A Project on Developing Online Stud Farm Management System for Globex
VerifiedAdded on 2021/05/31
|15
|2490
|38
Project
AI Summary
This project outlines the development of an online stud farm management system for Globex, encompassing various phases from planning and initiation to execution, training, and project closure. The project aims to enhance revenue, improve service delivery, and eliminate human errors through automation. It includes detailed scope, assumptions, constraints, and a comprehensive resource plan featuring human resources, technology, and facilities. The project milestones, activities, and budget are meticulously defined, with time estimations and risk management strategies. The project also incorporates quality control measures, verification, and validation activities, along with an annotated bibliography and a closure checklist, demonstrating a structured approach to project management. The project utilizes ISO 9001 standards and service legal agreements to ensure quality and successful delivery, along with an evaluation criteria section.

Student Name
ID Developing Online Stud
Farm Management
System
ID Developing Online Stud
Farm Management
System
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1. Part One
1. 1 MOV - Measurable Organisational Value
Ranking Area of Impact
1 Overall revenue of the Globex
2 Increase the accuracy to maximize level
3 Manage the data and information
4 Business operation Strategy
5 Social connectivity
1.2 Project value
The project will provide following values:
Better: The standard of the daily operational activities will be enhanced from existing to better services
and on the other hand the customers will be provided with enhanced and faster services.
Faster: the services and the product being availed by the Globex will become more faster than earlier in
manner to enhance the existing services.
1.3 Comparison Metric and Time Frame
Rank Area of Impact Time Frame Metric
1 Overall revenue of
the Globex 3 months Increase the yearly revenue
by 20%
2 Increase the
accuracy to
maximize level
2 months Increase the efficiency up to
more than 90%
3 Manage the data
and information 3 months Faster the services through
automating the database
management
4 Business operation
Strategy 2 month Fasting and enhancing the
services and ways of
delivering services
5 Social connectivity 2 months Connect the employees and
customers in social network
platform
2. Part Two:
2.1 Scope
Scope of this project can be listed as:
Increase the overall revenue
Fastening and enhancing the manner of service delivery
1. 1 MOV - Measurable Organisational Value
Ranking Area of Impact
1 Overall revenue of the Globex
2 Increase the accuracy to maximize level
3 Manage the data and information
4 Business operation Strategy
5 Social connectivity
1.2 Project value
The project will provide following values:
Better: The standard of the daily operational activities will be enhanced from existing to better services
and on the other hand the customers will be provided with enhanced and faster services.
Faster: the services and the product being availed by the Globex will become more faster than earlier in
manner to enhance the existing services.
1.3 Comparison Metric and Time Frame
Rank Area of Impact Time Frame Metric
1 Overall revenue of
the Globex 3 months Increase the yearly revenue
by 20%
2 Increase the
accuracy to
maximize level
2 months Increase the efficiency up to
more than 90%
3 Manage the data
and information 3 months Faster the services through
automating the database
management
4 Business operation
Strategy 2 month Fasting and enhancing the
services and ways of
delivering services
5 Social connectivity 2 months Connect the employees and
customers in social network
platform
2. Part Two:
2.1 Scope
Scope of this project can be listed as:
Increase the overall revenue
Fastening and enhancing the manner of service delivery

Eliminate the human errors to the extent level
Allow data access and management in effective and efficient manner
Provide a sophisticated model to be followed for the accomplishment of the enhancement for the
Globex
Targeting enhancement in the customer satisfaction
Migrating data over an online system and allow data and information access for 24*7
Allowing the employees of the Globex to minimize the workload
Complete the project within deadline
Accomplish all the milestones without altering the milestones
2.2 Out of Scope
compatibility with the devices having different operating systems, coding, hosting, programming, and
others
Conflicts among the staffs and employees
Changes implemented after evaluation
Uncertainties due to natural calamity
2.3 Assumptions
Executives will approve the project draft
Resources will be available throughout the project lifecycle
Risks has been minimized to the extent level
The prices of the resources will be same throughout the project development
2.4 Constraints
The quality of the project will be of highest quality
The project will be completed within 190 days
The cost of the project will not increase more than $ 35,000
2.5 Scope Management Plan
Manage resource availability
Comply the business rules with new implementation
Impact of the risk is managed to the minimum level
Risk handling delivery considering the identification of the positive and negative risks
Regular monitor and audit
2.6 Resource Plan
Human Resources
Resource Name Std. Rate
Project Manager $50.00/hr
Marketing and Commerce Manager $45.00/hr
Technical Expert $40.00/hr
System Trainer $35.00/hr
Technical Integration Specialist $40.00/hr
Developer $35.00/hr
IT Manager $40.00/hr
Allow data access and management in effective and efficient manner
Provide a sophisticated model to be followed for the accomplishment of the enhancement for the
Globex
Targeting enhancement in the customer satisfaction
Migrating data over an online system and allow data and information access for 24*7
Allowing the employees of the Globex to minimize the workload
Complete the project within deadline
Accomplish all the milestones without altering the milestones
2.2 Out of Scope
compatibility with the devices having different operating systems, coding, hosting, programming, and
others
Conflicts among the staffs and employees
Changes implemented after evaluation
Uncertainties due to natural calamity
2.3 Assumptions
Executives will approve the project draft
Resources will be available throughout the project lifecycle
Risks has been minimized to the extent level
The prices of the resources will be same throughout the project development
2.4 Constraints
The quality of the project will be of highest quality
The project will be completed within 190 days
The cost of the project will not increase more than $ 35,000
2.5 Scope Management Plan
Manage resource availability
Comply the business rules with new implementation
Impact of the risk is managed to the minimum level
Risk handling delivery considering the identification of the positive and negative risks
Regular monitor and audit
2.6 Resource Plan
Human Resources
Resource Name Std. Rate
Project Manager $50.00/hr
Marketing and Commerce Manager $45.00/hr
Technical Expert $40.00/hr
System Trainer $35.00/hr
Technical Integration Specialist $40.00/hr
Developer $35.00/hr
IT Manager $40.00/hr
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Data Management Officer $25.00/hr
Project Supervisor $25.00/hr
Technology
Hardware Cloud Storage, computers, cables, electric connections,
switches, wireless connectivity appliances
Software My – SQL database, software, MS office
Network Internet, Intranet
Facilities
Network connection will be available throughout the project cycle including all the resources
necessary for the deployment of the successful project. the budget will be signed by the contractor and
further raise in the prices will be handled by themselves.
3. Part Three:
3.1 Project Milestones
Task Name Duration Start Finish
Online Stud Farm Management System
Development 188 days Mon 12/18/17 Wed 9/5/18
Phase 1: Planning 35 days Mon 5/21/18 Fri 7/6/18
Milestone 1: planning completed 0 days Fri 7/6/18 Fri 7/6/18
Phase 2: Initiation 10 days Mon 7/9/18 Fri 7/20/18
Milestone 2: initiation completed 0 days Fri 7/20/18 Fri 7/20/18
Phase 3: Execution 29 days Wed 7/25/18 Mon 9/3/18
Milestone 3: execution completed 0 days Thu 8/16/18 Thu 8/16/18
Phase 5: Training 188 days Mon 12/18/17 Wed 9/5/18
Milestone 5: completed 0 days Thu 12/21/17 Thu 12/21/17
phase 6: Project Closing 9 days Fri 12/22/17 Wed 1/3/18
Milestone 6: completed 0 days Wed 1/3/18 Wed 1/3/18
3.2 Project Activities
0 Online Stud Farm Management System Development
1 Phase 1: Planning
1.1 Meeting with stakeholders
Project Supervisor $25.00/hr
Technology
Hardware Cloud Storage, computers, cables, electric connections,
switches, wireless connectivity appliances
Software My – SQL database, software, MS office
Network Internet, Intranet
Facilities
Network connection will be available throughout the project cycle including all the resources
necessary for the deployment of the successful project. the budget will be signed by the contractor and
further raise in the prices will be handled by themselves.
3. Part Three:
3.1 Project Milestones
Task Name Duration Start Finish
Online Stud Farm Management System
Development 188 days Mon 12/18/17 Wed 9/5/18
Phase 1: Planning 35 days Mon 5/21/18 Fri 7/6/18
Milestone 1: planning completed 0 days Fri 7/6/18 Fri 7/6/18
Phase 2: Initiation 10 days Mon 7/9/18 Fri 7/20/18
Milestone 2: initiation completed 0 days Fri 7/20/18 Fri 7/20/18
Phase 3: Execution 29 days Wed 7/25/18 Mon 9/3/18
Milestone 3: execution completed 0 days Thu 8/16/18 Thu 8/16/18
Phase 5: Training 188 days Mon 12/18/17 Wed 9/5/18
Milestone 5: completed 0 days Thu 12/21/17 Thu 12/21/17
phase 6: Project Closing 9 days Fri 12/22/17 Wed 1/3/18
Milestone 6: completed 0 days Wed 1/3/18 Wed 1/3/18
3.2 Project Activities
0 Online Stud Farm Management System Development
1 Phase 1: Planning
1.1 Meeting with stakeholders
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1.2 Drafting project proposal
1.3 Analysing requirements
1.4 Draft proposition
1.5 Approval
1.6 Sign-off
1.7 Project charter development
1.8 Approval
1.9 Milestone 1: planning completed
2 Phase 2: Initiation
2.1 Analysing budget
2.2 Requirement analysis
2.3 System Design development
2.4 Assigning roles and responsibilities of stakeholders
2.5 Milestone 2: initiation completed
3 Phase 3: Execution
3.1 Software Analysis
3.2 Hardware analysis
3.3 Software Integration
3.4 Hardware integration
3.5 Incorporating Hardware and software for the system
3.6 UI integration
3.7 Online storage
3.8 Data migration to the database
3.9 Milestone 3: execution completed
3.10 Phase 4: Monitoring and controlling
3.10.1 Simulation testing
3.10.2 Black box testing
1.3 Analysing requirements
1.4 Draft proposition
1.5 Approval
1.6 Sign-off
1.7 Project charter development
1.8 Approval
1.9 Milestone 1: planning completed
2 Phase 2: Initiation
2.1 Analysing budget
2.2 Requirement analysis
2.3 System Design development
2.4 Assigning roles and responsibilities of stakeholders
2.5 Milestone 2: initiation completed
3 Phase 3: Execution
3.1 Software Analysis
3.2 Hardware analysis
3.3 Software Integration
3.4 Hardware integration
3.5 Incorporating Hardware and software for the system
3.6 UI integration
3.7 Online storage
3.8 Data migration to the database
3.9 Milestone 3: execution completed
3.10 Phase 4: Monitoring and controlling
3.10.1 Simulation testing
3.10.2 Black box testing

3.10.3 Real world application testing
4 Phase 5: Training
4.1 training to employees
4.2 Analysing learning enhancement
4.3 system tutorial
4.4 Milestone 5: completed
5 phase 6: Project Closing
5.1 project review
5.2 project documentation
5.3 stakeholders sign-off
5.4 Milestone 6: completed
3.3 Project Resources
Resource Name Type Std. Rate
Project Manager Work $50.00/hr
Marketing and Commerce Manager Work $45.00/hr
Technical Expert Work $40.00/hr
System Trainer Work $35.00/hr
Technical Integration Specialist Work $40.00/hr
Developer Work $35.00/hr
IT Manager Work $40.00/hr
Data Management Officer Work $25.00/hr
Project Supervisor Work $25.00/hr
Hardware Material $2,500.00
Development Software Material $4,000.00
Figure 2: Project resources
(Source: Created by Author)
3.4 Time Estimation
The project is expected to be completed within 188 days and the whole estimated expanses is $34,640 as explained in the below
screenshot of the MS project:
4 Phase 5: Training
4.1 training to employees
4.2 Analysing learning enhancement
4.3 system tutorial
4.4 Milestone 5: completed
5 phase 6: Project Closing
5.1 project review
5.2 project documentation
5.3 stakeholders sign-off
5.4 Milestone 6: completed
3.3 Project Resources
Resource Name Type Std. Rate
Project Manager Work $50.00/hr
Marketing and Commerce Manager Work $45.00/hr
Technical Expert Work $40.00/hr
System Trainer Work $35.00/hr
Technical Integration Specialist Work $40.00/hr
Developer Work $35.00/hr
IT Manager Work $40.00/hr
Data Management Officer Work $25.00/hr
Project Supervisor Work $25.00/hr
Hardware Material $2,500.00
Development Software Material $4,000.00
Figure 2: Project resources
(Source: Created by Author)
3.4 Time Estimation
The project is expected to be completed within 188 days and the whole estimated expanses is $34,640 as explained in the below
screenshot of the MS project:
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Figure 3: Time estimation
(Source: Created by Author)
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

3.5 Project Budget
Figure 4: Project budget
(Source: Created by Author)
Figure 4: Project budget
(Source: Created by Author)

3.6 Time Phase Budget
Phase 1:
Planning Phase 2:
Initiation Phase 3:
Execution Phase 5:
Training phase 6:
Project
Closing
$0.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
$14,000.00
$16,000.00
$18,000.00
$20,000.00
Actual Cost Remaining Cost Baseline Cost
Figure 5: Time phase budget
(Source: Created by Author)
Name Remaining Cost Cost Cost Variance
Phase 1: Planning $17,160.00 $17,160.00 $17,160.00
Phase 2: Initiation $2,920.00 $2,920.00 $2,920.00
Phase 3: Execution $5,840.00 $5,840.00 $5,840.00
Phase 5: Training $1,680.00 $1,680.00 $1,680.00
phase 6: Project Closing $7,040.00 $7,040.00 $7,040.00
4. Part Four:
4.1 Assumptions
The assumptions are as follows:
The available human resources will work as per the determined work hours
Project will not increase more than $ 40,000
The milestones will be accomplished within the planned constraints
Phase 1:
Planning Phase 2:
Initiation Phase 3:
Execution Phase 5:
Training phase 6:
Project
Closing
$0.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
$14,000.00
$16,000.00
$18,000.00
$20,000.00
Actual Cost Remaining Cost Baseline Cost
Figure 5: Time phase budget
(Source: Created by Author)
Name Remaining Cost Cost Cost Variance
Phase 1: Planning $17,160.00 $17,160.00 $17,160.00
Phase 2: Initiation $2,920.00 $2,920.00 $2,920.00
Phase 3: Execution $5,840.00 $5,840.00 $5,840.00
Phase 5: Training $1,680.00 $1,680.00 $1,680.00
phase 6: Project Closing $7,040.00 $7,040.00 $7,040.00
4. Part Four:
4.1 Assumptions
The assumptions are as follows:
The available human resources will work as per the determined work hours
Project will not increase more than $ 40,000
The milestones will be accomplished within the planned constraints
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

4.2 Project Risk and Management Strategy
Risk
ID
Description Probability Impact Rate Assigned
To
Response
Strategy
Threat or
Opportunity
Probability
after
mitigating
Risk
01
Glitches
and bugs
40% 4 250 Software
engineer
An IT
committee for
evaluation
Threat 10%
Risk
02
Risks
associated
with
resources
10% 2 150 Resource
manager
Resource
management
in efficient
manner
Threat 2%
Risk
03
Issues
associated
in the
developed
design
30% 3 250 Web
Designer
Mock-up
presentation
and approval
from real users
Threat 5%
Risk
04
Increase in
Schedule
50 % 5 400 Project
planner
Preparing
Gantt chart
with
milestones
Opportunity 10%
Risk
05
Increase in
budget
60% 5 400 Project
manager
Estimating cost
for every
aspect
Threat 10%
5. Part Five:
5.1 Statement on Project Quality
The project will be managed as per the stated milestones and schedules and alterations will be made if
certain activities are not meeting with the project constraints
ISO 9001 standard will be applied for the management system
Service legal agreements will be prepared and the project will be delivered accordingly
Experienced and educated human resources will be appointed
Knowledge related to previous projects will be applied
5.2 Set of Verification Activities
Verification Activity When?
Risk
ID
Description Probability Impact Rate Assigned
To
Response
Strategy
Threat or
Opportunity
Probability
after
mitigating
Risk
01
Glitches
and bugs
40% 4 250 Software
engineer
An IT
committee for
evaluation
Threat 10%
Risk
02
Risks
associated
with
resources
10% 2 150 Resource
manager
Resource
management
in efficient
manner
Threat 2%
Risk
03
Issues
associated
in the
developed
design
30% 3 250 Web
Designer
Mock-up
presentation
and approval
from real users
Threat 5%
Risk
04
Increase in
Schedule
50 % 5 400 Project
planner
Preparing
Gantt chart
with
milestones
Opportunity 10%
Risk
05
Increase in
budget
60% 5 400 Project
manager
Estimating cost
for every
aspect
Threat 10%
5. Part Five:
5.1 Statement on Project Quality
The project will be managed as per the stated milestones and schedules and alterations will be made if
certain activities are not meeting with the project constraints
ISO 9001 standard will be applied for the management system
Service legal agreements will be prepared and the project will be delivered accordingly
Experienced and educated human resources will be appointed
Knowledge related to previous projects will be applied
5.2 Set of Verification Activities
Verification Activity When?
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Resource Quality and quantity During planning phase
Developed system After execution phase
Regular audit After execution till closure phase
Survey from customers and consumers After the development of system
5.3 Set of validation activities
6.
Part Six:
6.1 Annotated Bibliography
Please see in Appendix
6.2 Closure Checklist
Closure checklist Checklist options
Documents have been reviewed done
Testing completed done
Risks have been managed Not done
Training to the employees done
Project is change acceptable done
Project hand over Not done
6.3 Project Evaluation
Evaluation Criteria Option
Feasibility of design that is created for the system Yes No
Project plan feasibility Yes No
Feasibility of the organizational operation Yes No
Testing the results Yes No
Validation Activity When?
Testing After the development of the system
Simulation During execution phase
ROI and NPV After executing the estimation of the budget
Developed system After execution phase
Regular audit After execution till closure phase
Survey from customers and consumers After the development of system
5.3 Set of validation activities
6.
Part Six:
6.1 Annotated Bibliography
Please see in Appendix
6.2 Closure Checklist
Closure checklist Checklist options
Documents have been reviewed done
Testing completed done
Risks have been managed Not done
Training to the employees done
Project is change acceptable done
Project hand over Not done
6.3 Project Evaluation
Evaluation Criteria Option
Feasibility of design that is created for the system Yes No
Project plan feasibility Yes No
Feasibility of the organizational operation Yes No
Testing the results Yes No
Validation Activity When?
Testing After the development of the system
Simulation During execution phase
ROI and NPV After executing the estimation of the budget

Bibliography
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with
each other. Routledge.
Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical
framework. Journal of Risk Research, 18(2), 232-248.
Coombs, C.R., 2015. When planned IS/IT project benefits are not realized: a study of inhibitors and facilitators
to benefits realization. International Journal of Project Management, 33(2), pp.363-379.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management
Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a
necessity. International Journal of Project Management, 33(2), pp.291-298.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing
project manager. John Wiley & Sons.
Riol, H., & Thuillier, D. (2015). Project management for academic research projects: balancing structure and
flexibility. International Journal of Project Organisation and Management, 7(3), 251-269.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a
critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Terlizzi, M.A., de Souza Meirelles, F. and de Moraes, H.R.O.C., 2016. Barriers to the use of an IT project
management methodology in a large financial institution. International Journal of Project Management,
34(3), pp.467-479.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with
each other. Routledge.
Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical
framework. Journal of Risk Research, 18(2), 232-248.
Coombs, C.R., 2015. When planned IS/IT project benefits are not realized: a study of inhibitors and facilitators
to benefits realization. International Journal of Project Management, 33(2), pp.363-379.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management
Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a
necessity. International Journal of Project Management, 33(2), pp.291-298.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing
project manager. John Wiley & Sons.
Riol, H., & Thuillier, D. (2015). Project management for academic research projects: balancing structure and
flexibility. International Journal of Project Organisation and Management, 7(3), 251-269.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a
critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Terlizzi, M.A., de Souza Meirelles, F. and de Moraes, H.R.O.C., 2016. Barriers to the use of an IT project
management methodology in a large financial institution. International Journal of Project Management,
34(3), pp.467-479.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 15
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.