Gantt
chart
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
1 Online Straming Project
for Hardens.com
37 days Mon 5/6/19 Tue 6/25/19 £12,720.00
2 Phase one: Analyse
the problem
3 days Mon 5/6/19 Wed 5/8/19 £1,040.00
3 Visit the website 1 day Mon 5/6/19 Mon 5/6/19 System analyser £520.00
4 Gather relevant data 1 day Tue 5/7/19 Tue 5/7/19 3 £0.00
5 Conclude Problem 1 day Wed 5/8/19 Wed 5/8/19 4 System analyser £520.00
6 Milestone 1 0 days Wed 5/8/19 Wed 5/8/19 5 £0.00
7 Phase two: Solution
framing
3 days Thu 5/9/19 Mon
5/13/19
£1,560.00
8 Find solution
according to problem
2 days Thu 5/9/19 Fri 5/10/19 6 System analyser £1,040.00
9 Frame solution 1 day Mon 5/13/19Mon 5/13/198 System analyser £520.00
10 Milestone 2 0 days Mon 5/13/19Mon 5/13/199 £0.00
11 Phase three: System
designing
8 days Tue 5/14/19 Thu 5/23/19 £2,400.00
12 Finding relevant platform2 days Tue 5/14/19 Wed 5/15/1910 Proejct designer £1,200.00
13 Designing system 4 days Thu 5/16/19 Tue 5/21/19 12 £0.00
14 Designing modules 2 days Wed 5/22/19Thu 5/23/19 13 Proejct designer £1,200.00
15 Milestone 3 0 days Thu 5/23/19 Thu 5/23/19 14 £0.00
16 Phase four: System
development
10 days Fri 5/24/19 Thu 6/6/19 £1,920.00
17 Work division 1 day Fri 5/24/19 Fri 5/24/19 15 Developer £640.00
18 Individual module
generation
7 days Mon
5/27/19
Tue 6/4/19 17 £0.00
19 Module Integration 2 days Wed 6/5/19 Thu 6/6/19 18 Developer £1,280.00
20 Milestone 4 0 days Thu 6/6/19 Thu 6/6/19 19 £0.00
21 Phase 5: Testing phase7 days Fri 6/7/19 Mon 6/17/19 £2,800.00
22 Hardware based testing2 days Fri 6/7/19 Mon 6/10/1920 Tester £1,280.00
23 Software based testing2 days Tue 6/11/19 Wed 6/12/1922 Tester £1,280.00
24 End-user Testing 3 days Thu 6/13/19 Mon 6/17/1923 User £240.00
25 Milestone 5 0 days Mon 6/17/19Mon 6/17/1924 £0.00
26 Phase 6: Installation
and maintenance
3 days Tue 6/18/19 Thu 6/20/19 £1,800.00
27 System installation 1 day Tue 6/18/19 Tue 6/18/19 25 System analyser £520.00
28 website maintenance 2 days Wed 6/19/19Thu 6/20/19 27 Tester £1,280.00
29 Milestone 6 0 days Thu 6/20/19 Thu 6/20/19 28 £0.00
30 Phase 7: Project
completion and
3 days Fri 6/21/19 Tue 6/25/19 £1,200.00
31 Project report 2 days Fri 6/21/19 Mon 6/24/1928 Documentation incharge £800.00
32 Deliverables checking1 day Tue 6/25/19 Tue 6/25/19 31 Documentation incharge £400.00
33 Milestone 7 0 days Tue 6/25/19 Tue 6/25/19 32 £0.00
System analyser
System analyser
5/ 8
System analyser
System analyser
5/ 13
Proejct designer
Proejct designer
5/ 23
Developer
Developer
6/ 6
Tester
Tester
User
6/ 17
System analyser
Tester
6/ 20
Documentation incharg
Documentation inchar
6/ 25
6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29
May 2019 June 2019
chart
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
1 Online Straming Project
for Hardens.com
37 days Mon 5/6/19 Tue 6/25/19 £12,720.00
2 Phase one: Analyse
the problem
3 days Mon 5/6/19 Wed 5/8/19 £1,040.00
3 Visit the website 1 day Mon 5/6/19 Mon 5/6/19 System analyser £520.00
4 Gather relevant data 1 day Tue 5/7/19 Tue 5/7/19 3 £0.00
5 Conclude Problem 1 day Wed 5/8/19 Wed 5/8/19 4 System analyser £520.00
6 Milestone 1 0 days Wed 5/8/19 Wed 5/8/19 5 £0.00
7 Phase two: Solution
framing
3 days Thu 5/9/19 Mon
5/13/19
£1,560.00
8 Find solution
according to problem
2 days Thu 5/9/19 Fri 5/10/19 6 System analyser £1,040.00
9 Frame solution 1 day Mon 5/13/19Mon 5/13/198 System analyser £520.00
10 Milestone 2 0 days Mon 5/13/19Mon 5/13/199 £0.00
11 Phase three: System
designing
8 days Tue 5/14/19 Thu 5/23/19 £2,400.00
12 Finding relevant platform2 days Tue 5/14/19 Wed 5/15/1910 Proejct designer £1,200.00
13 Designing system 4 days Thu 5/16/19 Tue 5/21/19 12 £0.00
14 Designing modules 2 days Wed 5/22/19Thu 5/23/19 13 Proejct designer £1,200.00
15 Milestone 3 0 days Thu 5/23/19 Thu 5/23/19 14 £0.00
16 Phase four: System
development
10 days Fri 5/24/19 Thu 6/6/19 £1,920.00
17 Work division 1 day Fri 5/24/19 Fri 5/24/19 15 Developer £640.00
18 Individual module
generation
7 days Mon
5/27/19
Tue 6/4/19 17 £0.00
19 Module Integration 2 days Wed 6/5/19 Thu 6/6/19 18 Developer £1,280.00
20 Milestone 4 0 days Thu 6/6/19 Thu 6/6/19 19 £0.00
21 Phase 5: Testing phase7 days Fri 6/7/19 Mon 6/17/19 £2,800.00
22 Hardware based testing2 days Fri 6/7/19 Mon 6/10/1920 Tester £1,280.00
23 Software based testing2 days Tue 6/11/19 Wed 6/12/1922 Tester £1,280.00
24 End-user Testing 3 days Thu 6/13/19 Mon 6/17/1923 User £240.00
25 Milestone 5 0 days Mon 6/17/19Mon 6/17/1924 £0.00
26 Phase 6: Installation
and maintenance
3 days Tue 6/18/19 Thu 6/20/19 £1,800.00
27 System installation 1 day Tue 6/18/19 Tue 6/18/19 25 System analyser £520.00
28 website maintenance 2 days Wed 6/19/19Thu 6/20/19 27 Tester £1,280.00
29 Milestone 6 0 days Thu 6/20/19 Thu 6/20/19 28 £0.00
30 Phase 7: Project
completion and
3 days Fri 6/21/19 Tue 6/25/19 £1,200.00
31 Project report 2 days Fri 6/21/19 Mon 6/24/1928 Documentation incharge £800.00
32 Deliverables checking1 day Tue 6/25/19 Tue 6/25/19 31 Documentation incharge £400.00
33 Milestone 7 0 days Tue 6/25/19 Tue 6/25/19 32 £0.00
System analyser
System analyser
5/ 8
System analyser
System analyser
5/ 13
Proejct designer
Proejct designer
5/ 23
Developer
Developer
6/ 6
Tester
Tester
User
6/ 17
System analyser
Tester
6/ 20
Documentation incharg
Documentation inchar
6/ 25
6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29
May 2019 June 2019

PERT
chart
chart
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Resource cost overview
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Task cost overview

Resource overview
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Project milestones
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Project
logbook
logbook

Home
Page
Page
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Website
Home Page
Home Page
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Website
Restaurants
Page
Restaurants
Page

Restaurants
Page
Page
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 18

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.