Project Plan: Western Australia Petrol Tank Improvement Project
VerifiedAdded on 2023/06/04
|27
|3058
|209
Project
AI Summary
This project management assignment presents a comprehensive plan for improving the health, safety, and environmental conditions of unleaded petrol storage tanks in Western Australia. The project involves addressing issues like tank leakages and ensuring compliance with safety standards. The assignment details the project's overview, including the implementation plan, which encompasses risk identification, stakeholder engagement, and organizational structure. It also outlines the challenges in the implementation plan, such as managing pollution and resource allocation. Furthermore, the assignment provides a detailed management plan covering time, cost, and quality management, including resource allocation and project performance evaluation. The project uses various methodologies for evaluating success and failure and concludes with a project closure phase and references.

Project Management
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Contents
1. Project Overview:..........................................................................................................................2
2. Implementation Plan:....................................................................................................................2
Risks Identification plan:....................................................................................................................2
Stakeholder Engagement plan...........................................................................................................4
Organization Structure....................................................................................................................10
3...........................................................................................................................................................10
Challenges in the implementation plan:..........................................................................................10
4. Management Plan.......................................................................................................................11
Time Management Plan:..................................................................................................................12
Cost Management Plan...................................................................................................................13
Quality Management Plan...............................................................................................................13
5. Project Performance Evaluation..................................................................................................21
6. Project Closure............................................................................................................................23
7. References:..................................................................................................................................25
1. Project Overview:..........................................................................................................................2
2. Implementation Plan:....................................................................................................................2
Risks Identification plan:....................................................................................................................2
Stakeholder Engagement plan...........................................................................................................4
Organization Structure....................................................................................................................10
3...........................................................................................................................................................10
Challenges in the implementation plan:..........................................................................................10
4. Management Plan.......................................................................................................................11
Time Management Plan:..................................................................................................................12
Cost Management Plan...................................................................................................................13
Quality Management Plan...............................................................................................................13
5. Project Performance Evaluation..................................................................................................21
6. Project Closure............................................................................................................................23
7. References:..................................................................................................................................25

1. Project Overview:
The Western Australia government is looking forward to design a project plan for improving
the health, safety and environmental condition for storing the unleaded petrol in the different
capacity of tanks. The conditions of the tanks are not good for storing the ULP. The patching
is required for resolving the leakages in the tanks. The purpose of this paper is to develop the
implementation plan and management plan to manage the storage of the petrol successfully.
2. Implementation Plan:
The implementation plan focuses on analysing the risks and uncertainty associated with the
project, development of the organization structure, and development of the stakeholder
engagement plan (PM4Dev, 2007).
Risks Identification plan:
Risks
Identified
Risks
Severity
Risks
Likelihood
Risks
Ranking
Risks
Priority
Risks
Impact
Risk
Mitigation
plan
Leakages of
the petrol
2 3 5 Medium High The
patching
should be
done on the
leakages
point of the
tank
Poor work,
health, and
safety
standards
3 4 7 High Low The new
machinery,
new
equipment
should be
provided to
the
employees
for
improving
The Western Australia government is looking forward to design a project plan for improving
the health, safety and environmental condition for storing the unleaded petrol in the different
capacity of tanks. The conditions of the tanks are not good for storing the ULP. The patching
is required for resolving the leakages in the tanks. The purpose of this paper is to develop the
implementation plan and management plan to manage the storage of the petrol successfully.
2. Implementation Plan:
The implementation plan focuses on analysing the risks and uncertainty associated with the
project, development of the organization structure, and development of the stakeholder
engagement plan (PM4Dev, 2007).
Risks Identification plan:
Risks
Identified
Risks
Severity
Risks
Likelihood
Risks
Ranking
Risks
Priority
Risks
Impact
Risk
Mitigation
plan
Leakages of
the petrol
2 3 5 Medium High The
patching
should be
done on the
leakages
point of the
tank
Poor work,
health, and
safety
standards
3 4 7 High Low The new
machinery,
new
equipment
should be
provided to
the
employees
for
improving
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

the working
standards
Oil spilling 2 1 3 Low High The Oil
spilling is
the major
hazard
marine life.
The good
condition
trucks,
trained
drivers
should be
employed
for the
parcel of the
fuel oil
High
Volume of
inflammabl
e vapours
3 4 7 High High The
employees
should be
provided
with the
masks and
safety
uniform.
Pollution
level in the
environment
should be
checked
regularly.
Filling time 1 2 3 Low Medium The
patching on
the leakages
standards
Oil spilling 2 1 3 Low High The Oil
spilling is
the major
hazard
marine life.
The good
condition
trucks,
trained
drivers
should be
employed
for the
parcel of the
fuel oil
High
Volume of
inflammabl
e vapours
3 4 7 High High The
employees
should be
provided
with the
masks and
safety
uniform.
Pollution
level in the
environment
should be
checked
regularly.
Filling time 1 2 3 Low Medium The
patching on
the leakages
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

point help in
improving
the filling
time and
decreasing
the rate of
pollution in
the air
Stakeholder Engagement plan
Stakeholders Role and
Responsibiliti
es
Stakehold
er
contributio
n
Stakehold
er
legitimacy
Stakehold
er
willingnes
s
Influenc
e
Stakeholde
r
Involveme
nt
requiremen
t
improving
the filling
time and
decreasing
the rate of
pollution in
the air
Stakeholder Engagement plan
Stakeholders Role and
Responsibiliti
es
Stakehold
er
contributio
n
Stakehold
er
legitimacy
Stakehold
er
willingnes
s
Influenc
e
Stakeholde
r
Involveme
nt
requiremen
t

Project
Manager
Preparation of
the project
charter for
approval of
the project
Preparation
project
activity
schedule
Systematic
division of
responsibilitie
s to the
working team
members
Consulting
with the
project owner
Communicati
on strategies
Risks
assessment
Low High Medium Medium Low
Construction
Engineer
Development
of the
construction
design for
improving the
condition of
the tank 1, 2,
Medium Low High High Low
Manager
Preparation of
the project
charter for
approval of
the project
Preparation
project
activity
schedule
Systematic
division of
responsibilitie
s to the
working team
members
Consulting
with the
project owner
Communicati
on strategies
Risks
assessment
Low High Medium Medium Low
Construction
Engineer
Development
of the
construction
design for
improving the
condition of
the tank 1, 2,
Medium Low High High Low
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

and 3
Development
of the
construction
plan for
setting of
steel pipes
and anchors
(Owens,
2010)
Repairing of
the leakages
Patching of
the leakages
Architect Development
of engineering
drawings
Repairing the
leakages
High High Medium Low Medium
Contractors Provides raw
material at
construction
site
Provides
cranes and
trucks
Managing
supply and
Low Low High Medium High
Development
of the
construction
plan for
setting of
steel pipes
and anchors
(Owens,
2010)
Repairing of
the leakages
Patching of
the leakages
Architect Development
of engineering
drawings
Repairing the
leakages
High High Medium Low Medium
Contractors Provides raw
material at
construction
site
Provides
cranes and
trucks
Managing
supply and
Low Low High Medium High
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

demand of
resources
required
Business
Analyst
Analysing the
situation of
the site
location
Providing
new and
innovative
ideas for
resolving the
safety issues
Checks safety
requirement
for the project
Medium Medium Low High Medium
Painting
Workers
Painting work
Patching of
the leakages
Painting from
inside
Painting from
outside
High Low High Medium High
Cleaning
staff
Cleaning of
the tank 1, 2,
and 3
Low High Medium High Low
Labours and
workers
Undertake the
construction
work
Low Medium High Low High
resources
required
Business
Analyst
Analysing the
situation of
the site
location
Providing
new and
innovative
ideas for
resolving the
safety issues
Checks safety
requirement
for the project
Medium Medium Low High Medium
Painting
Workers
Painting work
Patching of
the leakages
Painting from
inside
Painting from
outside
High Low High Medium High
Cleaning
staff
Cleaning of
the tank 1, 2,
and 3
Low High Medium High Low
Labours and
workers
Undertake the
construction
work
Low Medium High Low High

Undertake the
filling work
Undertake the
painting work
Environment
al Manager
Analyse the
level of
pollution in
the air
Proposes
parameters for
minimizing
the pollution
Providing
alternative
solution to
resolve the
problem of
pollution
Medium Low Medium Low High
Health and
Safety
manager
Checks the
Safety
requirement
of the workers
(Seppala,
2013)
Checks the
working
condition
Checks the
High Low Medium High Low
filling work
Undertake the
painting work
Environment
al Manager
Analyse the
level of
pollution in
the air
Proposes
parameters for
minimizing
the pollution
Providing
alternative
solution to
resolve the
problem of
pollution
Medium Low Medium Low High
Health and
Safety
manager
Checks the
Safety
requirement
of the workers
(Seppala,
2013)
Checks the
working
condition
Checks the
High Low Medium High Low
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

level of
pollution
Checks the
working of
the machinery
and other
equipment
Risk
Manager
Identification
of risks and
uncertainty
Identification
of severity
risks
Identification
of risks
Likelihood
Evaluation of
risks Ranking
Evaluation of
risks priority
Analysing of
risks impact
Proposing the
development
strategy for
mitigating
risks
High Low Medium High Medium
pollution
Checks the
working of
the machinery
and other
equipment
Risk
Manager
Identification
of risks and
uncertainty
Identification
of severity
risks
Identification
of risks
Likelihood
Evaluation of
risks Ranking
Evaluation of
risks priority
Analysing of
risks impact
Proposing the
development
strategy for
mitigating
risks
High Low Medium High Medium
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Financial
Manager
Develops the
Cost
estimation
plan
Develops the
project budget
Develops cost
variation
report
Low Medium High Low Medium
Organization Structure
Project Manager
Construction Engineer
Architect
Financial Manager
Contractors and Sub-contractorBusiness analyst
Environmental Manager
Risks Manager Health and
safety
Manager
Cleaning Staff,
Worker, and Labour
Manager
Develops the
Cost
estimation
plan
Develops the
project budget
Develops cost
variation
report
Low Medium High Low Medium
Organization Structure
Project Manager
Construction Engineer
Architect
Financial Manager
Contractors and Sub-contractorBusiness analyst
Environmental Manager
Risks Manager Health and
safety
Manager
Cleaning Staff,
Worker, and Labour

3.
Challenges in the implementation plan:
The challenges which comes forward in the development of the project repairing system for
improving the condition of the tanks:
Identification of the leakages part in the tanks 1, 2, and 3
Cleaning of the tank
Rising level of pollution from highly flammable vapours
Poor condition of health and safety standards
Managing supply and demand of the resources at site location
Managing chaos and conflicts among the working team due to the difference in
culture and languages (Wilson, 2012)
Non-ethical behaviour at work site
Resistance from the local people in undergoing the cleaning and painting of the tanks
4. Management Plan
The systematic approach should be undertaken for completion of the painting and repairing
of the tanks effectively. The proper management of the activities helps in minimizing the
level of risks and uncertainties associated with the project. The focus should be given on
analysing the critical factors of the developed project schedule so that overrunning of time
and cost can be effectively managed (Rauber, 2014). The quality standards and control policy
framework should be developed for managing the painting work at site location. The project
can be successfully completed by deploying the effective resource utilization plan.
Challenges in the implementation plan:
The challenges which comes forward in the development of the project repairing system for
improving the condition of the tanks:
Identification of the leakages part in the tanks 1, 2, and 3
Cleaning of the tank
Rising level of pollution from highly flammable vapours
Poor condition of health and safety standards
Managing supply and demand of the resources at site location
Managing chaos and conflicts among the working team due to the difference in
culture and languages (Wilson, 2012)
Non-ethical behaviour at work site
Resistance from the local people in undergoing the cleaning and painting of the tanks
4. Management Plan
The systematic approach should be undertaken for completion of the painting and repairing
of the tanks effectively. The proper management of the activities helps in minimizing the
level of risks and uncertainties associated with the project. The focus should be given on
analysing the critical factors of the developed project schedule so that overrunning of time
and cost can be effectively managed (Rauber, 2014). The quality standards and control policy
framework should be developed for managing the painting work at site location. The project
can be successfully completed by deploying the effective resource utilization plan.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 27
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.