This report provides a comprehensive analysis of a PLC project, covering various aspects of project management. It begins with an abstract summarizing the key findings, including the role of iron triangular parameters (cost, time, scope) in defining project goals and objectives, and the importance of a risk register in identifying and mitigating potential risks like budget increases, resource constraints, and delays. The report then delves into project planning, including network diagrams, Gantt charts, and a detailed budget calculation of £2,602,500. The progress of the project is assessed after 17 weeks, revealing delays of 7-8 weeks. Finally, the report includes an earned value analysis with key metrics such as BCWS (23.33), BCWP (13.90), and EAC (£9.73), offering insights into project performance and cost management, and recommendations.
Document Page
Fundamental of project
management
1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
ABSTRACT
The report is based on project management and undertaking of PLC project. It has been
described about role of iron triangular parameter in forming goals. Also, certain risks like
increase is budget, delay in completion etc has been mentioned in risk register along with some
mitigation measures. Besides, that it is explained about network diagram and Gantt chart of
entire project. The budget of project is calculated that is 2602500. Furthermore, progress of
project and its comparison has been done after 17 week and there is delay of 7 -8 weeks. Also,
earned value analysis of project is done which is BCWS is 23.33 and BCWP is 13.90. and EAC
of project is £9.73.
2
Document Page
Table of Contents
ABSTRACT.....................................................................................................................................2
INTRODUCTION...........................................................................................................................4
PART A...........................................................................................................................................4
1. Project definition..........................................................................................................................4
a). Importance of iron triangular parameters in project objective...............................................4
b) Risk register.............................................................................................................................5
2. Planning and cost ........................................................................................................................7
a) Network diagram ....................................................................................................................7
Ghantt chart..................................................................................................................................8
c) Budget of project ..................................................................................................................10
3. Managing progress and spending...............................................................................................10
a) Determine the planned progress after 17 weeks ..................................................................11
b) Actual progress values of project from revised table............................................................11
4 Earned value analysis and acceleration.......................................................................................13
A) Earned value.........................................................................................................................13
Acceleration...............................................................................................................................14
PART B..........................................................................................................................................14
CONCLUSION .............................................................................................................................14
REFERENCES..............................................................................................................................16
3
Document Page
INTRODUCTION
Project management is process of planning, organising, initiating, completion, etc of specific
tasks and objectives to attain particular goals and objectives. A project needs to be broken down
into various activities so that it becomes easy to plan and organize things. However, for every
small and large project this concept is followed. Also, it depends on project manager as well that
how this concept is applied into it. For manager it is essential to monitor progress so that project
goes in right direction and also the impact of risk is mitigated as well. However, there are some
Factor which affects on project such as stakeholders expectations, environment, etc (Klemt-
Albert, Hagedorn, and Pullmann, 2018)
In this it wll be discussed about role of iron triangular parameter in forming goals. Also, it will
be mentioned risk register of PLC project along with some mitigation measures. Besides, that it
will be explained about network diagram and Gantt chart of entire project. The budget of project
will be calculated as well. Furthermore, progress of project and its comparison will be done after
17 weeks. Also, earned value analysis of project will be done.
PART A
1. Project definition
a). Importance of iron triangular parameters in project objective
In every project there are basically 3 components which is essential in it. They are cost,
time and scope. So, the project manager has to defined these all in effective way so that project is
successfully completed. However, on basis of goals and objectives project scope is defined.
Along with it, there are several parameters which is followed in it (Coccia, 2017). They help in
proper planning and organising of activities in efficient way. Usually, the iron triangular
parameters defines interrelationship between cost, time and scope. This makes it easy for project
manager to find out that how change in any one of them will impact on another. Besides, by
understanding relationship between them manager tries to maintain balance between it. Also, it
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
provide description about this to manager so accordingly changes are made in plans and tasks.
Hence, the parameters are mentioned as :
Cost- here,all cost and expense which will be incurred during whole project is mentioned. It
contains fixed, variable, labour costs, etc. hence on basis of it budget is estimated. This gives
insight to manager about benchmark of cost. Thus, if there occur any variance in cost then
manager is able to compare it with budget and accordingly it is controlled and monitored. Any
affect on cost result in impact on scope and time as well.
Time- in this it gives estimate of time required to completed project. The manager prepare
schedule of activities and start and end date of each tasks. So, if there is any delay in start or
finish of any task then it directly affect on scope and cost. There is rise in cost a more resources
are required. Besides, scope is modified as well. It enables manager to maintain and control
progress of project (Edwards, 2018).
Scope – scope includes all the tasks which are to be carried out in order to complete project in
specified time. The scope is developed on basis of goals and objectives and stakeholder
expectations. Therefore, any change in scope impact on cost and time. There is increase in both
time as well as cost. So, project manager prioritize task to control its impact.
Thus, it is evaluated that iron triangular parameters are significant in determining impact
of core elements of project on one another.
b) Risk register
In a project there are various types of risks which occurs. These risks highly impact on
project goals and its completion. So, it is necessary for manager to identify those risk an take
appropriate measure to minimise its impact. For that a risk register tool is used. It helps in
determining the types of risks, its likelihood, factor, etc. besides that, it include mitigation
measures as well that what measure is take for what type of risk. Thus, it makes it easy for
project manager to mitigate impact on risk. The main purpose of risk register is it provide in
depth detail and make manager aware about risks. Therefore, on right time effective and proper
measures are taken and risk impact is minimised (Klemt-Albert, Hagedorn, and Pullmann,
2018). So, in PLC project as well the risk register is as below :
5
Document Page
Risk Likelihood Impact Mitigation
measures
Risk factor
1= low
5 = high
Increase in budget 4 5 The budget will
be properly
estimated with
help of expert and
additional cost
will be mentioned
in it
5
Lack of resources 4 5 Here, resources
will be allocated
as per need of
tasks and its
monitoring will
be done.
5
Delay in
completion
3 4 Entire project
progress will be
monitored every
week.
4
Technical fault 2 3 Proper testing
will be done of all
equipments.
3
Damage of
equipment during
transportation
2 3 There will be use
of boxes for it and
safety measures
are taken.
4
Software failure 4 5 There will be
proper testing
5
6
Document Page
done again and
again. Back up
software will be
used as well.
Error in product
line
3 4 In this high tech
and advance
software will be
used to monitor it.
3
Lack of labor 4 5 Back up plan will
be made.
4
Improper tool for
training
3 4 All tools will be
checked and
tested .
4
Failure of
production of
product
4 5 Initially testing
will be done and
automated
software will be
used to control
process.
5
2. Planning and cost
In this stage the planning is done and on basis of it cost of each task is determined. This is
crucial stage as entire success of project is dependent on it. If planning is not done properly then
it lead to failure of project. However, cost determined is based on budget. In this team members
get detailed info on how much cost is incurred on which stage.
a) Network diagram
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Ghantt chart
The ghant chart is part of network diagram and consists of graphs of overall project tasks.
It is a step by step procedure which state tasks to be completed one by one. It provide description
of start and end date of each task (Kordijazi and Silva, 2018). Moreover, manager is able to
identify and analyse that when each task begin and end and how may days, weeks it takes to
finish it. In addition, ghantt chart shows flow of activities and its connection between them.
Here, predecessors are mentioned in it which shows which task gets started after other one and
how they all are interrelated to one another. The ghantt chart is below
Task Name Duration Start Finish Predecessors
Project initiation 1 wk Mon 7/8/19 Fri 7/12/19
Commission of design of 3 wks Mon 7/15/19 Fri 8/2/19 1
8
Document Page
factory
Commission of outline
design of automation
equipment
2 wks Mon 7/15/19 Fri 7/26/19 1
Commission outiline- design
inverter product 1 wk Mon 7/15/19 Fri 7/19/19 1
Detailed design of factory 8 wks Mon 8/5/19 Fri 9/27/19 2
Detailed design of
automation equipment and
inverter product
8 wks Mon 7/29/19 Fri 9/20/19 3,4
Commission and develop
software for automation
equipment and inverter
product
10 wks Mon 9/23/19 Fri 11/29/19 6
manufacture automatiton
equipment 10 wks Mon 9/23/19 Fri 11/29/19 6
manufacture modular factory
units 9 wks Mon 9/30/19 Fri 11/29/19 5,6
transport and construct
modular factory on site in
germany
8 wks Mon 12/2/19 Fri 1/24/20 9
test automation equipment 6 wks Mon 12/2/19 Fri 1/10/20 7,8
transport automation
equipment to new factory 4 wks Mon 1/13/20 Fri 2/7/20 11
install automation in new
factory 6 wks Mon 2/10/20 Fri 3/20/20 9,12
install software for
automation equipment 4 wks Mon 3/23/20 Fri 4/17/20 13
install software for inverter 5 wks Mon 4/20/20 Fri 5/22/20 7,14
9
Document Page
product line
test inverter product line 6 wks Mon 5/25/20 Fri 7/3/20 14,15
handovr and train TTf
engineer 6 wks Mon 7/6/20 Fri 8/14/20 16
project closure 0 wks Mon 8/17/20 Mon 8/17/20 17
c) Budget of project
Budget is estimation of cost incurred in project. It is a prepared for a particular project
and time period. It includes various types of costs such as fixed, variable, labor, etc. Generally,
main purpose of budget is to provide estimate of costs. Then, accordingly project manager
10
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
allocate resources to each tasks (McGrath, O'Toole, and Canning, 2019). The budget can vary
on basis of type and nature of project. It plays vital role as costs resources are allocated and
proper monitoring is done of its utilization.
Expenses
Per
hour
Electrician 69 1656000
Technician 39 936000
2 Assistant
Project
Manager
and 2
Project
Planner 5500 5500
2
Commercial
Manager 2750*2 5000
Total 2602500
The above table determine overall budget of PLC project. It shows that total amount
required is 2602500. in this the expense of electrician is 1656000 and of technician is 936000.
this cost is variable as it varies on basis of per hour worked. Here, fixed cost is also included in it
which is of 2 assistant project manager and planner.
3. Managing progress and spending
This stage is very crucial as it allow project manager to measure progress with cost. Here,
it is identified that whether cost incurred is according to planned progress or not. If cost incurred
is high then manager find out reason behind it. So, the main purpose of manager is to maintain
balance between progress and spending. It allows in making changes in plans as well as budget.
Thus, it is ensured that project moves in right direction and as per planning done.
a) Determine the planned progress after 17 weeks
Task Planned Actual
11
Document Page
PI 1 1
A 3 3
B 2 2
C 1 1
D 8 6
E 8 8
F 10 3
G 10 4
H 9 4
It can be analyzed from above that PLC project progress is 100% till 4 tasks. But after
that as coming further to F G H task the progress is delayed and there is only 35% completion of
each tasks. Thus, it will highly affect on further activities of project. It might incur more cost
require to complete it on time.
b) Actual progress values of project from revised table
In this, a table is formed in which comparison is done between actual and planned
progress of project (Rosa, and Rozenfeld, 2016). Then, ghantt chart is developed again to find
out how much more time is required for its completion. Along with it, manager can now find out
start and end date of task and do further planning accordingly. Besides, prioritize tasks are found
out and they are completed first.
Task Name Duration Start Finish Predecessors
Project initiation 1 wk Mon 7/8/19 Fri 7/12/19
Commission of design of
factory 3 wks Mon 7/15/19 Fri 8/2/19 1
Commission of outline
design of automation
2 wks Mon 7/15/19 Fri 7/26/19 1