are many online stud farm system those are
used for service booking and breeding management. The system is required to be faster so that
it can grab more consumers accordingly.
Cheaper: The growth of any system depends upon its service timing, affordability and quality.
For this particular management system the affordability is again very important. Thus, the price
of booking should be cheaper so that it can grab more number of consumers accordingly.
Develop an appropriate metric - this sets the target and expectation of all the stakeholders.
It is important to determine a quantitative target that needs to be expressed as a metric in
terms of an increase or decrease of money.
Stakeholder Expectation
Project manager To track and monitor the project to meet its
objectives
Finance manager To complete the project within the estimated
budget.
Operation manager To maintain all the necessary system operation
in terms of booking breeders details, stud details
and payment gateway.
System developer To provide a secured system with secured
payment to the consumers.
Determine the timeframe for achieving the MOV - ask yourselves, when do we want to
achieve this target metric?
Document Page
Based on the details of the system requirements and their backgrounds it can be said that for the
successful accomplishment of this particular project the project manager and the project team
members will be required 6 months time.
Part Two: (10 Marks)
Scope (minimal 10 items) – 10 Marks
Requirements are gathered and documented accurately
Design and Develop the online stud farm management system
Test and Implement the designed and developed online system
Reports are implemented
Support the system through warranty period of 6 months
The service should be affordable
The system offers the consumers an online payment gateway opportunity
The consumers should operate the system from any location and any time
The system should possess public liability insurance
System has a feedback ort invoice option
Out of Scope
There is not particular marketing strategies developed for the online Stud farm
management system
No future development plans are developed for this project
Assumptions
After analysing the details of the online stud farm management system developed by Globex it has
been found that, the project objectives can be reached by the project team members within 6
months and the total budget estimated for the successful implementation of the project is $40,000.
It is assumed that with the successful implementation of the project the consumers will be able to
book online with a faster and cheaper cost amount. Again they will also be able to get a secured
system where the details will be stored absolutely securely.
Constraints
For this project triple project constraints are cost, time and scope. The online stud farm
management system is estimated to be completed within 6 months with a cost of $40,000. It is
defined that the system will reduce the issues of traditional manual and spreadsheet maintained
record keeping system.
Scope Management Plan
In order to gain effective success from the online stud farm management system it is necessary for
the system developers to consider a scope plan and that must be followed by the project team
members and the project manager as well. Experienced system developers, Operation manager and
finance manager should be hired for implementing system. Before its implementation a prototype
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
should be designed and tested accordingly to make sure that whether the system is reaching its
desire outcome or service to the consumers.
Resource Plan (from MS-Project)
People (and their roles), plus any extra personnel that is required for the project – Project
screenshot.
Figure 1: Resource allocated for the online system
(Source: Created by author)
Resource Name Type Max.
Units Std. Rate Accrue At Base
Calendar
Responsibility
Project manager Work 100% $28.00/hr Prorated Standard Control and
monitor
finance manager Work 100% $22.00/hr Prorated Standard Budget
preparation
operation manager Work 100% $25.00/hr Prorated Standard Checking system
operation
system developer Work 100% $18.00/hr Prorated Standard
Developing the
online stud farm
management
system
system tester Work 100% $15.00/hr Prorated Standard Testing the online
system
project sponsor Work 100% $32.00/hr Prorated Standard Invest capital for
the project
HR manager Work 100% $15.00/hr Prorated Standard Manages the
employees
hardware
requirements Material $26.00 Prorated To develop the
system
software
requirements
Material $25.00 Prorated To increase the
efficiency of the
Document Page
system
network
requirements Material $20.00 Prorated To give security to
the system
Technology - any hardware, network and software needs to support the team and your
client.
Hardware Processors, Ethernet, hard drives,
memory, sound cards
Software Operating system, server side scripting
language, database(MySQL), local
caching software
Network Network diagnostic tools, bandwidth,
TCP/IP network model
Facilities - where will most of the teamwork be situated?
According to the analytical details of the system it has been found that for this
particular project most of the teamwork will be suited for are onsite.
Other - for example, travel, training etc.
Travel Requirements The consumers are allowed to
book in stud farm management
system from different geographical
location as it offers online booking
option according to their new
service. On the other hand, the
travel requirements are different
for the different countries. The
travel requirements include:
unexpired passport (DFA issued),
Unexpired Visa, return tickets.
Training Requirements Training is not required for the
consumers but it is needed for the
system developers and other
employees who will be operating
the new booking system. Technical
and cultural training and
development program should be
arranged by the developers.
Part Three: (15 Marks)
Document Page
Using MS Project, develop a schedule using a high level Work Breakdown Structure (WBS). It
should include:
Milestones for each phase and deliverable (4 marks)
Milestone 1: Completion of project initiation phase
Milestone 2: Completion of project planning phase
Milestone3: Completion of project design phase
Milestone 4: Completion of project testing phase
Milestone 5: Completion of project closure phase
Activities / Tasks(4 marks)
Task Name Duration Start Finish Resource Names Cost
Developing project
schedule for Online Stud
Farm management system
180 days Thu
5/10/18
Wed
1/16/19 $39,877.00
Project initiation phase 34 days Thu
5/10/18
Tue
6/26/18 $5,926.00
Understanding project
requirement for Stud farm 5 days Thu
5/10/18
Wed
5/16/18
operation
manager, Project
manager
$2,120.00
Hiring sponsors and
discussion with Globex 6 days Thu
5/17/18
Thu
5/24/18 HR manager $720.00
Developing business
strategies 8 days Fri 5/25/18 Tue 6/5/18 operation
manager $1,600.00
Demo version installation 6 days Fri 5/25/18 Fri 6/1/18 Project manager $1,344.00
Resource identification 5 days Wed 6/6/18 Tue
6/12/18
hardware
requirements
[1],network
requirements
[1],software
requirements [1]
$71.00
Resource gathering 10 days Wed
6/13/18
Tue
6/26/18
hardware
requirements
[1],network
requirements
[1],software
requirements [1]
$71.00
Milestone 1: Completion of
project initiation phase 0 days Tue
6/26/18
Tue
6/26/18 Project manager $0.00
Project planning phase 35 days Wed
6/27/18
Tue
8/14/18 $7,608.00
Developing project team 9 days Wed Mon 7/9/18 operation $1,800.00
736643.mpp
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
6/27/18 manager
Risk management planning 10 days Tue
7/10/18
Mon
7/23/18 Project manager $2,240.00
Stakeholders management
plan development 5 days Tue
7/24/18
Mon
7/30/18
HR manager,
system tester $1,200.00
Communication and
procurements management
plan
8 days Tue
7/24/18 Thu 8/2/18 HR manager $960.00
Budget planning 8 days Fri 8/3/18 Tue
8/14/18 finance manager $1,408.00
Milestone 2: Completion of
project planning phase 0 days Tue
8/14/18
Tue
8/14/18 Project manager $0.00
Design and implementation
phase 88 days Wed
8/15/18
Fri
12/14/18 $22,767.00
Collecting non-functional
and functional requirements 6 days Wed
8/15/18
Wed
8/22/18
operation
manager, project
sponsor
$2,736.00
Collecting hardware
requirements 5 days Thu
8/23/18
Wed
8/29/18
hardware
requirements
[1],project
sponsor
$1,306.00
Software requirements
specification 8 days Thu
8/30/18
Mon
9/10/18
project sponsor,
software
requirements [1]
$2,073.00
Network requirements
specification 8 days Tue
9/11/18
Thu
9/20/18
network
requirements
[1],project
sponsor
$2,068.00
Prototype designing 9 days Fri 9/21/18 Wed
10/3/18
system
developer $1,296.00
Approval of the design
outline 10 days Thu
10/4/18
Wed
10/17/18
operation
manager, Project
manager
$4,240.00
Modeling 12 days Thu
10/18/18 Fri 11/2/18 system
developer $1,728.00
Coding 15 days Mon
11/5/18
Fri
11/23/18
system
developer $2,160.00
Complete development
with Graphical User Interface 15 days Mon
11/5/18
Fri
11/23/18
operation
manager $3,000.00
Adding mobile features 15 days Mon
11/26/18
Fri
12/14/18
system
developer $2,160.00
Milestone3: Completion of
project design phase 0 days Fri
12/14/18
Fri
12/14/18 Project manager $0.00
Testing phase 20 days Mon
12/17/18 Fri 1/11/19 $2,400.00
Unit testing of the online
management system 10 days Mon
12/17/18
Fri
12/28/18 system tester $1,200.00
Integrated testing 10 days Mon Fri 1/11/19 system tester $1,200.00
Document Page
12/31/18
Milestone 4: Completion of
project testing phase 0 days Fri 1/11/19 Fri 1/11/19 system tester $0.00
Closure phase 3 days Mon
1/14/19
Wed
1/16/19 $1,176.00
Stakeholders signoff 1 day Mon
1/14/19
Mon
1/14/19
HR manager,
project sponsor $376.00
Final document submission 1 day Tue
1/15/19
Tue
1/15/19
operation
manager, Project
manager
$424.00
Post maintenance plan 1 day Wed
1/16/19
Wed
1/16/19
finance
manager,
operation
manager
$376.00
Milestone 5: Completion of
project closure phase 0 days Wed
1/16/19
Wed
1/16/19 Project manager $0.00
Document Page
Resource Assignments(4 marks)
Task Name Resource Names
Developing project schedule for Online Stud Farm
management system
Project initiation phase
Understanding project requirement for Stud farm operation manager, Project
manager
Hiring sponsors and discussion with Globex HR manager
Developing business strategies operation manager
Demo version installation Project manager
Resource identification
hardware requirements
[1],network requirements
[1],software requirements [1]
Resource gathering
hardware requirements
[1],network requirements
[1],software requirements [1]
Milestone 1: Completion of project initiation phase Project manager
Project planning phase
Developing project team operation manager
Risk management planning Project manager
Stakeholders management plan development HR manager, system tester
Communication and procurements management plan HR manager
Budget planning finance manager
Milestone 2: Completion of project planning phase Project manager
Design and implementation phase
Collecting non-functional and functional requirements operation manager, project
sponsor
Collecting hardware requirements hardware requirements
[1],project sponsor
Software requirements specification project sponsor, software
requirements [1]
Network requirements specification network requirements
[1],project sponsor
Prototype designing system developer
Approval of the design outline operation manager, Project
manager
Modeling system developer
Coding system developer
Complete development with Graphical User Interface operation manager
Adding mobile features system developer
Milestone3: Completion of project design phase Project manager
Testing phase
Unit testing of the online management system system tester
Integrated testing system tester
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Milestone 4: Completion of project testing phase system tester
Closure phase
Stakeholders signoff HR manager, project sponsor
Final document submission operation manager, Project
manager
Post maintenance plan finance manager, operation
manager
Milestone 5: Completion of project closure phase Project manager
Estimates for Each Activity / Task (3 Marks)
Figure 2: Project Timeline for the online Stud Farm project development
(Source: Created by author)
Document Page
Part Four: (15 Marks)
Assumptions - Document any assumptions you have made about the project (5 Marks)
For this particular project the assumptions are as follows:
The project is assumed to e completely risk and error free, user friendly and fast
The project is estimated to be completed in 6 months
The assumed cost for the successful completion of the project is $40,000
Using the Risk Identification Framework as a basis, identify five risks to the project –
Analyse these risks, assign a risk to an appropriate member, and describe a strategy for
the management of each specific risk. (10 Marks)
List at least 5
Ris
k ID
Description Probabilit
y
Impac
t
Rate Assigned
To
Response
Strategy
Threat or
Opportunity
1 Improper
resource
identification
70% 5 High Project
manager
At the project
initiation
phase the
project
manager
should create
identify the
required
resources
(human,
physical)
depending on
experience.
If proper
resources are
not chosen
during the
project
development
phase the
time and cost
both will be
overrated.
2 Incorrect cost
management
60% 3 High Finance
manager
At the
initiation
phase
feasibility
should be
done by the
finance
manager to
make sure that
the project is
beneficial for
the stud farm.
If proper cost
is not
estimated by
the finance
manager
then during
the project
ongoing
phase the
overall
estimation
will exceed
the estimated
budget.
3 Lack of
technical
experience
80% 5 High HR
manager
Professional
training and
development
program
should be
It will help
the project
team
members to
gain more
chevron_up_icon