Earned Value Management in Project: PMAN 650 Cost Analysis

Verified

Added on  2023/06/03

|6
|527
|240
Homework Assignment
AI Summary
This assignment provides a detailed earned value management (EVM) analysis for a project consisting of seven activities. It includes the computation of earned value measures such as Planned Value and Earned Value, followed by the calculation of performance parameters like Schedule Variance, Schedule Performance Index, Cost Variance, and Cost Performance Index. The analysis determines whether the project is ahead of schedule or over budget based on these parameters. Furthermore, the assignment calculates the Cumulative Cost Performance Index (CPI), Estimate at Completion (EAC), and Estimate to Completion (ETC) using various formulas and scenarios, including adjustments for cost overruns and budget provisions. Finally, it computes the changed cost performance index required to complete the project within the original budget. The assignment leverages provided project data, including activity budgets, planned start and finish dates, and earned value accrual rules, to provide a comprehensive assessment of project cost and schedule performance.
Document Page
Project Management
STUDENT NAME/ID
[Pick the date]
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Question 1
(a) Computation of earned value measures for each of the given activity
Formula used:
Planned Value=Budget at costPercentage completed planned
Percentage completed planned =100 %
Earned Value ( EV )=Budget at costActual percentage completed
Computation table
Final table
1
Document Page
Question 2
(a) Earned value performance parameter for each of the given activity
Formulae used
Schedule Variance = Earned value – Planned value
Schedule performance Index = Earned value / Planned cost
Cost Variance = Earned value – Actual cost
Cost performance Index = Earned value / Actual cost
(b) It can be said that project is “ahead of schedule.” It is concluded based on the earned value
and planned value. In present scenario, the earned value is higher than planned value.
(c) It can be said that project is “over budget.” It is concluded based on the earned value and
actual cost. The over budget has been determined based on the fact that earned value is
higher than actual cost and hence, the project would be termed as over budget.
Question 3
2
Document Page
(a) Cumulative Cost performance Index (CPI) and Estimate at completion (EAC)
CPI would be computed based on the CPI of each of the activity whereby, EAC has been
computed based on CPI and budget at cost.
Computation for CPI
CPI = Sum of CPI of all the activities
Hence, Cost performance Index (CPI) = 6.936
Computation for EAC
Estimate at completion (EAC) = Sum of BAC / CPI
3
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Hence, EAC = 215000/6.936 = 30,997.693
(b) Estimate to completion (ETC)
ETC can be determined with the help of CPI and cost overrun. Here, cost overrun would be
calculated with the help of budget provisions and actual cost.
Cost Overrun=Actual cost budget provision=9500096846=1,846
Now,
Estimate to completion (ETC) = Cost Overrun * CPI = -1846*6.936 = -12,803.85
(c) Estimate At Completion (EAC)
EAC= AC+ {BAC EV
CPISPI }
Where,
AC=95000
BAC=215000
EV =157000
CPI=6.936
SPI=5.361
Now,
EAC= AC+ {BAC EV
CPISPI }=95000+ {215000157000
5.3616.936 }=96,560
4
Document Page
The budget provision of the project is 96846 whereas. The EAC comes out to be 96,560 which
implies that project would require additional $286 in order to meet the current budget
requirement.
(d) The changed cost performance index (CPI0) as to complete the project with the help of
original budget has been computed as shown below.
EAC= AC+ { BACEV
CPI 'SPI }
Where,
AC=95000
BAC=215000
EV =157000
CP I'=?
SPI=5.361
EAC=96846
Now,
EAC= AC+ {BAC EV
CPISPI }
96846=95000+ { 215000157000
5.361CP I ' }
CP I'=5.861
The change in CPI is computed as given below.
CPI0= CPI – CPI’ = 6.936 – 5.861 = 1.075
5
chevron_up_icon
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]